Method Statement For Block Works Rev01
Method Statement For Block Works Rev01
METHOD STATEMENT
REVIEWER /
REV DATE STATUS REVISION DETAILS APPROVER
RCC EHAF
Page 1 of
Client: Jabal Omar Dev. PMC: Hill Main Consultant: Ehaf Contractor: RCC
Corp International Consulting
Page 2 of
Client: Jabal Omar Dev. PMC: Hill Main Consultant: Ehaf Contractor: RCC
Corp International Consulting
Content
Page no.
Reply Sheet 2
Contents 3
Introduction 4
Scope 4
Material Specification 4
Accessories Specification 5
Inspection Procedure 8
Work procedures 9
Tolerances 15
Risk Assessment 19
Page 3 of
Client: Jabal Omar Dev. PMC: Hill Main Consultant: Ehaf Contractor: RCC
Corp International Consulting
INTRODUCTION
The purpose of this method statement is to provide a clear and safe step by step
procedure for the execution of a particular work. This method statement covers the
proposed methodology for installation of Blockworks specified below, and as per
specification division 04810: Unit Masonry Assemblies
Thickness w 15 mm plaster
Solid kg/m2 (PSF) bare one side both sides
100 mm 200 (41.50) 47 48 48
150 mm 300 (62.25) 51 52 53
200 mm 400 (83) 55 56 57
250 mm 500 (103.75) 58 59 60
300 mm 600 (124.5) 62 63 64
Page 4 of
Client: Jabal Omar Dev. PMC: Hill Main Consultant: Ehaf Contractor: RCC
Corp International Consulting
Page 5 of
Client: Jabal Omar Dev. PMC: Hill Main Consultant: Ehaf Contractor: RCC
Corp International Consulting
workers hauling of materials and ensure they are complete with safety
gears and equipment.
o Site Control
1. KE QA/QC inspector together with the foreman will check if the site is
already suitable to install the Block works and if find any discrepancies or
deviation according to plan notify and submit to RCC QA/QC.
2. Surveying, checking lines, fixing necessary points, should be done by KE
Surveyor. The KE Surveyor shall be responsible to coordinate with Main
Contractor to provide primary reference to establish lines and points
necessary to complete the works in accordance with the tolerances of
specification. Main contractor to render datum and grid line plans clearly
marked on site, carried out in accordance with the For Construction
Drawings.
3. Copy of approved shop drawings shall be available on site. KE
Document controller upon receiving of the approved drawings, shall
provide copies to site in charge, 1 copy to the Site Engineer, 1 copy to
the foreman, 1 copy to QA/QC and 1 to be posted on site.
4. Logistic officer shall coordinate with main contractor to secure availability
of water and electricity supplies.
5. Safety officer is responsible to clean the area and clear any obstructions,
make necessary sign on areas prone to accidents.
6. The site shall be inspected by the owner or its representative prior to
commencement of any work identified as Hold Points in the Inspection
and Test Plans.
7. Method statement shall be introduced by the QA/QC Manager to all workers
and site in charge prior to commencement of block work installation, on tool
box meeting.
Page 6 of
Client: Jabal Omar Dev. PMC: Hill Main Consultant: Ehaf Contractor: RCC
Corp International Consulting
A. Store masonry units on elevated platforms in a dry location. If units are not
stored in an enclosed location, cover tops and sides of stacks with waterproof
sheeting, securely tied. If units become wet, do not install until they are dry.
1. Protect Type I concrete masonry units from moisture absorption so that, at the
time of installation, the moisture content is not more than the maximum allowed at the
time of delivery.
B. Deliver pre-blended, dry mortar mix in moisture-resistant containers designed
for lifting and emptying into dispensing silo. Store pre-blended, dry mortar mix in
delivery containers on elevated platforms, under cover, and in a dry location or in a
metal dispensing silo with weatherproof cover.
C. Store masonry accessories, including metal items, to prevent corrosion and
accumulation of dirt and oil.
Page 7 of
Client: Jabal Omar Dev. PMC: Hill Main Consultant: Ehaf Contractor: RCC
Corp International Consulting
INSPECTION PROCEDURE:
STEP 1:
KE QA/QC Inspector / Construction Manager identifies the key stages of inspection with full compliance
with the requirements of specification, A check list has to be signed by KE for acceptance of the area
ready to work RCC has to formally send a clearance form prior to check the area “
STEP 2:
KE Construction Manager and QA/QC Inspector shall be responsible to ensure that any snags written on the
check list is done by the main contractor.
STEP 3:
Upon Completion of the snagging items, KE QA/QC will sign the clearance form and work preparation will
commence.
STEP 4:
Main contractor shall be responsible to notify the consultant about the progress of work step by step
STEP 5:
RCC shall inspect the works, if inspection is not approved they shall issue a snag list. KE shall repeat
starting step 3 until work is approved by RCC after which and IR will be issued to consultant
STEP 6:
RCC shall endorse to the consultant upon approving the inspection request
STEP 7:
Consultant shall inspect the work, and add his comments if any.
STEP 8a:
If Approval is coded A, KE Document controller shall be responsible for the documentation of the results.
KE shall now proceed to the next stage of work. If all works are already finished and inspected, Protection
of work shall be KE Construction Managers responsibility until the work is properly Handed over.
STEP 8b:
If Approval is coded B, KE Site Engineer and foreman shall address the comments in respect with the agreed
time period.
Page 8 of
Client: Jabal Omar Dev. PMC: Hill Main Consultant: Ehaf Contractor: RCC
Corp International Consulting
STEP8c:
If inspection request is rejected , consultant should address his snags and KE shall repeat point 3 onward
Work Procedure:
WORK PROCEDURE
Work Description
1. Before installation, examine rough-in and built-in construction for piping systems to verify
actual locations of piping connections.
2. Make sure all proper installations, cutting and levelling tools are ready for use at the site
8. The floor slab where CMU walls to be built will be chipped and cleaned
9. Prepare a sufficient amount of cement, sand and water ready for mixing at the time of
installation note that mix shall be used within 45 minutes maximum, hence no extra
mix shall be mixed.
10. Make sure that all materials and quality of work meet the requirements of the
specifications and shop drawings.
11. Prepare the floor for installation of first course by washing with water and keeping area
moist for proper bonding.
Page 9 of
Client: Jabal Omar Dev. PMC: Hill Main Consultant: Ehaf Contractor: RCC
Corp International Consulting
12. Set-out the first course (base course) as a mock up with proper levelling. This course
will act as the foundation course for the remaining levels.
13. Prepare the mortar mix. Make sure not to mix a large batch. Mix enough mortar for your
immediate work. Any excess mix will be discarded. No mix will be used after left
standing
14. Standard Walls
A running bond system is to be used for installation and any cutting of blocks will
be done with the proper cutting tools or half blocks are to be used where
applicable.
Lay out walls in advance for accurate spacing of surface bond patterns with
uniform joint thicknesses and for accurate location of openings, movement-type
joints, returns, and offsets.
Lay concealed masonry with all units in a Wythe in running bond or bonded by
lapping not less than 50 mm. Bond and interlock each course of each Wythe at
corners. Do not use units with less than nominal 100-mm horizontal face
dimensions at corners or jambs.
Drill and grout steel reinforcement before installation of 1st layer of CMU blocks.
Place mortar in masonry unit bed joint back 6mm from edge of unit grout spaces,
bevel back and upward. Permit mortar to cure before placing grout.
Install the first course using block and mortar as per plan and wall location. Make
sure the base course is properly leveled and straight with proper jointing
distances as per specifications.
Connect the first course to the wall or column with the proper metal accessories
as per specifications and as indicated in approved shop drawings. Make sure to
install the required filler board backing rod at connection to walls and columns. At
the connection to the reinforced side walls and columns, use corrugated tie
anchors (L shaped) as per specifications to tie to column and walls every 3
courses continuously on center. Make sure the anchors are secured with butt
head pans explosive cartridges.
Continue the next 3 courses, maintaining the proper level. Maintain a proper flush
wall and running bond construction. Wet the installed blocks and new blocks prior
to installation to prevent too rapid drying out of the mortar but make sure they are
not over saturated with water. This should apply to all block works.
Make sure excess mortar from joint are continuously removed in order to have
proper packed joints.
Page 10 of
Client: Jabal Omar Dev. PMC: Hill Main Consultant: Ehaf Contractor: RCC
Corp International Consulting
Do not shift blocks or tap masonry units after mortar has initially set.
Perform on site cutting with proper tools for straight, clean and unchipped edges.
At the top of course number 3, install a 3.76mm ladder mesh reinforcement laid
on top and remaining course. Repeat this process every 3 courses until the ceiling
slab or ceiling beam is reached.
For connection with the ceiling slab or ceiling beam, use rigid steel anchor (block
wall up blinding anchor) as per specifications and as indicated in the approved
shop drawings.
Fasten partition top anchors to structure above and build into top of partition.
Grout cells of CMUs solidly around anchors and push tubes down into grout to
provide 13- mm clearance between end of anchor rod and end of tube. Space
anchors 1200 mm
o.c. unless otherwise indicated.
Horizontal 10mm joint between block work internal partition and soffits of beams
or slab shall be left clear and free from mortar and compressible joint filler shall be
placed into the joints.
All corners and intersection of block work walls are to be bonded or tied at every
other course for the full height of the wall, unless movement joints are required
(see specifications for the type of accessories used)
For all opening in block work walls, build two continues voids of hollow block work
for the full height of the wall immediately adjacent to the opening: they are to be
completely filled concrete or grout. The two filled voids are to be reinforced with 1
number 12mm. dia steel bar per void at 1250mm O.C. and secured with tying
wire.
Horizontal bond beams: Where horizontal bond beams are required for lateral
support, they shall be located at the door height or as directed by the Engineer.
Lintels, pad stone etc. shall be true to the line and level and bedded on mortar of
the specified quality.
For the 200mm x 400mm post, install 6T12 vertical bars and T10 stirrups spaced
at every 200mm. Construct necessary formwork.
After completion of installation, cure the CMU blocks prior to plastering.
15. Fire Stopping
Procedure is the same as normal block however the top treatment will be different
At fire-rated partitions, treat joint between top of partition and underside of structure
Page 11 of
Client: Jabal Omar Dev. PMC: Hill Main Consultant: Ehaf Contractor: RCC
Corp International Consulting
A. Fabricate shelf angles from steel angles of sizes indicated and for attachment
to concrete framing. Provide horizontally slotted holes to receive 19-mm bolts,
spaced not more than 150 mm from ends and 600 mm o.c., unless otherwise
indicated.
1. Provide mitered and welded units at corners.
2. Provide open joints in shelf angles at expansion and control joints. Make
open joint approximately 50 mm larger than expansion or control joint.
B. For cavity walls, provide vertical channel brackets to support angles from
backup masonry and concrete.
B. Form control joints in concrete masonry using one of the following methods as
directed by Engineer:
1. Fit bond-breaker strips into hollow contour in ends of CMUs on one side of control
joint. Fill resultant core with grout and rake out joints in exposed faces for
application of sealant.
2. Install preformed control-joint gaskets designed to fit standard sash block.
3. Install interlocking units designed for control joints. Install bond-breaker strips at joint.
Keep head joints free and clear of mortar or rake out joint for application of sealant.
4. Install temporary foam-plastic filler in head joints and remove filler when unit
masonry is complete for application of sealant.
Page 12 of
Client: Jabal Omar Dev. PMC: Hill Main Consultant: Ehaf Contractor: RCC
Corp International Consulting
C. Install Single-Wythe CMU flashing system in bed joints of CMU walls where
indicated to comply with manufacturer's written instructions. Install CMU cell pans with
upturned edges located below face shells and webs of CMUs above and with weep
spouts aligned with face of wall. Install CMU web covers so that they cover
upturned edges of CMU cell pans at CMU webs and extend from face shell to face
shell.
D. Install reglets and nailers for flashing and other related construction where they
are shown to be built into masonry.
Page 13 of
Client: Jabal Omar Dev. PMC: Hill Main Consultant: Ehaf Contractor: RCC
Corp International Consulting
E. Install weep holes in head joints in exterior wythes of first course of masonry
immediately above embedded flashing and as follows:
1. Use specified weep/vent products to form weep holes.
2. Use wicking material to form weep holes above flashing under brick sills.
Turn wicking down at lip of sill to be as inconspicuous as possible.
3. Space weep holes 600 mm o.c. unless otherwise indicated.
4. Cover cavity side of weep holes with plastic insect screening at cavities
insulated with loose-fill insulation.
5. Trim wicking material flush with outside face of wall after mortar has set.
H. Install vents in head joints in exterior wythes at spacing indicated. Use specified
weep/vent products to form vents.
1. Close cavities off vertically and horizontally with blocking in manner
indicated. Install through-wall flashing and weep holes above horizontal
blocking.
4.Reinforced Unit
A. Temporary Formwork and Shores: Construct formwork and shores as needed
to support reinforced masonry elements during construction.
1. Construct formwork to provide shape, line, and dimensions of completed
masonry as indicated. Make forms sufficiently tight to prevent leakage of mortar and
grout. Brace, tie, and support forms to maintain position and shape during
construction and curing of reinforced masonry.
2. Do not remove forms and shores until reinforced masonry members have
hardened sufficiently to carry their own weight and other loads that may be
placed on them during construction.
B. Placing Reinforcement: Comply with requirements in ACI 530.1/ASCE
6/TMS 602. C. Grouting: Do not place grout until entire height of masonry to be
grouted has attained enough strength to resist grout pressure.
1. Comply with requirements in ACI 530.1/ASCE 6/TMS 602 for cleanouts and for
grout placement, including minimum grout space and maximum pour height.
2. Limit height of vertical grout pours to not more than 1520 mm.
Page 14 of
Client: Jabal Omar Dev. PMC: Hill Main Consultant: Ehaf Contractor: RCC
Corp International Consulting
5.Repairing/Jointing/Cleaning .
A. Remove and replace masonry units that are loose, chipped, broken, stained,
or otherwise damaged or that do not match adjoining units. Install new units to
match adjoining units; install in fresh mortar, pointed to eliminate evidence of
replacement.
B. Pointing: During the tooling of joints, enlarge voids and holes, except weep
holes, and completely fill with mortar. Point up joints, including corners, openings,
and adjacent construction, to provide a neat, uniform appearance. Prepare joints for
sealant application, where indicated
6.Waste disposal.
A. Salvageable Materials: Unless otherwise indicated, excess masonry
materials are Contractor's property. At completion of unit masonry work,
remove from Project site.
B. Waste Disposal as Fill Material: Dispose of clean masonry waste, including excess
or soil- contaminated sand, waste mortar, and broken masonry units, by crushing
and mixing with fill material as fill is placed.
1. Crush masonry waste to less than 100 mm in each dimension.
2. Mix masonry waste with at least two parts of specified fill material for each
part of masonry waste. Fill material is specified in Division 2 Section
"Earthwork."
3. Do not dispose of masonry waste as fill within 450 mm of finished grade.
C. Excess Masonry Waste: Remove excess clean masonry waste that cannot be used
as fill, as described above, and other masonry waste, and legally dispose of off
Employer's property.
TOLERANCES
Page 15 of
Client: Jabal Omar Dev. PMC: Hill Main Consultant: Ehaf Contractor: RCC
Corp International Consulting
2. For location of elements in plan do not vary from that indicated by more than plus
or minus 12 mm.
3. For location of elements in elevation do not vary from that indicated by more
than plus or minus 6 mm in a story height or 12 mm total
B. Lines and Levels:
1. For bed joints and top surfaces of bearing walls do not vary from level by more
than 6 mm in 3 m, or 12 mm maximum.
2. For conspicuous horizontal lines, such as lintels, sills, parapets, and
reveals, do not vary from level by more than 3 mm in 3 m, 6 mm in 6 m, or 12 mm
maximum.
3. For vertical lines and surfaces do not vary from plumb by more than 6 mm in
3 m, 9 mm in 6 m, or 12 mm maximum.
4. For conspicuous vertical lines, such as external corners, door jambs,
reveals, and expansion and control joints, do not vary from plumb by more than
3 mm in 3 m, 6 mm in 6 m, or 12 mm maximum.
5. For lines and surfaces do not vary from straight by more than 6 mm in 3 m, 9
mm in 6 m, or 12 mm maximum.
6. For vertical alignment of exposed head joints, do not vary from plumb by more
than 6 mm in 3 m, or 12 mm maximum.
C. Joints:
1. For bed joints, do not vary from thickness indicated by more than plus or minus
3 mm, with a maximum thickness limited to 12 mm.
2. For exposed bed joints, do not vary from bed-joint thickness of adjacent courses
by more than 3 mm.
3. For head and collar joints, do not vary from thickness indicated by more than
plus 9 mm or minus 6 mm.
4. For exposed head joints, do not vary from thickness indicated by more than
plus or minus 3 mm. Do not vary from adjacent bed-joint and head-joint
thicknesses by more than 3 mm.
5. For exposed bed joints and head joints of stacked bond, do not vary from a
straight line by more than 1.5 mm from one masonry unit to the next.
Page 16 of
Client: Jabal Omar Dev. PMC: Hill Main Consultant: Ehaf Contractor: RCC
Corp International Consulting
Responsibilities:
Project Manager should ensure:
All work is carried out within the terms of relevant specifications and drawings
Specific attention is paid to all safety measures and quality control in
coordination with Safety Engineer and QC Engineer and in line with HSE
plan and Quality plan.
Project Manager shall be responsible for overall project execution, he will
coordinate with client and head office, progress monitoring, attending review
meeting, resource management, overall he will be responsible for timely
completion of project in accordance to all contractual requirements.
The implementation of any request that might be raised by the Consultant.
Location of manpower, materials and equipment a n d monitoring their
timely supply at construction location.
Page 17 of
Client: Jabal Omar Dev. PMC: Hill Main Consultant: Ehaf Contractor: RCC
Corp International Consulting
9 Testing of Blocks for Compressive Strength Every 464 sq.m Test Report Sub H R&A
Abbreviations: Sub- SUBMIT, H- HOLD, R&A- REVIEW & APPROVE, RC- RANDOM CHECK, I&A- INSPECT &
APPROVE, S- SURVEILANCE, CL= CHECKLIST, IR- INSPECTION REQUEST, I- INSPECT
Page 18 of
KOCACHE RISK ASSESSMENT For: Installation OF BLOCKWORKS
6. Head, Hand and Foot Injuries 6 8 9 7.7 (High) Use safety shoes, hard hats and Workers, All site H&S Dept, Site
gloves personnels, Visitors, Engineer in‐
Contractors, Passerby charge
Note: To Control the Site work hazards the following should be observed;
Site work hazard are common to all The value of each parameter (CR, TR and VR) varies from 1 to 10, where 1 Safety rules enforcements, Regular inspection on site, Regular inspection of tools and equipments,
works varying only according to Risk represents the lowest risk and 10 represents the highest contribution of Awareness to safety hazards by making perimeter protections and signs, Wearing PPE’s at all times
assessment Ratings in each type of risk.
work.
Low (1‐3), Moderate (4‐6), High (7‐9) and 100%probability (10)
Page 19 of