Parametric - Analogous - Three-Point Estimating - P1 - Practice Test
Parametric - Analogous - Three-Point Estimating - P1 - Practice Test
10. **Which of the following best describes the type of projects where analogous estimating is most
effective?**
a) Unique projects with no historical data
b) Projects that are similar to previous projects
c) Projects with a high degree of uncertainty
d) Small projects with detailed cost information
**Answer:** b) Projects that are similar to previous projects
12. **The formula for calculating the three-point estimate (using the PERT method) is:**
a) (Optimistic + Pessimistic + Most Likely) / 3
b) (Optimistic + Pessimistic + (4 * Most Likely)) / 6
c) (Optimistic + Pessimistic + (2 * Most Likely)) / 4
d) (Optimistic + Most Likely + (4 * Pessimistic)) / 6
**Answer:** b) (Optimistic + Pessimistic + (4 * Most Likely)) / 6
15. **In three-point estimating, which estimate represents the most pessimistic scenario?**
a) Optimistic estimate
b) Most likely estimate
c) Pessimistic estimate
d) Average estimate
**Answer:** c) Pessimistic estimate
16. **Which estimating technique would be most appropriate for a high-level, early project estimate?**
a) Bottom-up estimating
b) Parametric estimating
c) Analogous estimating
d) Three-point estimating
**Answer:** c) Analogous estimating
18. **Which of the following techniques can provide a range of possible estimates rather than a single
value?**
a) Parametric estimating
b) Analogous estimating
c) Three-point estimating
d) Bottom-up estimating
**Answer:** c) Three-point estimating
19. **In which estimating technique is the accuracy highly dependent on the quality of the historical data
used?**
a) Three-point estimating
b) Analogous estimating
c) Parametric estimating
d) Expert judgment
**Answer:** c) Parametric estimating
20. **Which estimating method is likely to produce the most accurate estimates if detailed project
information is available?**
a) Parametric estimating
b) Analogous estimating
c) Three-point estimating
d) Bottom-up estimating
**Answer:** d) Bottom-up estimating