Chat GPT Content For Smaran

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
6 views4 pages

Chat GPT Content For Smaran

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 4

Based on the WBS structure from the image provided, I will create a PERT analysis for each task

listed.
Here's the breakdown of the tasks and how I'll estimate their time:
WBS Levels and Tasks
1. 1.1: Identify Medical Illness
o 1.1.1: Research on Medical Facilities

o 1.1.2: Research on Specialized Hospitals

o 1.2.1: Schedule Meetings with Doctors

o 1.2.2: Schedule Interviews

o 1.2.5: Schedule Personal Testimonials

2. 1.3: Record and Transcribe Interviews


o 1.3.2: Record and Transcribe Interviews

o 1.3.3: Collect Photo Testimonials

3. 2.1: Review Medical Data


4. 2.2: Review Budget Report
5. 2.3: Review Testimonials
6. 2.5: Finalize Report
7. 3.1: Tailoring Bids
8. 3.2: Scoping Out Potential Bidders
9. 3.4: Send Bids Out
Randomized Time Estimates for PERT Analysis
For each of these tasks, I will estimate optimistic (O), most likely (M), and pessimistic (P) durations.
Task 1.1: Identify Medical Illness
 1.1.1 Research on Medical Facilities
o O: 4 days

o M: 6 days

o P: 10 days

o TE: 4+4(6)+106=6.33\frac{4 + 4(6) + 10}{6} = 6.3364+4(6)+10=6.33 days

 1.1.2 Research on Specialized Hospitals


o O: 3 days

o M: 5 days
o P: 9 days

o TE: 3+4(5)+96=5.33\frac{3 + 4(5) + 9}{6} = 5.3363+4(5)+9=5.33 days

Task 1.2: Scheduling & Testimonials


 1.2.1 Schedule Meetings with Doctors
o O: 2 days

o M: 4 days

o P: 7 days

o TE: 2+4(4)+76=4.17\frac{2 + 4(4) + 7}{6} = 4.1762+4(4)+7=4.17 days

 1.2.2 Schedule Interviews


o O: 3 days

o M: 5 days

o P: 8 days

o TE: 3+4(5)+86=5.17\frac{3 + 4(5) + 8}{6} = 5.1763+4(5)+8=5.17 days

 1.2.5 Schedule Personal Testimonials


o O: 4 days

o M: 6 days

o P: 9 days

o TE: 4+4(6)+96=6.17\frac{4 + 4(6) + 9}{6} = 6.1764+4(6)+9=6.17 days

Task 1.3: Interviews & Photos


 1.3.2 Record and Transcribe Interviews
o O: 5 days

o M: 7 days

o P: 12 days

o TE: 5+4(7)+126=7.67\frac{5 + 4(7) + 12}{6} = 7.6765+4(7)+12=7.67 days

 1.3.3 Collect Photo Testimonials


o O: 3 days

o M: 5 days

o P: 8 days

o TE: 3+4(5)+86=5.17\frac{3 + 4(5) + 8}{6} = 5.1763+4(5)+8=5.17 days


Task 2.1: Review Medical Data
 O: 4 days
 M: 7 days
 P: 10 days
 TE: 4+4(7)+106=7.00\frac{4 + 4(7) + 10}{6} = 7.0064+4(7)+10=7.00 days
Task 2.2: Review Budget Report
 O: 3 days
 M: 5 days
 P: 8 days
 TE: 3+4(5)+86=5.17\frac{3 + 4(5) + 8}{6} = 5.1763+4(5)+8=5.17 days
Task 2.3: Review Testimonials
 O: 2 days
 M: 4 days
 P: 7 days
 TE: 2+4(4)+76=4.17\frac{2 + 4(4) + 7}{6} = 4.1762+4(4)+7=4.17 days
Task 2.5: Finalize Report
 O: 5 days
 M: 8 days
 P: 12 days
 TE: 5+4(8)+126=8.50\frac{5 + 4(8) + 12}{6} = 8.5065+4(8)+12=8.50 days
Task 3.1: Tailoring Bids
 O: 3 days
 M: 5 days
 P: 9 days
 TE: 3+4(5)+96=5.33\frac{3 + 4(5) + 9}{6} = 5.3363+4(5)+9=5.33 days
Task 3.2: Scoping Out Potential Bidders
 O: 2 days
 M: 4 days
 P: 7 days
 TE: 2+4(4)+76=4.17\frac{2 + 4(4) + 7}{6} = 4.1762+4(4)+7=4.17 days
Task 3.4: Send Bids Out
 O: 2 days
 M: 3 days
 P: 5 days
 TE: 2+4(3)+56=3.17\frac{2 + 4(3) + 5}{6} = 3.1762+4(3)+5=3.17 days
Summary of Expected Times (TE)
 Task 1.1.1: 6.33 days
 Task 1.1.2: 5.33 days
 Task 1.2.1: 4.17 days
 Task 1.2.2: 5.17 days
 Task 1.2.5: 6.17 days
 Task 1.3.2: 7.67 days
 Task 1.3.3: 5.17 days
 Task 2.1: 7.00 days
 Task 2.2: 5.17 days
 Task 2.3: 4.17 days
 Task 2.5: 8.50 days
 Task 3.1: 5.33 days
 Task 3.2: 4.17 days
 Task 3.4: 3.17 days