Leed Exam AP BD C
Leed Exam AP BD C
1- LEED PROCESS:
1-Which design decisions can earn a project IN Credit for exemplary performance?
B. Purchasing 50%, by cost, of the total value of permanently installed building products
meet the responsible extraction criteria.
2-Which project would not meet the minimum program requirements for certification?
B. A modular classroom that can be moved to another location on the school property.
3-The project team for an office building is considering a composting program. Which
statement is true regarding the IN Credit Innovation for a composting program?
C. IN Credit Innovation can only be earned if all occupants of the building are allowed to
participate in the program.
4-If a project boundary is not obvious because of ownership by multiple entities, which
action should the project team take?
5-Which project strategy would earn an exemplary performance point under IN Credit
Innovation Option 3 Additional Strategies?
A. Manage 100% of the rainwater that falls within the project boundary.
6-A project team wishes to get a Credit Interpretation Request on a credit and
prerequisite that are unrelated. Which action will assist with this process?
C. Submit two CIRs: one for the credit and one for the prerequisite.
7-A project team member finds an issue not addressed in the LEED reference guide
regarding indoor plumbing fixtures and submits a suggested approach to the credit
during the standard LEED review process. What is true about this approach?
A. They will receive a determination in the review comments at the discretion of the
reviewer assigned to the project.
8-Which project strategy would earn an exemplary performance point under IN Credit
Innovation Option 3 Additional Strategies?
B. Doubling the highest transit service point threshold for alternative transportation.
10-The LEED Pilot Credit for Occupant Engagement is listed only for the O+M rating
systems. What is true about a LEED BD+C project's ability to use the credit on the
project?
C. If the pilot credit does not have your rating system listed as applicable; the project
cannot pursue the pilot credit.
11-The owner of a space has had a lot of turnover in the project team, resulting in
delays in LEED documentation. How long can the project team wait to submit the
construction phase review?
12-How can a project team avoid errors and expenses in LEED documentation prior to
submitting the project for review?
C. Verify that numeric values (FTE, site area, etc.) are consistent across credits.
13-The LEED project boundary may not include land that is owned by a party other than
that which owns the LEED project unless:
B. The land is associated with and supports normal building operations for the LEED
project building.
14-Which of the following may earn a project IN Credit Innovation for Innovation?
B. Platted property line of the project defining land and water within it.
16-A LEED AP in a goal setting workshop is working on their first LEED BD+C: Schools
project. What prerequisites would be applicable to the project and need to be assigned
to team members?
17-Which project strategy would earn an exemplary performance point under IN Credit
Innovation Option 3 Additional Strategies?
18-A team member is reviewing the LCA narrative for MR Credit Building Life-Cycle
Impact Reduction Option 4 Whole-Building Life Cycle Assessment. What table is going to
be included in the narrative?
B. Table showing the percent changes for all impact indicators between the baseline and
proposed buildings.
19-A 2-story mixed use project will have retail space on the first floor and hospitality
space on the second floor. Since there more than two rating systems that might be
applicable to a project, how should the project team decide which rating system to use?
D. If an appropriate rating system falls between 40% and 60% of the gross floor area,
project teams must independently assess their situation and decide which rating system
is most applicable.
20-A hotel project in a historic district requests that the walk off mats in the primary
direction of travel for the main building's entrance be less than 10 feet (3 meters) long
due to the constraints of the historic building porch depths. Who should address this
request?
21-During an early design review, a project team has decided to consolidate the
building footprint and add underground parking. These changes can contribute to
earning which credits?
22-A national park located in MLO lighting zone 2 has walking paths around a lake, a
150-car parking lot, a national flag in front of the visitors center, and a small
amphitheater for giving presentations. The road leading to the park has government
mandated lighting. What exterior lighting would be exempt from SS Credit Light
Pollution Reduction?
23-A project team for a LEED BD+C Healthcare is in a goal setting workshop. What
credits would be applicable to the project and need to be assigned to team members?
A. SS Credit Places of Respite, SS Credit Direct Exterior Access, MR Credit PBT Source
Reduction – Mercury.
24-The LEED reviewer response from a preliminary review indicates a project will be 1
point short of LEED Platinum. What should the project team do if they still want to
pursue LEED Platinum?
LEED AP BD+C QUESTIONS
A. Submit new or revised documentation for credits that were denied or require more
information, or attempt additional credits before submitting the final review.
25-A LEED reviewer has sent a project team technical advice on one of the design
credits that was submitted in a split review. What does the project team need to do?
26-A project was registered in January of 2013. In April 2013 USGBC published Addenda
for a credit the project team is pursuing. What statements are true regarding this
project?
B. The project team can choose to follow any addenda published after April, 2013 .
D. The project team must follow any addenda published prior to January, 2013.
C. An off-site amenity.
28-Which part of the LEED development cycle is used for streamlining the approach to
particular needs, constraints, and opportunities of different project types?
B. Adaptations.
29-A LEED BD+C project will be constructed and operated on a permanent location on
existing land, and will be a minimum of 1,000 SF (93 m2). What else must the project do
to meet the minimum program requirements?
C. The project boundary must include all contiguous land that is associated with the
project and supports its typical operation.
30-A project team in a goal-setting meeting is discussing potential sites and integrative
synergies. What strategy would earn the project a LEED credit?
C. Locating the site in an area with a combined surrounding density of 22,000 SF / acre
(5,050 m2 / hectare) of buildable land.
31-Which elements are not covered under the LEED BD+C: Core and Shell rating
system?
D. Tenant fit-out.
32-Which action is an example of an overlapping benefit that a project team might find
during ongoing discovery while iteratively testing alternatives and refining an analysis?
LEED AP BD+C QUESTIONS
C. Using the waste heat from a mechanical system to heat hot water.
A. Achieve double the requirements or meet the next incremental percentage threshold
of an existing LEED credit.
34-Which design decisions can earn a project IN Credit Option 1 Innovation in a new
construction project?
C. Green housekeeping program that uses cleaning chemicals approved by Green Seal.
35-A 100,000 SF (9,290 m2) new office building will have mixed-mode ventilation and
steam boilers. The building owner wants to hire a consulting firm owned by a relative for
the Cx process. What is true about this decision?
C. The firm can be hired if they have worked on at least two other projects that were
around 100,000 SF (9,290 m2) in size and had mixed-mode ventilation and steam
boilers.
36-A project has achieved one pilot credit, has earned exemplary performance in three
credits, and has used a strategy for innovation. How many points would this project
earn?
B. 4.
37-Which project strategy would earn an exemplary performance point under IN Credit
Innovation Option 3 Additional Strategies?
38-A 10 acre multi-building development has five buildings. How is the LEED boundary
determined if each building will be a separate LEED project?
D. The project team determines the LEED boundary for each LEED project.
40-A team in a goal setting-workshop has selected to pursue LEED Gold, identified
credits to pursue and assigned responsible parties to each credit and prerequisite. After
evaluating possible energy strategies what does the team need to document for IP
Credit Integrative Process?
A. How the analysis informed the design decisions in the OPR and BOD.
LEED AP BD+C QUESTIONS
41-A project building that originally registered as one building has undergone a design
change and now has two different structures. Which action should be taken to
determine if the building can remain a single project?
42-A project team member has excluded a section of land in order to meet the
requirements of one of the LEED credits. Which statement is true about this action?
43-An office complex near a lake is being designed. The project will be built on a prime
tract of undeveloped real-estate 40 ft. (12 meters) from the lake. The project will be
located 1/8 mile (200 meters) from 3 public bus lines.
2-Integrative Strategies:
1-A project team has hired a LEED consultant to assist them with their first LEED
project. What will the consultant need to tell the project team to take photographs
of if they choose to pursue those credits?
2-Identifying at least one on-site, non-potable water source that could be used to offset
water demand is required for which credit?
D. Integrative Process.
3-A new government office building will provide individual occupant controls for lighting.
What design strategy would most reduce the operational energy use associated with
task lighting?
4-If a project team is pursuing both the Integrative Process credit and EA Credit
Optimize Energy Performance, which action should occur first?
5-Which situation might be a result of addressing the surrounding density and diverse
uses early in the integrative process?
6-During the design phase of a new commercial development the design team finds that
changing the orientation of the building and adding exterior horizontal louvers above
the South-facing windows will be beneficial. Which credit would NOT be affected by
these changes?
7-A project team is removing cisterns from a project design and will install a green roof
instead. The building has a FAR of 1.7. What project area would this change impact the
least?
8-A project moved beyond the design phase before a green-building consultant was
asked to join the project team. The building owner wants to hear about design
strategies that can have minimal impact on the project budget. The design consultant
suggests using light-colored pervious paving in lieu of a black asphalt parking lot. This
design strategy would assist in all of the following credits EXCEPT:
LEED AP BD+C QUESTIONS
9-What is the benefit of preparing a concept model for compliance with the Integrative
Process credit?
C. It can form the basis of the preliminary energy model for a whole-building energy
simulation.
10-Which action would NOT earn a project an Innovation credit for a LEED BD+C: New
Construction project?
A. Discovery.
12-Which action must a project team take for implementation of the Integrative Process
credit?
B. Document how the analysis informed building and site design decisions in the
project's OPR and BOD.
13-A project team has convened to identify targeted LEED credits, identify initial
responsibilities and deliverables, and identify potential integrative strategies for
achieving performance targets. What is their next step in the project timeline?
14-Which statement is true regarding a project team's ability to use the water budget
from a school project and apply it to an office project?
A. The application of the school project's water budget will not apply to the office
project because water budgets are project-specific.
16-A project team has completed preliminary energy and water research and analysis
that will help with the discussions for integrative design opportunities. What should be
the project team's next step?
17-Which water-budget information provides enough data for use in the Discovery
phase of water-related systems?
A. A week's worth of data showing that 5,000 gallons (18,900 liters) of water will be
used.
18-A project team for a new hospital is having an integrative design charrette to discuss
the budget, schedule, and functional programmatic requirements, health mission
statement, credits to target and the LEED certification level. What will the project team
need to document from the charrette for IP Prerequisite Integrative Project Planning and
Design?
A. Narrative explaining how the health mission statement addresses the credit
requirements and a plan of action.
19-A building design includes such green building strategies as a vegetated roof, task
lighting, photovoltaic cells, and operable windows. What credit will these design
strategies NOT help achieve?
C. EQ Credit Daylight.
20-For which reason would it be suggested that someone review the ANSI Consensus
National Standard Guide 2.0 for Design and Construction of Sustainable Buildings and
Communities?
21-A project team has discovered local code allows the collection of rainwater for
irrigation use and offsetting potable water use to reduce indoor water demand and
process water demand. If the project wants to earn Integrative Process credit, rainwater
must be incorporated into how many water demand components (indoor, outdoor,
process)?
A. 2.
22-A LEED AP is exploring possible strategies for a building's energy related systems.
Which aspects must be evaluated for a simple box energy model to earn Integrative
Process credit?
23-Which documentation do project teams need to submit for Integrative Process credit?
D. Engagement of the owner and primary project team, setting a target certification
level, picking LEED credits and assigning responsibilities.
D. Rainwater collection can be used for both SS Credit Rainwater Management and WE
Credit Outdoor Water-Use Reduction.
A. The contractor is responsible for filling out the checklist and returning it to the CxA.
28-A building owner and primary project team have convened for a goal-setting
workshop. Which factors are examples of what would NOT be determined in the
workshop?
29-A project team for a 3-story mixed-use project wants to increase the daylighting of
the store on the ground floor to help the owner better display products for sale. What
factors are critical for allowing more daylight into the building?
32-Which factors are aided by establishing regular meeting dates and clear
communication channels?
E. Discovery.
34-Energy-related research for the Integrative Process credit should include all EXCEPT
which element?
D. Contractor.
36-A hospital project's preliminary energy model reveals high internal loads. Which
suggestion would reduce energy use?
D. Provide daylighting.
37-In the integrative process, which statement is true about how the energy and water
systems should be analyzed to identify the most synergies?
D. The energy and water systems should be analyzed at the same time.
39-Which project team members' presence on a project would help meet the
requirements of multiple credits for a prospective LEED BD+C: Data Center?
40-A project team is reviewing a simple box energy model for a large commercial
building dominated by external loads. Which strategy can help decrease envelope
loads?
B. Increasing the insulating value of the glazing and window frame system .
41-A new library will have a 5% energy improvement over a baseline building. The
project team is considering increasing ventilation. The project uses mechanical
ventilation. This change could have a negative impact on:
42-Which action does a project team need to take in the discovery phase for water-
related systems to earn IP Credit Integrative Process?
B. Identify at least one on-site, non-potable water source that could supply a portion of
at least two demand components.
44-An owner, architect, and general contractor in a goal-setting workshop for a school
project are discussing how installing a large quantity of skylights in the building's roof
would increase daylighting in the core of the building. What could help them with this
decision and help with earning IP Credit Integrative Process?
45-A new 10 story office building will be built in an arid region. Installing occupancy
sensors would impact which credits?
46-The design of a new five-story school includes plans for using stone from local
quarries, a rainwater harvesting system, stacking the building program, solar thermal
roof panels to heat hot water, and open grid paving.
What green building strategies will these design decisions contribute toward?
47-Which tool will assist the project team when conducting a preliminary energy
research and analysis for Integrative Process credit?
48-The coordination of energy and water systems for the Integrative Process credit
should be addressed before which phase?
D. Schematic design.
D. The water required by both the building and the associated grounds.
LEED AP BD+C QUESTIONS
50-A project team for a school wants to increase the daylighting and views for students
in classrooms. What issue should be considered if the design team chooses to increase
the amount of glazing?
51-For Integrative Process credit which factors must project teams assess through
simple box energy modeling before completion of schematic design?
2-A retail project includes 30 FTE and 800 daily visitors. The parking lot will
have 20 employee parking spaces and 100 visitor parking spaces. How many
spaces, and of what type, are needed for LT Credit Green Vehicles?
3-In an urban area an existing building has a parking deck with 200 parking
spaces. A project for a new building adjacent to the parking deck will be
allowed to share 100 of these spaces. When determining the parking
capacity for the project, how should the parking capacity be calculated?
4-A project team is reviewing a map showing an office project, two functional
entrances, transit stop locations, and walking routes and distances to transit
stops. Which transit options do NOT qualify toward LT Credit Access to
Quality Transit?
C. A bus line a 1/4-mile (400-meter) walking distance of the project boundary that
offers transit in only one direction.
5-A retail project has 100 employee parking spaces in the rear of the building
and 500 customer parking spaces in the front of the building. If the project
installs fueling stations for LT Credit Green Vehicles, which distribution
strategy would earn the credit?
B. Ten (10) fueling stations in the front of the building and (2) fueling stations in the
rear of the building.
6-A mixed-use office and retail project has both short and long-term parking.
The office space includes 80 long-term parking spaces, and the retail space
has 30 short-term parking spaces. The space has one main entrance for all
users. How should the preferred parking be allocated?
LEED AP BD+C QUESTIONS
D. By a map showing the project, project boundary, transit stop locations, walking
routes, and distances to those stops.
8-A new construction project has a single parking lot with a capacity of 425
spaces. If the project team includes EVSE for plug-in vehicles, how many and
what type of parking spaces are required for LT Credit Green Vehicles?
9-A developer of a retail store has located the project site in a dense area
with diverse uses. The uses include the following:
Given this information, which of the following uses, if located within a 1/4-mile (800
meter) walking distance of the project site, would earn LT Credit Surrounding
Density and Diverse Uses?
A. A convenience store.
12-A project site located on 140 acres (57 hectares) has the following
densities:
The land area of the residential portion is 70 acres (28 hectares) and has 700
dwelling units.
The land area of the nonresidential portion is 60 acres (24 hectares) or 2,178,000 SF
LEED AP BD+C QUESTIONS
What is true about the project's ability to meet the density requirements of LT Credit
Surrounding Density and Diverse Uses?
D. The project meets both the residential and nonresidential density of the credit.
15-An urban new construction project with a zero lot line will have a roof
vegetated with diverse native and adaptive plants and will be built on a
previously developed lot. The surrounding combined density for the project is
63,157 SF / acre (25,558 m2 / hectare). The total building footprint is 57,860
SF with a FAR of 1.7. The vegetated roof is 25,000 SF. What credit would the
project NOT be able to earn?
17-A LEED BD+C project that wants to maximize the number of points in the
Location and Transportation category should consider locating the project in
which location?
18-When determining the total vehicle parking capacity for a site, which
information should be included?
A. Off-street parking available to the project building's users outside of the project
boundary.
LEED AP BD+C QUESTIONS
19-A project team that selects a high-priority site is likely to fulfill the
requirements of which other credit?
B. By including a vicinity map showing the bicycle network, route, and distance
along the network to eligible destinations.
21-A 90-unit apartment complex in an urban area has 200 residents, 50 peak
visitors, and no employees. How many long-term and short-term bicycle
storage spaces would be required for LT Credit Bicycle Facilities?
22-A developer has purchased two sites next to each other and plans to
combine them in order to develop a new mixed-use project. One of the sites
is on the National Priorities List. Which statement is true about the project's
ability to earn LT Credit High-Priority Site?
A. The project will qualify for the credit, because a portion of the new site is in the
high-priority designated area.
A. Allow telecommuting.
Light rail:
80 weekday trips
60 Saturday trips
50 Sunday trips
Commuter rail:
40 weekday trips
12 Saturday trips
0 Sunday trips
LEED AP BD+C QUESTIONS
Given this information, which statement is true about the transit service and the
project's ability to earn LT Credit Access to Quality Transit?
A. The commuter rail weekend trips can be averaged to meet the minimum
required.
25-A project team is pursuing both LT Credit Reduced Parking Footprint and
LT Credit Green Vehicles. Which statement is true in order for the team to
obtain both of these credits?
D. Enough preferred parking must be provided for both green vehicles and
carpools/vanpools.
26-If a project team is pursuing the option to install EVSE for green parking,
to which requirements regarding charging must the team adhere?
27-A LEED AP is documenting five uses within walking distance of the main
entrance of an office building. What is an acceptable way to document LT
Credit Surrounding Density and Diverse Uses?
C. By including a map showing the project site, location and type of each use, and
walking routes from the main entrance to each use.
D. If the site is within a 1/2-mile (800 meters) driving distance to a freight line.
30-A LEED AP is collecting information about a site that includes the dwelling
units per acre (hectare) and total floor-area ratio per acre (hectare) of
buildings in the surrounding area. What would this information be used for?
31-For a LEED BD+C: School Project, which details will the project team need
to show regarding pedestrian access to the school for LT Credit Access to
Quality Transit?
32-A developer has located an empty building in a historic district that could
be renovated. What should the project team determine next to confirm
whether LT Credit High-Priority Site can be earned?
Given this information, what is the total number of uses and the total number of
eligible uses for LT Credit Surrounding Density and Diverse Uses?
35-A project team is reviewing potential sites that have a diversity of transit
routes. Which site feature would help the project earn more points for LT
Credit Access to Quality Transit?
C. A site served by a bus route and a light rail route for which no one route provides
more than 60% of the total trips.
39-A building owner is reviewing sites that could meet LT Credit Surrounding
Density and Diverse Uses. Which site would earn this credit?
40-A school project is located within 1.5 miles walking distance from 916
students in grades 9-12. The school is expected to have 1,200 students when
complete. The school has built two walking and biking routes, one going
north and the other south. The school has a busing system that uses 6
buses. What is true about the project's ability to earn LT Credit Access to
Quality Transit?
D. Buildable land.
E. Types of buildings.
LEED AP BD+C QUESTIONS
44-On a previously developed site with a water body on the property, which
minor improvements are allowed in the water-body buffer?
C. Bike pathways.
D. Maintenance shed.
B. Complete the building design review phase first, then the LEED ND Plan
certification.
47-A 500,000 SF (46,500 m2) mixed-use building pursuing LEED BD+C: New
Construction includes office space and residential space. The office space
has 102 regular building occupants and 40 peak visitors. The residential
space has 30 units with 40 residents and 20 peak visitors. How many shower
facilities are required for LT Credit Bicycle Facilities?
C. 2.
49-A project site contains a large greenfield area, a pond, and an old parking
lot. The new building design will require building on more than the previously
LEED AP BD+C QUESTIONS
developed area. Which statement is true about the project's ability to earn LT
Credit Sensitive Land Protection?
D. The credit can be earned by not disturbing any sensitive land areas.
C. Forests.
D. 3 spaces.
53-A three-story retail project has a main entrance on the first level. The
building has 420 parking spaces in an attached three-story garage with an
elevator on the second and third levels that allows access to the main
entrance. How many preferred parking spaces are required for LT Credit
Green Vehicles, and where should they be located?
Given this information, which statement is true about the project's ability to earn LT
Credit Surrounding Density and Diverse Uses?
LEED AP BD+C QUESTIONS
D. The project could earn the credit if another use in a different category was within
walking distance.
56-An apartment building pursuing LEED BD+C: New Construction has two
functional building entries. One entrance is within a 1/4-mile (400 meters)
walking distance of a bus stop. The other entrance is within a 1/2-mile (800-
meters) walking distance of multiple stops of a rail station. Each transit route
has service in both directions. Which criterion is true for how these stops
count toward LT Credit Access to Quality Transit?
B. Only trips from one stop of the rail station may be counted.
58-In which ways can a project team influence change if a LEED project is not
already located near a bicycle network or a transit stop?
A. By getting the local government to commit to striping bike lanes or lower the
street speed limit.
B. By seeing if the local transit agency will commit to providing additional service to
the project.
59-Which of the following descriptions does NOT meet the criteria for
sensitive land on which project teams should avoid building?
B. An area with trees more than 6 inches (150 millimeters) in diameter at breast
height.
C. A planned supermarket located in the same building that will be operating within
one year of the LEED project's initial certificate of occupancy.
4- Sustainable site:
B. Luminaries that minimize up light and light trespass from the site.
LEED AP BD+C QUESTIONS
4-A building planned for a previously developed site has a zero-lot-line and a
single flat roof. The project has a FAR of 1.7. Given that the project will earn
LT Credit Surrounding Density and Diverse Uses what additional credits could
be earned by installing an intensive vegetated roof?
B. An ESC Plan.
B. 52,272 SF.
7-A project team has calculated the runoff volume of a project that will need
to be managed. The site includes impervious hardscapes and a parking lot,
as well as preserved open space. How much runoff does the project need to
manage for the 95th percentile storm event for SS Credit Rainwater
Management?
8-A project is located in an area where the local code does not cover all
requirements of the Construction General Permit (CGP), and some of the
local code requirements are less stringent. When developing an ESC plan,
which action should the civil engineer take?
B. A compliant ESC plan must have been in place prior to construction to earn the
prerequisite.
9-A project team must protect which percentage of the greenfield area onsite
from development and construction to earn SS Credit Site Development -
Protect or Restore Habitat?
LEED AP BD+C QUESTIONS
C. 40%.
10-A project team has completed a site assessment and will use the results
to inform decisions about rainwater management. Which factor is the
primary difference in the credit options the project team must follow for SS
Credit Rainwater Management?
11-A project team reviews a project design and finds that the design does not
comply with SS Credit Heat Island Reduction using the standard non-roof/roof
calculation due to the project having multiple roof angles and materials that
fall above and below the minimum SRI and SR values. Which action should
the project team take next?
C. Use the weighted non-roof/roof calculation to see if the design will comply.
12-A lighting designer has completed the lighting boundary for a project site
and is gathering data on luminaires to use for the BUG method for SS Credit
Light Pollution Reduction. Some of the luminaires do not have BUG ratings.
Which action should the project team take next?
B. Use software to calculate the BUG rating for the luminaires that don't have
ratings.
13-A site master plan includes the development of stores, restaurants, and
other businesses. The site is not a LEED-ND project. For a LEED BD+C: New
Construction project that is part of the site master plan, which statement is
true about open space as it relates to SS Credit Open Space?
C. Open space adjacent to the building could count toward the credit.
14-A project team will attempt to replicate the natural land cover conditions
for SS Credit Rainwater Management. All EXCEPT which action could help the
project team estimate the natural land cover conditions?
15-A LEED BD+C: Hospital project located in MLO lighting zone LZ1 has
selected lighting for the parking lot and walkways that have appropriate BUG
ratings. The hospital has a helipad which requires additional lighting. The
additional lighting for the helipad exceeds the minimum vertical illuminance
of SS Credit Light Pollution Reduction. What should the project team do to
earn the credit?
LEED AP BD+C QUESTIONS
A. When lighting is used solely for façade and landscape lighting in MLO lighting
zones 3 and 4, and is automatically turned off from midnight until 6 a.m.
17-Why should a project team for a new office project conduct a site
inventory and corresponding site analysis for project site?
18-A project team has determined a project's lighting zone and is now
working with a lighting designer on the lighting boundary for the project.
Which statement is true about creating the lighting boundary site plan?
B. The lighting boundary can differ from the project boundary if the change is
justified.
A. 60.
C. Adjust the design based on the volume each technique can manage.
22-A project's total site area is 280,000 SF (26,000 m2). The total previously
developed area on site is 100,000 SF (9,290 m2). The building FAR is 1.7.
LEED AP BD+C QUESTIONS
C. $112,000.
24-A project team is designing a parking strategy that will include parking
spaces under cover to mitigate the heat island effect. How should the top
level of each multilevel parking structure be classified and/or calculated?
C. As a non-roof surface if there are parking spaces present or as a roof area if there
are no parking spaces present.
25-Encouraging human interaction with wetland and natural areas for open
space can be accomplished with all of the following EXCEPT:
26-A project site's total area 100,000 SF (9,290 m2), of which 80,000 SF
(7,432 m2) is previously developed. The building has a FAR of 1.8. The
project team is considering installing an 8,000 SF (740 m2) green roof. If the
green roof is installed, how much additional area would need to be restored
to earn SS Credit Site Development - Protect or Restore Habitat?
27-A project team has engaged local experts prior to conceptual design to
help inventory site elements. Which action will be aided by filling out the
USGBC worksheet to document existing site conditions?
28-For international projects using products that may not have SRI values,
which actions should the project team take to make purchasing decisions for
materials that can mitigate the heat island effect?
B. Compare materials listed in the Cool Roof Rating Council Standard Database.
LEED AP BD+C QUESTIONS
30-A project team working on light pollution reduction needs to address all
EXCEPT which factor?
31-Which fact should project teams consider for SS Credit Site Development
Protect or Restore Habitat in an urban versus a rural environment?
C. Urban projects have higher density, which changes the strategies for
development.
32-The total site area (including the building footprint) of a project is 100,000
SF. The project has a FAR of 1.75. How much vegetated area is required to
earn SS Credit Open Space?
B. 7,500 SF.
A. Have 100% underground parking and install a vegetated roof on top of the
building.
35-A project design will include bioretention areas, porous paving, rain
gardens, and pervious decking. Which type of strategies are these?
38-A school will be providing the community with access to some of the
school's facilities including playing fields and a gymnasium. What must be
provided for SS Credit Joint Use of Facilities when a school is providing the
facilities?
39-A project's total site area is 280,000 SF (26,000 m2). At the beginning of a
project, a landscape architect has categorized all areas of a site as either
greenfield (180,000 SF/16,700 m2) or previously developed (100,000
SF/9,290 m2). Which strategy could the project team use to earn SS Credit
Site Development - Protect or Restore Habitat?
D. Preserve the greenfield and restore 30,000 SF (2,787 m2) of the previously
developed area.
A. Helps tenants design and build sustainable interiors and adopt green building
practices.
43-Which strategy is the most effective for reducing overall heat island effect
while additionally supporting the achievement of other LEED credits?
LEED AP BD+C QUESTIONS
B. Limiting the amount of hardscapes on the site and increasing the landscaping
area.
44-A new office project building will be occupied in the month of June when the
weather starts getting hot. Which eligible non-roof inclusions would mitigate the
heat island effect for SS Credit Heat Island Reduction?
45-A project team is planning to restore the soil and habitat of a previously
developed site in parallel. When identifying the areas to be restored, which
elements can the project team exclude from the calculations?
46-Which feature is open space required to have for SS Credit Open Space?
47-Which tool would a project team use to calculate the 95th percentile
rainfall event for SS Credit Rainwater Management?
C. A swimming pool across the street from the school accessible via a continuous
sidewalk.
49-A developer is building an office project in an urban area. The project has
a zero-lot line. Which design feature must the building have to achieve SS
Credit Rainwater Management?
A. Habitat.
E. Soil.
51-Community leaders are meeting with the school board to discuss sharing
some of a new school's facilities. If the community engages in a contract with
the school for dedicated-use spaces, in addition to providing access to toilets
what other space types would qualify for SS Credit Joint Use of Facilities?
53-An office park will contain 450 parking spaces. There will be 30 preferred
parking spaces and 3 spaces for van or carpools. The team wants to earn a
point for SS Credit Heat Island Reduction by placing parking underground.
What should be done to earn the credit?
D. 25.
55-When restoring disturbed and compacted soils, which action must the
project team take to restore soils in areas being revegetated?
A. Plant vegetation such as grass, ground covers, trees, and shrubs to stabilize soils.
D. Cover soils with products including mulch, tarps, filters, and fabrics so that soil
won't erode.
LEED AP BD+C QUESTIONS
E. Install structural controls such as earth dikes, silt fences, sediment traps, and
catch basins to divert water and to capture sediment from the storm water runoff.
5- Water efficiency:
2-Which types of fixtures are NOT eligible for Water Sense labels?
D. A waterless toilet.
4-Which are the primary factors a project team should consider when
deciding which water subsystems to meter?
C. The systems that most closely align with the goals of building management.
D. WE Credit Indoor Water Use Reduction and WE Credit Outdoor Water Use
Reduction.
LEED AP BD+C QUESTIONS
6-After the design phase of a school project the team decided to replace
outdoor basketball courts with an athletic field covered in turf grass. What
statement is true regarding this design change?
A. The field can be included or excluded in WE Credit Outdoor Water Use Reduction
calculations at the project team's discretion.
7-When calculating the landscape water budget for a site, which areas must
be included?
A. Trees.
F. Groundcover.
8-Which water subsystems must have 100% of the source sub metered for
WE Credit Water Metering?
B. Reclaimed water.
D. Boiler water.
9-A project with an evaporative condenser uses 100% potable water for
cooling. Which action would the project owner need to take to achieve WE
Credit Cooling Tower Water Use?
10-The project team for a small office is calculating the daily baseline indoor
water use. There will be two men and one woman in the office. What is the
daily baseline water usage?
B.14.25 gallons.
11-Why should a project team consider sub metering during the building
design when it is relatively easy to locate them?
D. The amount of water used if the project used only code-compliant fixtures and
fittings.
LEED AP BD+C QUESTIONS
13-A global restaurant chain is building a new restaurant. The restaurant will
include an ice machine. The project is located in a country that doesn't have
ENERGY STAR appliances. What is true about the project's ability to earn WE
Prerequisite Indoor Water Use Reduction?
D. The project can meet the prerequisite if the appliance meets the ENERGY STAR
product specifications available on the ENERGY STAR website.
C. Planting density/distribution.
E. Types of plants.
16-A new 5-story office building is being planned in an urban area. The
building footprint is 50,000 SF (4,645 m2) and has a zero-lot-line. The
building will feature an indoor fountain in the lobby, a rainwater collection
system to offset indoor potable water use, a high-SRI white roof. What is true
about the project's ability to achieve WE Prerequisite Outdoor Water Use
Reduction?
17-How can a project owner share building-level watering meter data with
USGBC on a monthly basis?
19-A project team in an area that receives extensive rainfall wants to install a
rainwater cistern to supply 75% of the water needed for irrigation for a LEED
BD+C: Healthcare project. The landscape design would include perennial
plants and turf grass irrigated with overhead sprinklers. Which outcome
would be the result of this design?
D. The project would not meet the requirements of WE Prerequisite Outdoor Water
Use Reduction.
Which is the maximum number of cycles of concentration for this makeup water?
22-A project team trying to achieve LEED BD+C: Multifamily Midrise for a
new residential project would need to do which of the following?
A. Janitor's sink.
C. Coffee maker.
LEED AP BD+C QUESTIONS
24-The Water Sense Water Budget tool uses which variables to determine
how much landscape water a project needs?
B. Example fixture cut sheets that fulfill the intent of the credit.
26-A building has a restaurant on the first floor and office space on the
second and third floors. When using the indoor water use calculator, how
should the information be calculated?
28-A project design will use no potable water sources for cooling tower
makeup water. A rainwater collection system will store water from the
building's roof and a storage pond will collect storm water runoff from the
grounds. What is true regarding the project's use of the water?
C. The rainwater collected from the roof will require less treatment before use.
29-When occupancy data is entered into the indoor water use calculator; it is
split by default to a 50/50 gender ratio. Under which circumstance should
this be ratio changed?
B. Vegetated playground.
32-The landscape designer for a project has created a design that will not
require long-term irrigation for the property. Which pieces of information will
need to be documented in the plant species and water requirement narrative
for WE Prerequisite Outdoor Water Use Reduction?
33-A project team is working in a country that does not have Water Sense
equivalents for fixture performance. For the prescriptive compliance path of
WE Prerequisite Indoor Water Use Reduction, which action should the project
team take to achieve the prerequisite?
D. Select a fixture performance of at least 20% below the baseline of EPAct 1992.
34-If a project team is going to use aerators without a Water Sense label in
private lavatories as part of a strategy to meet WE Prerequisite Indoor Water
Use Reduction, which is the maximum flow rate allowed?
C. Overflow alarm.
36-A project team is working in a country where the Water Sense label is
unavailable and there is no acceptable substitute for the country in the
International Water Labeling Program. What is true about the project team's
ability to earn WE Prerequisite Indoor Water Use Reduction?
D. The fixtures and fittings must comply with the 20%-below baseline requirement.
37-An office project is estimated to have 200 FTE occupants and 30 daily
visitors. The project team is attempting to earn points under WE Credit
Indoor Water Reduction. When using the indoor water use calculator, which
information will the project team need to enter to accommodate the visitors?
41-A team member is entering toilet information for calculating the design
case for indoor water use. In addition to the fixture type and its flush rate,
which information must be entered into the calculator for the toilet?
43-A public utility uses proprietary wireless technology to read the water
meter for a project building. Since access to the water-metering data is
restricted, which statement is true of the project team's ability to achieve WE
Prerequisite Building-Level Water Metering?
D. The project team can track water usage through monthly billing statements.
LEED AP BD+C QUESTIONS
45-A project with an evaporative condenser uses 100% potable water for
cooling. Which action would the project team need to take to achieve WE
Prerequisite Indoor Water Use Reduction?
46-A new church is pursuing LEED BD+C: New Construction. The facility will
have soup kitchen to serve the community that includes a commercial
dishwasher, ice machine, and combination oven. In addition to the fixtures
and fittings, what else must be included in WE Prerequisite Indoor Water Use
Reduction?
D. Ice machine.
48-A project team will not pursue points under WE Credit Indoor Water Use
Reduction. Which information should be documented by the MEP engineer for
the prescriptive path of WE Prerequisite Indoor Water Use Reduction?
49-The entire water supply for a building is provided by a public water supply
and uses a single water meter. The meter is not accessible for reporting to
achieve WE Prerequisite Building-Level Water Metering. Which action can the
project team take to track water usage?
D. Install a second private water meter downstream of the public water supply
meter.
50-A design team is working on water use reduction strategies for a new
school project. What could the project team include to help reduce appliance
and process water use for WE Prerequisite Indoor Water Use Reduction?
51-A project team will earn one point for WE Credit Cooling Tower Water Use
by meeting the maximum number of cycles without additional treatment.
Which action can the project team take to earn an additional point?
52-A site project has two landscaped sections: one that requires irrigation
and one that does not because it is Xeriscaped. How should the project team
calculate the landscape water budget?
C. By making two separate calculations, one for the irrigation section and one for
the unirrigated area.
C. The system will earn the project a 15% reduction in landscape water
requirements (LWR) for WE Credit Outdoor Water Use Reduction.
C. Cooling towers.
1-A Core and Shell project in Nevada has a wind energy system added to the
roof. According to the US DOE's Commercial Buildings Energy Consumption
Survey the estimated electricity the project will use will be 1,000,000
kWh/year. Energy costs in the area are $0.08/kWh. What must the wind
system produce to earn 3 points for EA Credit Renewable Energy Production?
C. $4,000 of energy.
To earn 3 points, a Core and Shell project must get 5% of the building's
annual energy cost from on-site renewable energy.
LEED AP BD+C QUESTIONS
The estimated energy use is 1,000,000 kWh from the CBECS database. This
multiplied by the cost per kilowatt hour gives an annual energy cost of $80,000.
2-A design firm is bidding on a new school project. What would be the benefit
of creating an energy model and using it as a design tool?
5-A project team is planning to use green power obtained from a separate
campus facility through an internal campus agreement. The project team did
not use an energy model for EA Credit Optimize Energy Performance. No
other buildings on campus obtain power from this facility. What is true about
the project's ability to earn EA Credit Green Power and Carbon Offsets?
A. The campus facility that supplies the power does not have to be Green-e
Certified.
6-A project team is using a whole building energy simulation for EA Credit
Optimize Energy Performance. All of the following quality assurance checks
would be flagged by the reviewer except:
7-A project with a 30,000 sq. ft. building footprint has been designed with a
100% green roof. The project team is revising the design to decrease the size
of the green roof by 5,000 sq. ft. and add 5,000 sq. ft. of photovoltaic cells to
the roof. What credits will this design change NOT affect?
B. May require more energy to achieve the same level of cooling as HCFC.
10-An office project in a cold climate burns natural gas on-site for heating
and uses electricity from the grid in warmer seasons for cooling. Which
option can be used to mitigate both Scope 1 and Scope 2 emissions?
C. Carbon offsets.
Only carbon offsets can be used for both emission types - non-electricity and electricity.
11-A project has a 150-kW PV array that will produce 210,458 kWh of
electricity per year after transmission and conversion losses. The virtual rate
for the electricity generated is $0.092/kWh. The total building annual energy
B. 32%.
12-A new suburban retail project will be implemented using a bio-fuel based
electrical system. Which bio-fuels are excluded from eligibility for EA Credit
13-A new office building with a retail component on the first floor totals
company will qualify the project for EA Credit Green Power and Carbon
Offsets?
B. 7,429,500 kWh.
Credit is achieved by purchasing 50% renewable power for a period of five years.
performance tests, issues log that details open and closed issues?
B. Cx report.
15-After the owner documents their owner's project requirements (OPR), the
project team will take that document to create the basis of design (BOD).
and assumptions.
16-Which first step must all projects take before attempting EA Prerequisite
The climate zone determines which mandatory requirements from ASHRAE need to
17-A CxA has arrived on a project site to verify the installation and
the following are NOT typical steps the CxA will perform?
18-A residential building will include a common laundry room, postal area,
and heated swimming pool. An independent CxA has been hired to help the
20-The owner of a new oceanfront museum project wants to use 50% green
power, but the direct purchase of Green-e certified power is not available
through the local utilities. An energy model was not done for EA Credit
A. The project can't earn any points under EA Credit Optimize Energy Performance.
interior lighting, space heating and cooling, receptacle equipment, and fans.
D. Educating occupants with information about which subsystems use the most
energy.
23-A CxA has finished preparing their Cx report for the building owner, and
the project team is compiling the current facility requirements (CFR) and
operations and maintenance (O&M) plan. Which information should the CFR
manager?
LEED AP BD+C QUESTIONS
C. Set points for all HVAC equipment, sequence of operations for the building,
lighting levels.
A. The project team can use space peak-load calculations to calculate the minimum
Demand Response. Which actions will the project team need to take in order
to participate?
B. Participate in a program for at least 10% of peak demand and conduct one full
regulated load savings. Which statement is true regarding how these savings
Performance, the modeling data can be used to inform decisions in all of the
C. An independent system operator sends a DR event over the Internet and pre-
E. Ongoing commissioning.
32-Which minimum contract length is required for Green Power and Carbon
Offsets?
33-On a project with older existing HVAC&R system that uses CFCs what can
D. Replace the HVAC&R system with one that does not use CFCs.
credit?
D. MWh.
37-The commissioning authority, with the help of the design team and
contractors, is writing functional test scripts for a new school building. Which
38-A 400,000 square foot (37,161 square meter) commercial building has a
A. Thermal imaging.
B. A field mock-up.
39-Which of the following are NOT eligible for EA Credit Renewable Energy
Production?
LEED AP BD+C QUESTIONS
A. Donating materials
Donation, resale, or on-site reuse are ways to divert waste, not reduce it at the
source.
(Choose 3)
A. Roof assemblies
C. Covered parking
This credit requires all that all assessed materials include the complete building
Footings
Foundations
Structural walls
Structural floors
Ceilings
Structural parking
3-What minimum time period must a waste stream audit be conducted for a retail
project?
B. 24-hour period
LEED AP BD+C QUESTIONS
project. If a salvaged material came from on-site, how will the contractor determine the
D. Using a comparable material in the local market, excluding labor and shipping
Material reuse is based on the total cost of the materials and the total cost of any
reused/salvaged materials.
If a salvaged material came from on-site, the replacement value of the material is
determined by comparing the material to something available in the local market. Labor
and shipping are excluded, as are any discounts the seller may apply.
5- A project team is reviewing Type III EPDs for the impact reduction of different office
Eutrophication
Note that for Option 2 the product must have an industry wide (generic) EPD or Type III
EPD.
LEED AP BD+C QUESTIONS
the future expansion of the building. The building may be expanded both up and out.
B. Oversized corridors
least how many materials to be diverted, and explain diversion plans for those
materials?
C. Five (5)
Five (5) material streams must be identified in the plan for diversion.
8- A project will include carpet tile and walk-off mats from one manufacturer, as well as
ceramic tile and wood flooring from another manufacturer. All of the products have
industry-wide (generic) EPDs. How many permanently installed products would this
B. 2
It's necessary to know first what constitutes a product in LEED as it applies to these
credits.
A product is defined by serving the distinct function. This includes the physical
components and services needed to serve the intended function of the permanently
installed building product. Similar products from the same manufacturer can be counted
as separate products if they have distinct formulations, but not if there are aesthetic
variations or reconfigurations.
In this question there are four distinct products from two different manufacturers.
The item stem mentions four products, all of which have generic EPDs, so each counts
considering is not in the LCA tool's data set. Which option does the project team have
D. If the product has a critically reviewed LCA or EPD, the product's impact-measure
If an LCA or EPD is available, the product could be added into the software.
The product must perform better than the industry average in at least 3 of 6 impact
categories.
11- A project team is close to meeting the 25% threshold for building and material reuse
for MR Credit Building Life-Cycle Impact Reduction. Which strategy would assist the
D. Obtain reused materials from off site for inclusion in the project
LEED AP BD+C QUESTIONS
If the credit threshold isn't met, the project team could find more materials that would
contribute to a greater surface area and count toward the area of reuse.
12- A project team has identified enough qualifying products to meet MR Credit Building
Product Disclosure and Optimization - Sourcing of Raw Materials, Option 1 Raw Material
Source and Extraction Reporting. What must be submitted for documentation of the
credit?
C. The corporate sustainability reports from each manufacturer and the building
13- For a product to count toward the achievement of MR Credit Building Disclosure and
The report has to be current at the time of installation, not published within one year of
installation.
14- A project team is considering options for earning MR Credit Construction and
Demolition Waste Management Option 1 Diversion. The school is in a rural area with
little waste infrastructure, and the project cannot meet the waste diversion
15- A developer has purchased a blighted 100,000 SF (9,290 m2) warehouse. Part of the
roof and one of the exterior walls, totaling 30,000 SF (2,787 m2), are structurally
unsound and must be demolished. The developer will maintain 60,000 SF (5,574 SF) of
the surface area of the building. Which statement is true about the project team's ability
A. The project team can pursue Option 3 Building and Material Reuse.
LEED AP BD+C QUESTIONS
For Option 2, projects are only allowed to exclude up to 25% of the surface area
Remember to start by looking at the percentage that is unsound to see if the credit can
be pursued. Don't subtract the unsound portion from the total as a means of
16- A renovation project includes removing part of an old building, re-grading some of
the site, and taking down some trees for a building expansion. What item must be
The carpet would need to be included in the calculations for the total of all construction
waste management. If the carpet were recycled or donated it would be included in the
Notes:
assessment?
B. Cradle-to-grave
building.
18- A project team member was not clear about the specifications for building materials,
D. Exclude the product from the disclosure option and include it in the optimization
option
Each Building Product Disclosure and Optimization credit has an option for disclosure
and another option for optimization. Each option is worth 1 point, and projects can earn
Earning 1 point for Option 2 optimization is allowed without earning Option 1 disclosure
In this scenario, the product does not have disclosure (because the product was
substituted), but it does have optimization by having the GreenScreen v1.2 Benchmark
19- A project will renovate a building with historic designation into new office space. The
surface area of the existing building structure and envelope is 100,000 SF. How much of
the existing building will need to be reused to earn 5 points for MR Credit Building Life-
A. There is no minimum
There is no threshold of compliance for Option 1 Historic Building Reuse. However any
20- A project includes some salvaged wood flooring costing $50,000 and that was
purchased 500 miles (804 km) from the project site. What value does the wood have
Materials?
C. $50,000
LEED AP BD+C QUESTIONS
The wood meets a sustainability criteria, but since it was purchased more than the 100
miles (160 km) from the project, it is valued at 100% (not 200%) of the cost.
For a product to qualify for the location valuation factor two criteria must be met:
1. Sustainability
If the product meets multiple sustainability criteria, it doesn't count more toward the
total (salvaged material that contains recycled content can't be double counted).
21- A project team is reviewing material choices before deciding which products to
include. The team located interior wall partitions made with recycled content that have
been salvaged from another building. The partitions are available from a company
located 50 miles (80 km) from the project site for the price of $20,000. What value do
the partitions have toward MR Credit Building Product Disclosure and Optimization -
C. $40,000
For a product to qualify for the location valuation factor, two criteria must be met:
1. Sustainability criteria
If the product meets multiple sustainability criteria, it doesn't count more toward the
total (salvaged material that contains recycled content can't be double counted).
22- Which type of project would require the project team to conduct a whole-building
23- A project team has purchased 7,500 SF (696 m2) of salvaged wood flooring from a
barn at a cost of $22,500. How can the reused materials be applied toward LEED
credits?
B. The surface area of the flooring can be applied to MR Credit Building Life-Cycle
Impact Reduction, Option 3 Building and Material Reuse; OR the cost of the flooring can
24- A project team is deciding if the project will generate more than 2.5 pounds of
construction waste per square foot (12.2 kg/m2). MR Credit Construction and Demolition
Project teams choosing Option 2 need to use source reduction strategies to reduce the
Retail projects require a waste stream audit conducted over a 24-hour period that must
be documented.
26- Which is a key strategy for project teams to earn multiple points and credits for the
Materials that have lots of documentation and sustainable attributes can count toward
multiple credits.
For example in the EPD, credit Option 1 can be earned if materials have an EPD.
27- A project team believes they can generate less than 2.5 pounds of construction
waste per square foot (12.2 kg/m2) by using source reduction strategies such as
modular components and prefabricated wall assemblies for the project. What will the
project team need to document for MR Credit Construction and Demolition Waste
Management Option 2 Reduction of Total Waste Material?
Project teams choosing Option 2 need to use source reduction strategies to reduce the
quantity of waste generated on site.
The required documentation is the total waste per area.
28- Cabinetry that is low VOC and made with FSC Certified Wood would contribute to
what credits?
29- What products would both contribute towards MR Credit Building Product Disclosure
and Optimization - Sourcing of Raw Materials, Option 2 Leadership Extraction Practices?
For this option choose products that meet one of these extraction criteria:
Extended producer responsibility
Bio-based materials
Certified wood
Materials reuse
Recycled content
30- A project has a cost of $21M. The cost of the optional products and materials
(furniture and MEP) for the project is $500,000. Given this information, what is the
default materials cost of the project?
B. $9,950,000
If the project team doesn't use the actual materials cost, a default materials cost of 45%
of the total construction cost can be used. If optional products and materials are
included in the credit calculations, the actual value of those materials must be added to
the default value.
$21,000,000 X 45% = $9,450,000
$9,450,000 + $500,000 = $9,950,000
32- Why should a project team ensure proper storage locations and sizes for recyclable
materials in the building floor plan during the initial design phase?
D. To avoid later difficulties in finding available areas for storage after the design is
complete
Designing the areas early avoids cramming the storage spaces in odd locations later on.
LEED AP BD+C QUESTIONS
33- The architect and other project designers are reviewing material choices for a new
office space. Which reused materials will NOT contribute to optimization of MR Credit
Building Product Disclosure and Optimization - Sourcing of Raw Materials?
In the case of an owner moving to a new site furniture that is leased must have been in
service for 2-years to count in the current project.
34- A project team is reviewing a new insulation material that is Cradle to Cradle v3
Gold certified. If they use this product on the project what credits would it contribute to?
Cradle to Cradle products (depending on the level) can be applied to both the disclosure
and optimization options of MR Credit Building Product Disclosure and Optimization -
Material Ingredients.
For Option 1 the product must has been certified at the Cradle to Cradle v2 Basic level
or Cradle to Cradle v3 Bronze level.
For Option 2 the following are accepted:
Cradle to Cradle v2 Gold
Cradle to Cradle v2 Platinum
Cradle to Cradle v3 Silver
Cradle to Cradle v3 Gold or Platinum
35- A project team is pursuing MR Credit Building Life-Cycle Impact Reduction Option 3
Building and Material Reuse. The surface areas of what elements need to be included in
the reused elements table and calculations for documenting the credit?
All three of these elements count in the total surface area and as reused elements.
37- A project team is reviewing ceiling tiles that would contribute to material ingredient
optimization. If all of the products have similar prices, which products would contribute
LEED AP BD+C QUESTIONS
the most to the criteria of 25% of the total of permanently installed materials for the
credit?
Note which products are worth a higher percentage of cost for Option 2. The correct
choices are valued at 150% of their cost.
38- A chair has the following components, weight percentages, and sustainability
criteria:
D. $31
The product value is based on the weight of the components that meet the
sustainability criteria as a percent of the total product weight.
Total product cost ($) X % product component by weight X (%) meeting sustainable
criteria
$100 X 5% X 100% = $5
$100 X 30% X 0% = $0
$100 X 65% X 40% = $26
= $31
warehouse into a mixed-use retail and office building. The project is trying to divert as
much construction waste as possible from landfills. The following is a construction waste
management summary. How many points would the project earn for MR Credit
Waste Weight
----------------------------------------------
LEED AP BD+C QUESTIONS
D. 1
40- For a building renovation the architect's plan indicates reuse of interior elements
including wall partitions, flooring, doors, cabinets, and ceramic bathroom tile.
If the total interior surface area is 30,000 SF, how many square feet must be reused to
comply with MR Credit Building Life-Cycle Impact Reduction?
A. 7,500 SF
A minimum of 25% of building materials from off site or on site as a percentage of the
surface area must be reused.
30,000 X 25% = 7,500 SF
41- A developer selected a building with a historic designation for a project. The
necessary building alterations for bringing the building up to code caused the building
to lose its historic status. Which action should the project team consider for earning MR
Credit Building Life-Cycle Impact Reduction?
C. Seek the credit option for Building and Material Reuse for the reuse of the building
A building that loses its historic designation may apply for Option 3.
42- Which type(s) of EPD (is/are) always created from a product category rule?
43- Which design strategy carries the highest value by LEED in the Material and
Resources category?
B. Reuse
Building and material reuse is prioritized and rewarded through credits with higher point
values.
44- A tenant is moving into a new space and is planning for the future growth of the
company. What project feature allows the space to be changed more easily to support
growth?
A. Demountable partitions
45- A project team is adding up the number of separate products used on a project to
see if the project meets the 20-product minimum required for one of the Building
Product Disclosure and Optimization credits. Which products would count as two
separate products?
C. Carpet tile for a lobby with low pile and carpet tile for an office with a higher pile,
each from the same manufacturer
LEED AP BD+C QUESTIONS
The tiles serve different functions and would count as different products even though
they are from the same manufacturer.
46- A project located in a rural area without a recycling program must take which action
for MR Prerequisite Storage and Collection of Recyclables?