Gorong 2
Gorong 2
2 3 4 5
Vb
V = P X L X T
= 3.60 X 0.50 X 0.10
= 0.18
RENCANA ANGGARAN BIAYA (RAB)
Kegiatan : Gorong-gorong
Volume : 3m
Lokasi : RW 2
Tahun anggaran : 2018
No Uraian Pekerjaan Koef. Volume Satuan Harga Bahan / Upah Harga Satuan Jumlah Harga Total
................................................... .................................................
REKAP KEBUTUHAN BAHAN DAN TENAGA KERJA
Kegiatan : Drainase
Volume : 3m
Lokasi : RW 2
Tahun anggaran : 2018
1 2 3 4 5.00 6=4x5
1 TENAGA KERJA
1 Tukang HOK 3.00 110,000.00 330,000.00
2 Pekerja HOK 26.00 95,000.00 2,470,000.00
Sub Total Bahan (1) 2,800,000.00
2 BAHAN
1 Kayu Bekesting Meranti m³ - 3,500,000.00 -
2 Paku Biasa 2" - 5" Kg 1.00 16,000.00 16,000.00
3 Minyak Bekesting (Solar) liter - - -
4 Besi Beton Polos Kg 108.00 12,000.00 1,296,000.00
5 Kawat Beton Kg 2.00 13,500.00 27,000.00
6 Semen Portland kg 12.00 58,000.00 696,000.00
7 Pasir Beton m³ 0.75 250,000.00 187,500.00
8 Kerikil m³ 1.50 241,500.00 362,250.00
9 Kayu Meranti Balok m³ 3,500,000.00 -
10 Multipleks 9 mm Lembar 2.00 117,000.00 234,000.00
11 Batu Kali m³ 2.00 185,000.00 370,000.00
Sub Total Bahan (2) 3,188,750
2 ALAT
1 Arco bh 550,400.00 0
2 Timba bh 7 10,000.00 70,000
3 Benang Buah 1.00 4,000.00 4,000
6 Sewa Alat Bantu (1 set @ 3 alat) Jam 12,200.00 0
7 Molen Sewa-hari - 100,000.00 0
Sub Total Bahan (2) 74,000
3 BU 303,250
Sub Total (3) 303,250
JUMLAH TOTAL BIAYA 6,366,000
................................................... .................................................
REKAP KEBUTUHAN BAHAN DAN TENAGA KERJA
Kegiatan : Drainase
Volume : 3m
Lokasi : RW 2
Tahun anggaran : 2018
1 2 3 4 5.00 6=4x5
1 TENAGA KERJA
1 Tukang HOK 6.00 110,000.00 660,000.00
2 Pekerja HOK 52.00 95,000.00 4,940,000.00
Sub Total Bahan (1) 5,600,000.00
2 BAHAN
1 Kayu Bekesting Meranti m³ - 3,500,000.00 -
2 Paku Biasa 2" - 5" Kg 2.00 16,000.00 32,000.00
3 Minyak Bekesting (Solar) liter - - -
4 Besi Beton Polos Kg 216.00 12,000.00 2,592,000.00
5 Kawat Beton Kg 4.00 13,500.00 54,000.00
6 Semen Portland kg 24.00 1,450.00 34,800.00
7 Pasir Beton m³ 1.50 250,000.00 375,000.00
8 Kerikil m³ 3.00 241,500.00 724,500.00
9 Kayu Meranti Balok m³ - 3,500,000.00 -
10 Multipleks 9 mm Lembar 4.00 117,000.00 468,000.00
11 Batu Kali m³ 4.00 185,000.00 740,000.00
Sub Total Bahan (2) 5,020,300
2 ALAT
1 Arco bh 0 550,400.00 0
2 Timba bh 14 10,000.00 140,000
6 Sewa Alat Bantu (1 set @ 3 alat) Jam 0 12,200.00 0
7 Molen Sewa-hari 0 100,000.00 0
Sub Total Bahan (2) 148,800
3 BU 606,500
Sub Total (3) 606,500
JUMLAH TOTAL BIAYA 11,375,600
................................................... .................................................
RENCANA ANGGARAN BIAYA (RAB)
2 3 4 5 6 7 8 9 10
Kegiatan : Drainase
Volume : 666.28 x 0.95 x 1.20 m
Lokasi : Dsn. Kedungbendo
Tahun anggaran : 2017
Harga Satuan
No Uraian Pekerjaan Koef. Volume Satuan Jumlah Harga Total
Bahan/ Upah HS Pekerjaan
1 2 3 4 5 6 7=6x3 8=6x4
1 Pekerjaan Galian 639.47 M3
- Pekerja 0.75 479.60 HOK 95,000 71,250 45,562,238
Sub Total 71,250 45,562,238
2 Pek. Urugan Tanah
Pek. urugan - M3
Tanah Urug 1.20 0.00 m3 110,000 132,000 0
Pekerja 0.30 0.00 HOK 95,000 28,500 0
Sub Total 160,500 0
3 1 m³ Pekerjaan Pemadatan Tanah setiap 20 cm
Pek. Pemadatan - M3
Stamper 0.05 0.00 unit/hr 237,900 11,895 0
Pekerja/Buruh TPekerja/Buruh Tak Ter 0.50 0.00 HOK 95,000 47,500 0
Sub Total 59,395 0
4 Pek. Urugan Pasir
Pek. urugan - M3
- Pasir Urug 1.20 0.00 m3 115,000 138,000 0
- Pekerja 0.30 0.00 HOK 95,000 28,500 0
Sub Total 166,500 0
4 Pek. Pasang batu kali 1.35 M3
- Batu Kali 1.2 2 m3 180,000 216,000 291,600
- Semen 40 kg 4.1 6 zak 58,000 236,350 319,073
- Pasir Pasang 0.52 0.70 m3 250,000 130,000 175,500
- Tukang 0.75 1.01 HOK 115,000 86,250 116,438
- Pekerja 1.50 2.03 HOK 95,000 142,500 192,375
Sub Total 811,100 1,094,985
5 Pemasangan pipa
Pipa PVC 1,5" 0.00 M
Pipa 1,5" 1.2 0.00 m 10,000 12,000 0
- Tukang 0.06 0.00 HOK 115,000 6,900 0
- Pekerja 0.036 0.00 HOK 95,000 3,420 0
Sub Total 22,320 0
6 Plesteran 1:4 - m2
- Semen 40 kg 0.13 0.00 zak 58,000 7,540 0
- Pasir Pasang 0.02 0.00 m3 250,000 5,000 0
- Tukang 0.15 0.00 HOK 115,000 17,250 0
- Pekerja 0.20 0.00 HOK 95,000 19,000 0
Sub Total 48,790 0
Total per Unit 46,657,223
BU 3% 1,399,717
Total Anggaran 48,056,000
Gemekan, 2017
................................................... .................................................