Station Limits: Total Project Duration: 796.00 CD
Station Limits: Total Project Duration: 796.00 CD
54
Station Limits : Total Project Duration :
0.009% 397,950.00
0.000% 8,948.58
0.047% 2,198,000.92
0.090% 4,200,000.00
0.387% 18,042,645.66
78.345% 3,652,215,078.23
0.012% 560,206.83
0.101% 4,715,251.82
9.264% 431,862,175.91
1.661% 77,446,429.90
0.067% 3,113,328.82
0.009% 433,379.72
0.317% 14,796,761.99
8.195% 382,031,498.89
1.495% 69,674,135.89
100.00% 4,661,695,793.16
Approved:
HON. RODOLFO O. ESTRELLA, JR.
MUNICIPAL MAYOR
Page 1 of 2
Sta. 0+000 - Sta. 0+337.54
Station Limits : Total Project Duration :
PPLY PROJECT
ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST % DIRECT COST
AL UNIT COST (DIRECT + INDIRECT)
AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATE AS EVALUATED
15,000.00 18,000.00
4,474.29 5,369.15
2,198,000.92 2,373,840.99
4,200,000.00 5,040,000.00
274.92 329.90
1,045.84 1,255.01
1,037.30 1,244.76
1,746.18 2,095.42
15,389.48 18,467.38
55.88 67.06
56.48 67.78
8,229.77 9,875.72
715.05 858.06
6,154.80 7,385.76
1,590.55 1,908.66
Approved:
MUNICIPAL MAYOR
Page 1 of 1
VINCE OF MASBATE MUNICIPALITY OF BALUD
HE MUNICIPAL ENGINEER
CONSTRUCTION OF BALUD DAM WATER SUPPLY PROJE
DETAILED BREAKDOWN OF COM
ITEM DESCRIPTION % QUANTITY DIRECT COST
NO. MATERIAL LABOR
PART A FACILITIES FOR THE ENGINEER
A.1.1(6) Provision of Combined Field Office, Laboratory
and Living Quarters Building for the Engineer AS SUBMITTED 26.53 397,950.00 -
(Rental Basis)
AS EVALUATED
Approved:
HON. RODOLFO O. ESTRELLA, JR.
MUNICIPAL MAYOR
Page 1 of 1
ITEM DESCRIPTION QUANTITY UNIT ESTIMATED DIRECT TOTAL MARK UP
NO. COST %
PART A FACILITIES FOR THE ENGINEER AS SUBMITTED
AS EVALUATED
Provision of Combined Field Office, Laboratory AS SUBMITTED 26.53 month 397,950.00 8%
and Living Quarters Building for the Engineer
A.1.1(6)
(Rental Basis) AS EVALUATED
Page 1 of 2
ITEM DESCRIPTION QUANTITY UNIT ESTIMATED DIRECT TOTAL MARK UP
NO. COST % VALUE
PART G DRAINAGE AND SLOPE AS SUBMITTED
PROTECTION STRUCTURES AS EVALUATED
405(1)b2 Structural Concrete (27.58 Mpa, Class AS SUBMITTED 28,062.17 sq.m. 431,862,175.91 20% 86,372,435.18
A, 14 days) AS EVALUATED
404(1)a Reinforcing Steel (Grade 40) AS SUBMITTED 1,386,007.98 kg. 77,446,429.90 20% 15,489,285.98
AS EVALUATED
404(1)b Reinforcing Steel (Grade 60) AS SUBMITTED 55,125.28 kg. 3,113,328.82 20% 622,665.76
AS EVALUATED
407(8) Lean Concrete, Class B (16.5 Mpa) AS SUBMITTED 52.66 cu.m. 433,379.72 20% 86,675.94
AS EVALUATED
505(3) Filter Layer of Granular Material AS SUBMITTED 20,693.35 cu.m. 14,796,761.99 20% 2,959,352.40
(Coarse Filter) AS EVALUATED
506 (1) Stone Masonry AS SUBMITTED 62,070.54 cu.m. 382,031,498.89 20% 76,406,299.78
AS EVALUATED
TOTAL OF PART G AS SUBMITTED 909,683,575.23 181,936,715.04
AS EVALUATED
PART H MISCELLANEOUS STRUCTURES AS SUBMITTED
AS EVALUATED
715(1) Geotextile AS SUBMITTED 43,805.02 cu.m. 69,674,135.89 20% 13,934,827.18
AS EVALUATED
TOTAL OF PART D AS SUBMITTED 69,674,135.89 13,934,827.18
AS EVALUATED
TOTAL AS SUBMITTED 4,661,695,793.16 931,187,644.52
AS EVALUATED
Prepared by: Recommending Approval:
ALLEN P. ESTRELLA ARNEL F. AROLLADO
MUNICIPAL ENGINEER MPDC
Approved:
HON. RODOLFO O. ESTRELLA, JR.
MUNICIPAL MAYOR
Page 2 of 2
Approved:
HON. RODOLFO O. ESTRELLA, JR.
MUNICIPAL MAYOR
Page 1 of 1
DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No. : A.1.1(6)
Description : Provision of Combined Field Office, Laboratory and Living Quarters Building
for the Engineer (Rental Basis)
Unit of Measurement : month
Output - As Submitted: 1.0
Output - As Evaluated:
Labor
Sub-Total for A2- As Evaluated
Equipment
Sub-Total for B2- As Evaluated
Materials
Sub-Total for F2- As Evaluated
15,000.00 15,000.00
15,000.00
15,000.00
1,200.00
1,134.00
17,334.00
wed by:
RNEL F. AROLLADO
MPDC
DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No. : B.5
Description : Project Billboard / Signboard
Unit of Measurement : each
Output per Hour - As Submitted: 1.0
Materials
Sub-Total for F2- As Evaluated
111.44 111.44
80.75 80.75
62.40 249.60
441.79
441.79
1.00
441.79
50.00 1,600.00
30.00 1,260.00
110.00 82.50
1,090.00 1,090.00
4,032.50
4,474.29
536.91
357.94
375.84
5,744.98
wed by:
ADO
DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No. : B.7(2)
Description : Occupational Safety and Health Program
Unit of Measurement : l.s.
Output per Hour - As Submitted: 1.00
Output per Hour - As Evaluated:
Labor
Sub-Total for A2- As Evaluated
Equipment
Sub-Total for B2- As Evaluated
Materials
Sub-Total for F2- As Evaluated
1,006.77 801,388.92
494.00 196,612.00
998,000.92
998,000.92
1.00
998,000.92
2,198,000.92
175,840.07
166,168.87
2,540,009.86
wed by:
ADO
DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No. : B.9
Description : Mobilization/Demobilization
Unit of Measurement : l.s.
Output per Hour - As Submitted: 1.00
Output per Hour - As Evaluated:
Labor
Sub-Total for A2- As Evaluated
Name and Capacity No. of No. of
Units Hours
B.1 Equipment
B.2 Mobilization/Demoblization
Sub-Total for B1- As Submitted
Equipment
Sub-Total for B2- As Evaluated
F.1 Materials
F.2 Sub-Total for F1- As Submitted
Materials
Sub-Total for F2- As Evaluated
4,200,000.00
4,200,000.00
4,200,000.00
1.00
4,200,000.00
4,200,000.00
294,000.00
4,494,000.00
wed by:
ADO
DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No. : 102(1)
Description : Unsuitable Excavation
Unit of Measurement : cu.m.
Output per Hour - As Submitted: 20.00
Output per Hour - As Evaluated:
Labor
Sub-Total for A2- As Evaluated
Equipment
Sub-Total for B2- As Evaluated
F.1 Materials
F.2 Sub-Total for F1- As Submitted
Materials
Sub-Total for F2- As Evaluated
111.44 111.44
80.75 242.25
353.69
2,096.00 2,096.00
1,420.00 2,840.00
1,733.00 173.30
35.37
5,144.67
5,498.36
20.00
274.92
274.92
32.99
21.99
23.09
352.99
+H.2+I.2+J.3
wed by:
ADO
DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No. : 104(2)a
Description : Embankment From Borrow (Common Soil)
Unit of Measurement : cu.m.
Output per Hour - As Submitted: 50.00
Output per Hour - As Evaluated:
Labor
Sub-Total for A2- As Evaluated
Equipment
Sub-Total for B2- As Evaluated
Materials
Sub-Total for F2- As Evaluated
111.44 111.44
80.75 161.50
272.94
2,173.00 2,173.00
1,846.00 1,846.00
2,450.00 612.50
4,019.00
4,291.94
50.00
85.84
768.00 960.00
960.00
1,045.84
125.50
83.67
87.85
1,342.86
wed by:
ADO
DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No. : 200(1)
Description : Aggregate Subbase Course
Unit of Measurement : cu.m.
Output per Hour - As Submitted: 50.00
Output per Hour - As Evaluated:
Labor
Sub-Total for A2- As Evaluated
Equipment
Sub-Total for B2- As Evaluated
Materials
Sub-Total for F2- As Evaluated
111.44 111.44
62.40 124.80
236.24
2,173.00 2,173.00
1,846.00 1,846.00
2,450.00 612.50
4,019.00
4,255.24
50.00
85.10
828.00 952.20
952.20
1,037.30
124.48
82.98
87.13
1,331.89
wed by:
ADO
DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No. : 311(1)a2
Description : PCCP (Unreinforced, 200mm thk., 14 days)
Unit of Measurement : sq.m.
Output per Hour - As Submitted: 80.50
Output per Hour - As Evaluated:
Equipment
Sub-Total for B2- As Evaluated
Materials
Sub-Total for F2- As Evaluated
111.44 111.44
80.75 323.00
62.40 748.80
1,183.24
1,318.00 5,272.00
91.25 182.50
1,733.00 1,733.00
545.00 545.00
2,450.00 2,450.00
32.63 32.63
219.75 21.98
59.16
10,296.27
11,479.51
80.50
142.60
1,746.18
209.54
139.69
146.68
2,242.09
wed by:
ADO
DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No. : 405(1)b2
Description : Structural Concrete (27.58 Mpa, Class A, 14 days)
Unit of Measurement : cu.m.
Output per Hour - As Submitted: 10.00
Output per Hour - As Evaluated:
Labor
Sub-Total for A2- As Evaluated
Equipment
Sub-Total for B2- As Evaluated
Materials
Sub-Total for F2- As Evaluated
ys)
111.44 111.44
80.75 323.00
62.40 499.20
111.44 2,228.80
80.75 6,460.00
62.40 9,984.00
19,606.44
1,318.00 2,636.00
91.25 182.50
1,759.50 879.75
1,733.00 866.50
2,450.00 612.50
2,282.00 1,141.00
6,318.25
25,924.69
10.00
2,592.47
15,389.48
1,846.74
1,231.16
1,292.72
19,760.10
wed by:
ADO
DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No. : 407(8)
Description : Lean Concrete, Class B (16.5 Mpa)
Unit of Measurement : cu.m.
Output per Hour - As Submitted: 0.357
Output per Hour - As Evaluated:
Labor
Sub-Total for A2- As Evaluated
Equipment
Sub-Total for B2- As Evaluated
Materials
Sub-Total for F2- As Evaluated
111.44 111.44
80.75 80.75
62.40 249.60
441.79
172.00 172.00
44.18
216.18
657.97
0.36
1,843.05
2,937.00 2,937.00
2,722.00 1,361.00
348.12 2,088.72
6,386.72
8,229.77
987.57
658.38
691.30
10,567.02
wed by:
ADO
DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No. : 404(1)a
Description : Reinforcing Steel (Grade 40)
Unit of Measurement : kg.
Output per Hour - As Submitted: 180.0
Output per Hour - As Evaluated:
Labor
Sub-Total for A2- As Evaluated
Equipment
Sub-Total for B2- As Evaluated
Materials
Sub-Total for F2- As Evaluated
111.44 111.44
80.75 161.50
62.40 499.20
772.14
219.75 109.88
351.50 175.75
1,522.00 228.30
783.00 117.45
631.38
1,403.52
180.00
7.80
87.00 1.83
44.05 46.25
48.08
55.88
6.71
4.47
4.69
71.75
wed by:
ADO
DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No. : 404(1)b
Description : Reinforcing Steel (Grade 60)
Unit of Measurement : kg.
Output per Hour - As Submitted: 180.0
Output per Hour - As Evaluated:
Labor
Sub-Total for A2- As Evaluated
Equipment
Sub-Total for B2- As Evaluated
Materials
Sub-Total for F2- As Evaluated
111.44 111.44
80.75 161.50
62.40 499.20
772.14
219.75 109.88
351.50 175.75
1,522.00 228.30
783.00 117.45
631.38
1,403.52
180.00
7.80
87.00 1.83
44.62 46.85
48.68
56.48
6.78
4.52
4.74
72.52
wed by:
ADO
DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No. : 506 (1)
Description : Stone Masonry
Unit of Measurement : cu.m.
Output per Hour - As Submitted: 1.60
Output per Hour - As Evaluated:
Equipment
Sub-Total for B2- As Evaluated
Materials
Sub-Total for F2- As Evaluated
111.44 111.44
80.75 161.50
62.40 499.20
772.14
172.00 172.00
2,450.00 122.50
1,537.00 1,152.75
38.61
1,485.86
2,258.00
1.60
1,411.25
6,154.80
738.58
492.38
517.00
7,902.76
wed by:
ADO
DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No. : 505(3)
Description : Filter Layer of Granular Material (Coarse Filter)
Unit of Measurement : cu.m.
Output per Hour - As Submitted: 1.20
Output per Hour - As Evaluated:
Labor
Sub-Total for A2- As Evaluated
Materials
Sub-Total for F2- As Evaluated
111.44 111.44
62.40 499.20
610.64
130.00 130.00
61.06
191.06
801.70
1.20
668.08
3,751.93
450.23
300.15
315.16
4,817.47
wed by:
ADO
DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No. : 715(1)
Description : Geotextile
Unit of Measurement : sq.m.
Output per Hour - As Submitted: 100.0
Output per Hour - As Evaluated:
Labor
Sub-Total for A2- As Evaluated
Equipment
Sub-Total for B2- As Evaluated
Materials
Sub-Total for F2- As Evaluated
111.44 111.44
80.75 161.50
62.40 499.20
772.14
783.00 783.00
783.00
1,555.14
100.00
15.55
1,500.00 1,575.00
1,575.00
1,590.55
190.87
127.24
133.61
2,042.27
wed by:
ADO
QUANTITY DERIVATION
CONSTRUCTION OF BALUD DAM WATER SUPPLY PROJECT
A.1.1(6) Provision of Combined Field Office, Laboratory and Living Quarters Building for the Engineer (Rental Basis)
Project Duration 796.00 c.d.
Project Duration 26.53 month
B.5 Project Billboard / Signboard
Beginning 1.00 each
End 1.00 each
Total 2.00 each
B.7(2) Occupational Safety and Health Program
1.00 l.s.
B.9 Mobilization/Demobilization
1.00 l.s.
102(1) Unsuitable Excavation
See Quantity Sheet = 65,629.19 cu.m.
104(2)a Embankment From Borrow (Common Soil)
See Quantity Sheet = 3,492,139.59 cu.m.
200(1) Aggregate Subbase Course
Station Length Width Thickness subtotal
Sta. 0+000 - Sta. 0+337.54 337.54 8.00 0.20 = 540.06
Grand Total = 540.06 cu.m.
311(1)a2 PCCP (Unreinforced, 200mm thk., 14 days)
Station Length Width subtotal
Sta. 0+000 - Sta. 0+337.54 337.54 8.00 = 2,700.32
Grand Total = 2,700.32 sq.m.
405(1)b2 Structural Concrete (27.58 Mpa, Class A, 14 days)
Structure subtotal unit
Concrete Slab = 23,687.14 cu.m.
Footing = 3,742.98 cu.m.
(See Quantity Sheet)
Parapet Wall = 185.90 cu.m.
Wave Deflector = 446.15 cu.m.
Grand Total = 28,062.17 sq.m.
404(1)a Reinforcing Steel (Grade 40)
Structure Dia. (mm) Quantity (6m) subtotal unit
Concrete Slab
Front 12.00 (See Quantity Sheet) 132,432.00 = 705,449.97 kg.
Back 12.00 120,397.00 = 641,340.91 kg.
Dia. (mm) Bar Length Quantity Length
12.00 1.225 5.00 337.54 = 1,835.88 kg.
12.00 1.41 1.00 337.54 = 422.63 kg.
Wave Deflector 12.00 0.85 13.00 337.54 = 3,312.08 kg.
12.00 1.88 6.00 337.54 = 3,386.41 kg.
12.00 1.68 6.00 337.54 = 3,014.14 kg.
Footing
Top Stirrups 12.00 7.50 5.00 337.54 = 11,240.08 kg.
Bot. Stirrups 12.00 8.00 5.00 337.54 = 11,989.42 kg.
Parapet Wall
Stirrups 12.00 2.68 5.00 337.54 4,016.46 kg.
Grand Total = 1,386,007.98 kg.
.
unit
cu.m.
540.06 cu.m.
unit
sq.m.
2,700.32 sq.m.
unit
cu.m.
cu.m.
cu.m.
cu.m.
sq.m.
unit
kg.
kg.
kg.
kg.
kg.
kg.
kg.
kg.
kg.
kg.
kg.
404(1)b Reinforcing Steel (Grade 60)
Dia. (mm) Bar Length Quantity Length subtotal unit
25.00 1.802 3.00 337.54 = 7,030.73 kg.
16.00 0.88 6.00 337.54 = 2,796.35 kg.
Wave Deflector
16.00 1.01 12.00 337.54 = 6,423.62 kg.
20.00 0.85 3.00 337.54 = 2,122.55 kg.
Footing 16.00 1.00 45.00 337.54 = 23,968.72 kg.
Parapet Wall 16.00 1.00 24.00 337.54 12,783.31 kg.
Grand Total = 55,125.28 kg.
407(8) Lean Concrete, Class B (16.5 Mpa)
Station Length Width Thickness subtotal
Sta. 0+000 - Sta. 0+337.54 337.54 1.56 0.10 = 52.66 cu.m.
Grand Total = 52.66 cu.m.
506 (1) Stone Masonry
See Quantity Sheet = 62,070.54 cu.m.
505(3) Filter Layer of Granular Material (Coarse Filter)
See Quantity Sheet = 20,693.35 cu.m.
715(1) Geotextile
See Quantity Sheet = 43,805.02 sq.m.
Prepared by: Submitted by:
ALLEN P. ESTRELLA ARNEL F. AROLLADO
MUNICIPAL ENGINEER MPDC
unit
kg.
kg.
kg.
kg.
kg.
kg.
kg.
unit
52.66 cu.m.
52.66 cu.m.
EL F. AROLLADO
MPDC
QUANTITY SH
CONSTRUCTION OF BALUD DAM WA
B. DAM Structure
Length AREA AREA
(m.) (sq.m.) (sq.m.)
0.6m Thk.
STATION
Length Stone
(0+ ) Masonry Coarse Footing Wave
GeoTextile Cut Fill Concrete Slab Parapet Wall GeoTextile
Filter Structure Deflector
0.00 22.62 51.31 226.40 49.04 28.29 16.34 11.09 0.65 1.56
5.00 140.38
5.00 33.53 64.73 567.56 54.46 20.96 18.15 11.09 0.55 1.32
5.00 195.15
10.00 44.53 66.30 985.19 64.51 24.82 21.49 11.09 0.55 1.32
5.00 225.48
15.00 45.66 56.57 1443.13 77.18 29.70 25.71 11.09 0.55 1.32
5.00 252.68
20.00 55.41 70.12 2012.29 92.31 35.52 30.76 11.09 0.55 1.32
5.00 302.18
25.00 65.46 98.87 2693.57 110.11 42.36 36.70 11.09 0.55 1.32
5.00 347.38
30.00 73.49 116.40 3437.41 128.09 49.28 42.69 11.09 0.55 1.32
5.00 382.75
35.00 79.61 110.65 4214.72 138.45 53.22 46.18 11.09 0.55 1.32
5.00 415.25
40.00 86.49 96.53 5024.34 145.09 55.78 48.39 11.09 0.55 1.32
5.00 448.20
45.00 92.79 85.90 5838.19 151.22 18.14 50.43 11.09 0.55 1.32
5.00 480.80
50.00 99.53 90.34 6727.23 164.39 62.70 54.38 11.09 0.55 1.32
5.00 516.43
55.00 107.04 127.20 7665.71 173.64 66.76 57.90 11.09 0.55 1.32
5.00 552.85
60.00 114.10 160.54 8607.83 183.24 70.44 61.10 11.09 0.55 1.32
5.00 588.28
65.00 121.21 195.82 9609.73 194.51 74.78 64.86 11.09 0.55 1.32
5.00 621.18
70.00 127.26 227.32 10659.89 203.03 78.06 67.70 11.09 0.55 1.32
5.00 650.28
75.00 132.85 263.34 11632.37 209.76 80.64 69.94 11.09 0.55 1.32
5.00 678.18
80.00 138.42 274.73 12593.47 218.09 83.84 72.72 11.09 0.55 1.32
5.00 703.05
85.00 142.80 280.02 13478.40 229.31 88.16 76.45 11.09 0.55 1.32
5.00 730.00
90.00 149.20 325.67 14491.66 244.45 94.00 81.51 11.09 0.55 1.32
5.00 762.90
95.00 155.96 371.14 15559.51 249.64 95.98 83.24 11.09 0.55 1.32
5.00 797.15
100.00 162.90 424.85 16597.64 258.21 99.28 86.09 11.09 0.55 1.32
5.00 828.68
105.00 168.57 463.86 17409.53 258.27 99.30 86.11 11.09 0.55 1.32
5.00 859.10
110.00 175.07 503.34 17822.41 256.18 98.50 85.41 11.09 0.55 1.32
5.00 884.53
115.00 178.74 512.40 18074.18 255.09 98.08 85.05 11.09 0.55 1.32
5.00 908.23
120.00 184.55 503.94 18260.41 255.13 98.10 85.06 11.09 0.55 1.32
5.00 933.10
125.00 188.69 487.43 18438.37 256.45 98.60 85.50 11.09 0.55 1.32
5.00 952.55
130.00 192.33 466.94 18680.26 259.12 99.62 86.40 11.09 0.55 1.32
5.00 962.10
135.00 192.51 428.42 18971.77 265.27 102.00 88.44 11.09 0.55 1.32
5.00 961.50
140.00 192.09 381.34 19339.45 294.61 113.28 98.23 11.09 0.55 1.32
5.00 961.53
145.00 192.52 345.67 19940.56 296.70 114.08 98.92 11.09 0.55 1.32
5.00 964.55
150.00 193.30 289.74 20422.85 298.74 114.86 99.61 11.09 0.55 1.32
5.00 971.48
155.00 195.29 231.97 20785.82 297.06 114.22 99.05 11.09 0.55 1.32
5.00 1,000.40
160.00 204.87 367.88 21235.14 294.87 113.38 98.31 11.09 0.55 1.32
5.00 1,024.35
165.00 204.87 256.26 20945.09 292.15 112.34 97.41 11.09 0.55 1.32
5.00 1,024.35
170.00 204.87 204.96 20472.82 290.80 111.82 96.95 11.09 0.55 1.32
5.00 1,024.35
175.00 204.87 247.99 19824.52 289.76 111.42 96.60 11.09 0.55 1.32
5.00 1,031.85
180.00 207.87 340.58 18994.28 288.20 110.82 96.08 11.09 0.55 1.32
5.00 1,031.85
185.00 204.87 440.48 18114.77 281.74 108.32 93.94 11.09 0.55 1.32
5.00 992.78
190.00 192.24 145.80 16748.15 258.14 99.26 86.07 11.09 0.55 1.32
5.00 953.00
195.00 188.96 114.49 15869.30 253.21 97.36 84.42 11.09 0.55 1.32
5.00 936.60
200.00 185.68 114.61 15112.39 246.65 94.84 82.24 11.09 0.55 1.32
5.00 926.88
205.00 185.07 236.24 14553.11 235.33 90.48 78.47 11.09 0.55 1.32
5.00 918.83
210.00 182.46 254.94 13930.43 228.81 87.98 76.30 11.09 0.55 1.32
5.00 890.55
215.00 173.76 147.49 12761.05 219.90 84.54 73.32 11.09 0.55 1.32
5.00 849.40
220.00 166.00 80.57 12302.78 210.39 80.90 70.15 11.09 0.55 1.32
5.00 815.93
225.00 160.37 90.37 11534.44 202.09 77.70 67.38 11.09 0.55 1.32
5.00 786.20
230.00 154.11 84.50 10789.22 194.70 74.86 64.92 11.09 0.55 1.32
5.00 756.80
235.00 148.61 86.51 10106.84 187.81 72.20 62.62 11.09 0.55 1.32
5.00 731.98
240.00 144.18 108.24 9421.24 181.78 69.88 60.62 11.09 0.55 1.32
5.00 706.50
245.00 138.42 102.13 8664.64 176.03 67.68 58.70 11.09 0.55 1.32
5.00 679.55
250.00 133.40 110.77 8107.45 147.58 56.74 49.22 11.09 0.55 1.32
5.00 655.08
255.00 128.63 120.91 7545.53 142.01 54.60 47.36 11.09 0.55 1.32
5.00 630.45
260.00 123.55 131.00 6998.20 137.27 52.76 45.77 11.09 0.55 1.32
5.00 602.95
265.00 117.63 150.64 6470.98 133.03 51.14 44.37 11.09 0.55 1.32
5.00 571.10
270.00 110.81 154.61 5926.32 128.51 49.40 42.86 11.09 0.55 1.32
5.00 535.15
275.00 103.25 143.14 5359.00 124.36 47.80 41.47 11.09 0.55 1.32
5.00 500.30
280.00 96.87 123.53 4805.71 120.59 46.34 40.22 11.09 0.55 1.32
280.00 96.87 123.53 4805.71 120.59 46.34 40.22 11.09 0.55 1.32
5.00 468.90
285.00 90.69 108.48 4248.41 115.43 44.36 38.49 11.09 0.55 1.32
5.00 432.93
290.00 82.48 77.53 3678.61 109.06 41.92 36.37 11.09 0.55 1.32
5.00 394.20
295.00 75.20 74.35 3123.43 102.28 39.32 34.11 11.09 0.55 1.32
5.00 357.45
300.00 67.78 68.56 2555.64 98.09 37.70 32.72 11.09 0.55 1.32
5.00 320.00
305.00 60.22 58.32 2023.94 91.83 35.34 30.60 11.09 0.55 1.32
5.00 282.50
310.00 52.78 48.31 1529.71 85.22 32.78 28.39 11.09 0.55 1.32
5.00 249.00
315.00 46.82 44.16 1119.94 78.29 30.12 26.09 11.09 0.55 1.32
5.00 219.28
320.00 40.89 38.45 749.97 71.23 27.40 23.74 11.09 0.55 1.32
5.00 191.73
325.00 35.80 41.00 430.29 44.98 17.30 14.99 11.09 0.55 1.32
5.00 173.28
330.00 33.51 38.10 223.18 33.51 12.90 11.17 11.09 0.55 1.32
5.00 134.85
335.00 20.43 27.90 69.95 12.57 4.84 4.19 11.09 0.55 1.32
2.54 25.95
337.54 - - 0.00 8.92 3.44 2.96 11.09 0.55 1.32
-
-
VOLUME
(cu.m.)
- - - - - - - -
- - - - - - - -
Page 1 of 1
QUANTITY SHEET
CONSTRUCTION OF BALUD DAM WATER SUPPLY PROJECT
B. DAM Structure
STATION Length Bars
(0+ ) (m.)
Length
Front Back Bar Dia. No. of Bars No. of Bars Total No. of 6m-
(Trans.) (Longi.) bar (Trans.)
0.00 5.00 154.29 - 12.00 772.00 25.00 772.00
5.00 5.00 166.17 8.97 12.00 831.00 25.00 831.00
10.00 5.00 191.67 22.11 12.00 959.00 25.00 959.00
15.00 5.00 225.96 36.60 12.00 1130.00 25.00 1130.00
20.00 5.00 266.25 54.48 12.00 1332.00 25.00 1332.00
25.00 5.00 303.36 85.83 12.00 1517.00 25.00 1517.00
30.00 5.00 326.76 131.58 12.00 1634.00 25.00 1634.00
35.00 5.00 339.00 152.22 12.00 1695.00 25.00 1695.00
40.00 5.00 350.70 166.05 12.00 1754.00 25.00 1754.00
45.00 5.00 360.00 180.30 12.00 1800.00 25.00 1800.00
50.00 5.00 377.13 208.83 12.00 1886.00 25.00 1886.00
55.00 5.00 394.80 231.75 12.00 1974.00 25.00 1974.00
60.00 5.00 409.08 254.37 12.00 2046.00 25.00 2046.00
65.00 5.00 424.14 282.66 12.00 2121.00 25.00 2121.00
70.00 5.00 440.55 299.04 12.00 2203.00 25.00 2203.00
75.00 5.00 456.57 308.88 12.00 2283.00 25.00 2283.00
80.00 5.00 476.01 321.48 12.00 2381.00 25.00 2381.00
85.00 5.00 501.15 339.51 12.00 2506.00 25.00 2506.00
90.00 5.00 536.94 361.98 12.00 2685.00 25.00 2685.00
95.00 5.00 540.21 378.66 12.00 2702.00 25.00 2702.00
100.00 5.00 538.26 413.55 12.00 2692.00 25.00 2692.00
105.00 5.00 524.79 1,159.65 12.00 2624.00 25.00 2624.00
110.00 5.00 515.28 428.73 12.00 2577.00 25.00 2577.00
115.00 5.00 509.73 430.05 12.00 2549.00 25.00 2549.00
120.00 5.00 506.76 433.17 12.00 2534.00 25.00 2534.00
125.00 5.00 504.87 440.19 12.00 2525.00 25.00 2525.00
130.00 5.00 507.39 447.90 12.00 2537.00 25.00 2537.00
135.00 5.00 518.70 460.23 12.00 2594.00 25.00 2594.00
140.00 5.00 622.50 469.29 12.00 3113.00 25.00 3113.00
145.00 5.00 619.83 480.00 12.00 3100.00 25.00 3100.00
150.00 5.00 617.19 490.50 12.00 3086.00 25.00 3086.00
155.00 5.00 610.89 490.38 12.00 3055.00 25.00 3055.00
160.00 5.00 602.40 490.38 12.00 3012.00 25.00 3012.00
165.00 5.00 591.99 490.38 12.00 2960.00 25.00 2960.00
170.00 5.00 586.77 490.38 12.00 2934.00 25.00 2934.00
175.00 5.00 582.75 490.38 12.00 2914.00 25.00 2914.00
180.00 5.00 576.78 490.38 12.00 2884.00 25.00 2884.00
185.00 5.00 551.91 490.38 12.00 2760.00 25.00 2760.00
190.00 5.00 538.71 412.83 12.00 2694.00 25.00 2694.00
195.00 5.00 528.45 404.13 12.00 2643.00 25.00 2643.00
200.00 5.00 516.48 390.87 12.00 2583.00 25.00 2583.00
205.00 5.00 487.08 376.74 12.00 2436.00 25.00 2436.00
210.00 5.00 475.08 363.69 12.00 2376.00 25.00 2376.00
215.00 5.00 455.13 349.32 12.00 2276.00 25.00 2276.00
220.00 5.00 435.15 332.76 12.00 2176.00 25.00 2176.00
225.00 5.00 420.63 315.30 12.00 2104.00 25.00 2104.00
230.00 5.00 406.74 300.81 12.00 2034.00 25.00 2034.00
235.00 5.00 396.21 284.85 12.00 1982.00 25.00 1982.00
240.00 5.00 383.01 274.83 12.00 1916.00 25.00 1916.00
245.00 5.00 370.95 264.78 12.00 1855.00 25.00 1855.00
250.00 5.00 286.26 240.06 12.00 1432.00 25.00 1432.00
255.00 5.00 276.24 228.66 12.00 1382.00 25.00 1382.00
260.00 5.00 267.72 218.91 12.00 1339.00 25.00 1339.00
265.00 5.00 263.31 207.03 12.00 1317.00 25.00 1317.00
270.00 5.00 259.38 193.56 12.00 1297.00 25.00 1297.00
275.00 5.00 255.06 181.95 12.00 1276.00 25.00 1276.00
280.00 5.00 253.17 169.32 12.00 1266.00 25.00 1266.00
285.00 5.00 247.56 155.07 12.00 1238.00 25.00 1238.00
290.00 5.00 238.50 139.65 12.00 1193.00 25.00 1193.00
295.00 5.00 225.60 185.88 12.00 1128.00 25.00 1128.00
300.00 5.00 218.01 117.93 12.00 1091.00 25.00 1091.00
305.00 5.00 206.91 111.99 12.00 1035.00 25.00 1035.00
310.00 5.00 196.95 96.51 12.00 985.00 25.00 985.00
315.00 5.00 190.35 76.47 12.00 952.00 25.00 952.00
320.00 5.00 182.22 57.42 12.00 912.00 25.00 912.00
325.00 5.00 98.34 40.35 12.00 492.00 25.00 492.00
330.00 5.00 69.57 25.02 12.00 348.00 25.00 348.00
335.00 2.54 4.68 9.39 12.00 24.00 12.70 13.00
337.54 - - 0.00 0.00 0.00 0.00
120,397.00
Page 1 of 1
Unit Cost Analysis for Hauling Cost for Embankment & Sub-base Course
CONSTRUCTION OF BALUD DAM WATER SUPPLY PROJECT
Sta. 0+000 - Sta. 0+337.54
BRGY. ILAYA - MAPILI - VICTORY, BALUD, MASBATE
Quarry Site
Hauling Distance = 40.0 kms.
Item No. : All Aggregates
Terrain : Flat to Rolling
Effective Working Hours : 8.00 hrs
Time Motion Analysis :
Dumptruck :
Speed when Loaded : 30.0 kph
Speed when Unloaded : 40.0 kph
121 = 29.88
= X8
3.24 x 10
Computation of Hauling Cost : Say 30.0 Dumptrucks
Equipment :
Labor : 13,864.00
340,800.0
354,664.00
=
Hauling Cost per cu.m. = 356,308.40 368.09
968.0
Say 368.00
Amount of items are based on Construction Materias Price Data (CMPD) Validation Q2 CY2024
Aggregate Sub Base Course Ᵽ690.00
Embankment Ᵽ480.00
Cost of Sub Base Course = Ᵽ690.00 + 368 =
Cost of Embankment = Ᵽ480.00 + 368 =
Prepared by:
Submitted by:
80.0 mins.
0.00 mins.
3.24 Trips
.m.
29.88
13,864.00
340,800.00
354,664.00
646.00
998.40
1,644.40
356,308.40
368.09
828.00
668.00
. AROLLADO
Unit Cost Analysis for Hauling Cost for Fine Sand & Coarse Aggregates
CONSTRUCTION OF BALUD DAM WATER SUPPLY PROJECT
Sta. 0+000 - Sta. 0+337.54
BRGY. ILAYA - MAPILI - VICTORY, BALUD, MASBATE
Terrain Road Condition Ave. Travel Speed Hauling Distance Travel Time (hr)
Loaded Empty (km) Loaded
Flat Paved 35 55 56.0 1.60
Unpaved 30 45 0.0 0
Rolling Paved 30 40 16.0 0.53
Unpaved 25 35 0.0 0
Mountainous Paved 20 30 8.0 0.4
Unpaved 10 25 0.0 0
Total travel Time (hr) Loading Time (hr) Unloading Time (hr)
Allowance for delay (10% of Cycle Time)
Total Cycle Time (hr)
Trips/ day 8.00 trip-hr
No. of Trips 1.86 trip trips per day/ total cycle time No. of bags
hauled per day 18.61 loading capacity x No. of trips
Price for Hauling
I. Equipment :
Say 637.00
Base Cost from Masbate City: Derived Cost:
Fine Aggregates 2,085.00 /cu.m. 2,722.00 /cu.m.
Natural Gravel 995.00 /cu.m. 1,632.00 /cu.m.
Gravel (G3/4) 2,300.00 /cu.m. 2,937.00 /cu.m.
Gravel (G1) 2,157.00 /cu.m. 2,794.00 /cu.m.
Gravel (G1-1/2) 2,102.00 /cu.m. 2,739.00 /cu.m.
Gravel (G2) 2,046.00 /cu.m. 2,683.00 /cu.m.
Gravel (G2-1/2) 1,990.00 /cu.m. 2,627.00 /cu.m.
Boulders (Stone Masonry) 1,300.00 /cu.m. 1,937.00 /cu.m.
Prepared by: Submitted by:
ALLEN P. ESTRELLA ARNEL F. AROLLADO
MUNICIPAL ENGINEER MPDC
DERIVATION OF HAULING COST FOR REINFORCING STEEL BAR
rse Aggregates
ROJECT
11,360.00
0.00
0
9.20
637.16
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
ADO
Project: CONSTRUCTION OF BALUD DAM WATER SUPPLY PROJECT
Limit: Sta. 0+000 - Sta. 0+337.54
Location: BRGY. ILAYA - MAPILI - VICTORY, BALUD, MASBATE
A. Hauling from Source to Site:
Source: Masbate City
Project Site: BRGY. ILAYA - MAPILI - VI - Estimated
Hauling Equiptment Used: Cargo Truck (5T)
Loaded Empty
1.43 0.91
0.00 0.00
0.43 0.33
0.00 0.00
0.37 0.25
0.00 0.00
3.71
0.59
0.59
0.49
5.39
6,264.00 = P 6,264.00
P 646.00
P 1,996.80
8,906.80
1.58
Total
44.05
44.62
DERIVATION OF HAULING COST FOR PORTLAND CEMENT
Project:
CONSTRUCTION OF BALUD DAM WATER SUPPLY PROJECT
= 300.00 + 48.12
= 348.12 /bag
Prepared by: Checked by: Submitted by:
ALLEN P. ESTRELLA ARNEL F. AROLLADO
MUNICIPAL ENGINEER MPDC
quiptment Used: Dumptruck 10.00
Empty
0.91
0.00
0.33
0.00
0.25
0.00
3.71
1.88
1.88
0.75
8.21
,360.00 = P 11,360.00
P 646.00
P 1,996.80
14,002.80
48.12