Employer Construction of Townhouses & Semi-Detached Villas Phase 1B & 1C
Employer Project Manager Royal Development Company
Employer Project Manager RAPM Architect Project Management Engineer AECOM Middle East LLC Main Contractor M/s. Trojan General Contracting LLC MEP Contractor M/s. Royal Advance Electromechanical Works LLC Name: Ahmed M S Abouswirh Position: Project Manager Company: ROYAL ADVANCE ELECT. From Name: Sharaf Shaban Bamne Position: Projects Director/Project Manager Company: TROJAN To Name: Suheib Aboamir Position : Resident Engineer (RE) Company: AECOM Name: Mohammad Mostafa Position: Project Manager Company: RAPM cc1 Name: Azem Al-Kurdi Position : Project Manager Company:RDC Name: Tan Choon Wiew Position : Project Director Company: Q - Properties MATERIAL INSPECTION REQUEST Material Submittal Reference : RHP1P2-BW-TGC-ZZ-XX-MT-EL-00002_01 MIR Ref.No : : RHP1P2-BW-TGC-ZZ-XX-MI-EL-00003_00
Description/Source of Material :
Material Inspection request for PVC Conduit & Accessories (Decoduct)
Delivery Note Ref: WS0705705,WS0705709,WS0705706
Quantity : As per attached Dos
Supplier : :M/s.Interplast CO. LTD Manufacturer: M/s. Decoduct Date of Receipt of Material On Site : 23/07/2024 Storage Location : Site Yard
Contractor Signature Date :24/07/2024 Notification Received by Consultant Signature Date
Inspection Report Check One Initials
Physical Damage ? [ ] Yes [ ] No Details Given Above Correct ? (Type, size, wt, qty, etc) [ ] Yes [ ] No Conform With Approval Submission ? (Certificate, etc) [ ] Yes [ ] No Engineer's Remarks: 1. Material inspected as per attached DO and Material submittal, Subject to fully compliance with the Engineer's given comments on the relevant material submittal. 2. PVC solvent cement & Adapter box 30X30cm are excluded from inspection, since both material are not part of approved material submittal. 3. Required wall thickness measurement shall be verified in line with the project specification and relevant material submittal. 4. Contractor shall protect the material properly in line with manufacturer recommendation. Irfan/Emad Ali Name : Date & Signature 29-07-2024 Material Engineer's Remarks The above materials have been inspected on Site and found at the time of inspection to be : [ ]- Satisfactory [ ] - Unsatisfactory Name : Date & Signature RE's Remarks
Name : Suheib Aboamir 30/07/2024 Date & Signature
Approved Approved as Noted Revise & Resubmit Rejected