Ceramic Tile Method Statement

Uploaded by

adilazam608
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 4

Ceramic Tile Method Statement

Ceramic Tile Method Statement


The purpose of this civil work method statement is to outline and describe in
details the procedure such as setting and lay-out plan on actual location, laying of
tiles, final laying of tiles and all other related activity.

This flooring tiles activity should be performed with strict compliance and
implementation of project safety, requirement, quality procedure and project.

Specifications to complete the work both the floor and wall tiling works.

When materials are delivered. M/s Reliant Contracting will Check, examine
marks and the condition of material and components ,tile sizes, thickness and
colors are as grouts are as specified and are suitable for the conditions to which
the tiling will be used.

List Mandatory Tools and Materials

 Ceramic Tiles
 Cement
 Black Sand
 Grout Material
 Diamond Cutter
 Sprit Levels
 Tile Spacers
 Scaffolding
 Measuring Tapes
 Steel Trowels
 Other Tools
Preparatory Requirements
 M/s Reliant Contracting shall clean of completed floor slab and masonry
wall prior for start survey marking and layout .Layout and put marking on
Ceramic Tile Method Statement

the concrete floor slab the correct tile layout and make sure it is aligned
with the markings on the masonry wall for tiles.
 M/s shall provide temporary lumber for guide/references to check plumb
and alignment.
 We do not begin tiling work until all concealed conduits, pipes, electrical
boxes, etc., that penetrate the tiling have been fixed securely in position
and making good is completed.
 Also we ensure that waterproofing for wet areas are already done including
leak test before tile works.
 We discard any tiles that are chopped or cracked.
 Cut tile neatly and accurately.

Health and Safety Requirements

 M/s Reliant Contracting will make sure all works comply with safety
procedure or instruction as set out in project safety plan rules and
regulations.
 And urban safety personnel will be on site during work.
 Qualified and skilled worker should be assign to the installation.
 All field personnel shall be required to wear their PPE.
 Preparatory meet should be conducted before start the work.
 Provide lighting when work at night.
 Provide scaffolding when work at height.

Procedure For Floor Tiling Work:

M/s Reliant Contracting shall:

 Establish a datum level for finished floor.


 Clean the floor slab remove/chip harden mortar and concrete. All area of
slab should at the required level.
 After cleaning the slab mix cement, black sand at the area where the
installation occurs.
 Follow the approved drawings where the first tiles location installed, first
tile should be the guide for installation.
Ceramic Tile Method Statement

 Tiles must be correctly positioned at the time they are placed and laid with
joints.
 Use 2mm PVC tile spacers to keep the joint of each tile.
 Control the overall level of the finished floor.
 Provide slope going to floor drain (areas with floor drain).
 Set out the tiling width joints of consistent width, ensuring they are
horizontal and parallel.
 Cleaning the tiles from dirty cement or mortar.
 Remove all the PVC spacer before grouting.
 Use the approved grout and apply the grout in every joint smooth, level
and clean application.

Wall Tiles Installation Work

M/s Reliant Contracting Shall:

 Provide a rough wall finish of plastering prior to receive wall tiles.


 Establish datum line should be parallel and align with the floor layout.
 Tile layout plan shall be made in accordance with the approved shop
drawings
 The use of approved adhesive.
 Clean the tiles from dirty cement or mortar.

Tile Outer Corner Wall Joint Installation

M/s Reliant Contracting shall:

 Remove all PVC spacer before grouting.


 Use the approved grout and apply the grout in every joint smooth, level
and clean application.
 Cut and fit tiling neatly around pipes, electrical boxes, etc.
 Damage, hollow surface installed tiles should be removed and replaced.

Protecting and Cleaning of Tiling Work

M/s Reliant Contracting shall:


Ceramic Tile Method Statement

 We not permit any traffic at all on floor.


 Provide adequate protection if heavy loads are to be moved across the
flooring.
 Brush of loose materials, wash with clean water and remove surplus water
with cloth.

Inspection Checklist for Tiling Work

M/s Reliant Contracting shall:

A) Check Before Installation:-


 Check setting out and surface preparation.
 Clean, free of any debris.
 Waterproof applied and tested.
 Services within floor and wall have been tested & approved.
 Starting tile.
B) Check After Installation:-
 Level.
 Layout.
 Alignment.
 Slope going to drain.
 No defective tiles was been installed.
 Grouting application is even, smooth and level.
 Proper cutting of tile, no chipped or broken edges.
 Protection for the installed tiles especially floor tiles.
 Housekeeping.