DOW - ROM - Cleaning Tips
DOW - ROM - Cleaning Tips
FILMTEC Membranes
Cleaning and Sanitization: Cleaning Tips
Cleaning Tips 1. It is strongly recommended to clean the stages of the RO or NF system separately. This is
to avoid having the removed foulant from stage 1 pushed into the 2nd stage resulting in
minimal performance improvement from the cleaning. If the system consists of 3 stages,
stage 2 and stage 3 should also be cleaned separately. For multi-stage systems, while
each stage should be cleaned separately, the flushing and soaking operations may be
done simultaneously in all stages. Fresh cleaning solution needs to be prepared when the
cleaning solution becomes turbid and/or discolored. High-flow recirculation, however,
should be carried out separately for each stage, so the flow rate is not too low in the first
stage or too high in the last. This can be accomplished either by using one cleaning pump
and operating one stage at a time, or by using a separate cleaning pump for each stage.
If the RO system suffers from colloidal, organic fouling or biofouling in combination with
calcium carbonate, then a two-step cleaning program will be needed: alkaline cleaning
followed by an acid cleaning. The acid cleaning may be performed when the alkaline
cleaning has effectively removed the organic fouling, colloidal fouling and biofouling.
3. Always measure the pH during cleaning. If the pH increases more than 0.5 pH units
during acid cleaning, more acid needs to be added. If the pH decreases more than 0.5
pH units during alkaline cleaning, more caustic needs to be added.
4. Long soak times. It is possible for the solution to be fully saturated and the foulants can
precipitate back onto the membrane surface. In addition, the temperature will drop during
this period, therefore the soaking becomes less effective. It is recommended to circulate
the solution regularly in order to maintain the temperature (temperature should not drop
more than 5°C) and add chemicals if the pH needs to be adjusted.
5. Turbid or strong colored cleaning solutions should be replaced. The cleaning is repeated
with a fresh cleaning solution.
6. If the system has to be shutdown for more than 24 hours, the elements should be stored
in 1% w/w sodium metabisulfite solution.