DOE - LBNL Data Center Energy Assessment Process Manual DOE v3 - 032222
DOE - LBNL Data Center Energy Assessment Process Manual DOE v3 - 032222
Assessment Process
Manual
Version 2.0
This document was prepared as part of work sponsored by the United States Government.
While this document is believed to contain correct information, neither the United States
Government, nor any agency thereof, nor The Regents of the University of California, operator
of the Lawrence Berkeley National Laboratory under DOE Contract No. DE-AC02-05CH11231,
nor any of their employees or licensors, make any warranty, express or implied, or assumes any
legal responsibility for the accuracy, completeness, or usefulness of any information, apparatus,
product, or process disclosed, or represents that its use would not infringe privately owned
rights. Reference herein to any specific commercial product, process, or service by its trade
name, trademark, manufacturer, or otherwise does not necessarily constitute or imply its
endorsement, recommendation, or favoring by the United States Government or any agency
thereof, or The Regents of the University of California. The views and opinions of the authors
expressed herein do not necessarily state or reflect those of the United States Government or
any agency thereof or The Regents of the University of California. The materials contained in this
document are being provided for training purposes only and may not be reproduced by any
means; including electronic, mechanical photocopying or recording, except as may be expressly
permitted by the 1976 Copyright Act or with the prior written permission of The Regents of the
University of California. Distribution for commercial purposes, and/or the preparation and
dissemination of derivative works based on these materials is strictly prohibited.
Notice: Materials contained in this document were produced under Contract DE-AC02-
05CH11231 with the U.S. Department of Energy. Accordingly, the Government has certain rights
in this copyrighted work.
Copyright© 2020 The Regents of the University of California, operator of the Lawrence Berkeley
National Laboratory. All Rights Reserved.
2
CONTENTS
1. INTRODUCTION 4
1.1 Energy in Data Centers 4
1.2 Role of DOE/LBNL Energy Assessments in the Process to Implement Efficiency
4
1.3 Purpose of this Process Manual and Other Resources 5
APPENDICES
A: Terminology 15
RESOURCES 25
1 INTRODUCTION
The slower growth is attributable to energy efficiency improvements and a lower server
installed base, arising in part from the Great Recession. The total energy savings potential
3
in data centers is still large, and energy assessments are an effective way to identify those
potential savings.
Figure 1. Historical and projected data center energy use (Shehabi et al., 2018)
1.2 Role of DOE/LBNL Energy Assessments In the Process of Identifying and Implementing
Energy Efficiency
Although a DOE/LBNL energy assessment is not a traditional investment-grade audit, the
assessment is designed to provide the data center industry with rapid, tangible, and
sustainable results such as energy, economic, and environmental savings. For best results,
it is recommended that the individual conducting the energy assessment (the assessor) be
a trained Data Center Energy Practitioner (DCEP).1
The DOE/LBNL assessment is aimed at developing an action plan for progress. The
assessment strategy has two main objectives:
• Accelerate energy savings by developing an energy profile with the internal data
center team, reviewing select data center systems (HVAC, air management,
electrical power chain, IT equipment), identifying potential energy-saving
measures and documenting cost and energy savings from the measures.
1
For details, see datacenters.lbl.gov/dcep
4
• Multiply savings through replication by building internal awareness and expertise,
e.g., at the site or regional level. Specifically, help the organization form an energy
management program, cultivate internal champions to lead energy savings efforts
and train the site lead in the DOE/LBNL Energy Assessment Process and the use of
the Data Center Energy Efficiency Toolkit.
The role of the DOE/LBNL energy assessments in the overall energy-efficiency process and
how private sector consultants fit in are depicted in Figure 2. The top two (blue) blocks
represent the DOE/LBNL Energy Assessments (high-level profiling and in-depth system
assessments). The next three (brown) blocks describe work by private sector consultants.
Lastly, the last two (green) blocks represent savings validation and documentation by site
personnel and engineering firms.
Retrofit/RCx Implementation
Measurement and verification (M&V) is
conducted by site personnel and
Savings Validation (M&V) • M&V by site personnel
engineering firms toand eng firms
confirm and track
• DOE tools used to document results,
performance. M&V is key for continuous
track performance improvements, and
Documentation improvement.
disseminate best practices
5
Table 1: Data Center Energy Assessment Resources
6
Electric Power Chain Tool This Excel-based tool helps data center
• Intuitive, question-based owners identify energy efficiency
• Diagrammed data center power chain opportunities in the electrical power
w/measuring points chain of a data center (transformers,
• Updated UPS efficiency curve generators, UPSs, power distribution
units). The tool quantifies the energy
and cost savings of the selected
https://datacenters.lbl.gov/resources/data-center- measures and calculates the payback
electrical-power-chain-tool periods for each measure.
7
# Process Step Description Available Resources
Introduce the DOE/LBNL assessment process. Identify
preliminary goals, scope, onsite activities, and key
personnel. Arrange for onsite logistics.
2 Preliminary assessment by site lead using DC Pro or * DC Pro Tools/Manuals
the PUE Estimator.
3 Phase 2: Pre-Onsite Preparation * DC Pro results
Kick-off conference call * Target System List (App. E)
- Review scope, onsite activities, team, and logistics * Selected System
- Identify target systems, tools, and data to collect Tool(s)/Manuals
- Identify safety issues.
4 Off-site compilation of information * Assessment Worksheets
- Collect technical info from drawings, logs, etc. * Site Survey (App. C)
- Collect Site Description Survey * Energy Management Practices
- Collect Energy Management Practices Survey Survey (App. D)
- Review required measurement equipment
- Ensure functioning of the toolkit onsite
- Review Safety, Health, and Environmental Training
- Review confidentiality agreements.
5 Phase 3: Onsite Activities (2-3 days per system) * Assessment Participants
Initiation onsite meeting with all stakeholders: Template (App. I)
- Collect participant list
- Overview presentation by the Assessor
- Safety, health, and environmental training
- Site tour of data center
- Develop detailed work plan (measurements)
- Assign roles and responsibilities
6 Training to allow replication (mainly part of Step 7) * DC Pro Tools/Manuals
- Training on efficiency toolkit * Air Management Tool
- Energy management best practices * Air Management Estimator
* Power Chain Tool
7 Fundamental investigations * Selected System
- Field measurements Tool(s)/Manuals
- System modeling with selected System Tools * Assessment Worksheets
- Assessment Worksheets
- Results compilation and presentation
8 Preliminary Findings Meeting * Evaluation Template (App. J)
- Directed to site management
- Complete Assessment Evaluation
9 Phase 4: Post-Onsite Activities * Process Manual (this doc)
Compilation of Assessment Report * Assessment Report Template
- Observations and opportunities and Example Report
- Estimated energy savings for each opportunity * Assessment Worksheets
- Estimated costs for implementing each opportunity * DC Pro
* Selected System
Tool(s)/Manuals
* Master List of Actions
* Any complete surveys and
templates (App. B-J)
10 Finalize reporting requirements + Follow up Same as above
8
# Process Step Description Available Resources
- Draft to site for review, document savings
9
– Arrange gate-pass for the assessor
– Identify a conference room that can serve as an uninterrupted base
– Identify lodging issues
– Consider food services onsite to minimize lost time.
10
– Primary System description
▪ Type and number of equipment/systems
▪ Redundancy
▪ Control strategies
▪ Power requirements and fuel types
▪ Operating characteristics, normal operating conditions.
11
– Perform the training the first day of the onsite activities
– Training must be completed and documented before onsite activities.
Agreements
The site lead must provide the assessor with the appropriate confidentiality agreements:
– The parties must ensure the agreements are understood.
– The assessor must have reviewed, signed, and return the agreements prior to
entering the site.
The initial meeting is an energy training-assessment in that the assessment lead team
should be an active participant in the assessment. Creating the ability for replication is a
key goal of the energy assessment.
– The energy assessment is not a fault-finding activity but an activity designed to:
▪ Share knowledge
▪ Provide tools
▪ Teach energy management best practices
▪ Identify opportunities for improvement
12
▪ Identify opportunities for replication
Site Tour
Conduct a brief site tour to familiarize the assessor with the data center facility. This is an
excellent opportunity to ask and answer questions.
This step is where the rubber hits the road. First, the lead team collects the missing
information based on the data gaps identified in Steps 4 and 5. Second, selected system
tool modeling is performed to quantify potential energy opportunities. The assessment
workbook can be useful if a particular system tool is not available. Finally, the results are
compiled into a presentation directed to the site management.
Some missing information (data) will be readily available, including data that can be
collected from building management systems, equipment read-outs (e.g., UPS), operating
13
information, and design data. Other data collection may require measurements and
temporary metering. The assessment team could decide to use a design value in lieu of a
measured value or decide to use estimates rather than actual data.
Field Measurements
Field measurements provide key input data to the Air Management Tool and other
analyses. The detailed Measurement Plan developed in Step 5 should be applied. Ensure
that all measurements required for determining critical data are performed while on site.
Measurement Plan modifications are likely as the fundamental investigations proceed.
Assessment Worksheets
The Assessment Workbook can be useful if a particular system tool is not available. The
workbook can be used for collecting data (Step 4) but also for documenting
measurements, metrics, calculations, and actions from the assessment. Data from the
one of the DC Pro Tools (Step 2) can be used as a starting point for the more detailed
assessment.
2
For organizations that are mature in energy management and actively seeking additional opportunities, it
may be appropriate to recommend enhancing their existing energy management system to be compliant
with DOE-‘s 50001 Ready program or the ISO 50001 standard. Both emphasize continuous improvement
following a holistic and systematic approach with top management commitment. For organizations with
14
– Present the Roadmap
– Modify recommendations based on information obtained during the meeting.
The site lead and other participants should complete an assessment evaluation prior to
the conclusion of the onsite activities.
Executive Summary
The executive summary should include key observations, opportunities, and estimated
energy savings.
less sophisticated energy management, it could be appropriate to recommend certain essential elements for
near-term benefit. Guidance for implementing these elements are found in the 50001 Ready Navigator tool
(https://navigator.lbl.gov/guidance/dashboard). Such opportunities may include, but not limited to,
collecting energy data for analysis, developing clear energy performance indicators and baselines,
establishing energy objectives and targets, monitoring performance improvement, and engaging senior
management in energy management activates.
15
Site Description Survey (see Appendix C)
The survey identifies the general characteristics of the data center (Step 4).
The survey provides a picture of the current energy management practices (Step 4).
– Brief description
– Estimate impact ($/year and kWh/year)
– Estimate cost for implementation
– Calculate simple payback (years)
– Identify the time horizon for completion:
16
Roadmap
The roadmap (action plan) initially developed in Step 7 should be refined and discussed.
As mentioned in the Introduction, this roadmap is a key outcome of the DOE/LBNL Energy
Assessment.
Benchmarking
The purpose of this section is to summarize the metrics that were utilized as part of the
assessment process and compare them to data from other facilities, where available.
Useful metrics may include the following:
– PUE (-)
– DCiE (%)
– Cooling Efficiency (kW/ton) [kW/kW]
– UPS System Efficiency (%)
– Rack Cooling Index (RCI) (%)
– Return Temperature Index (RTI)TM (%)
Follow Up
Follow up with the site to document implemented solutions and savings.
17
Appendix A: Terminology
Assessor
The energy expert assigned to complete the DOE/LBNL Assessment; the expert
serves as the facilitator for all activities and often is a Data Center Energy
Practitioner (DCEP).
DC Pro Tools
DC Pro Tools include the DC Pro and the PUE Estimator
DOE
U.S. Department of Energy
Lead Team
Core personnel participating in the assessment, including assessor and site lead
Primary Systems
– IT Equipment
– HVAC Systems (Cooling and Air Management)
– Electrical Systems
Site Lead
Data center technical representative that will be the primary person
participating in the assessment
Site Management
Data center personnel to whom the site lead wishes to communicate the
findings
System Tools
18
The in-depth System Tools include the Air Management Tool, the Air
Management Estimator, the Electrical Power Chain Tool, and the forthcoming IT
Equipment Efficiency Tool.
19
Appendix B: General Information
Name
Address
City/State
Phone
20
Appendix C: Site Description Survey
Request the Site Lead to complete the Site Description Survey to identify the general
characteristics of the data center.
21
Appendix D: Energy Management Practices Survey
Request the Site Lead to complete the following Energy Management Practices Survey to identify
energy policies implemented at the data center.
• Does your organization have a written CEO- or Board-approved policy that includes
reducing energy consumption?
□ No □ Yes □ Unknown or no answer
• Does your company/agency have a formal written energy management plan that is
updated at least every two years?
□ No □ Yes □ Unknown or no answer
• Do the duties of manager include finding and implementing ways of reducing the energy
consumption?
□ No □ Yes
• In the last two years, have there been any corporate/agency or facility mandates to
reduce energy consumption by a targeted percentage or amount?
□ No □ Yes □ What was the percentage? _____%
• Does the annual performance rating for the data center manager include a component
with energy reduction goals that influence bonuses?
□ No □ Yes □ Unknown
• In the last two years, have there been any projects in your data center to reduce energy
consumption or projects that included a component aimed at reducing or managing
energy?
□ No □ Yes
22
• When you purchase new or replace equipment at the data center, does the life cycle
cost, including energy use, affect what is purchased?
□ Always
□ Usually
□ Sometimes
□ Occasionally
□ Never
□ Unknown
• In managing operations and maintenance, do you analyze energy use trends to identify
needed changes to operations or maintenance practices to reduce energy use?
□ No □ Yes
• Which financial methods does your firm typically use to evaluate energy efficiency
improvements?
□ Initial Cost
□ Simple payback
□ Internal rate of return
□ Life cycle cost
□ Other (please explain) ______________________
□ Unknown
• What rate of return do you typically require to regard an energy investment cost
effective?
□ _______%
• What discount rate do you normally use in determining the life-cycle costs of various
equipment options?
□ _______%
23
Appendix E: Target System List (Assessment Scope)
The three primary systems are IT Equipment, HVAC Systems, and Electrical Systems. Each
primary system, in turn, consists of key sub-systems as shown below. Check the selected
subsystems for the assessment.
Systems Target
System(s)
IT Equipment
Servers
Storage
Networking
HVAC Systems
Air Management
Cooling Systems
Chilled-Water Plant
Electrical Systems
UPS
PDU
Lighting
Onsite generation
Impact
HVAC Systems
Electrical Systems
Total
24
Appendix G: Detailed Energy Savings
(One table for each Primary System: IT Equipment, HVAC Systems, and Electrical Systems)
Impact
Total
Footnote 1:
N = Near-Term
M = Medium-Term
L = Long-Term
25
Appendix H: Identified Actions
(One table for each Primary System: IT Equipment, HVAC Systems, and Electrical Systems)
# Opportunity Action(s)
26
Appendix I: Assessment Participants (attendance)
27
Appendix J: Assessment Evaluation
28
Resources
Shehabi, Arman, Sarah J. Smith, Eric Masanet and Jonathan Koomey. 2018. “Data center growth
in the United States: decoupling the demand for services from electricity use” Environmental
Research Letters, Volume 13, Number 12. Dec. 18, 2018
https://iopscience.iop.org/article/10.1088/1748-9326/aaec9c/meta
29