0% found this document useful (0 votes)
23 views

NG Electricity System Operator - Introduction To The Compliance Process

Uploaded by

maulker86
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
23 views

NG Electricity System Operator - Introduction To The Compliance Process

Uploaded by

maulker86
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 11

NG Electricity System

Operator
Introduction to the Compliance Process
March 2021
Introduction to Compliance | March 2021

Contents
Purpose of this document ..................................................................................................................................... 3

The “Compliance Toolkit”....................................................................................................... 3


Additional Compliance Process Templates: ................................................................................................. 4

Overview of Timescales......................................................................................................... 5
24-18 Months Prior to Energisation/Export .................................................................................................. 5
18-12 Months Prior to Energisation/Export .................................................................................................. 5
12 Months Prior to Energisation/Export ....................................................................................................... 5
9 Months Prior to Energisation/Export ......................................................................................................... 5
6 Months Prior to Energisation/Export ......................................................................................................... 5
6-3 Months Prior to Energisation/Export ...................................................................................................... 5
2 Months Prior to Energisation/Export ......................................................................................................... 5
1 month to 1 week Prior to Energisation/Export ........................................................................................... 6
28 days Prior to Synchronisation.................................................................................................................. 6
1 Week Prior to Energisation/Export ............................................................................................................ 6
1 week Prior to Energisation/Export ............................................................................................................. 6

Operational Notifications for New Connections ..................................................................... 6


Energisation Operational Notifications ......................................................................................................... 6
Interim Operational Notifications .................................................................................................................. 6
Derogations for New Connections................................................................................................................ 6
Final Operational Notifications for New Connections ................................................................................... 6

Operational Notifications for Offshore Connections ............................................................... 7


Section K Notifications ................................................................................................................................. 7
Derogations for Offshore Connections ......................................................................................................... 8
Final Operational Notifications for Offshore Connections ............................................................................ 8

Operational Notifications for Existing Connections ................................................................ 8


Limited Operational Notifications .................................................................................................................. 8
Derogations for Existing Connections .......................................................................................................... 9
Final Operational Notifications for Existing Connections ............................................................................. 9

Useful Website Links ............................................................................................................. 9


National Grid ESO Compliance Guidance Notes ......................................................................................... 9
National Grid ESO – BM Registration Guidance Notes ............................................................................... 9
Grid Code ..................................................................................................................................................... 9
Elexon – Market Entry .................................................................................................................................. 9
Elexon – Balancing Mechanism Unit ............................................................................................................ 9
Elexon – Guidance notes library ................................................................................................................ 10
Ofgem – Asset Transfer Process ............................................................................................................... 10

2
Introduction to Compliance | March 2021

Purpose of this document


This document summarises the Operational Notification and Compliance Process (ONCP) facilitated by
National Grid ESO in respect of new generation connections. The ONCP embraces the requirements of the
Compliance Processes section of the Grid Code and the specific requirements of Bilateral Agreements.
The latest version of the Grid Code can be accessed via the National Grid ESO website and the link provided
in the “Useful Website Links” section of this document.
Whilst this document focusses on new generation connections, the guidance may also be considered to
represent best practice and be applied in respect of new demand connections.
All customers that are party to either a Bilateral Connection Agreement (BCA), Bilateral Embedded Generation
Agreement (BEGA) or Bilateral Embedded Licence exemptable Large power station Agreement (BELLA) and
Construction Agreement, where applicable, with National Grid ESO in respect of a new generation connection
will be required to demonstrate compliance with the relevant requirements of these agreements together with
the relevant requirements of the Grid Code prior to receiving Operational Notifications for their connection.
There are three types of Operational Notification issued by National Grid ESO in respect of new generation
connections, which are referred to within the Grid Code, as follows:
• Energisation Operational Notification (EON): This is required for first energisation (back feed) of a
new connection when connecting directly to the National Electricity Transmission System.

Note, an EON will not be issued by National Grid ESO to customers that are party to either a BEGA or
BELLA as energisation will be managed between the host Distribution Network Owner and the
customer.
• Interim Operational Notification (ION): This is required for first export (either reactive power or active
power). The ION will include a schedule of unresolved issues that will need to be satisfactorily
completed following commencement of export of reactive and active power and prior to a Final
Operational Notification being issued. The ION may also include Operational Restrictions that will apply
to the new connection until satisfactorily addressed.
• Final Operational Notification (FON): This is issued when all issues identified within the ION have
been satisfactorily addressed.

If you have any feedback or questions in respect of any part of this guidance document, we would welcome
your feedback and encourage you to discuss this with your ESO Contract Compliance Manager

The “Compliance Toolkit”


National Grid ESO will initiate and chair a series of Operational Notification and Compliance Panel Meetings to
facilitate the ONCP. The timing of these meetings is as referred to in Section 3 of this document.
The focus of these meetings is ensuring that the customer has fulfilled their obligations and that National Grid
ESO is able to issue the appropriate Operational Notification in line with customer aspirations.
Several documents will be issued to the customer by National Grid ESO prior to the first Operational Notification
and Compliance Panel Meeting, these are as summarised below:
• Compliance Statement: This lists the requirements of the Grid Code and the site-specific requirements
of the Appendix F (Site Specific Technical Requirements) to the BCA, BEGA or BELLA as applicable.
The customer will complete this to confirm their compliance with the relevant requirements providing
supporting comments as appropriate. The Compliance Statement will make reference to the version of
the Grid Code referenced at the time of preparation and this can be used as a reference point against
which the requirements of any subsequent Grid Code updates and their applicability to a new generation
connection can be assessed. Example Compliance Statements have been provided in Appendix 1.
• Operational Notification and Compliance Checklist (ONCC): This is a high-level checklist of key
milestones and activities for the customer to complete through the ONCP and prior to the issue of an
EON, ION and FON. A number of example ONCCs have been provided in Appendix 2. The ONCC
specifies the lead party between the Relevant Transmission Owner and National Grid ESO for the
approval of each of the compliance items.

3
Introduction to Compliance | March 2021

• User Data File Structure (UDFS): This is a blank folder structure which is to be populated by the
customer to demonstrate compliance with the items identified within the Compliance Statement and
ONCC. The customer will submit the UDFS to National Grid ESO for review. Submissions can be made
using National Grid ESO’s web-based facility and access details will be provided once the ONCP
commences. In line with STCP19-3, the data is shared with the Relevant Transmission Owner who also
provides acceptance of some of the compliance items.

Additional Compliance Process Templates:


• User Self Certification of Compliance: The customer will be required to complete and sign this
document and submit together with the final Compliance Statement prior to the issue of an EON, ION
and FON. This should reflect all the items that remain outstanding as on the ION’s Schedule of
Unresolved Items.
• Notice of Intention to Synchronise: This is submitted by the customer prior to commencing export of
reactive power and / or active power and requests the issue of an ION.
• Certificates of Readiness: There are a number of certificates of readiness that are submitted by the
customer, as follows:

For customers who will connect directly to the National Electricity Transmission System, these are:
• Certificate of Readiness to Commence the Commissioning Programme
• Certificate of Readiness to Complete the Commissioning Programme,
• Certificate of Readiness to Energise High Voltage Equipment.

For customers who will connect to a distribution system, this is:


• Certificate of Readiness to Use the Transmission System.

4
Introduction to Compliance | March 2021

Overview of Timescales
The timeline below provides a high-level overview of the Compliance Process. It does not cover all process
steps required to demonstrate Compliance. For more detailed timescales on specific documents or milestones
please refer to the Operational Notification and Compliance Checklist (ONCC) or contact your Contract
Compliance Manager.

24-18 Months Prior to Energisation/Export


Following the customer signing the Bilateral Agreement, the Electricity Connections Contract Manager will
provide the contact details of the allocated Contract Compliance Manager (if they have not already been in
contact).

18-12 Months Prior to Energisation/Export


The inaugural Operational Notification and Compliance Panel meeting to be held. This is arranged and chaired
by the National Grid ESO Contract Compliance Manager. Attendees will include the customer (or
representative), National Grid ESO Contract Compliance Manager, National Grid ESO Generator Compliance
Engineer (where required) and a representative from the Relevant Transmission Owner. The “Compliance
Toolkit” documents will be provided in advance of this meeting. The agenda of the meeting will be to introduce
the scheme and also the Compliance Process and documentation.

12 Months Prior to Energisation/Export


Balancing and Settlement Code registrations with Elexon to be commenced by the customer. It is advised that
contact is made with Elexon 12 months in advance. Please refer to the guidance note provided on the Elexon
website contained in the “Useful Website Links” section of this guide.

9 Months Prior to Energisation/Export


The generator Control Point to be confirmed by the customer via return of National Grid ESO Registration Form
(which can be requested via the National Grid ESO BM Registration team email address
([email protected]). If it is to be a new Control Point, it will require communication facilities
to be established. Please refer to the National Grid ESO Registration Form guidance note on the National Grid
ESO Compliance website (link has been provided at the end of this guide) for details of how to obtain and
complete the form. If an established Control Point, or Control Point Service Provider is being used, this form
should be submitted 6 months prior to anticipated export date.

6 Months Prior to Energisation/Export


UDFS to be submitted by the customer to National Grid ESO and the Relevant Transmission Owner for review,
along with a compliance statement. A follow up Operational Notification and Compliance Panel meeting will be
arranged to discuss the content of the UDFS revision and any feedback. Guidance notes for Data Registration
Code submission, and Generator Compliance Connection Conditions can be found on the National Grid ESO
Compliance Website (the link is provided at the “Useful Website Links” section of this guide). These documents
will help for preparation of the required schedules and reports to be included within the UDFS.

6-3 Months Prior to Energisation/Export


Further UDFS revisions to be submitted by the customer to National Grid ESO for review. Final submission is
to be submitted 3 months prior to first energisation / export date.

2 Months Prior to Energisation/Export


National Grid ESO and Relevant Transmission Owner complete the review of the final UDFS revision. Any
feedback that is provided must be addressed by the customer.

5
Introduction to Compliance | March 2021

1 month to 1 week Prior to Energisation/Export


The customer signs and submits the User Self Certification of Compliance and Certificates of Readiness to
National Grid ESO. The Relevant Transmission Owner will counter sign where required, and also submit their
authorisation for National Grid ESO to issue the Operational Notification. Data communication links will be
validated with the customer’s Control Point by National Grid ESO where required by the Bilateral Agreement,
and Operational Metering will be confirmed.

28 days Prior to Synchronisation


The customer submits a Notice of Intention to Synchronise prior to commencing export of reactive power and /
or active power and requests the issue of an ION.

1 Week Prior to Energisation/Export


Elexon issue their Approval to Energise to the customer and National Grid ESO, confirming all Balancing and
Settlement Code registrations with Elexon have been completed.

1 week Prior to Energisation/Export


EON/ION issued to the customer by National Grid ESO with an effective from date stated.
Note: Energisation/Export can commence from the effective from date stated in the relevant Operational
Notification.

Operational Notifications for New Connections


Energisation Operational Notifications
Upon receipt of the required documentation, National Grid ESO will issue the EON with an effective from date
stated. Energisation/Export can commence from the effective from date stated in the relevant Operational
Notification.

Interim Operational Notifications


Upon receipt of the required documentation, National Grid ESO will issue the with an ION with an effective from
date and expiry date stated. Depending on the site-specific detail of the Bilateral Agreement and size/type of
the generator, witnessed testing will be required to be undertaken with National Grid ESO. This will be advised
upon during Operational Notification and Compliance Panel meetings, and items required to be satisfied prior
to the issuing of the FON will be stated within a schedule of unresolved issues attached the ION.
The lifetime of an ION is 24 months; the period within which all items should be resolved.

Derogations for New Connections


As soon as the customer is aware of their inability to resolve any outstanding items within the ION timescales,
they should notify National Grid ESO as a derogation would be required. Any ION extensions (beyond the 24
months) would be subject to the Customer having applied to Ofgem for a derogation for any remaining
Unresolved Issues. Upon a derogation being granted by Ofgem, the Customer should submit their final
Compliance Statement accompanied by a final User Self Certification of Compliance and final UDFS including
any updated and / or new submissions as may be applicable.

Final Operational Notifications for New Connections


Once all of the items listed within the ION schedule have been satisfactorily completed and the customer has
submitted a final Compliance Statement accompanied by a final User Self Certification of Compliance and final

6
Introduction to Compliance | March 2021

UDFS submission including any updated and / or new submissions as may be applicable, a FON can be issued,
signifying completion of the Operational Notification and Compliance process.

Operational Notifications for Offshore Connections


The Compliance Process timeline for offshore projects is broadly similar to that summarised above. For more
detailed timescales on specific documents or milestones for offshore projects, please refer to the Operational
Notification and Compliance Checklist (ONCC) which your allocated Contract Compliance Manager will provide
specifically for your offshore connection.

Generator build offshore projects are subject to OTSDUW Arrangements, as defined in Grid Code, whereby
certain aspects of the design, consenting, construction, installation and/or commissioning of transmission assets
are capable of being undertaken by a customer prior to the transfer of those assets to a Relevant Transmission
Licensee under an Offshore Tender Process. When the customer is acting in such a capacity, they will be
referred to as the OTSDUW User.

The site-specific technical requirements applicable to the customer at the Offshore Grid Entry Point, as defined
in the Grid Code, will be specified in the Appendix F to the relevant bilateral agreement. The site-specific
technical requirements applicable to the customer, in their capacity as OTSDUW User, at the Transmission
Interface Point, as defined in the Grid Code, will be specified in the Appendix OF to the relevant construction
agreement.

For offshore connections, two separate Compliance Statements will be provided by the allocated Contract
Compliance Manager: one to the customer for completion with respect to their compliance requirements at the
Offshore Grid Entry Point and one to the customer, in their capacity as OTSDUW User, for completion with
respect to their compliance requirements at the Transmission Interface Point.

A single ONCC will be provided which specifies a high-level checklist of key milestones and activities for the
customer to complete through the Compliance Process in their role as both wind farm owner and OTSDUW
User. The range of examples of ONCC’s in Appendix 2 of this guidance document includes an example specific
to Generator build offshore projects.

The ION is split into ION Part A and ION Part B for offshore connections both of which have a lifetime of 24
months. ION Part A is required for commissioning of any dynamic reactive compensation equipment for export
of reactive power. ION Part B is required for first export of active power from the wind farm.

The customer will be issued with a Completion Notice at the time of issue of the ION Part B to initiate the asset
transfer (to an OFTO) process. Under any scenario whereby the issue of the ION Part B is staged, the
Completion Notice will be issued at the time of issue of the final stage of the ION Part B.
Further guidance on the asset transfer process can be found on Ofgem’s website which can be accessed via
the link provided in the “Useful Website Links” section of this document:

Section K Notifications
The steps below are followed leading up to the issuing of a Section K Notification:
• National Grid ESO has monthly update meetings with Ofgem in which asset transfer dates for offshore
networks and the preferred bidder / Section 8A dates are discussed. The Section 8A date is the date
when an OFTO is appointed/issued a Transmission Owner Licence. This 8A date is in advance of the
OTSUA Transfer date.

7
Introduction to Compliance | March 2021

• On confirmation that an OFTO has been appointed (and before the offshore asset transfer occurs),
there will be an OTSDUW completion report issued to the National Grid ESO Connections Contract
Manager.
• The Completion Report is reviewed and amended as appropriate. Once the Completion Report is
accepted, the Connections Contract requests for ed and accepted.

An Interim Section K Notification (ISKN) is issued by National Grid ESO to the appointed OFTO listing the parts
of the Compliance process requiring completion (the elements outstanding on the ION Part A). These items
are to be transferred onto the ISKN schedule.

A Final Section K Notification (FSKN) is issued by National Grid ESO to the appointed OFTO following
successful completion of the Compliance process i.e. there are no outstanding items on the ION Part A).

This will be advised upon during Operational Notification and Compliance Panel meetings and items required
to be satisfied prior to the issuing of the Section K Notification to the assigned Relevant Transmission Licensee.
A Final Section K Notification (FSKN) is issued if all items within the schedule of unresolved issues attached
the ION Part A are closed whereas an Interim Section K Notification (ISKN) is issued should any of them remain
open at this time.

Derogations for Offshore Connections


As soon as the customer is aware of their inability to resolve any outstanding items within the ION Part A and/or
ION Part B timescales, they should notify National Grid ESO as a derogation would be required. Any ION
extensions (beyond the 24 months) would be subject to the Customer having applied to Ofgem for a derogation
for any remaining Unresolved Issues.

Upon a derogation being granted by Ofgem, the Customer should submit their final Compliance Statement
accompanied by a final User Self Certification of Compliance and final UDFS including any updated and / or
new submissions as may be applicable.

Final Operational Notifications for Offshore Connections


Once all of the items listed within the ION Part B schedule have been satisfactorily completed and the customer
has submitted a final Compliance Statement accompanied by a final User Self Certification of Compliance and
final UDFS submission including any updated and / or new submissions as may be applicable, a FON can be
issued, signifying completion of the Operational Notification and Compliance Process.

Operational Notifications for Existing Connections

Limited Operational Notifications


Following the issue of a FON, the Grid Code stipulates that should the customer and/or National Grid ESO
become aware of the customer being unable to meet any of their Grid Code or Bilateral Agreement
requirements, the following steps should be followed:
• The Customer should notify National Grid ESO as soon as they become aware of their inability to meet
any of its Grid Code and/or Bilateral obligations. The notification should provide details of the non-
compliance, operational restrictions that should be applied ad an indication when the resolutions will be
resolved.
• Depending on the severity of the non-compliance, the Customer maybe disconnected in line with
Paragraph 5.4 of the CUSC https://www.nationalgrideso.com/document/91366/download

8
Introduction to Compliance | March 2021

• Should the non-compliance remain unresolved within 28 days of notifying National Grid ESO, then the
Customer shall undertake an investigation to determine the causes of and solution to the non-
compliance. Such investigation shall continue for no longer than 56 days.
• Should the non-compliance remain unresolved at the end of the 56-day period, National Grid ESO shall
issue a Limited Operational Notification to expire no later than 12 months

A LON will also be issued by National Grid ESO requesting the Customer to go through the compliance process:
• Upon receipt of notification from the Customer of their intention to modify their Plant and Apparatus; or
• Upon receipt of documentation indicating a change in Plant and Apparatus that National Grid ESO
deems to result in a material change of performance.

Derogations for Existing Connections


If the non-compliance is to remain unresolved by the time the LON is due to expire, the Customer should apply
to Ofgem for a derogation before the LON expiry date. Any LON extensions (beyond the 12 months) would be
subject to the Customer having applied to Ofgem for a derogation for any remaining Unresolved Issues.

Final Operational Notifications for Existing Connections


Upon a derogation being granted by Ofgem, the Customer should submit their final Compliance Statement
accompanied by a final User Self Certification of Compliance and final UDFS including any updated and / or
new submissions as may be applicable.

Refer to Compliance Process Section 8 and Section 9 for the of the Grid Code for further details on LONs and
derogations.

Useful Website Links


National Grid ESO Compliance Guidance Notes
https://www.nationalgrideso.com/industry-information/connections/compliance-process

National Grid ESO – BM Registration Guidance Notes


https://www.nationalgrideso.com/document/150281/download

Grid Code
https://www.nationalgrideso.com/industry-information/codes/grid-code/code-documents

Elexon – Market Entry


https://www.elexon.co.uk/reference/market-entry-and-exit/market-entry/

Elexon – Balancing Mechanism Unit


https://www.elexon.co.uk/reference/technical-operations/balancing-mechanism-units/

9
Introduction to Compliance | March 2021

Elexon – Guidance notes library


https://www.elexon.co.uk/bsc-related-documents/bsc-guidance-notes/

Ofgem – Asset Transfer Process


https://www.ofgem.gov.uk/ofgem-publications/87040/gccdecisiondocument020414finalforpublication.pdf

10
Introduction to Compliance | March 2021

Faraday House, Warwick Technology Park,


Gallows Hill, Warwick, CV346DA
nationalgrideso.com

11

You might also like