اختيارات ادارة مشاريع
اختيارات ادارة مشاريع
• الرسائل1
• عبدالرحمن الفقيه
o 2008
o :المشاركات5212
o
o
مشاركة
#1
Project Quality Management PMP Exam
01-31-2009, 12:23 AM
Answer: D
Explanation: Memorize the numbers for 1–, 2–, 3- and 6-sigma.
16. All of the following are examples of a variable EXCEPT?
A. Size
B. Shape
C. Pounds
D. Weight
Answer: C
Explanation: A variable is something that will be measured.
Choice C is an attribute; what unit the variable will be measured
in.
17. A control chart shows seven data points in a row on side of
the mean. What should be done?
A. A design of experiments
B. Adjust the chart to reflect the new mean
C. Find an assignable cause
D. This is the rule of seven and can be ignored
Answer: C
Explanation: The rule of seven applies here. If you have seven
data points in a row on the same side of the mean, statistically,
the mean has shifted, calling for action to correct the problem.
18. You are managing a project in a just in time environment.
This will require more attention, because the amount of
inventory in such an environment is generally?
A. 45%
B. 10%
C. 12%
D. 0%
Answer: D
Explanation: With just in time, supplies are delivered when you
need them and not before. Therefore, you have little or no
inventory.
19. An Ishikawa diagram helps to:
A. Put information in its order of priority
B. Explore past outcomes
C. Show team responsibilities
D. Show functional responsibilities
Answer: B
Explanation: Notice that the choices for this question include the
definitions for many of the control tools. Such questions can
easily confuse you if you do not remember why you use each of
the tools. Choices C and D refer to the many responsibility charts
and therefore cannot be the best answer. Choice A refers to the
function of a Pareto chart.
20. In planning your project, which would generally have the
highest priority; quality, cost or schedule?
A. Cost is most important, quality next, and then schedule
B. Quality is more important than cost and schedule
C. Schedule is most important, quality next, and then cost
D. It is situational and must be decided by the project objectives
Answer: D
Explanation: This question is asking about overall importance of
quality. The triple constraint may be prioritized on each project
but they are generally of equal importance. In other words, do
not dismiss quality.
21. A project manager is using a cause-and-effect diagram with
the team to determine how various factors might be linked to
potential problems. In which step of the quality management
process is the project manager involved?
A. Quality analysis
B. Quality assurance
C. Quality control
D. Quality planning
Answer: D
Explanation: The key words here are “potential problems.” They
are looking into the future and, therefore, must be in quality
planning.
22. A project manager and team from a firm that designs railroad
equipment are tasked to design a machine to load stone onto
railroad cars. The design allows for 2% spillage, amounting to
over two tons of spilled rock per day. In which of the following
does the project manager document quality control, quality
assurance and quality improvements for this project?
23. During a team meeting, the team adds a specific area of extra
work to the project because they have determined it would
benefit the customer. What is wrong in this situation?
A. The team is gold plating
B. These efforts shouldn’t be done in meetings
C. Nothing. This is how to meet or exceed customer expectations
D. Nothing. The project manager is in control of the situation.
Answer: A
Explanation: This is an example of gold plating. You should
provide ONLY what the customer asked for in the scope
statement. The team does not know if their change will provide
benefit to the customer. Focus efforts on conforming to
requirement.
24. The project team has created a pain describing how they will
implement the quality policy. It addresses the organizational
structure, responsibilities, procedures and other information
about plans for quality. If this changes during the project,
WHICH of the following plans will also change?
A. Quality assurance
B. Quality management
C. Project
D. Quality control
Answer: C
Explanation: The plan described is the quality management plan.
Since this plan is include in the project plan, changing the quality
management plan will also change the project plan.
25. You are a project manager for a major information systems
project when someone from the quality department comes to
see you about it beginning a quality audit of your project. The
team, already under pressure to complete the project as soon as
possible, objects to the audit. You should explain to the team that
the purpose of a quality audit is.
A. Part of an ISO 9000 investigation
B. To check if the customer is following its quality process
C. To identify lessons learned that can improve performance on
the project
D. To check the accuracy of costs submitted by the team
Answer: C
Explanation: PMP’s definition of an audit is different from what
we are used to. An audit is a structured review of quality
activities to identify lessons learned. These lessons are used for
process improvement.
30. A project manager has just taken over the project from
another project manager during the executing phase. The
previous project manager created a project budget, determined
communications requirements and when on to complete work
packages. What should the new project manager do NEXT?
A. Coordinate performance of work packages
B. Identify quality standards
C. Begin risk identification
D. Execute the project plan
Answer: B
Explanation: Since the previous project manager did not finish
planning, choice D should not be the next activity. Risk
identification (choice C) sounds like a good choice, however,
choice B occurs before choice C. Performance of work packages
(choice A) is done after planning. The best answer is B.
31. A project is facing a major change to its project deliverables.
If the project manager is involved in determining which quality
standards are relevant to the change, the project manager must
be involved in:
A. Quality management
B. Quality assurance
C. Quality planning
D. Quality control
Answer: C
Explanation: Although quality planning usually occurs during
planning, it can occur during executing when there is a change.
خيارات أكثر+
o معجب0
•
•
•
•
•
الصلة
تقليص
AM.