Nozzle Final Dimension
Nozzle Final Dimension
SCH.
1 LG2 2" 300# WNRF At 225˚ At 225˚ 200 mm from T.L 200 mm from T.L 1280 mm from C/L 1281 mm from C/L ACCEPTABLE
XXS
Signature : Signature :
Date : Date :
GEMINI ENGI-FAB LIMITED
INTERNAL INSPECTION REPORT Date : 10.07.2023
Stage of Inspection / Tests Job No. :11529A/HE
A : Material B : Interim C : Re-Inspection D : Final
Client : Indian Oil Corporation Limited ProjectQty
Equpt. : LUPEC(J-18)
: 01 No. Inspection Agency :
Equipment Name : REGENERATOR REBOILER
VCS
P.O. NO. & Date: 77154/109/27621024 DT: 02.03.2022
ITP NO: 077154C-000-SR-0610-001B-B1002-0004
Drawing No. : 077154-000-SR-0610-001B-A2001-0007, Rev:05 EQPT. No. : 1814-E-002A
FINAL NOZZLE VISUAL & DIMENSION ON MAIN SHELL AS BELOW.
Sr. Nozzle Nozzle SCH. Orientation Elevation Projection
Rating/Type Remark
No. No. Size THK Reqd. Actual Reqd. Actual Reqd. Actual
SCH 1250 mm from sliding 1251 mm from 1470 mm from centre 1473 mm from
1 N3 10" 300# WNRF At 180˚ At 180˚ ACCEPTABLE
100 saddle sliding saddle line centre line
SCH 2100 mm from fixed 2103 mm from fixed 1470 mm from centre 1475 mm from
2 N4 10" 300# WNRF At 180˚ At 180˚ ACCEPTABLE
100 saddle saddle line centre line
Signature : Signature :
Date : Date :
GEMINI ENGI-FAB LIMITED
INTERNAL INSPECTION REPORT Date : 10.07.2023
Stage of Inspection / Tests Job No. :11529A/HE
A : Material B : Interim C : Re-Inspection D : Final
Client : Indian Oil Corporation Limited ProjectQty
Equpt. : LUPEC(J-18)
: 01 No. Inspection Agency :
Equipment Name : REGENERATOR REBOILER
VCS
P.O. NO. & Date: 77154/109/27621024 DT: 02.03.2022
ITP NO: 077154C-000-SR-0610-001B-B1002-0004
Drawing No. : 077154-000-SR-0610-001B-A2001-0007, Rev:05 EQPT. No. : 1814-E-002A
FINAL NOZZLE VISUAL & DIMENSION ON MAIN SHELL AS BELOW.
Sr. Nozzle Nozzle SCH. Orientation Elevation Projection
Rating/Type Remark
No. No. Size THK Reqd. Actual Reqd. Actual Reqd. Actual
SCH
1 V1 2" 300# WNRF At 0˚ At 0˚ 2250 mm from N5 2252 mm from N5 1470 mm from C/L 1472 mm from C/L ACCEPTABLE
XXS
SCH
2 D 2" 300# WNRF At 180˚ At 180˚ 1750 mm from N3 1752 mm from N3 1470 mm from C/L 1475 mm from C/L ACCEPTABLE
XXS
SCH
3 LT1 2" 300# WNRF At 45˚ At 45˚ 200 mm from T.L 199 mm from T.L 1280 mm from C/L 1280 mm from C/L ACCEPTABLE
XXS
SCH
4 LT2 2" 300# WNRF At 135˚ At 135˚ 200 mm from T.L 203 mm from T.L 1280 mm from C/L 1280 mm from C/L ACCEPTABLE
XXS
SCH
5 LG1 2" 300# WNRF At 315˚ At 315˚ 200 mm from T.L 200 mm from T.L 1280 mm from C/L 1280 mm from C/L ACCEPTABLE
XXS
Signature : Signature :
Date : Date :
GEMINI ENGI-FAB LIMITED
INTERNAL INSPECTION REPORT Date : 17.07.2023
Stage of Inspection / Tests Job No. :11529B/HE
A : Material B : Interim C : Re-Inspection D : Final
Client : Indian Oil Corporation Limited ProjectQty
Equpt. : LUPEC(J-18)
: 01 No. Inspection Agency :
Equipment Name : REGENERATOR REBOILER
VCS
P.O. NO. & Date: 77154/109/27621024 DT: 02.03.2022
ITP NO.: 077154C-000-SR-0610-001B-B1002-0004
Drawing No. : 077154-000-SR-0610-001B-A2001-0007, Rev:01 EQPT. No. : 1814-E-002A
FINAL NOZZLE VISUAL & DIMENSION ON BARREL SHELL AS BELOW.
Sr. Nozzle Nozzle SCH. Orientation Elevation Projection
Rating/Type Remark
No. No. Size THK Reqd. Actual Reqd. Actual Reqd. Actual
SCH.
1 LG2 2" 300# WNRF At 225 At 225 200 mm from T.L 203 mm from T.L 1280 mm from C/L 1281mm from C/L ACCEPTABLE
XXS
At 180˚
At 180˚ ( offset
SCH. ( offset of
3 U2 2" 300# WNRF of 775 dishend 850 mm from T.L 849 mm from T.L 850 mm from T.L 850 mm from T.L ACCEPTABLE
XXS centre)
775 dishend
centre)
Signature : Signature :
Date : Date :
GEMINI ENGI-FAB LIMITED
INTERNAL INSPECTION REPORT Date :17.07.2023
Stage of Inspection / Tests Job No. :11529B/HE
A : Material B : Interim C : Re-Inspection D : Final
Client : Indian Oil Corporation Limited ProjectQty
Equpt. : LUPEC(J-18)
: 01 No. Inspection Agency :
Equipment Name : REGENERATOR REBOILER VCS
P.O. NO. & Date: 77154/109/27621024 DT: 02.03.2022
ITP NO. & Date: 077154C-000-SR-0610-001B-B1002-0004
Drawing No. : 077154-000-SR-0610-001B-A2001-0007, Rev:01 EQPT. No. : 1814-E-002A
FINAL NOZZLE VISUAL & DIMENSION ON CHANNEL SHELL AS BELOW.
Sr. Nozzle Nozzle SCH. Orientation Elevation Projection
Rating/Type Remark
No. No. Size THK Reqd. Actual Reqd. Actual Reqd. Actual
SCH.
1 V1 2" 300# WNRF At 0˚ At 0˚ 1300 mm from N5 1300 mm from N5 1470 mm from C/L 1473 ACCEPTABLE
XXS
SCH.
2 D 2" 300# WNRF At 180˚ At 180˚ 1750 mm from N4 1750 mm from N4 1470 mm from C/L 1471 ACCEPTABLE
XXS
SCH.
3 LT1 2" 300# WNRF At 45˚ At 45˚ 200 mm from T.L 200 mm from T.L 1280 mm from C/L 1282 ACCEPTABLE
XXS
SCH.
4 LT2 2" 300# WNRF At 135˚ At 135˚ 200 mm from T.L 200 mm from T.L 1280 mm from C/L 1280 ACCEPTABLE
XXS
SCH.
5 LG1 2" 300# WNRF At 315˚ At 315˚ 200 mm from T.L 200 mm from T.L 1280 mm from C/L 1281 ACCEPTABLE
XXS
Signature : Signature :
Date : Date :
GEMINI ENGI-FAB LIMITED
INTERNAL INSPECTION REPORT Date : 17.07.2023
Stage of Inspection / Tests Job No. :11529B/HE
A : Material B : Interim C : Re-Inspection
Equpt. Qty : 01 No. D : Final
Client : Indian Oil Corporation Limited Project : LUPEC(J-18) Inspection Agency :
Equipment Name : REGENERATOR REBOILER
VCS
P.O. NO. & Date: 77154/109/27621024 DT: 02.03.2022
ITP NO. & Date: 077154C-000-SR-0610-001B-B1002-0004
Drawing No. : 077154-000-SR-0610-001B-A2001-0007, Rev:01 EQPT. No. : 1814-E-002A
FINAL NOZZLE VISUAL & DIMENSION ON MAIN SHELL AS BELOW.
Sr. Nozzle Nozzle SCH. Orientation Elevation Projection
Rating/Type Remark
No. No. Size THK Reqd. Actual Reqd. Actual Reqd. Actual
SCH 300# 2250 mm from 2250 mm from 1470 mm from 1472 mm from
1 V1 2" At 0˚ At 0˚ ACCEPTABLE
XXS WNRF N5 N5 C/L C/L
SCH 300# 1750 mm from 1750 mm from 1470 mm from 1473 mm from
2 D 2" At 180˚ At 180˚ ACCEPTABLE
XXS WNRF N3 N3 C/L C/L
SCH 300# 200 mm from 200 mm from 1470 mm from 1472 mm from
3 LT1 2" At 45˚ At 45˚ ACCEPTABLE
XXS WNRF T.L T.L C/L C/L
SCH 300# 200 mm from 200 mm from 1470 mm from 1470 mm from
4 LT2 2" At 135˚ At 135˚ ACCEPTABLE
XXS WNRF T.L T.L C/L C/L
SCH 300# 200 mm from 200 mm from 1470 mm from
5 LG1 2" At 315˚ At 315˚ 1473 mm from C/L ACCEPTABLE
XXS WNRF T.L T.L C/L
All dimension are in 'mm' unless otherwise specified.
Visual Inspection is carried out and found satisfactory.
Measuring instruments:- 1) measuring tape: MT-04, Due date:01.02.2024.(5 Meter)
2) measuring tape: MT-02, Due date:01.02.2024.(30 meter)
For Gemini Engi-Fab Limited For VCS
Name : Name :
Signature : Signature :
Date : Date :