Ex. Seq. Component Total Scope Progress (Cum) Planned Completion Date For The Day For The Month
Ex. Seq. Component Total Scope Progress (Cum) Planned Completion Date For The Day For The Month
Ex. Seq. Component Total Scope Completion For the For the
Date Day Month
1 Clariflocculator-1 3,927 7/1/2024 0
Telescope Valve Chamber-1 27 7/2/2024 0
2 Sludge Sump 499 7/4/2024 0
3 Clariflocculator-2 3,927 7/10/2024 0
Telescope Valve Chamber-2 27 7/11/2024 0
4 Filter Bed 5,861 7/20/2024 0
5 Clear water Sump 6,126 7/26/2024 0
7 Pump House 1,835 7/29/2024 0
8 Cascade Aerator 52 8/1/2024 0
9 Recirculation Tank 1,673 8/4/2024 300
10 Sludge Thickener 329 8/7/2024 0
11 Thickened Sludge Sump 185 8/10/2024 217
12 Centrifuge Building 126 8/13/2024 0
13 Raw Water Channel 15 8/16/2024 0
14 Flash Mixer 35 8/19/2024 0
15 Chlorine Tank & Room 0
16 Primary Settling Tank 339 8/22/2024 0
17 PST- Sludge Sump 1,156 8/25/2024 0
18 Staff Quarters 0
Total 26,141
ogress (Cum)
Balance As
Cumm. on Date
1762.5 1762.5
0 0
0
2143.3 2143.3
0 0
0
0
0
0
396.2 696.2
0
39.8 256.8
0
0
0
0
0
0
18 18
4359.8 4876.80
Sr.No. DESCRIPTION OF STRUCTURE GAD Available
Approved Non
Approval
1 Cascade Aerator Yes
2 Raw Water Channel , Parshall Flume, & Bulk Flow Meter Yes
Approved Non
Approval
No Yes To be started Central shaft bot lvl not clear
Yes 90 % Completed
No Yes To be started
No Yes 90 % Completed
No No
No Yes To be started
No No
No No
No Yes Hold. clearnce req from farmers
No Yes To be started
No Yes To be started
No Yes To be started
No Yes To be started
No No 1 no. hold. Land clearance req.
No Yes bottom lvl not available
No No Hold . Land clearance required
No No Hold . Land clearance required
Intake Concrete History
21.53333