Method Statement For Column Formworks - July 31.2024
Method Statement For Column Formworks - July 31.2024
Formworks
DOCUMENT TITLE
Doc. No.:
1.0 SCOPE
2.0 PURPOSE
3.0 DEFINITIONS
4.0 RESPONSIBILITIES
6.0 SAFETY
8.0 MANPOWER
1.1 Procedure for Column Rebar Works and formworks in special need school center
Ph-1
1.2 Column Rebar works and Formworks under this method of statement are
categorized as follows
Fabrication of rebars
Installation of Rebars
Fabrication of forms
Installation of forms
Removal of forms
1.3 Prior to commencement of works, construction meeting will be held at the site
offices with the construction staff and contractor carrying out the work to discuss
the methodology of the works, comprehension of the risks and risk mitigation
plan. Emergency procedures and supervision carrying out the work.
2.0 PURPOSE
The purpose of this Method statement is to establish guidelines addressing all the
requirements for the scaffolding works conform to the design, approved IFC drawings
and specifications in the special need school center Phase-1 project.
3.0 DEFINITIONS
All works will be carried out in accordance with the project Health and Safety plan
The Project Manager is responsible for liaising with Saudi Aramco and the
supplier with regards to deliveries, construction dates, conveying the information
to the Construction manager ensuring the method statement is approved and
passed to the construction manager.
The HSE Manager is responsible for reviewing these procedures in the method
statement, ensuring that the method statement, JSA and STA are carried out at
the required time by the safety officer. Ensuring that all operatives are briefed on
the method statement and operatives have signed to confirm receipt of briefing.
Ensure that all safety requirements to start the activity are provided by the
construction group as per project HSE manual and specification
To conduct daily inspection to ensure that safety requirements are being
maintained up to the completion of this activity
Review the method of working and ensure safety measures are being
adhered to at all times and advising supervisors of any issues arising.
To monitor all the labor and equipment operators and other associated
craftsman performing their tasks accordingly. Submit daily work report
progress to the site engineer. Site supervisor shall be on site, supervising the
work all the times.
Boom truck
Mobile Crane
Scaffolding Materials
Circular Saw
Jig Saw
Electric Drill
Bending Machine
Electric Bar Cutter
Ladder
Electrical Cord
Manual tools.
- Hammer
- Meter tape
6.0 SAFETY
All work shall be undertaken in accordance with the PROJECT HSE manual
and all individual activities will be set up in an orderly manner to ensure
compliance with the requirements.
Work permit shall be obtained prior to start of any work activity and work
shall commence in accordance with the specific measures itemized in the
permit.
Project Engineer
Site Engineer
Civil QC inspector
Safety officer
Civil Supervisor/Foreman
Surveyor and Helper
Carpenter and Helpers
Heavy Equipment operators
Rigger