Social Networking
Social Networking
Graph Theory
It provides a set of abstract concepts and methods for the analysis of graphs.
These, in combination with other analytical tools and with methods developed
specifically for the visualization and analysis of social (and other) networks, form the
basis of what we call SNA methods.
• Weighted strengths
• Network topology
• Linked networks
What is a Network?
Undirected relations
o Attended meeting with
o Communicates daily with
Directed relations
o Lent money to
Logically vs empirically directed ties
o Empirically, even undirected relations can be non- symmetric due to
measurement error
Group “is the collection of all actors on which ties are to be measured”
(Wasserman/Faust 2008:19)
Subgroup of actors is defined “as any subset of actors, and all ties among them”
(Wasserman/Faust 2008:19)
Actors in a group “belong together in a more or less bounded set (…) consists of
a finite set of individuals on which network measurements are made”
(Wasserman/Faust 2008:19)
“however, in research applications we are usually forced to look at finite
collections of actors and ties between them.” (Wasserman/Faust 2008:20)
A. SCHEDULING METHOD
Project schedule network analysis is an analytical technique to identify critical path and
list of critical project activities. It further specifies the degree of schedule flexibility in a
given network logic. The output of this analysis is a schedule model. This project
schedule model serves as a basis for further project execution, analysis, and reporting.
Critical Path Method (CPM) is the most common schedule analysis technique.
The Schedule network analysis allows all stakeholders are aware of activities that
define project success. It is an essential project management tool that finds application
in not only schedule development but also schedule control process.
Following are some of the advantages of performing project schedule network analysis
In PDM technique nodes represent the schedule activities. A graphical link between the
nodes establishes logical relationships. The links also shows the sequence of
performing the schedule activities. Activity-On-Node (AON) is one such method of
representing the schedule network logic using the PDM technique. Critical Path Method
(CPM) uses AON method for constructing the project schedule network diagram.
Following are the two most popular project network analysis techniques.
Program evaluation and review technique uses three point estimation to calculate the
duration estimates. However, PERT is used mainly to control the time aspect of
projects.
Critical Path Method (CPM) is the most common schedule network analysis
methodology. CPM analysis also calculates early start, early finish, late start and late
finish with ease. Moreover, CPM is used mainly to control both time and cost aspects of
the project.
Schedule network analysis technique chiefly identifies the critical path. Both PERT and
CPM aim to establish critical path and critical activities of a project. The following
snapshot enumerates critical path characteristics.
Any systematic display of the logical relationship between the project’s activities.
It is always depicted from left to right to of the logical show the chronological
sequence of project execution.
Vulgarly known as PERT network.
The diagram shows the interrelationships between all activities in a project
REFERENCE:
https://www.slideshare.net/ricardo.vargas/ricardo-vargas-diagrama-rede-projeto-ppt-en
https://milestonetask.com/schedule-network-analysis/#.Xk2PX4hS-M-
https://slideplayer.com/slide/4631158/?fbclid=IwAR1EqA6aYMwZmaPqLa9Z_AEbv-
AmdNICtmpRNR6uatrzT0gu0EENl3RLHcc