Exercise -1:
1. Create a New Project in MS Project: BidSubmision
2. Create two levels of WBS for this project as given below:
Page 1 of 4
MS Project
2.Gather Technical
Documentation 2.2.1 Send to Technical Personnel 1 2.1.2
2.2 Manage
Technical Collection 2.2.2 Meetings with Tech Dept 10 2.2.1
3.Gather Financial
Documentation 3.2.1 Send to Financial Personnel 1 3.1.2
3.2 Manage
Financial Collection 3.2.2 Meetings with Fin Dept 12 3.2.1
5. Insert Milestone:
- At the end of Compile & Submit Docs in the Gather Financial Documentation, insert a Milestone-
“Review Readiness”.
- Change relationships -> (i) Remove the predecessors of Bind Documents and add that predecessors to
this milestone-“Review Readiness”. Make Bind Documents as successor of this Milestone.
Page 2 of 4
MS Project
Page 3 of 4
MS Project
RESOURCE $/hour
MarEx 18
PrintEx 15
Ana 16
BidMan-Tech 27
Marissa 20
BidMan-Fin 28
Alex 15
Tanya 20
Desjardine 15
Clark 15
Exercise 9: Export project data to an Excel File. Save this file for submission
Exercise 10: Set Baseline: