NG Electricity System Operator - Introduction To The Compliance Process
NG Electricity System Operator - Introduction To The Compliance Process
Operator
Introduction to the Compliance Process
March 2021
Introduction to Compliance | March 2021
Contents
Purpose of this document ..................................................................................................................................... 3
Overview of Timescales......................................................................................................... 5
24-18 Months Prior to Energisation/Export .................................................................................................. 5
18-12 Months Prior to Energisation/Export .................................................................................................. 5
12 Months Prior to Energisation/Export ....................................................................................................... 5
9 Months Prior to Energisation/Export ......................................................................................................... 5
6 Months Prior to Energisation/Export ......................................................................................................... 5
6-3 Months Prior to Energisation/Export ...................................................................................................... 5
2 Months Prior to Energisation/Export ......................................................................................................... 5
1 month to 1 week Prior to Energisation/Export ........................................................................................... 6
28 days Prior to Synchronisation.................................................................................................................. 6
1 Week Prior to Energisation/Export ............................................................................................................ 6
1 week Prior to Energisation/Export ............................................................................................................. 6
2
Introduction to Compliance | March 2021
Note, an EON will not be issued by National Grid ESO to customers that are party to either a BEGA or
BELLA as energisation will be managed between the host Distribution Network Owner and the
customer.
• Interim Operational Notification (ION): This is required for first export (either reactive power or active
power). The ION will include a schedule of unresolved issues that will need to be satisfactorily
completed following commencement of export of reactive and active power and prior to a Final
Operational Notification being issued. The ION may also include Operational Restrictions that will apply
to the new connection until satisfactorily addressed.
• Final Operational Notification (FON): This is issued when all issues identified within the ION have
been satisfactorily addressed.
If you have any feedback or questions in respect of any part of this guidance document, we would welcome
your feedback and encourage you to discuss this with your ESO Contract Compliance Manager
3
Introduction to Compliance | March 2021
• User Data File Structure (UDFS): This is a blank folder structure which is to be populated by the
customer to demonstrate compliance with the items identified within the Compliance Statement and
ONCC. The customer will submit the UDFS to National Grid ESO for review. Submissions can be made
using National Grid ESO’s web-based facility and access details will be provided once the ONCP
commences. In line with STCP19-3, the data is shared with the Relevant Transmission Owner who also
provides acceptance of some of the compliance items.
For customers who will connect directly to the National Electricity Transmission System, these are:
• Certificate of Readiness to Commence the Commissioning Programme
• Certificate of Readiness to Complete the Commissioning Programme,
• Certificate of Readiness to Energise High Voltage Equipment.
4
Introduction to Compliance | March 2021
Overview of Timescales
The timeline below provides a high-level overview of the Compliance Process. It does not cover all process
steps required to demonstrate Compliance. For more detailed timescales on specific documents or milestones
please refer to the Operational Notification and Compliance Checklist (ONCC) or contact your Contract
Compliance Manager.
5
Introduction to Compliance | March 2021
6
Introduction to Compliance | March 2021
UDFS submission including any updated and / or new submissions as may be applicable, a FON can be issued,
signifying completion of the Operational Notification and Compliance process.
Generator build offshore projects are subject to OTSDUW Arrangements, as defined in Grid Code, whereby
certain aspects of the design, consenting, construction, installation and/or commissioning of transmission assets
are capable of being undertaken by a customer prior to the transfer of those assets to a Relevant Transmission
Licensee under an Offshore Tender Process. When the customer is acting in such a capacity, they will be
referred to as the OTSDUW User.
The site-specific technical requirements applicable to the customer at the Offshore Grid Entry Point, as defined
in the Grid Code, will be specified in the Appendix F to the relevant bilateral agreement. The site-specific
technical requirements applicable to the customer, in their capacity as OTSDUW User, at the Transmission
Interface Point, as defined in the Grid Code, will be specified in the Appendix OF to the relevant construction
agreement.
For offshore connections, two separate Compliance Statements will be provided by the allocated Contract
Compliance Manager: one to the customer for completion with respect to their compliance requirements at the
Offshore Grid Entry Point and one to the customer, in their capacity as OTSDUW User, for completion with
respect to their compliance requirements at the Transmission Interface Point.
A single ONCC will be provided which specifies a high-level checklist of key milestones and activities for the
customer to complete through the Compliance Process in their role as both wind farm owner and OTSDUW
User. The range of examples of ONCC’s in Appendix 2 of this guidance document includes an example specific
to Generator build offshore projects.
The ION is split into ION Part A and ION Part B for offshore connections both of which have a lifetime of 24
months. ION Part A is required for commissioning of any dynamic reactive compensation equipment for export
of reactive power. ION Part B is required for first export of active power from the wind farm.
The customer will be issued with a Completion Notice at the time of issue of the ION Part B to initiate the asset
transfer (to an OFTO) process. Under any scenario whereby the issue of the ION Part B is staged, the
Completion Notice will be issued at the time of issue of the final stage of the ION Part B.
Further guidance on the asset transfer process can be found on Ofgem’s website which can be accessed via
the link provided in the “Useful Website Links” section of this document:
Section K Notifications
The steps below are followed leading up to the issuing of a Section K Notification:
• National Grid ESO has monthly update meetings with Ofgem in which asset transfer dates for offshore
networks and the preferred bidder / Section 8A dates are discussed. The Section 8A date is the date
when an OFTO is appointed/issued a Transmission Owner Licence. This 8A date is in advance of the
OTSUA Transfer date.
7
Introduction to Compliance | March 2021
• On confirmation that an OFTO has been appointed (and before the offshore asset transfer occurs),
there will be an OTSDUW completion report issued to the National Grid ESO Connections Contract
Manager.
• The Completion Report is reviewed and amended as appropriate. Once the Completion Report is
accepted, the Connections Contract requests for ed and accepted.
An Interim Section K Notification (ISKN) is issued by National Grid ESO to the appointed OFTO listing the parts
of the Compliance process requiring completion (the elements outstanding on the ION Part A). These items
are to be transferred onto the ISKN schedule.
A Final Section K Notification (FSKN) is issued by National Grid ESO to the appointed OFTO following
successful completion of the Compliance process i.e. there are no outstanding items on the ION Part A).
This will be advised upon during Operational Notification and Compliance Panel meetings and items required
to be satisfied prior to the issuing of the Section K Notification to the assigned Relevant Transmission Licensee.
A Final Section K Notification (FSKN) is issued if all items within the schedule of unresolved issues attached
the ION Part A are closed whereas an Interim Section K Notification (ISKN) is issued should any of them remain
open at this time.
Upon a derogation being granted by Ofgem, the Customer should submit their final Compliance Statement
accompanied by a final User Self Certification of Compliance and final UDFS including any updated and / or
new submissions as may be applicable.
8
Introduction to Compliance | March 2021
• Should the non-compliance remain unresolved within 28 days of notifying National Grid ESO, then the
Customer shall undertake an investigation to determine the causes of and solution to the non-
compliance. Such investigation shall continue for no longer than 56 days.
• Should the non-compliance remain unresolved at the end of the 56-day period, National Grid ESO shall
issue a Limited Operational Notification to expire no later than 12 months
A LON will also be issued by National Grid ESO requesting the Customer to go through the compliance process:
• Upon receipt of notification from the Customer of their intention to modify their Plant and Apparatus; or
• Upon receipt of documentation indicating a change in Plant and Apparatus that National Grid ESO
deems to result in a material change of performance.
Refer to Compliance Process Section 8 and Section 9 for the of the Grid Code for further details on LONs and
derogations.
Grid Code
https://www.nationalgrideso.com/industry-information/codes/grid-code/code-documents
9
Introduction to Compliance | March 2021
10
Introduction to Compliance | March 2021
11