Ceramic Tile Method Statement
Ceramic Tile Method Statement
This flooring tiles activity should be performed with strict compliance and
implementation of project safety, requirement, quality procedure and project.
Specifications to complete the work both the floor and wall tiling works.
When materials are delivered. M/s Reliant Contracting will Check, examine
marks and the condition of material and components ,tile sizes, thickness and
colors are as grouts are as specified and are suitable for the conditions to which
the tiling will be used.
Ceramic Tiles
Cement
Black Sand
Grout Material
Diamond Cutter
Sprit Levels
Tile Spacers
Scaffolding
Measuring Tapes
Steel Trowels
Other Tools
Preparatory Requirements
M/s Reliant Contracting shall clean of completed floor slab and masonry
wall prior for start survey marking and layout .Layout and put marking on
Ceramic Tile Method Statement
the concrete floor slab the correct tile layout and make sure it is aligned
with the markings on the masonry wall for tiles.
M/s shall provide temporary lumber for guide/references to check plumb
and alignment.
We do not begin tiling work until all concealed conduits, pipes, electrical
boxes, etc., that penetrate the tiling have been fixed securely in position
and making good is completed.
Also we ensure that waterproofing for wet areas are already done including
leak test before tile works.
We discard any tiles that are chopped or cracked.
Cut tile neatly and accurately.
M/s Reliant Contracting will make sure all works comply with safety
procedure or instruction as set out in project safety plan rules and
regulations.
And urban safety personnel will be on site during work.
Qualified and skilled worker should be assign to the installation.
All field personnel shall be required to wear their PPE.
Preparatory meet should be conducted before start the work.
Provide lighting when work at night.
Provide scaffolding when work at height.
Tiles must be correctly positioned at the time they are placed and laid with
joints.
Use 2mm PVC tile spacers to keep the joint of each tile.
Control the overall level of the finished floor.
Provide slope going to floor drain (areas with floor drain).
Set out the tiling width joints of consistent width, ensuring they are
horizontal and parallel.
Cleaning the tiles from dirty cement or mortar.
Remove all the PVC spacer before grouting.
Use the approved grout and apply the grout in every joint smooth, level
and clean application.