Interview Preparation For MEP Site Engineer
Interview Preparation For MEP Site Engineer
First of all, thank you so much for giving me this type of opportunity to introduce myself in
front of you and your esteemed organisation.
My Name is Sushil Kumar Singh, | am from Bihar, Patna City and Vaishali District.
| have completed my class 10th from Bihar School Examination Board Patna in 2010 with
57.8 % of Marks. Also, | have completed class 12th from Bihar School Examination Board
Patnain 20212 with 73 % of Marks. then | have completed my Batchlar of Technology
Electrical and Electronics Engineering from Aryabhata knowledge university Patna, with 73%
of Marks.
When | have completed B. Tech, | have joined BL Kashyap and Sons Ltd as an Assistant
Electrical Engineer
for AIIMS Hospital Project Patna, From 2016 to 2019.
After completion of AlIMS Project | have joined Tribeni Construction Ltd as an Electrical
Engineer for Township Package where so many high rises building over there such as
Basement, ground Floor + 7th floor 5 tower, Shopping complex etc.
And when that project is completed, | have again joined BL Kashyap as a Senior Engineer
for
Redevelopment of Gomti Nagar Railway Station.
Where my job profile is to coordinate with Vendor, PMC, and Client.
Shop Drawing Review and Approval from PMC or Client.
Technical Data Sheet Review and Approval from PMC and Client.
Quantity Identify from Shop Drawing and Share with Procurement team for Procurement of
Materials.
When Contractor is onboard, | must conduct a Kick-off meeting and Work Progress Review
meeting on weekly of Half monthly basis. Where | have discussed with contractor how to
start smooth working and submission of required documents i.e. Labour Licence, CAR Policy,
or other compliances as per tender. Also discussed for Submission of Method statement,
Quality Plan, Checklist. Before starting a work, it is required to approved safe work method
statement and Inspection Testing Plan.
Classification - Public
Sushil Kumar
1S 694
4 | Copper Wire IS 732 Conductor IEC 60228
Insulation IEC 60502
5 PVC Conduit IS 732 1S 9537
6 MS Conduit IS 732 1S 9537
7 | Distribution Board IEC 61439
8 |SPMB IEC 61439
9 | RCCB IEC 61008
Conductor
1S 8130 & IEC 60228
10 | LV Cables IS 1255 Insulation
Classification - Public
Sushil Kumar
Classification - Public
Sushil Kumar
Multicriteria Detector - Above False Ceiling (Ceiling & False Ceiling 800 MM).
Response Indicator.
o
BULLET CAMERA
INFRA RED NIGHT VISION CAMERA
DAY NIGHT CAMERA
o
Classification - Public
Sushil Kumar
HVAC Works.
1. Ducting.
2. Piping.
3. Air Handling Unit Installation and Commissioning
a. Motor
b. Fan
c. Coil
d. Filter
Ceiling Suspended Unit.
Water Cooled Chiller.
Air Cooled Chiller.
Cooling Tower.
8. Expansion Tank.
HVAC Ventilation System
1. Public Toilet — 10 ACPH (Air Change Per Hour).
Plant Room and Substation — 15ACPH.
A ®N
Fire Fighting & Plumbing Works: A fire Fire Fighting system is an activity of prevention
during fire spread in a building.
1. Hydrant System
2. Water Curtain System
3. Sprinkler System
a. Fusible Link type
b. bulb cartage Type
A. Bulb cartage Type
a. Upright Type.
b. Pendent type.
c. Side Wall.
d. Concealed Type.
1. Moving Bed Bio Reactor (MBBR): moving bed biofilm reactor sewage treatment
plant is used in very less space, and that is known as a biofilm process. These are
Classification - Public
Sushil Kumar
the common definitions of all the sewage treatment plants. But what you must
choose is dependent on the situation as well as how you want to use them.
2. Membrane Bio Reactor (MBR): MBR water treatment plant uses the membrane
bioreactor for Wastewater Treatment Plant Design that is the combination of the
biological waste-water process and membrane process. This membrane
bioreactor design is the most used process to treat sewage water.
3. Sequential Batch Reactor (SBR): SBR- sequencing batch reactor plant uses the
activated sludge to treat the wastewater. It is used for reducing the organic
matters. It separates the water and activated sludge through the oxygen bubbles.
4. Component Of STP.
Bar Screen Chamber
oo
Pump
Details
For WTP:
Filter Feed Pump.
EalE o
Classification - Public
Sushil Kumar
5. Chlorinator.
6. Drainage Pump.
Type of transformer
1. Oil Type.
2. DryType
Testing Parameter of transformer
a. IRTest
b. Magnetic Balance Test.
c. Vector Group Test.
d. Winding Resistance Test.
e. Voltage Ratio Test
. Door Interlock.
g. Winding Trip Indicator.
h.
MCCB:
1. Thermal Magnetic
2. Thermal Electro Magnetic
3. RCCB: RCCB works on the principle of Kirchhoff's law, which states that the incoming
current must be equal to the outgoing current in a circuit.
4. MCB: When the current overflow occurs through MCB the Bimetallic Strip Get
Heated and MCB tripped.
General Note for Energizing of Panels: as per NBC 2026 Clouse. no 361 sub-Clouse 6E
4.1.2.1 Before energizing of LT and HT Panel we must ensure that all VCB, ACB, MCCB, CT,
PT, Busbar, Relay Setting testing is done before Prior to energizing.
1. ACB
a. Manual Draw Out (MDO)
b. Electrical Draw Out (EDO).
Testing Parameter of VACUUM / AIR CIRCUIT BREAKER TEST REPORT
Mechanical Checks
1. Mechanical charging-closing-tripping of breaker- 3 Operation
Classification - Public
Sushil Kumar
a. Metering Core
b. Protection Coré
c. Diffrential Core
Winding resistance test:
&
a. Core-1
b. Core-2
c. Core-3
d. Core-4
CT Ratio test
o
a. 50%
b. 100 %
Testing Parameter of Relay Setting.
1. OVER CURRENT PROTECTION: |EC CURVE TESTING — 51 [NI 3.0] (I>)
DEFINITE TIME / STAGE 1 O/C PROTECTION: 50 (I>>)
wN
Classification - Public
Sushil Kumar
Earthing: 1S 3043 and IEC Earthing is used to protect you from an electric shock. It does
this by providing a path (a protective conductor) for a fault current to flow to earth. It
also causes the protective device (either a circuit-breaker or fuse) to switch off the
electric current to the circuit that has the fault.
Type Of Earthing
1. 1T
2,17
3. TN-S: In this system, the Ground Conductor & Neutral Conductor are separate
throughout the distribution system. The protective conductor is the metallic
covering of the cable supplying the installation. All the exposed conductive parts of
the installation are connected to this protective conductor or via the main earthing
terminal of the installation.
TN-S System
m 2GRS
4. TN-C: The Neutral and the protective earth are combined into a single conductor
throughout the system. All the exposed & conductive parts of the installation are
connected to the PEN conductor. As per the 8(4) of the Electricity Safety, Quality and
Continuity Regulations 2002, “Consumer shall not combine the neutral and
protective functions in a single conductor in his customer’s installation”.
TN-C System
L3
PEN
5. TN-C-S: The Neutral and the protective earth are combined in a single conductor in a
part of the system. This type of earthing is also known as multiple protective
earthing. The supply system PEN conductor is earthed at two or more points and an
earth electrode may be necessary at or near the consumer’s installation. All the
exposed conductive parts of the installation are connected to the PEN conductor via
the main earthing terminal & the neutral terminal and these terminals are linked
Classification - Public
Sushil Kumar
together. TN-C-S
)
Supply Installation
™} Source
of Energy
S
—
CNE (PEN) Conductor
Source of Earth
Fuel System.
Water Level
S3~FT
Classification - Public
Sushil Kumar
Road: 5-20
o
Classification - Public