Draft Bar & Empr
Draft Bar & Empr
And
In terms of the Mineral and Petroleum Resources Development Act (Act 28 of 2002 as
amended), the Minister must grant a prospecting or mining right if among others the mining
“will not result in unacceptable pollution, ecological degradation or damage to the
environment”.
In terms of section 16(3) (b) of the EIA Regulations, 2014, any report submitted as part of
an application must be prepared in a format that may be determined by the Competent
Authority and in terms of section 17 (1) (c) the competent Authority must check whether the
application has taken into account any minimum requirements applicable or instructions or
guidance provided by the competent authority to the submission of applications.
Page | 0
Objective of the basic assessment process
The objective of the basic assessment process is to, through a consultative process─
(a) determine the policy and legislative context within which the proposed activity is
located and how the activity complies with and responds to the policy and legislative
context;
(b) identify the alternatives considered, including the activity, location, and technology
alternatives;
(c) describe the need and desirability of the proposed alternatives,
(d) through the undertaking of an impact and risk assessment process inclusive of
cumulative impacts which focused on determining the geographical, physical,
biological, social, economic, heritage , and cultural sensitivity of the sites and locations
within sites and the risk of impact of the proposed activity and technology alternatives
on the these aspects to determine:
(i) the nature, significance, consequence, extent, duration, and probability of the
impacts occurring to; and
(ii) the degree to which these impacts— (aa) can be reversed;
(bb) may cause irreplaceable loss of resources; and
Page | 1
EXECUTIVE SUMMARY
Malac Waste and Environmental Services (Pty) Ltd was appointed by Great Wall Mining (Pty) Ltd
to undertake Environmental Impact Assessment (EIA) process for the proposed 5 Ha mining
permit application situated on a portion of the remaining extent of the farm Kalverkraal 8 IU
Magisterial District of Eerstehoek in the Mpumalanga Province,
The proposed mining operation requires authorisations in terms of the MPRDA and NEMA. The
following applications have been made (Ref no: MP 30/5/1/1/3/ 13240 MP.
A mining permit application in terms of the provisions of the Mineral and Petroleum Resources
Development Act (Act No.28 of 2002) (MPRDA) regulated by the Department of Mineral
Resources (DMR);
Due to the non-hazardous nature of the Lithium ore, Gold ore, Jade(gemstone), and
Quartz(gemstone) mining operation and the already disturbed condition of the application area
(due to historical farming and mining activities) there are no potential impacts with a high
significance rating post mitigation. This report will show that the significance of most of the
potential environmental impacts is moderate to low. Furthermore, the potential impacts of the
operation can be reduced through the mitigation and careful management measures
recommended in this report. The EMPr and commitment made in this report must be adhered to
by mine management at all times. Annual audit must be conducted by an external auditor and
the reports submitted to the competent authority for review.
The supply of Lithium ore, Gold ore, Jade(gemstone), and Quartz(gemstone) will assist the
ongoing development of the socio economic structure in the area and the potential biophysical
impacts of the proposed operation can be managed to a large extend. Based on the above
reasoning it is the opinion of the EAP that the activity may be authorised.
Page | 2
Contents
Contents............................................................................................................................ 3
3.3.1 The decommissioning phase will comprise of the following activities: .............. 17
3.4.1 The post-closure phase will include the following activities: ............................. 18
6. Motivation for the overall preferred site, activities and technology alternative .............. 21
Full description of the process followed to reach the proposed preferred alternatives within
the site. ........................................................................................................................... 22
Page | 3
7.3 The technology to be used in the activity; ............................................................... 23
10. The Environmental attributes associated with the alternatives. (The environmental
attributed described must include socio-economic, social, heritage, cultural, geographical,
physical and biological aspects) ....................................................................................... 30
10.1.10 Noise............................................................................................................ 31
12. Description of specific environmental features and infrastructure on the site ............. 34
13. Impacts and risks identified including the nature, significance, consequence, extent,
duration and probability of the impacts, including the degree to which these impacts can be
reversed .......................................................................................................................... 34
14. Methodology used in determining and ranking the nature, significance, consequences,
extent, duration and probability of potential environmental impacts and risks;................ 60
Page | 4
Definitions.................................................................................................................... 60
15. The positive and negative impacts that the proposed activity (in terms of the initial site
layout) and alternatives will have on the environment and the community that may be
affected ........................................................................................................................... 65
15.1.1 Geology.......................................................................................................... 65
15.1.2 Topography.................................................................................................... 65
15.1.7 Fauna/Avifauna/Herpetofauna........................................................................ 68
15.1.10 Noise............................................................................................................ 70
15.2.8 Noise.............................................................................................................. 76
Page | 5
16. The possible mitigation measures that could be applied and the level of risk. ............ 75
17. Full description of the process undertaken to identify, assess and rank the impacts and
risks the activity will impose on the preferred site (In respect of the final site layout plan)
through the life of the activity. ........................................................................................ 99
18. Assessment of each identified potentially significant impact and risk....................... 100
21. Summary of the positive and negative impacts and risks of the proposed activity and
identified alternatives; ................................................................................................... 122
22. Proposed impact management objectives and the impact management outcomes for
inclusion in the EMPr; .................................................................................................... 123
24. Reasoned opinion as to whether the proposed activity should or should not be authorised
..................................................................................................................................... 124
25. Period for which the Environmental Authorisation is required. ................................. 125
27. Has a water use licence has been applied for? .......................................................... 125
30. Describe the closure objectives and the extent to which they have been aligned to the
baseline environment described under the Regulation. .................................................. 133
31. Confirm specifically that the environmental objectives in relation to closure have been
consulted with landowner and interested and affected parties. ...................................... 134
32. Provide a rehabilitation plan that describes and shows the scale and aerial extent of the
main mining activities, including the anticipated mining area at the time of closure. ..... 134
33. Explain why it can be confirmed that the rehabilitation plan is compatible with the closure
objectives. ..................................................................................................................... 135
34. Confirm that the financial provision will be provided as determined. ....................... 135
Page | 6
36. Action Required ....................................................................................................... 136
37. Indicate the frequency of the submission of the performance assessment/ environmental
audit report. .................................................................................................................. 136
38.1 Manner in which the applicant intends to inform his or her employees of any
environmental risk which may result from their work. ................................................ 136
39. Manner in which risks will be dealt with in order to avoid pollution or the
degradation of the environment. ................................................................................... 139
Page | 7
PART A
Ms. Pheladi Mphahlele obtained a Bachelor of Earth Science in Mining and Environmental
Geology (BESMEG) in September 2017 from University of Venda as well as a Certificate in
from VBK Business Venture in January 2015. She obtained knowledge in storm water
management projects while working on community project in 2015 (2 months) in the
construction sector. She also worked on research project while completing her honors in
BESMEG. She has 4 years working experience with Environmental Impact Assessment and
currently registered with EAPASA (2021/ 4112) as an EAP.
Page | 8
Project Experience
Environmental Assessment for the proposed sand mining permit on portion of portion
39 of the farm Haakdoornboom 267 JR, within City of Tshwane Metropolitan
Municipality, Gauteng Province, May 2019.
Environmental Assessment for proposed mining permit of gold ore on farm on the
remaining extent of farm kameelspoort 563 JU, within the jurisdiction of Mbombela
Local Municipality, Ehlanzeni District of Mpumalanga Province, October 2021.
Page | 9
2. Location of the overall Activity
The proposed application for a mining permit will cover 5 Ha area. The open cast mining
method will be utilised to extract the Lithium ore, Gold ore, Jade(gemstone), and
Quartz(gemstone) reserves that occur within the proposed mining permit boundary. A
moderate Blasting will take place. Excavators will be used to extract commodities and
transported to the stockpile area.
The application area has been disturbed through post-mining and farming activities. The
area is under little to no indigenous vegetation remain. The topography of the area is
categorised as mountainous.
The applicant intends to mine gold ore, lithium ore, jade(gemstone) and quartz(gemstone)
on the remaining extent of farm Kalverkraal 8 IU. The site is situated approximately 47km
south east of Pampoen within the jurisdiction of Chief Albert Luthuli Local Municipality, Gert
Sibande District in Mpumalanga Province.
The Application area can be described as open veld and Mountainous. It appears that some
of the land previously cultivated, has been left fallow or have recently been planted to
pastures. The area also comprised of Thorn trees, grasslands, maintained gravel road,
Page | 10
greenstone rocks as per the observation during the site visit. Please see attached site
photographs.
The proposed site is situated adjacent to the Mololotja Nature reserve and boundary line of
Eswatini and South Africa on the western side, There is a Kalverkraal village and Ebhusini
Tourism Centre on the south west of the site. Vast majority of the surrounding land
comprises of livestock incorporated and other fodder during the post-harvest period. Crops
produced. There are also existing post-mining activities as there are old mines and diggings.
The typical open cast mining method will be utilised to extract the Lithium ore, Gold ore,
Jade(gemstone), and Quartz(gemstone) that is existing within the proposed mining
boundary.
Page | 11
Figure 1.2: Regulation 2.2
Page | 12
3. Listed and specified activities
The proposed Lithium ore, Gold ore, Jade(gemstone), and Quartz(gemstone) mining operation
requires authorisations in terms of the MPRDA and NEMA. The following applications have been
made:
Activity 21: Any activity including the operation of that activity which requires a mining permit
in terms of Section 27 of the Mineral and Petroleum Resources Development Act, 2002 (Act No.
28 of 2002), including associated infrastructure, structures and earthworks directly related to
extraction of a mineral resource, including activities for which an exemption has been issued
in terms of section 106 of the Mineral and Petroleum Resources Development Act, 2002 (Act
No. 28 of 2002).
Ha or m² GNR 983
Page | 13
Establishment of infrastructure
including, container offices, mobile
and chemical toilets. 100m2 21 GNR 983
Hauling and Screening 2500m2 21 GNR 983
The proposed open cast mining method can be divided into four phases namely, construction,
operation, decommissioning and closure. The activities proposed during each of these phases
are listed below.
Page | 14
3.1 Construction Phase
The following activities are planned for the construction phase:
Stripping and stockpiling of soil in areas designated for surface infrastructure, stockpile areas,
and the initial box cut will be aligned with EMPr in order to effectively manage the topsoil for
rehabilitation purposes by the Applicant in the future. Topsoil will be stripped through a truck
and shovel stripping procedure. Over areas of deep excavation where the majority or all of the
soil profile is to be impacted) strip all usable soil (approx. 750mm) and stockpile as berms or
low, terraced dumps. Alluvial soils should be stockpiled separately from the colluvial (shallower)
and in-situ derived materials, which in turn should be stored separately from any ferricrete
material, while the soft overburden is stored as a separate unit, as a defined dump of less than
15m in height preferably. The limited height is important to preserve aerobic conditions in the
topsoil thereby preventing future reclamation problems. The height will also impact on dust
during windy conditions.
Over areas planned for less invasive structures (container offices etc.) and any material stockpile
or storage, strip the top 500 mm of usable soil over all affected areas including terraces and
strip remaining usable soil and ferricrete (if present in profile) where founding conditions require
further soil removal.
Stripping and stockpiling the topsoil first will ensure that the source of post mining rehabilitation
nutrients and seeds are retained.
Landscaping activities will involve the levelling of ground where surface infrastructure is planned
and the presence of construction vehicles on site.
Weighbridge
Mobile crushing and screening plant;
Container offices and change houses;
Security gate;
Chemical toilets.
Waste handling
General and hazardous waste as defined under National Environmental Management: Waste Act
will be generated during the construction phase. General waste may comprise concrete, rubble,
glass, plastics and recyclable metals and hazardous waste could include used oils, oily rags,
paint and chemicals containers etc.
Page | 15
Domestic and hazardous waste generated by the project will be collected, handled and
temporarily stored on site before being removed on a regular basis for disposal at appropriately
licenced facilities.
3.2 Operational Phase
The operational phase will include the excavation of Lithium ore, Gold ore, Jade(gemstone), and
Quartz(gemstone) from the proposed area. The commodity will be excavated, stockpiled and
loaded onto haulage trucks and transported to the desired location. No washing will occur on
site. The only process water required will be for dust suppression and it will be sourced from
the contract miner will brought onto site via a water tanker. The main activities planned for the
operational phase are:
As per the construction phase, the soils excavated will be separately pre-stripped as topsoil or
subsoil and stockpiled separately as stockpiles or berms of not more than 1.5 m around
infrastructure area ready for closure/rehabilitation purposes. Hydromorphic (wet) soils must be
stockpiled separately from the dry materials, and the “ferricrete” separately from all other
materials. Topsoil stockpiles will be vegetated and shaped to allow adequate drainage of storm
water to prevent erosion and contamination. Subsoil stripping and stockpiling should follow a
similar truck and shovel stripping procedure than the method used in the stripping of topsoil.
Lithium ore, Gold ore, Jade(gemstone), and Quartz(gemstone) raw product is required in
order to reach the desired size accepted by the existing markets.
Raw material and product stockpiling. The raw material product will be road hauled to
the product stockpile area on site.
Transportation of the raw product to the desired location using the existing access
road.
Generation and handling of general and hazardous waste (oil, diesel, chemical toilets)
General and hazardous waste as defined under National Environmental Management: Waste Act
will be generated at the proposed mine operation. General waste will comprise concrete, rubble,
glass, plastics and recyclable metals and hazardous waste will include used oils, oily rags, paint
and etc. Temporary waste storage facilities will be constructed for hazardous and general waste
within the mine infrastructure area. A facility for the bailing and sorting of waste will be provided
for within the temporary storage areas. No disposal of general or hazardous waste will take place
at the mine; such waste will be transported offsite for disposal at suitably licenced facilities. A
chemical toilet will be maintained on site and emptied on a regular basis by a suitable service
provider at a registered waste site.
Page | 16
Storm water management.
Clean and dirty water will be separated through berms. Water falling onto the operational area
will be contained inside the pit. The water accumulating in the pit will then be used for dust
suppression inside the mining area.
Presence of operational vehicles on site
The activities listed above will involve the operation of trucks, excavators and pick-ups.
Concurrent rehabilitation.
Concurrent rehabilitation will occur during the operational phase by means of the roll over
method.
Dismantling and removal of all infrastructure in meeting the closure objectives; Mining
infrastructure such as site offices, change houses, fences, haul roads etc. will be removed
from site. The roads will be ripped and reseeded with indigenous vegetation.
Page | 17
Maintenance of all re-vegetated areas up until such areas initiate succession and create
a sustainable cover;
The re-vegetated areas will be encouraged to grow and weeds removed on a regular
basis.
Monitoring of key environmental variables (i.e. soils, vegetation, groundwater and surface
water) in order to demonstrate stability of rehabilitated areas; and
Weed management after closure, limited to areas disturbed by mining or included as
infrastructure related to the mine.
Please refer to Table 4 below for a summary of the relevant policies and legislation:
Page | 18
MPRDA, 2002 (Act 28 of S.27 Mining permit
2002) MPRDA, 2002 (Act 28 application. A Mining Permit application was lodged
of 2002): MPRDA on the DMR SAMRAD system. The
Regulations, 2004 application reference number is 13240MP
NEMA, 1998 (Act 107 of This BA Report and An application for Environmental
1998) EMPr is to obtain Authorisation has been submitted with
NEMA EIA Regulations of Environmental the Mining Permit application to the
2014. Authorisation. DMR as the competent authority for
triggering listed activities 21 of GNR
983.
NWA, 1998 (Act 36 of 1998) The mining operation The operation must implement storm
does not require a water management features to divert
Water Use License clean water away from the operational
because it is a dry area.
process and Stone During concurrent rehabilitation the
Lithium ore, Gold ore, rehabilitated area must be shaped to
Jade(gemstone), and allow free drainage.
Quartz(gemstone)/ is
not considered as a
hazardous material.
Water will be required
for dust suppression
purposes.
Page | 19
Mining and Biodiversity The guideline The project area does not fall within any
Guideline distinguish between biodiversity priority area identified by
(DEA et al, four biodiversity the Mining and Biodiversity Guideline
2013) priority areas where
biodiversity may limit
the potential for
mining:
• Legally
Protected
Areas
• Highest
Biodiversity
Importance
• High
Biodiversity
Importance
• Moderate
Biodiversity
Importance
In previous years, the economic benefits of the mining sector were often concentrated in the
hands of small elite and not deployed optimally to further the development agenda of the
area concerned, although recent years have seen a fundamental shift towards recognising
the importance of sustainable business, which entails contributing to the socio-economic
strategies of the area concerned.
Mineral resources, such as Lithium ore, Gold ore, Jade(gemstone), and Quartz(gemstone),
should be seen as part of the natural endowment of any province/country, and their
extraction presents a finite opportunity for local and provincial governments to benefit from
their wealth. If the financial benefits form mining are correctly invested in education, health
care, the facilitation of secondary or service industries, and the diversification of the
economy away from dependence on natural resources, the financial benefits can yield
developmental benefits far exceeding the life of any mine as there mostly used in jewellery,
Page | 20
dentistry and medicines, batteries, ceramics and glass, primary aluminium production,
ornaments and urns, vases, watches and clock.
A maintenance period of 2-3 years must be incorporated into the closure cost, therefore
sufficient financial provision will be available for the rehabilitation and maintenance of the
disturbed area. Depending on the land and the population growth in the affected region, it
could be sold back as agricultural land or for either game farming purposes or for other
industrial applications.
Lithium ore, Gold ore, Jade(gemstone), and Quartz(gemstone) mining is the only activity that will
be conducted on site.
Page | 21
6.2 Technology alternatives
Blasting is required to loosen the deposit due to the cementation of the mining areas rock. From
there excavators will be used to remove the Lithium ore, Gold ore, Jade(gemstone), and
Quartz(gemstone) from the pit and transported to the stockpile.
The DEA Guidelines Series notes the consideration of alternatives as one of the most critical
elements of the environmental assessment process. Its role is to provide a framework for
sound decision-making based on the principles of sustainable development. The search for
alternatives should be well documented, and should take into account the views of
stakeholders. Key criteria for consideration when identifying alternatives are that they should
be: “practicable”, “feasible”, “relevant”, “reasonable” and “viable”. The Guideline further notes
that although a range of alternatives may exist for a project, they are not all necessarily
appropriate for each project under consideration and that the range of categories of
alternatives to be evaluated should be considered along with the “no-go” alternative.
Consideration of alternative activities is a critical element of both EIAs and SEAs. Identification
should take place during the scoping phase and should facilitate input from all stakeholders.
Evaluation should focus on a few preferred alternatives and should include a comprehensive
comparison of all potential impacts, including biophysical, social and economic aspects.
Key issues to consider when identifying alternatives are that:
• Alternatives to most proposals exist;
• The need for and purpose of a development activity must be clearly identified to
facilitate the identification of appropriate and feasible alternatives;
• The appropriate development response is identified from a range of possible options;
• The selection is based on a comprehensive and participatory assessment of the full
range of options;
• Social and environmental aspects are accorded the same significance as economic and
financial factors in the assessment process; and
Page | 22
• The assessment and evaluation of alternatives continues through all stages of the
project.
In order to give effect to the general objectives of integrated environmental management laid
down in Chapter 5 of the National Environment Management Act 107 of 1998 (NEMA), the
potential impact on the environment of listed activities must be considered, investigated,
assessed and reported on to the competent authority. The procedures for the investigation,
assessment and communication of the potential impact of activities must, inter alia, include
with respect to every application for an Environmental Authorisation –
It is clear from the above that the consideration of alternatives is an integral part of the EIA
process.
Page | 23
7.4 The operational aspects of the activity;
The operational aspects of the mine and potential alternatives are discussed below:
Limited water is required for operational purposes because it is a dry operation. Water will be
sourced out by the contract miner and brought onto site via a water tanker. Storm water
accumulating in the open pit can be used for dust suppression on the operational area.
A number of alternative options in terms of water supply exists; a borehole can be drilled (subject
to the approval from DWS), water can be sourced off-site from adjacent landowner’s farm dam
(if an agreement can be reached) or the municipality. The alternative water source options will
however require the Applicant to apply for a Water Use License which will delay the operation.
Public Participation is a legal requirement, where the potential exists for individuals and/or
parties to be affected by a proposed activity. According to the principles of Integrated
Environmental Management (IEM), these individuals and/or parties should be involved in the
decision-making process from an early stage in the project, with regard to any relevant issues
and concerns complementing the information on which the Regulating Authorities would base
their decision.
The decision would entail one of the following:
• proceeding to the next phase in the project, or
• supplementing inadequate information, or
• not approving the project.
“Stakeholders” refers to all individual(s) and institutions that are (potentially) directly
associated with the project including:
• The Applicant, namely Great Wall Mining (Pty) Ltd;
• Regulating (“Competent”) Authorities namely DMR (Mpumalanga region),
“Commenting Department of Water and Sanitation (DWS), “Commenting”
Authorities, namely Department of Agriculture and Environmental Affairs,
Chief Albert Luthuli Local Municipality;
• Mpumalanga Tourism and Parks Agency
• South Africa Heritage Resources Authority
Page | 24
• Kalverkraal Community
• Landowner (Department of Rural Development, tribal Authority adjacent
landowners;
The following steps were taken to inform the landowner, adjacent landowner, key stakeholders
and relevant authorities about the proposed project:
A newspaper advertisement was booked and published on the 19th August 2022 on the
Khanyisa Newspaper.
Refer to the title deeds and table below showing the landowner and I and Aps consulted.
Page | 25
8.3 List of I and Aps and Summary of issues raised
Interested and Affected parties Date Issued raised Eap ‘s response to issues as Section and
List the names of persons comments mandated by the applicant paragraph
consulted in this column received reference in
Mark with an X where who must this report
be consulted were in fact where the
consulted issues or
responses
were
incorporated
Affected parties
Landowner/s X
Still waiting for comments Appendix D
Tribal Authority
DALRRD
Page | 16
Municipal Councillor
Still waiting for response
Municipality
Chief Albert Luthuli X Still waiting for response Appendix D
Municipality
Organ of
state(Responsible for
infrastructure that may
be affected Roads
department, Eskom,
Telkom, DWA
Department of Water and X Still waiting for response Appendix D
Sanitation
Communities
N/A
Department of Land
Affairs
Department of Rural Still waiting for response Appendix D
Development and Land X
Reform
Page | 17
Traditional Leaders
N/A X
Department of
Environmental Affairs
Department of Economic X Still waiting for response Appendix D
Development,
Environmental and
Tourism
Page | 18
9. Impact Assessment and Mitigation Measures
Table 9: The main activities along with each activities impacts and mitigation measures are presented below.
ACTIVITIES PHASE SIZE AND TYPICAL MITIGATION COMPLIANCE WITH STANDARDS
SCALE MEASURES
Soil stripping and Pre-construction 5 ha Management of topsoil to National Environmental Management: Biodiversity
vegetation Operational prevent soil loss through Act, 2004 (NEMBA). The EMP will require the
clearing. erosion and excessive wind; Applicant to apply for a plant removal permit prior
Page | 20
Avoid areas with sensitive to the removal of sensitive/endangered species.
vegetation species;
Restrict vegetation clearance to Mining and Biodiversity Guideline (DEA et al, 2013)
construction areas; The project area does not fall within any biodiversity
Salvage indigenous vegetation priority area identified by the Mining and Biodiversity
for re-planting during post- Guideline.
construction rehabilitation;
Implement dust suppression; NEMA, 1998 (Act 107 of 1998) NEMA EIA Regulations
of 2014 GN983.
Site Construction 200m2 Dust Suppression; Remain within the NEMAQA, 2004. Dust Regulation
Establishment Container No removal of vegetation Guidelines for rural communities.
office and outside demarcated areas;
Page | 21
chemical Retain topsoil integrity for the Remain within the designated area demarcated for
toilets reuse during rehabilitation; mining activities
Noise control;
Domestic waste management
Maintaining of Construction 200m Dust from the access road will Remain within the NEMAQA, 2004. Dust Regulation
the access road Operational be suppressed with water Guidelines for rural communities.
Decommissioning and/or a dust inhibitor;
Roads should have adequate NEMA, 1998 (Act 107 of 1998) NEMA EIA Regulations
drainage to remove storm of 2014 GN983.
water as
rapidly as possible;
Page | 22
Carry out the noisiest labours
as quickly as possible and
during normal working hours
(07:00 – 17:00) or according to
applicable legal criteria.
Raw material and Operational 2000m2 Limit the heights of the NWA, 1998 (Act 36 of 1998).
product stockpiles as far as possible.
stockpiling Clean up any spills National Environmental Management: Waste Act,
immediately and dispose of the 2008.
soil at a registered waste site.
Apply dust suppression NEMA, 1998 (Act 107 of 1998) NEMA EIA Regulations
techniques. of 2014 GN983.
Page | 23
Storm water management –
separating clean water from
dirty water through berms and
trenches.
Apply to the Construction Not known at Clean up any spills immediately
standards of the Operational this stage and disposed of the soil at a
National Decommissioning registered waste site.
Environmental Minimise dirty water area and
Management: contain dirty water;
Waste Act, 2008.
Prevent run-off of water with
high suspended solid content;
Page | 24
Waste should be removed off-
site by specialist contractors
for disposal;
Domestic waste will be
disposed of at an appropriately
authorised landfill facility to
reduce the risk of it affecting
the water resources;
Use local contractors as far as
possible.
Lithium ore, Gold Operational N/A Defining routes for the Occupational Health and Safety Act (85 of 1993). All
ore, circulation of heavy machinery future employees must undergo health and safety
Jade(gemstone), and vehicles; Implement dust
Page | 25
and suppression spraying on access training. Mining must be conducted according to
Quartz(gemstone) roads and the operational area; these regulations.
Product Regular maintenance of the
Transportation operational vehicles and
machinery to avoid leaks and
spillages;
Transport powdered materials
in covered trucks.
Trucks should adhere to the
required speed limits to avoid
unnecessary injury or death to
animals.
Page | 26
Concurrent Operational The area will be shaped to NEMA, 1998 (Act 107 of 1998). GN 940 Regulations
rehabilitation Decommissioning emulate pertaining to the Financial Provision for the
Closure the pre-mining topography; Rehabilitation, Closure and Post Closure for
Mining, Exploration, Mining or Production
free draining;
Page | 28
Page | 29
10. The Environmental attributes associated with the alternatives.
(The environmental attributed described must include socio-
economic, social, heritage, cultural, geographical, physical and
biological aspects)
The application area consists mainly of mining activities for the same commodity. The
description of the baseline environment and surrounding areas were obtained by using
a desktop study.
10.1 Type of environment affected by the proposed activity.
The study area is characterised by open high hills or ridges. The area is located on undulating
landscape with intermittent hills. The intensity of the undulating increases from west to east
in the direction of the Drakensberg escarpment and Swaziland. The area receives a mean
annual rainfall of between 601mm and 800mm, a mean maximum temperature of between
19.1oC and 31oC, and a mean minimum temperature of between 14 0C and 26oC. The
Komatiriver is not far from the proposed site but it doesn’t fall within the activity boundaries.
The occurrence of minerals in Chief Albert Luthuli local municipality is very high in
comparison to the other local municipalities within the Gert Sibande District. The Barberton
Greenstone Belt is situated on the eastern edge of Kaapvaal Craton in South Africa. It is
known for its gold mineralization and for its komatites, an unusual type of ultramafic
volcanic rock named after the Komati River that flows through the belt. Some of the oldest
exposed rocks are located in the Barberton greenstone belt of the Swaziland-Barberton
areas. The belt consists of a sequence of mafic to ultramafic lavas and metasedimentary
rocks emplaced and deposited between 3.5 and 3.2 Ga. The granitoid rocks were emplaced
over a 500 million-year time span and can be divided into two suites: the tonaliti-
trondhjemite-granodiorite (TTG) suite, and the granite-monzogranite- granite (GMS) suite.
Page | 30
The GMS suite are found over large parts of the Kaapvaal Craton and their emplacement
coincides with the first stabilisation of the central parts of the craton. The GMS suite in the
Barberton granite-greenstone terrane shows very different internal and external
characteristics from the earlier TTG suite. Individual plutons may cover several thousand
square kilometres and these composite granitoid bodies have traditionally been referred to
as batholiths, alluding to their compositionally and texturally heterogeneous nature and
enormous areal extent.
Air Quality
Sources of emissions that occur in the region include Eskom power stations, industrial
emissions, blasting operations at mines and spontaneous combustion of discard at gold
mines, veld burning, vehicle exhaust emissions and household fuel burning.
Various local and far-a-field sources are expected to contribute to the suspended fine
particulate concentrations in the region. Local sources include wind erosion from
exposed areas, fugitive dust from agricultural and mining operations, particulate
releases from industrial operations, vehicle entrainment from roadways and veld
burning. Household fuel burning also constitutes a significant local source of low-level
emissions.
Noise
The application area is located in a district where the character of ambient noise is to
some extent determined by economic activity which over time has resulted in an
increase in the background ambient level. It should be noted that from the perspective
of noise-sensitive recipients in area, the character of the noise environment has not
been affected only by external factors such as industrial and mining activity. The
character is also affected and the background ambient level elevated by noises
produced by farming activity, which is the principle land-use activity exercised by
noise-sensitive recipients in the area. The sources of noise currently contributing to the
ambient level area:
Page | 31
• General and small-scale mining activities scattered over the area which
contribute to machinery, truck and road traffic noise;
• Agricultural activities where the main sources of audible noise are tractor diesel
engines.
Noise in the area is restricted to traffic from the district dirt road and normal routine
vehicle noises from the farming that is practiced in the area. Agricultural activities such
as the cultivation of lands and harvesting of crops also contribute a low scale source of
noise to the ambient level. Potential receptors which might be affected by the proposed
operation are the farmers and the local residents of the neighbouring farms and the
farm workers. The residential areas are not located in vicinity of the proposed activities
and they are thus too far from the operation to be regarded as a receptor.
The study area is associated with grasslands and agricultural activities. There are no
residential areas in close vicinity.
Heritage
No heritage resources were identified inside the application area during the site visit
conducted. The EAP has consulted with SAHRA utilizing the sahris portal in order to
advise if a heritage impact assessment should be conducted or not, we still waiting for
response.
According to the Screening Tool Report, the site comprises of the very high sensitivity
of aquatic biodiversity and terrestrial biodiversity theme, high sensitivity in animal
species, medium sensitivity in Agriculture, civil aviation, palaeontology and plant
species and low sensitivity in archaeological and Defence theme hence, an Ecological
Assessment and surface water assessment was deemed unnecessary because according
to the EAP’s observation during the site inspection, the area is a disturbed land whereby
mining activities took place and a water resources outside the proposed site, on the
northern side which is approximately 120m therefore, it will not be affected by the
proposed mining activities and there are still remains of the diggings from the
previously mining. In addition, the site is vacant, contains of grasslands and few thorn
trees. No water resources exist within or close to the proposed. The EAP has advised
the applicant to avoid sensitive’s areas e.g the water resources and valley and ensure
that animals are moved away safely from the mining activities as far as possible.
Page | 32
11. Description of the current land uses
Page | 33
12. Description of specific environmental features and infrastructure
on the site
The vegetation distribution of the Ka-ngwane Montane Grasslands within veld type supports
livestock such cattle, sheep for grazing. The Ka-ngwane Montane grassland is the dominant
vegetation type in the region, and covers most part of the farm. The eastern mountainous
areas are covered with the Ka-ngwane Montane grassland up to the western side. As far as
Soil Types are concerned, the mountainous areas comprise of surface outcrop of ancient
volcanic (ultramafic) and sedimentary rocks which have associates with the greenstone belt
giving rise to soils with high magnesium, calcium ratios and high concentration of heavy
metals such as nickel and chromium.
Page | 34
13. Impacts and risks identified including the nature, significance,
consequence, extent, duration and probability of the impacts,
including the degree to which these impacts can be reversed
The table below indicates the environmental aspects and the specific impact that each
of the proposed activities will have on this aspect. The table further assesses the
duration, probability and level of significance of the impact pre-mitigation. It is also
indicated whether the impact is reversible or if it will lead to an irreplaceable loss of
resource. Lastly it shows whether the impact can be avoided, managed or mitigated.
The methodology used as described in Section 8.6 below was used to complete the
Impact Assessment. Please refer to Table 12 for the Impact Assessment Variables
definitions
Page | 35
Please note the full impact assessment which shows the determination of the level of significance is included in this report.
Table 13.1: Table indicating possible impacts and whether or not it can be reversed
Aspect Impact Cause / Activity Duration Probability Level of Reversible Irreplaceable Can be
Significance loss of avoided,
(Pre Resource managed
mitigation or
mitigated
Construction Phase
Disturbance of geological Blasting – Opening of Long Possible Low Reversible Unlikely Can be
Geology profile. initial cut. term over time avoided.
Page | 36
Landscaping activities Medium Definite Medium Reversible Unlikely Can be
• Levelling off the term beyond managed.
ground level; project
• Presence of lifespan
vehicles on site.
Construction/upgrading
Compaction of soils. of access road.
Contamination due to Waste handling – Short Possible Medium Quickly Unlikely Can be
spillage. spillages from vehicles. term reversible avoided.
Page | 37
Blasting – Opening of
initial cut.
Page | 38
Preparation of footprint Short Possible Low Quickly Unlikely Can be
areas through the term reversible avoided.
clearing of vegetation in
areas designated for
Harm to Fauna. surface infrastructure.
Deterioration in Surface Water Waste handling – Short Possible Medium Reversible Unlikely Can be
Quality. spillages from vehicles. term over time avoided.
Page | 39
Preparation of footprint Medium Possible Medium Reversible Possible Can be
areas through the term beyond avoided.
Potential risk of fracturing clearing of vegetation in project
shallow aquifers and areas designated for lifespan.
depletion of aquifer. surface
infrastructure;
Removal of vegetation and
top soil decreases the Blasting – Opening of
Groundwater recharge of aquifers. initial cut;
Contamination of the Waste handling – Medium Possible Medium Non Unlikely Can be
underlying aquifer. spillages from vehicles. term reversible. avoided.
Air Quality Reduction in air ambient Construction/upgrading Short Probable Medium Quickly N/A Can be
Page | 40
Noise Short Definite Medium Quickly N/A Can be
term reversible managed.
Blasting – Opening of
initial cut.
Landscaping activities
• Levelling off the
ground level;
Increase in ambient noise • Presence of
levels. vehicles on site;
Page | 41
vehicles on site;
Page | 42
Health and Landscaping activities Short Unlikely Medium Not N/A Can be
safety Presence of term reversible avoided.
Vehicles on site.
Increased potential for Construction/upgrading
accidents. of access road.
Page | 43
Operational Phase
Geology Disturbance of geological Blasting to loosen the Medium Probable Medium Not Unlikely Can be
profile. deposit. term reversible avoided.
Topography Raw material and Short Definite Medium Reversible Unlikely Can be
product stockpiling. term over time managed.
Alteration of the natural
topography
Page | 43
location. Raw material
and product stockpiling.
Page | 44
Vegetation Changes in vegetation Long Probable Medium Reversible Possible Can be
(Flora) dynamics, potential Excavation of Lithium term beyond mitigated.
disturbance and loss of ore, Gold ore, project
sensitive flora. Jade(gemstone), and lifespan
Potential alteration of Quartz(gemstone) using
ecosystem functioning due to excavators.
increased human activities.
Page | 45
Fauna Excavation of Lithium Short Possible Low Reversible Unlikely Can be
ore, Gold ore, term over time managed.
Jade(gemstone), and
Quartz(gemstone) using
excavators.
Page | 46
Presence of haulage Short Possible Medium Reversible Unlikely Can be
trucks term over time avoided.
on site;
Transportation of
Lithium ore, Gold
ore, Jade(gemstone),
and
Quartz(gemstone)/
product to the
desired location.
Surface water contamination
through oil or diesel spills.
Page | 47
nitrates released from
explosions.
Page | 48
Air Quality Excavation of Lithium Short Probable Medium Quickly N/A Can be
ore, Gold ore, term reversible mitigated.
Jade(gemstone), and
Quartz(gemstone) using
excavators;
Dry screening;
Presence of haulage
trucks
on site;
Transportation of
Lithium ore, Gold ore,
Jade(gemstone), and
Quartz(gemstone)/
Reduction in air ambient product to the desired
quality. location.
Page | 49
Blasting to loosen
deposit.
Presence of haulage
trucks
on site;
Transportation of
Lithium ore, Gold
ore, Jade(gemstone),
and
Quartz(gemstone)/
product to the
desired location.
Page | 50
Jade(gemstone), and
Quartz(gemstone)
product to the desired
location.
The local and regional road Medium Definite High Reversible N/A Can be
transport network will suffer Transportation of term over time managed.
additional pressure from the product to the
haulage trucks. desired location.
Health and Safety of Transportation of Short Unlikely Medium Not Unlikely Can be
community. product to the term reversible avoided.
desired location.
Damage to surrounding Blasting to loosen the Medium Possible Medium Reversible N/A Can be
houses and infrastructure. deposit. term over time avoided.
Page | 51
Archaeology Excavation of Lithium Long Unlikely Medium Not Possible Can be
and Cultural ore, Gold ore, term reversible avoided.
Heritage Jade(gemstone), and
Quartz(gemstone) using
excavators;
Degradation of heritage and Blasting to loosen the
cultural sites deposit.
Decommissioning Phase
Ripping, landscaping
and re-vegetation of all
disturbed areas.
Page | 52
Soils Ripping, landscaping and Short Possible Medium Reversible Unlikely Can be
re-vegetation of all term (Positive) over time managed.
disturbed areas;
Minimisation of erosion.
Land Slow positive impact on areas Medium Possible Medium N/A Unlikely Can be
Maintenance of all
capability requiring rehabilitation and revegetated areas up term (Positive) managed.
transforming mining to a until such areas initiate
state of post-mining, succession and create a
engineered agricultural and sustainable cover.
wilderness areas.
Land use Maintenance of all Medium Possible Medium N/A Unlikely Can be
revegetated areas up term (Positive) managed.
Land use will change from until such areas initiate
mining back to agriculture succession and create a
and wilderness areas. sustainable cover.
Vegetation Establishment of pastures for Ripping, landscaping Medium Possible Medium N/A Unlikely Can be
livestock grazing. and re-vegetation of all term (Positive) managed.
disturbed areas;
Page | 53
Improvement in erosion
control of rehabilitated areas. Maintenance of all
revegetated areas up
until such areas initiate
succession and create a
sustainable cover;
Page | 54
Waste generation and Short Possible Medium Quickly Unlikely Can be
disposal (hazardous and term reversible avoided.
Contamination of surface domestic).
water.
Groundwater Replacement of soils and N/A N/A N/A N/A N/A N/A
backfilling of the pit.
No further impact expected.
Air Quality Dismantling and removal Short Probable Medium Quickly N/A Can be
of all infrastructure in term reversible managed.
meeting the closure
objectives;
Ripping, landscaping
Increase dust levels for a short and re-vegetation of all
period. disturbed areas.
Noise Dismantling and removal Short Definite Medium Quickly N/A Can be
of all infrastructure in term reversible managed.
meeting the closure
Increase noise levels for a objectives;
short period.
Visual Dismantling and removal Medium Possible Medium Reversible N/A Can be
Aspects Ongoing rehabilitation will of all infrastructure in term (Positive) over time managed.
improve the visual aesthetic of meeting the closure
the project site, thus objectives;
decreasing the visual impact.
Page | 55
Ripping, landscaping
and re-vegetation of all
disturbed areas.
Post Closure
Geology No further impact as geology N/A N/A N/A N/A N/A N/A
will remain intact and have a
stable geological foundation. N/A
Topography Removal of the Lithium Long Probable High Reversible Possible Can be
ore, Gold ore, term beyond managed.
Subsidence of mining area. Jade(gemstone), and project
Quartz(gemstone)/ layer lifespan
Page | 56
during the operational
phase.
Soil Subsidence could result in the Long Probable High Reversible Possible Can be
loss of the soil resources. term beyond managed.
Ponding on areas due to Removal of the topsoil project
subsidence and lack of layer during the lifespan
compaction. operational phase.
Page | 57
Monitoring of key Long Possible Medium N/A N/A Can be
environmental variables term (Positive) managed.
(i.e. soils, vegetation,
groundwater and surface
water) in order to
demonstrate stability of
rehabilitated areas.
Page | 58
Land Monitoring of key Long Possible Medium N/A N/A Can be
capability environmental variables term (Positive) managed.
(i.e. soils, vegetation,
groundwater and surface
water) in order to
demonstrate stability of
rehabilitated areas.
Land use Monitoring of key Long Possible Medium N/A N/A Can be
environmental variables term (Positive) managed.
(i.e. soils, vegetation,
groundwater and surface
water) in order to
demonstrate stability of
rehabilitated areas.
Weed management after
closure, limited to areas
Return to agricultural grazing disturbed by mining or
land. included as
Page | 59
infrastructure related to
the mine
Page | 60
Animal Life Monitoring of key Medium Possible Medium N/A N/A Can be
(mammals, environmental variables term (Positive) managed.
avifauna and (i.e. soils, vegetation,
herpetofauna) groundwater and surface
water) in order to
demonstrate stability of
rehabilitated areas.
Weed management after
closure, limited to areas
disturbed by mining or
included as
infrastructure related to
Recovery of area suitable for the mine.
livestock and wildlife.
Surface Water Monitoring of key Medium Possible Medium N/A N/A Can be
environmental variables term (Positive) managed.
(i.e. soils, vegetation,
groundwater and
Free drainage and surface water) in order
natural surface water to demonstrate stability
patterns stabilisation; of rehabilitated areas.
Ground Water No residual impacts are N/A N/A N/A N/A N/A N/A
expected once mining
operations cease. N/A
Page | 61
Air Quality No residual impacts are N/A N/A N/A N/A N/A N/A
expected once mining
operations cease. Air quality
will be ambient levels. N/A
Noise No residual impacts are N/A N/A N/A N/A N/A N/A
expected once mining
operations cease. Noise will
be at ambient levels. N/A
Page | 62
Archaeology N/A N/A N/A N/A N/A N/A
and Cultural
Heritage No further impact. N/A
Page | 63
14. Methodology used in determining and ranking the nature,
significance, consequences, extent, duration and probability of
potential environmental impacts and risks;
The methodology assesses environmental and social impacts by evaluating the consequence
(spatial extent, duration, and severity of the impact) and likelihood (probability and
frequency of the impact occurring) of each impact and providing a numerical score for each.
The significance of each impact is determined by ranking the total score of the consequence
with the likelihood of each impact using a matrix. The risk class for each impact is
determined through a separate matrix ranking the severity with the probability of the impact
occurring.
The definitions of terms used within the methodology are described below, followed by
stepped approach to the explanation of the methodology used.
Definitions
Aspect – a facet of the social or biophysical environment upon/within which impacts can
occur.
Impact – is defined as any change to the environment, whether positive or negative, resulting
from a facility/project/development’s products, development, and activities.
Significance Level – the degree of importance of the impact on the social and/or biophysical
environment; a proxy for the degree to which the impact is reversible and may cause
irreplaceable loss of a resource. The approach used to determine significance makes use of
value judgements to determine the degree of change on the social and/or biophysical
environment, after which the consequence and likelihood of the impact are ranked to provide
a significance level.
Extent – the spatial scope of the perceived impact. (How large an area will be impacted).
Duration – the temporal scope of the perceived impact, or the period of time during which
the social and/or biophysical environment is changed by the impact. (How long the impact
will last).
Page | 60
Severity – the degree to which the natural, cultural, and/or social functions and processes of
an environment may be affected or altered by a perceived impact. (How extreme/harsh the
impact will be. The degree of disturbance).
Risk – is defined as a function of the probability of an impact occurring and its severity.
Risk Class – grouping of the perceived risk of the impact occurring into categories (low,
medium, high, and very high) according to the function of the impact’s severity and
probability of occurrence.
Step 1: The potential aspects and activities are identified along with the associated social
and biophysical impacts which may occur during the construction, operation, and
decommissioning phases of the project.
Step 2: The consequence and likelihood of each impact identified in the preceding step is
evaluated and a rating score given for each variable following Table 13.
Step 3: The total score of the consequence and likelihood of each impact is ranked in the
matrix (Table 14), and the significance category determined.
Step 4: Mitigation measures for each impact are determined, and step 2 and 3 are repeated
to determine the significance of each impact post-mitigation.
Step 5: The risk class of each impact identified is calculated as a function of the severity and
probability of the impact, and by using a matrix (Table 15) the risk class category is
determined.
Page | 61
Short term Quickly reversible, less than project lifespan 1
Page | 62
Once off The activity occurs once off or it already happened 1
Table 13: Impact Significance Ranking Matrix and Significance Level Categories
Consequence
3 4 5 6 7 8 9 10 11 12
2 5 6 7 8 9 10 11 12 13 14
3 6 7 8 9 10 11 12 13 14 15
4 7 8 9 10 11 12 13 14 15 16
5 8 9 10 11 12 13 14 15 16 17
6 9 10 11 12 13 14 15 16 17 18
7 10 11 12 13 14 15 16 17 18 19
Likelihood 8 11 12 13 14 15 16 17 18 19 20
Low Where there will not be a significant influence on the environment. 5-10
Management measures can be proposed to ensure that the significance
does not increase.
Medium Where the impact could have a low to significant influence on the
environment unless it is mitigated and/or managed. More easily 11-
reversible. 14
Page | 63
High Where the impact would have a significant influence on the environment 15-
unless mitigated and/or managed. Difficult to reverse. 17
Very Where the impact would have a significant permanent influence on the 18-
High environment regardless of any possible mitigation, or mitigation is not 20
feasible, and hence must either be avoided or managed.
The risk ranking of the impact is determined through the function of the probability (chance
of the impact occurring) and severity.
Table 15: Impact Risk Ranking Matrix and Risk Class Categories
Severity
1 3 5
1 1 3 5
2 2 6 10
3 3 9 15
4 4 12 20
Page | 64
15. The positive and negative impacts that the proposed activity (in
terms of the initial site layout) and alternatives will have on the
environment and the community that may be affected
Due to the fact that this proposed activity will take part on the specific area that was
permitted by the DMR, no alternative area is assessed as part of this specific application.
The impacts have been discussed below in terms of the construction, operation,
decommissioning and closure phases.
15.1 Construction Phase
The environmental and socio economic aspects that will be impacted on during the
construction phase of the proposed mine have been described below. A description of the
impact has been provided along with a discussion in terms of advantages and disadvantages
of the initial site layout.
15.1.1 Geology
The geology of the site will be altered by the blasting activities during the opening of the
initial cut. As the Applicant plans to mine to a depth of approximately 10 -15m, the low
lying geology will be altered. The disturbance will be limited to part of the project area.
Discussion
The fact that this is an application for a mining permit and the Applicant will only be allowed
to mine within the 5ha boundary the location of the initial cut will not have a significant
impact because the whole 5ha area will be mined within the two years. The more significant
impact will be the indirect impact that blasting could have on the groundwater quantity
should an aquifer be breached in the process.
15.1.2 Topography
The topography will be levelled during the landscaping activities specifically in areas
designated for the establishment of surface infrastructure. The disturbance will be limited
to part of the project area, it is reversible in the long term (> 2 years) as the post mining
topography will be landscaped to emulate the pre-mining topography but the impact will
definitely happen.
15.1.3 Soils
Topsoil and subsoil will be disturbed during the construction phase when the footprint areas
for surface infrastructure are stripped. The topsoil and subsoil will be stockpiled for use
during rehabilitation upon closure of the mine. The soil in the areas to be disturbed that is
Page | 65
suitable for use as a growth medium will be excavated (pre-stripped) and stockpiled for use
during rehabilitation (decommissioning phase). The pre-stripping and stockpiling of the
soil will result in both physical and chemical changes in the soil due to the disturbance,
increased aeration and absence of vegetative cover.
This action on the soil will result in a breakdown of the macro- and micro-soil structure,
especially when excessively wet and with duplicate handling. As only the topsoil and subsoil
will be stockpiled, the mixing of the soil from the lower horizons with the bed rock would
alter the characteristics of the conglomerate as far as chemistry and water retention capacity
is concerned. The stockpiled topsoil and subsoil will be exposed to contamination (such as
oils lubricants) and erosion agents such as water and wind during the construction phase.
During construction there is the probability of sheet erosion occurring on the areas cleared
of vegetation. The extent of the cleared area is however relatively small and will only involve
portions of the mining area. As these sites will be actively managed (or be covered by
temporary structures) the duration will be long term. The probability of gully erosion will
be limited to the concentrated flow of collected water points or concentrated flow points
(such as culverts) around the planned activities. However proper berm construction and
erosion control measures will ensure that the intensity will be greatly reduced.
Discussion
The impact on the soils during the construction phase will be negative and is unavoidable.
However the soils can be used in a positive manner such as for berm construction. The
proposed mining area is currently used for grazing purposes therefor it is assumed that the
soil is of good quality. Based on this assumption it is important that the topsoil is correctly
managed from the construction phase to decommissioning phase to ensure that it retains
its characteristics. When this happen the positive impact of stripping the soils will occur
during the rehabilitation phase when topsoil containing a gene bank of seeds of indigenous
species can be spread over the rehabilitated area. A loss of topsoil (through sterilisation,
erosion or contamination) would generally result in a decrease in the rehabilitation and
future land use potential of any land that is disturbed by the construction of the proposed
infrastructure and mining activities.
Land capability will be compromised in the vicinity of the operational areas that are planned
to be pre-stripped of topsoil and growth medium material (for later re-use). The
disturbance will be limited to a relatively small part of the project area.
Page | 66
Where the land capability is grazing or wilderness, the post mining capability will not be
compromised and the impact is reversible in the long term (> 2 years) and will definitely
happen. However large parts of the proposed mining area is under crop production therefor
the land capability of the mining area will definitely be compromised during the construction
phase of the planned activities. This is mainly due to the impact that the construction
activities will have on the topsoil of the site.
Discussion
No alternative mining sites are being considered as part of this application therefore the
topsoil must be managed from the construction phase to decommissioning phase to ensure
that it retains its characteristics. When this happen the positive impact of stripping the soils
will occur during the rehabilitation phase when topsoil containing a gene bank of seeds of
indigenous species can be spread over the rehabilitated area. This will give the area the best
chance of returning back to the pre-mining land capability.
The land use will change from agriculture to mining during the construction phase. Due to
the small nature of the Lithium ore, Gold ore, Jade(gemstone), and Quartz(gemstone)/
mining operation adjacent land uses should not be impacted on during the construction
phase. The land use of the proposed site will definitely change but it can be reversed in the
long term.
Discussion
The site is currently used for agriculture (crop production) and post-mining activities
purposes. The negative impact is that the land use of the mining area will change from
agriculture to mining. The positive impact will be on the socio economic side for the
Applicant in terms of requiring the Lithium ore, Gold ore, Jade(gemstone), and
Quartz(gemstone)/ resource to supply to the growing building industry in the area. The land
use must be given the best chance to return to the pre-mining state through the correct
implementation of the EMP.
15.1.6 Flora
The construction activities will lead to loss of indigenous vegetation on the property. The
losses will come about mainly through site clearance activities specifically on area
designated for infrastructure establishment. Natural ecological processes will be disrupted
and there is a strong probability that alien weed species such as Wattle (Acacia mearnsii) will
become more prolific. The removal of flora will definitely occur but the impact is reversible
Page | 67
in the long term. By implementing a weed eradication program the probability of alien
species colonising the area can be decreased significantly.
The flora on adjacent properties could also be impacted on through dust fallout created by
the construction and transportation activities.
Discussion
The clearing of vegetation is unavoidable and necessary for the project. The impact is
considered negative but not highly significant seeing that the area has been used for
agriculture and it is not expected to find much indigenous or sensitive species within the
5ha.
15.1.7 Fauna/Avifauna/Herpetofauna
The terrestrial fauna at the site is already very severely depleted with many of the original
species, especially the larger mammals, now being locally extinct due to agricultural
activities. However, with the further degradation of the area as a result of the mine
development, further losses will take place. Affected groups will include the mammals,
birds, reptiles, amphibians, and a wide variety of invertebrate groups with the insects being
the most obvious. Several species of conservation have already been lost from the area as a
result of human activities.
The disturbance and consequent habitat destruction will comprise part of the mining permit
area during construction. It is estimated that the zone of influence would be temporary in
the long term and will happen. The associated loss of habitat, disturbance in the area in
terms of noise and dust pollution associated with construction activities will possibly have a
negative cumulative impact on the fauna in the surrounding area in the long term.
Discussion
Only part of the mining permit area will be disturbed during the construction phase but as
the operation continues the disturbed area will increase. However due to the small size of
the permit area (5ha) and the fact that the area has been used for crop production over the
last few years the impact on animal life is assessed to be of low significance.
Spillage from chemical toilets, oil spills and construction dumping may be picked up by
runoff and will contaminate the downstream watercourses. Sedimentation of the water
Page | 68
resources could occur from exposed surface during periods of high rainfall. Increased
sediment movement off the construction sites will add to the cumulative impact of increased
sediment loads in the watercourses down gradient of the site.
In order to prevent surface water contamination storm water falling within the construction
site will be contained and guided into the pit by the means of strategically placed berms.
This water will be prohibited from entering the drainage lines and will therefore affect the
quantity of surface water runoff negative.
Discussion
The containment of storm water within the construction area will decrease the surface water
runoff into the surrounding surface water resources. Thereby affecting the quantity of water
in these resources negatively. On the other hand the positive impact will be that it will
contain potentially contaminated water and decrease the risk of surface water pollution.
15.1.8 Groundwater
The opening of the initial cut through blasting could fracture the impermeable rock layers
and result in the depletion of the aquifer.
Spillage from chemical toilets, oil spills and construction dumping may infiltrate the
groundwater system and contaminate the groundwater resources. Dirty storm water
collecting in the pit has the potential to leach into the groundwater.
Discussion
The landowner and surrounding landowners is dependent on groundwater for their farming
activities as well as domestic use. The potential of the depletion of the groundwater aquifer
during the opening of the initial cut is considered a highly significant negative impact. Due
to the non-hazardous nature of the proposed Lithium ore, Gold ore, Jade(gemstone), and
Quartz(gemstone)/ mine the potential of groundwater being contaminated is unlikely. It
could occur from oil or diesel spillages but this can easily be avoided by implementing strict
management measures.
During the construction phase of the planned activities dust will mainly be produced by site
establishment operations, including stripping of topsoil and grading of access roads. The
carbon-dioxide emissions associated with the diesel machines are of such a small quantity
that the impact thereof on the air quality is considered to be of a low significance. The
impact on air quality is considered to be definite but of a low significance and it can be
reversed quickly. Dust suppression by water tanker will be employed to mitigate the release
of dust which will lower the significance rating of the impact.
Page | 69
Blasting will result in an increase in dust and possible “fly-rock”. Construction and
operational activities in the area associated with development and mining activities will
probably have a cumulative impact on the air quality of the area if mitigation measures are
not implemented.
Discussion
The ambient air quality will definitely be negatively impacted on during the construction
phase but should the necessary mitigation measures be applied the impact will be of low
significance. The main source of dust will be from the access road however most of the
construction vehicles will remain on site during the construction phase thereby limiting the
amount of dust generation in the surrounding area.
15.1.10 Noise
The main cause of an increase in the ambient noise level will be during the blasting activities
to open the initial cut. Haulage trucks and other machinery associated with site
establishment will also contribute to the increase in noise levels. The reverse sirens of the
construction vehicles and general diesel engine running noise will add to the industrial noise
of the site, which will be in stark contrast to the natural noise character that the site currently
has. The construction noise will extend from the site boundaries and will definitely
contribute to the existing noise levels.
Discussion
The increase in noise level cannot be avoided but measures can be put in place to decrease
the significance of the impact especially on the surrounding agricultural operations (chicken
farming). Construction activities should be limited to the day time only.
Of the planned activities, the vegetation stripping, soil stockpiling and infrastructure
establishment will have an impact on the visual character of the area. There are no residential
areas in the vicinity.
The new presence of mining equipment (mobile screening plant) will change the aesthetics
and “sense-of-place” of the area. Dust from the construction activities will also cause a
visual disturbance that is temporary.
Page | 70
Discussion
The visual impact of the construction activities will be negative and can’t be avoided. The
impact will occur from the construction to the decommissioning phase. Due to the small
nature of the Lithium ore, Gold ore, Jade(gemstone), and Quartz(gemstone)/ mining
operation there won’t be high overburden or soil stockpiles on site therefore the visual
impact will not extend far beyond the application area.
This project will ensure employment of personnel associated with the construction of the
mine, albeit on a temporary basis.
There will be an opportunity for a permanent employment framework, but this is covered
under the section below, operational phase.
Due to the small and non-hazardous nature of the Lithium ore, Gold ore, Jade(gemstone),
and Quartz(gemstone)/ mining operation it should not have a negative impact upon the
value of surrounding land. This is a subjective issue, (in that it would largely be determined
by market forces), and has not been quantified. The overall, residual impacts as determined
by this assessment are such that it is unlikely that a significant, long-term depreciation in
land value would result.
Additional heavy motor vehicle traffic will contribute to the road degradation of the
surrounding roads. However, it is not foreseen that the construction phase will contribute
significantly to the road infrastructure degradation as the construction vehicles will remain
on site during the construction period and will not travel on the surrounding district roads
frequently.
Discussion
The effect of the construction phase on the regional and socio-economic structure will
extend beyond the project area and will be temporary (short term <6 months). It will have a
low to moderate level of significance, both negative and positive. The biophysical negative
impacts will mainly be felt by the landowner in terms of land use and capability and the
positive impacts by the unemployed people in the surrounding area in terms of job
opportunities.
The increase of heavy vehicles movement on the district roads and surrounding farm roads
will result in a higher probability of accidents occurring. Unfortunately this can’t be
Page | 71
completely avoided but strict measures can be implemented to decrease the probability of
accidents occurring significantly.
The commuting of workers onto neighbouring properties may pose safety risks as well.
Discussion
The risk of accident occurring can significantly be decreased if the construction vehicles
remain on site thereby decreasing the amount of traffic on the district road.
The opening of the initial cut and levelling of the site has the potential to impact heritage
resources.
Discussion
Damage to heritage resources is considered a highly significant negative impact, which can’t
be reversed and must be avoided at all cost. The protection of archaeological features,
specifically graves is emphasised.
15.2.1 Soils
As per the construction phase, the soils excavated will be separately pre-stripped as topsoil
or subsoil and stockpiled separately in a designated area for use during rehabilitation.
During the stripping operation of the soil, soil layers will be mixed when removed,
transported and stockpiled by the bulldozers. Seeds and roots within these layers will be
uprooted and may be exposed to the open air elements which could damage and kill them.
This will render the topsoil less fertile. Further stockpiling of the soil will expose the soil to
elements of erosion such as wind and water as well as risking the occurrence of compaction.
The probability of gully erosion will be limited to the concentrated flow of collected water
points or concentrated flow points (such as culverts) around the mining area. However,
proper berm construction and erosion control measures will ensure that the intensity will be
greatly reduced. The impact on the soils of the area, due to erosion will therefore have a
low level of significance.
Page | 72
Sterilisation of footprint area could occur through compaction, stockpiling and operational
vehicle movement. As these sites will be actively managed (or be covered by temporary
structures) the duration will be long term.
The potential for soil contamination exists through oil or diesel spillages from operational
vehicles.
Concurrent rehabilitation will take place during the operational phase. The probability exists
that sheet erosion could occur on these areas if it is not revegetated and managed correctly.
Discussion
The negative impacts on the soils are definite but can be limited to the project area. The
potential of erosion and contamination of soils can be significantly reduced by implementing
sufficient mitigation and management measures. The topsoil should be returned to the land
as soon as possible and not stored for prolonged periods. If possible, take the topsoil that
is removed from the section that is opened for mining and place it directly on the one that
is being rehabilitated. This will reduce the time of exposure.
Topsoil should be placed in the two separate layers: the bottom 700mm and the top 400mm.
Apply fertilizers and rip the soil to a depth of 1, 6 meters and at 1, 5 meter intervals along
the contour. This action will ensure that there is a bond between the top and subsoil and
that infiltration of water, whether from rain or irrigation will take place. The topsoil must be
managed from construction through to decommissioning to enable the mine to rehabilitate
the area as close as possible to the pre-mining state. The positive impact of stripping the
soils will occur during concurrent rehabilitation when the topsoil containing a gene bank of
seeds of indigenous species can be spread over the rehabilitated area.
The land capability will continue to be impacted on by the activities associated with mining.
Discussion
The negative impact on the land capability during the operational phase cannot be avoided
but is reversible over a long period (>3 years). The impact on the infrastructure (access road)
will be less significant.
Page | 73
15.2.3 Land Use
The land use will remain as mining. There would be no further impact during the operational
phase as the land use was already changed to mining in the 5ha area during the construction
phase.
Discussion
As with the land capability the negative impact during the operational phase on the proposed
site is unavoidable but can be reversed over a long period (>3 years). Due to the non-
hazardous nature of the proposed activity the land use of the surrounding areas will not be
impacted on significantly.
15.2.4 Flora
The removal of vegetation as the mining pit extends over the 5ha area will change the
vegetation dynamics. The grassland will be impacted upon by the Lithium ore, Gold ore,
Jade(gemstone), and Quartz(gemstone)/-winning. The seed bank of indigenous vegetation
that occurs in the topsoil will be used throughout the full area being rehabilitated, and would
thus become “diluted”.
Alien invader species may further establish on the disturbed areas if a weed eradication plan
is not set in place.
Operational activities especially the screening of the raw Lithium ore, Gold ore,
Jade(gemstone), and Quartz(gemstone)/ and transport of Lithium ore, Gold ore,
Jade(gemstone), and Quartz(gemstone)/ product to the desired location, will produce dust
which may impact vegetation surrounding the operational areas.
Discussion
Impacts on the vegetation will be on-going from the construction phase. The severity of the
impact will increase as the open pit increase in size. Large areas of the site’s vegetation has
already been disturbed by agricultural activities therefore little indigenous vegetation remain
on site.
Slight contamination of surface water will result from the area being free of vegetation and
the soil being disturbed. The potential for hydrocarbon pollution also exists due to spillages
from vehicles and heavy machinery. The closest watercourse to the application area is
situated approximately …km from the 5ha boundary therefor the risk of surface water
resources being polluted is low.
Page | 74
Storm water will be contained within the mining area and diverted to the open pit via
strategically placed berms. The will result in the reduction of storm water runoff.
Discussion
Surface water in the area is essential to sustain agricultural activities and for domestic
purposes. Due to the non-hazardous nature of the Lithium ore, Gold ore, Jade(gemstone),
and Quartz(gemstone)/ mining operation as well as the application area’s distance from the
nearest surface water resources (500m) the risk of surface water resources being polluted
is low.
The main negative impact that the operation will have on the surface water will be in terms
of storm water runoff. By containing all the water falling onto the operational area during
operations the runoff within the natural draining lines will be reduced.
15.2.6 Groundwater
The mining activities have the potential to impact on the groundwater in the following ways:
• Blasting could fracture the weathered aquifer leading to the reduction in groundwater
yield in the regional area.
• The potential exists that oil/diesel spills can seep through and contaminate the
underlying aquifer.
Discussion
The negative impact on groundwater quantity is considered to be a highly significant risk
during the operation of the mine. In terms of groundwater quality during the operational
phase of the Lithium ore, Gold ore, Jade(gemstone), and Quartz(gemstone)/-winning
project, groundwater will seep into the Lithium ore, Gold ore, Jade(gemstone), and
Quartz(gemstone)/-winning area. However due to the non-hazardous and shallow nature
of this operation the impact is not considered to be significant.
15.2.7 Air Quality
The operation of the mine will continue to contribute to the reduction in air ambient quality
through excavation activities, dry screening and movement of the haulage trucks. Dust will
be created from the localised operational area and the untarred access and district roads
during the operational phase from the haulage trucks. Dust suppression by water tanker will
be employed to mitigate the release of dust which will lower the significance rating of the
impact.
Page | 75
Discussion
The ambient air quality will definitely be negatively impacted on during the operational
phase but should the necessary mitigation measures be applied the impact will be of low
significance.
The main source of dust will be the dry screening activities and transport activities on the
access road. Operational activities in the area associated with the mine will probably have a
cumulative impact on the air quality along with the other industrial operation and farming
activities.
15.2.8 Noise
Noise will be created on a daily basis by the haulage trucks, excavation and loading
machinery as well as their reverse sirens. Occasional blasting will also contribute to the noise
pollution of the area.
Discussion
The disturbance would extend beyond the project area due to the haulage trucks and sirens;
it would be a temporary disturbance but it will happen. The increase in noise level cannot
be avoided but measures can be put in place to decrease the severity of the impact especially
on the surrounding agricultural operations which is sensitive to noise such as chicken
farming. These measures include erecting noise barriers near the noise source, between the
noise source and receptors.
15.2.9 Visual Aspects
The visual impact will result from the raw material and Lithium ore, Gold ore,
Jade(gemstone), and Quartz(gemstone)/ product stockpiles as well as the mobile screening
plant. Dust created during the transportation of the Lithium ore, Gold ore, Jade(gemstone),
and Quartz(gemstone)/ product to the desired location will also contribute to the negative
impact on the visual character of the area.
Discussion
The visual impact is definite and can’t be avoided. This is an impact that will continue from
the construction through to the decommissioning phase but will not increase by a great
magnitude as it is really only applicable to the specific operational area and not the entire
area at one time.
15.2.10 Socio Economic
The operational phase of the mine will have both positive and negative impacts on the socio
economic conditions of the surrounding area. The positive impacts include:
• Additional employment opportunities for local people;
• The supply of Lithium ore, Gold ore, Jade(gemstone), and Quartz(gemstone)/ will
assist the ongoing development of the socio economic structure;
Page | 76
The negative impacts include:
• The local and regional road transport network will suffer additional pressure from the
haulage trucks;
• Damage to surrounding houses and infrastructure caused by blasting of overburden
material;
• Decrease in agricultural potential of the application area.
Discussion
The associated sustainable employment opportunities will be a low positive impact on the
economic structures of the area due to the small size of the proposed operation. The
negative impacts will mainly be felt by people using the local and regional transport network.
Page | 77
16. The possible mitigation measures that could be applied and the level of risk.
(With regard to the issues and concerns raised by affected parties provide a list of the issues raised and an assessment/ discussion of
the mitigations or site layout alternatives available to accommodate or address their concerns, together with an assessment of the
impacts or risks associated with the mitigation or alternatives considered).
The table below lists the mitigation measures that could be applied to mitigate the potential impacts per each activity during the
construction, operation, decommissioning and closure phases of the Lithium ore, Gold ore, Jade(gemstone), and Quartz(gemstone)/
winning operation.
Table 16.1: Possible Mitigation Measures
Potential for
Activity Potential Impact Mitigation Type Residual Risk
Construction Phase
Page | 75
Land Capability Restrict vegetation clearance to
Loss in agricultural potential. construction areas.
Animal life
Harm to Remove vegetation during periods of low
Page | 76
site as far as possible during the
construction period.
Page | 77
Soils
Over areas of deep excavation (Open Pit
Loss of soil resource (soils covered or
Mining) where the majority or all of the
removed) due to sedimentation and
soil profile is to be impacted) strip all
erosion (wind and/or water).
usable soil (approx. 750mm) and
stockpile as berms or low, terraced
Surface water
dumps.
Siltation of surface water due to
erosion of exposed surfaces.
Store the soil in stockpiles or berms of
not more than 1.5 m around
Air Quality
infrastructure area ready for closure
Reduction in air ambient quality. rehabilitation purposes. The gradient of
the sidewalls must be such as to prevent
Visual Aspects excessive wash during storms.
Visual intrusion. Disturbance to the
sense of place. Stockpile hydromorphic (wet) soils
separately from the dry materials, and
the “ferricrete” separately from all other
materials.
Page | 78
Protect all stockpiles from water and
wind erosion (loss of materials) and
contamination by dust and runoff water.
Clad stockpiles with larger rock or
vegetate the stored materials.
Page | 79
Control of the area disturbed during the
Animal life construction phase to ensure no
Destruction of natural habitat unplanned (and/or unauthorised)
affecting the animal life. expansion, with a direct effect on land
use.
Page | 80
Remove any oil or diesel spills as soon as
Surface water it occurs and dispose of it at a registered
Increased in Surface Water Runoff. waste site.
Page | 81
The location of the initial cut will be
Geology outside the 1:100 year flood line or
Disturbance of geological profile. 100m from a watercourse whichever is
greatest.
Land Use
Loss of agricultural land, change of Blasting must be controlled to prevent
Blasting – Opening of initial cut. land use from Agriculture to Mining. spillage of explosions; Possible
Page | 82
Carry out the noisiest labours as quickly
as possible and during normal working
hours (07:00 – 17:00) or according to
applicable legal criteria.
Page | 83
Roads should have adequate drainage to
remove storm water as rapidly as
possible;
Groundwater
Contamination of the underlying Remove any oil or diesel spills as soon as
Waste handling (domestic and aquifer. it occurs and dispose of it at a registered
hazardous). waste site. Unlikely
Page | 84
Surface water
Deterioration in Surface Water Quality. Clean up any spills immediately and
disposed of the soil at a registered waste
Soils site.
Contamination due to spillage.
Prevent run-off of water with high
suspended solid content;
Operational Phase
Page | 85
Land Use Restrict the area of impact to that which
Disruption of ecosystems and will be used for Lithium ore, Gold ore,
potential. Jade(gemstone), and
Quartz(gemstone)/-winning.
Page | 86
loss of agricultural land, land use
Clean up any oil/diesel spills
being reduced to mining.
immediately and disposed of the soil at a
registered waste site.
Vegetation
Changes in vegetation dynamics, Dust suppression will be implemented on
potential disturbance and loss of roads.
sensitive flora.
Use local workers as far as possible;
Potential alteration of eco-system
No mining activities can be conducted
functioning due to increased human
within the 1:100 year flood line or 100m
activities.
from a watercourse whichever is
Fauna greatest.
Displacement of indigenous faunal
species. Clearly demarcate the mining area within
which operational activities may take
Surface water place;
Surface water contamination due to
increased sediment load. Construct berms along strategic lines to
mitigate the visual impact of the
Groundwater operation.
Potential of seepage from hazardous
waste. Carry out the noisiest labours as quickly
as possible and during normal working
Air Quality hours (07:00 – 17:00) or according to
Reduction in air ambient quality. applicable legal criteria.
Page | 87
Noise Should a heritage resource be identified
Increase in the ambient noise level. all activities within a radius of at least
20m of the indicator should cease.
Page | 88
Visual
Disturbance to the sense of place.
Socio Economic
Additional employment opportunities
Blasting to loosen the deposit Geology Blasting must be controlled to prevent Possible
Disturbance of geological profile. spillage of explosions;
Fauna Blasting should be carried during normal
Displacement of indigenous faunal working hours (07:00 – 17:00) or
species. according to applicable legal criteria;
Surface water Apply blasting techniques to reduce
Potential contamination of surface shock waves;
water by nitrates released from Commit to provide adequate
explosions. compensation to affected households if
Groundwater required.
Reduction in groundwater yield. Dust suppression will be implemented
Air Quality on roads.
Increase in ‘fly rock’. Should a heritage resource be identified
Noise all activities within a radius of at least
Increase in the ambient noise level. 20m of the indicator should cease.
Page | 89
Visual
Disturbance to the sense of place.
Socio Economic
Damage to surrounding houses and
infrastructure.
Page | 90
Soils
Over areas of deep excavation (Open Pit
Loss of resource due to erosion. Mining) where the majority or all of the
soil profile is to be impacted) strip all
Vegetation usable soil (approx.750mm) and
Potential invasion of alien plants on stockpile as berms or low, terraced
disturbed areas. dumps.
Page | 91
The topsoil must be stockpiled
separately and used for the construction
of berms;
Page | 92
Maintain a vegetation layer on the
berms;
Page | 93
Use local workers as far as possible;
Visual
Disturbance to the sense of place.
Socio Economic
The local and regional road transport
network will suffer additional pressure
Page | 94
from the haulage trucks;
Health and safety.
Soils
Clean up any spills immediately and
Contamination of soils. disposed of the soil at a registered waste
site.
Surface water
Surface water contamination through Minimise dirty water area and contain
oil or diesel spills. dirty water;
Waste Management (Domestic as well as
hazardous wastes) including chemical Groundwater Prevent run-off of water with high
toilets. Potential of seepage from hazardous suspended solid content;
waste. Unlikely
Page | 95
Waste should be removed off-site by
specialist contractors for disposal;
Page | 96
Potential of seepage from hazardous Implement dust suppression spraying on
waste. access roads and the operational area;
Page | 97
The area will be shaped to emulate the
pre-mining topography and to allow free
drainage of storm water;
Page | 98
Implement weed eradication program.
Decommissioning Phase
Page | 99
Emphasis must be on ensuring that the
area is safe, stable and free draining;
Page | 100
Carry out the noisiest labours as quickly
Topography as possible and during normal working
Altering the established topography by hours (07:00 – 17:00) or according to
reshaping it to emulate pre-mining applicable legal criteria.
environment. Employ local works as far as possible.
Air quality Follow the equipment’s operation and
Increase in dust levels. maintenance procedures;
Noise Implement dust suppression during dry
Increase in the ambient noise level. and windy conditions.
Visual All vehicles must undergo periodic
Improvement of the visual aesthetic of maintenance and inspection;
Dismantling and removal of all the project site.
infrastructure in meeting the closure Socio Economic Appoint local contractors where possible.
objectives. Ripping, landscaping and Short term employment opportunities. Topsoil must be replaced over the area
re-vegetation of all disturbed areas. Topography to complement the growth medium Unlikely
Altering the established topography by (subsoil). Possible
Page | 101
Growth of invader species. operation and rehabilitated with the
addition of appropriate fertilizers, lime
Surface water and grass seed mixes.
Free drainage and natural surface
water patterns stabilisation. Air quality Implement dust suppression techniques
Increase in dust levels. during replacement of overburden and
topsoil and after replacement on bare
Visual surfaces.
Improvement of the visual aesthetic of
the project site.
Page | 102
Land Capability The pastures will be grazed and
Slow positive impact on areas maintained according to a formal pasture
requiring rehabilitation and management programme. The land
transforming mining to a state of should be protected from overgrazing.
Vegetation
Improvement in erosion control of
rehabilitated areas.
Animal life
Positive impact of livestock breeding
and naturally assisting the
transformation back to natural state.
Visual
Improvement of the visual aesthetic of
the project site.
Maintenance of all re-vegetated areas. Unlikely
Page | 103
Retrench and/or retraining of Socio Economic Implement training programs throughout
employees. Loss of jobs. the life of the mine in order to promote
long term sustainability of employees. Unlikely
Page | 104
Soils Implement weed eradication program
Recovery of topsoil that will ensure a biannually.
good growth medium.
Establish commercial species on site to
Land capability help the site to become stable.
Return to pre-mining state.
Land use
Return to agricultural/grazing land.
Vegetation
Pioneer species should return to
natural state.
Animal life
Recovery of area suitable for livestock
Weed management after closure. and wildlife. Possible
Page | 105
Soils Re-evaluate the nutrient status of the
Recovery of topsoil that will ensure a soils at regular intervals to determine the
good growth medium. possibility of needing additional fertilizer
applications.
Land capability
Return to pre-mining state. All domestic animals kept off the area
until the vegetation is self-sustaining.
Land use
Return to agricultural/grazing land. Newly seeded/planted areas must be
protected against compaction and
erosion.
Vegetation
Pioneer species should return to
natural state.
Repair any damage caused by erosion.
Socio Economic
The area will return to grazing
wilderness.
Visual
Page | 106
Improvement of the visual aesthetic of
the project site.
Page | 107
17. Full description of the process undertaken to identify, assess
and rank the impacts and risks the activity will impose on the
preferred site (In respect of the final site layout plan) through the
life of the activity.
(Including (i) a description of all environmental issues and risks that were identified during
the environmental impact assessment process and (ii) an assessment of the significance of
each issue and risk and an indication of the extent to which the issue and risk could be
avoided or addressed by the adoption of mitigation measures.)
The following steps were taken in order to identify the potential impacts of the proposed
mining activity:
• A detailed desktop study was undertaken to determine the biophysical and socio
economic characteristics of the application area and adjacent properties. These
reports were mainly used to determine the biophysical, socio economic and cultural
features on site along with other tools such as GIS, SANBI, Protected Area Maps and
Google earth.
• Site visits was conducted by trained consultants in order to identify specific
environmental features on site that require mitigation and/or avoidance. The site
visits was utilized to ensure that the information gathered as part of the desktop
study reflects the current status of the application area.
• Potential impacts and risks have been identified based on previous experience with
Lithium ore, Gold ore, Jade(gemstone), and Quartz(gemstone)/ mining operations.
During the site assessments, risks and impacts associated with the specific
environment was identified and is assessed in the report.
The methodology that will be used to rank the impacts assesses environmental and social
impacts by evaluating the consequence (spatial extent, duration, and severity of the impact)
and likelihood (probability and frequency of the impact occurring) of each impact and
providing a numerical score for each. The significance of each impact is determined by
ranking the total score of the consequence with the likelihood of each impact using a matrix.
The risk class for each impact is determined through a separate matrix ranking the severity
with the probability of the impact occurring. Refer to a full description of the impact
assessment methodology in Section 8.4 above.
Page | 99
Page | 100
18. Assessment of each identified potentially significant impact and risk
The table below describes the significance and risk of the potential impacts per activity.
Table 18: Impact Assessment
Construction Phase
Loss in agricultural potential. Medium Restrict the potential impacts as Low Low
follows:
Loss and degradation of vegetation.
Limit the size of the disturbed area as
Harm to Fauna. far as possible
Removal of vegetation and top soil decreases Activities must remain inside the
the recharge of aquifers. Agricultural land mining permit boundary at all times;
capability;
Vegetative Keep construction vehicles on site
growth; during construction;
Animal life;
Groundwater Maintain the best possible indigenous
Quantity. vegetation cover inside the mine
Preparation of footprint areas through the boundary;
clearing of vegetation in areas designated for
surface infrastructure. Prevent employees from moving
outside permitted areas.
Page | 100
Loss of soil resource (soils covered or Medium Minimize the potential impacts as Low Low
removed) due to sedimentation and erosion follows:
(wind and/or water). Over areas of deep excavation (Open
Pit Mining) where the majority or all of
Siltation of surface water due to erosion of the
exposed surfaces. soil profile is to be impacted) strip all
usable soil (approx.750mm) and
Reduction in air ambient quality. stockpile as berms or low, terraced
dumps.
Page | 101
the “ferricrete” separately from all
other materials.
Page | 102
Alteration of the natural topography. Medium Medium Medium
Avoid and minimize the potential
impacts as follows:
Compaction of soils.
Page | 103
The construction vehicles must
remain on site as far as possible
during the construction period.
Page | 104
Medium Minimize the potential impacts as Low Medium
Disturbance of geological profile. follows:
Loss of agricultural land, change of land use The location of the initial cut will be
from Agriculture to Mining. outside the 1:100 year flood line or
100m from a watercourse whichever
Potential risk of fracturing shallow aquifers is greatest.
and depletion of aquifer.
Blasting must be controlled to prevent
Dust form is likely to settle on vegetation and spillage of explosions;
other operational areas as dust
concentrations increase on the mine Blasting should be carried during
premises. normal working hours (07:00 – 17:00)
or according to applicable legal
Increase in ambient noise levels. criteria;
Page | 105
Compaction of soils. Medium Prevent the potential impacts as Low Low
follows: Define routes for the
Dust outfall on flora outside development circulation of heavy machinery and
footprint. vehicles and restrict machines’
movement to the necessary areas;
Reduction in air ambient quality.
Dust from the access road will be
Vegetative
growth; No bed and banks of any watercourse
Ecological must not be altered unless authorised
functioning; by DWS.
Dust pollution;
Health and Roads should have adequate drainage
Construction/Upgrading of the access road. Safety. to remove storm water as rapidly as
possible.
Loss of agricultural land, change of land use Low Avoid the potential impacts as Low Low
from Agriculture to Mining. follows:
Visual intrusion. Disturbance to the sense of Restrict the area of impact to that
place. which will be used for Lithium ore,
Gold ore, Jade(gemstone), and
Short term employment opportunities Quartz(gemstone)/-winning.
Agricultural
farmland; Use should be made of down-lighting
Sense of place; and directional lighting.
Establishment of additional infrastructure Local economy.
including the mobile screening plant. Employ local works as far as possible.
Page | 106
Remove any oil or diesel spills as soon
as it occurs and dispose of it at a
registered
Operational Phase
Page | 107
High Minimise the potential impacts as Medium High
follows:
Page | 108
Construct berms along strategic lines
Additional employment opportunities to mitigate the visual impact of the
operation.
Degradation of heritage resources.
Carry out the noisiest labours as
quickly as possible and during normal
working hours (07:00 – 17:00) or
according to applicable legal criteria.
Should a heritage resource be
identified all activities within a radius
of at least 20m of the indicator should
cease.
Disturbance of geological profile. Medium Minimise the potential impacts as Medium High
follows:
Displacement of indigenous faunal species.
Impact on geology and
Potential contamination of surface water by groundwater quantity is
nitrates released from explosions. unavoidable and cannot be
mitigated;
Page | 109
Should a heritage resource be
identified all activities within a radius
of at least 20m of the indicator should
cease.
Page | 110
Alteration of the natural topography. Low Prevent the potential impacts as Low Low
follows:
Sterilisation of footprint area through Stability of the
compaction. area; Soil Limit the height of the overburden
characteristics; and product stockpiles as far as
Surface water contamination due to increased Surface water possible;
sediment load. quality
Raw material and product stockpiling. Sense of place; Construct berms downslope of the
stockpile areas to trap sediment.
Page | 111
The berms must be grassed and
managed to prevent soil loss through
erosion and excessive dust;
Page | 112
Sterilisation of footprint area through High Prevent the potential impacts as Medium Medium
compaction and stockpiling. follows:
Dust outfall on flora outside the development Defining routes for the circulation of
footprint area. heavy machinery and vehicles;
Decrease in surface water quantity. Medium Minimise potential impacts as follows: Low Low
Page | 113
Contamination of soils. Medium Prevent potential impacts as follows: Medium Medium
Surface water contamination through oil or Clean up any spills immediately and
diesel spills. disposed of the soil at a registered
waste site.
Potential of seepage from hazardous waste.
Minimise dirty water area and contain
dirty water;
Page | 114
Sterilisation of footprint area through High Minimise potential impacts as follows: Medium Low
compaction.
Regular maintenance of the
Displacement of indigenous faunal species. operational vehicles and machinery to
avoid leaks and spillages;
Surface water contamination through oil or
diesel spills. Clean up any spills immediately and
disposed of the soil at a registered
Potential of seepage from hazardous waste. waste site.
Page | 115
Agricultural land the topsoil that is removed from the
capability. section that is opened for mining and
place it directly on the one that is
being rehabilitated.
Page | 116
Decommissioning Phase
Free drainage and natural surface water Medium Medium N/A. Positive
patterns stabilisation. (Positive) (Positive) impact
Enhance positive impacts as follows:
Page | 117
premining/construction land
capability rating.
Page | 118
Altering the established topography by Low Mitigate the potential impacts as Low Low
reshaping it to emulate pre-mining follows:
environment.
Carry out the noisiest labours as
Increase in dust levels. quickly as possible and during normal
working hours (07:00 – 17:00) or
Increase in the ambient noise level. according to applicable legal criteria.
Employ local works as far as possible.
Improvement of the visual aesthetic of the
project site. Follow the equipment’s operation and
maintenance procedures;
Short term employment opportunities.
Implement dust suppression during
dry and windy conditions.
Page | 119
Implement dust suppression
techniques during replacement of
overburden and topsoil and after
replacement on bare surfaces.
Page | 120
Slow positive impact on areas requiring Medium Medium N/A. Positive
rehabilitation and transforming mining to a (Positive) The pastures will be grazed and (Positive) impact.
state of post-mining, engineered agricultural maintained according to a formal
and wilderness areas. pasture management programme.
Protect the area against overgrazing.
Land use will change from mining back to
agriculture and wilderness areas. Implement weed eradication program.
Subsidence of mining area. Surface stability; High Manage potential impacts as follows: Medium Medium
Residual impact due to the removal of the Soil
Lithium ore, Gold ore, Jade(gemstone), and Loss of the soil resources. characteristics; Monitor vegetative growth.
Quartz(gemstone)/ layer during the Ponding on areas due to subsidence and lack Agricultural
operational phase. of compaction. potential;
Page | 121
Recovery of topsoil that will ensure a good Low (Positive) Minimize potential impacts as follows: Low N/A. Positive
growth medium. (Positive) impact.
Surface stability; Implement weed eradication program
Return to pre-mining state. Soil biannually.
characteristics;
Return to agricultural/grazing land. Agricultural Establish commercial species on site to
potential; help the site to become stable.
Pioneer species should return to natural state. Vegetative growth
and diversity;
Recovery of area suitable for livestock and Ecological
Weed management after closure. wildlife. functioning.
Recovery of topsoil that will ensure a good Medium Manage potential impacts as follows: Medium N/A. Positive
growth medium. (Positive) (Positive) impact.
Re-evaluate the nutrient status of the
Return to pre-mining state. soils at regular intervals to determine
the possibility of needing additional
Return to agricultural/grazing land. fertilizer applications.
Pioneer species should return to natural state. All domestic animals kept off the area
until the vegetation is self-sustaining.
Surface stability;
Recovery of area suitable for livestock and Soil
wildlife. Newly seeded/planted areas must be
characteristics;
protected against compaction and
Agricultural
Free drainage and natural surface water erosion.
potential;
patterns stabilisation;
Vegetative growth
and diversity;
The area will return to grazing wilderness. Repair any damage caused by erosion.
Monitoring of key environmental variables Ecological
(i.e. Improvement of the visual aesthetic of the functioning;
soils, vegetation, and surface water) in order project site. Surface water
to demonstrate stability of rehabilitated areas. quantity;
Sense of place.
Page | 122
19. Summary of specialist reports.
(This summary must be completed if any specialist reports informed the impact assessment and final site layout process and must be in
the following tabular form):-
RECOMMENDATIONS APPLICABLE
STUDIES UNDERTAKEN
SECTION
THAT HAVE BEEN
OF REPORT WHERE
INCLUDED IN THE
EIA SPECIALIST
REPORT RECOMMENDATIONS
HAVE BEEN
(Mark with an X
INCLUDED.
where applicable)
Page | 118
No specialist studies were undertaken, as this application is only for Lithium ore, Gold ore, Jade(gemstone), and
Quartz(gemstone) mining which is not considered to be a hazardous substance, and the site has already been disturbed
through post mining activities.
Page | 119
20. Environmental impact statement
20.3 DECOMMISSIONING
The decommissioning phase will be of short duration because most of the infrastructure on
site will be temporary structures. The main activities during the decommissioning phase will
Page | 120
involve the backfilling of the final pit, ripping of the compacted areas and spreading of the
topsoil over the disturbed area. The impacts during the decommissioning phase will mainly
be positive because the aim of this phase is to rehabilitate the environment so that it can
again be used for agricultural activities after mining. The success of the decommissioning
phase will mainly depend on how the topsoil was managed during the construction and
operational phases of the mine.
Page | 121
21. Summary of the positive and negative
impacts and risks of the proposed activity and identified
alternatives;
Any mining operation will have negative impacts on the biophysical aspects of the
environment. However due to the non-hazardous nature and small scale of the
proposed Lithium ore, Gold ore, Jade(gemstone), and Quartz(gemstone)/ mine these
impacts are much less significant compared to a large coal mine for instance? The
following negative impacts have been identified during the environmental impact
assessment:
• Ground and surface water pollution from hydrocarbon spills or diesel spills
during the construction and operational phase;
• Potential decrease in the groundwater quantity if an aquifer gets breached
during blasting;
• Surface water contamination from increased sediment load;
• Soil pollution resulting from hydrocarbon spills;
• Loss of soil resource due to compaction, excavation and erosion.
• Increase dust levels in and around the application area and access road will
have a cumulative impact on the ambient air quality of the surrounding area.
In terms of positive impacts the proposed Lithium ore, Gold ore, Jade(gemstone),
and Quartz(gemstone)/ mining operation will contribute to the local economy but
again due to the small size and short life of mine the impacts will not be felt by a
large number of people. The following positive impacts have been identified:
• Additional employment opportunities for local people;
• The supply of Lithium ore, Gold ore, Jade(gemstone), and Quartz(gemstone)/
will assist the ongoing development of the socio economic structure in the
area.
In terms of risks the proposed Lithium ore, Gold ore, Jade(gemstone), and
Quartz(gemstone)/ mining operation is classified as a Category C Mine but it does
still pose some risks to the biophysical and socio economic environment. These have
been listed below:
Page | 122
• Cracking and or subsidence to surface from areas of unconsolidated
rehabilitation will decrease the agricultural land capability and could result in
the change of land use;
• Breaching of an aquifer during blasting and excavation of Lithium ore, Gold
ore, Jade(gemstone), and Quartz(gemstone)/ will result in the depletion of
groundwater resources in and around the application area; Surface or
groundwater pollution from hazardous waste spillages.
The following goals and objectives have been set as targets for the effective
mitigation of impacts caused by the Lithium ore, Gold ore, Jade(gemstone), and
Quartz(gemstone)-winning operation. These goals and objectives will be measured
through the monitoring programme.
• The entire operational area will be managed as a disturbed area for the
duration of the project.
• The viability of the soils needs to be maintained for future rehabilitation
purposes. The goal is to prevent erosion and loss of top soil in order to ensure
effective rehabilitation. The objective is to separate growth medium to
facilitate the re-establishment of vegetation post closure.
• Minimise the impact of the change in land use from agriculture to Lithium ore,
Gold ore, Jade(gemstone), and Quartz(gemstone)/ winning by ensuring that an
acceptable post closure land capability is achieved.
• Minimise the proliferation of weeds and alien invaders of which the invasion
of wattle is the biggest threat. The objective is to control these species
throughout the life of mine so that there is no need for a prolonged control of
weeds during the maintenance period.
• Do not disturb the habitat outside of the Lithium ore, Gold ore,
Jade(gemstone), and Quartz(gemstone)/-winning area.
• Minimise the amount of water used during the mining operation and minimise
negative impacts on rain water runoff by preventing pooling of water.
• Surface water quality will be maintained by limiting contamination through
oils, greases etc. This is achieved by collecting and maintaining the used
grease and oil in drums which are collected by registered used oil contractors.
• Water from off site will be brought onto site to be used for domestic purposes.
• Minimise dust generation such that this will not cause a visual disturbance on
the adjacent tar road nor an unacceptable air quality. The objective is to
Page | 123
maintain an acceptable dust level. (Total suppression of dust during
excavation, screening and loading will not be possible).
• Work in such a way with the topsoil stockpiles so as to create the impression
of an ordered, visually pleasing pit, and to construct berms along strategic
lines to mitigate the visual impact of the operation.
• No mitigation of operational noise will be undertaken due to the absence of
neighbours within the zone of influence for noise (except for vehicles passing
along the tar road).
• Issues raised by the IAP’s will be dealt with as they arise.
Page | 124
structure in the area and the potential biophysical impacts of the proposed operation
can be managed to a large extend. Due to the non-hazardous nature of the Lithium
ore, Gold ore, Jade(gemstone), and Quartz(gemstone) mining operation and the
already disturbed condition of the application area (due to agricultural activities)
there are no potential impacts with a high significance rating post mitigation. Based
on the above reasoning it is the opinion of the EAP that the activity may be authorised.
According to the MPRDA Section 27 a mining permit is valid for two years and may
be renewed for three periods which may not exceed one year. The Environmental
Authorisation should therefore allow for the five years of mining taking into account
the potential renewal periods.
The total amount required to manage and rehabilitate the environment in respect of
rehabilitation is R 307 901,63
No. Limited water is required for operational purposes because it is a dry operation.
Water usage will be on average 308m3 per month with a maximum 616m3. The water
will be sourced from the contract miner. The water sourced can be considered clean
water based on the results provided therefore a Water Use License will not be required
in terms of Section 21 (g) to use this water for dust suppression purposes.
Page | 125
28. EMERGENCY PREPAREDNESS AND RESPONSE
The company shall respond to actual emergency situations and prevent or mitigate
associated adverse SHE consequences. In planning its emergency response, the
company shall take account of the needs of relevant interested parties, e.g. emergency
services and neighbours.
The company shall also periodically test its procedure(s) to respond to emergency
situations, where practicable, involving relevant interested parties as appropriate. The
company shall periodically review and, where necessary, revise its emergency
preparedness and response procedure(s), in particular, after periodical testing and after
the occurrence of emergency situations.
What must the industry do to properly meet the threats presented by unplanned,
emergency incidents? What processes, equipment, emergency teams and materials
must be available? We need to focus on practical preparation methods, and some
common codes and regulatory requirements. We will refer to codes and requirements
that will apply to most of our readers, realising those jurisdictional requirements are
so varied. There are a few basic requirements of an emergency plan that apply to
virtually all types of emergencies. These requirements are shown in Figure A
Emergency planning requirements fall into three distinct categories; Pre-Incident
Planning, Incident Response and Post-Incident Action.
Pre-Incident Planning
Identify Emergency Scenarios – This activity requires a group effort to ensure all
possible emergencies are considered. Engineers, environmentalists, operators,
maintenance, office staff, managers and janitors, all have a role to play in this process.
Each member of the group brings a unique perspective to bear on the potential
Page | 126
emergencies that occur at the plant. Using a questionnaire that stimulates
consideration of what might happen, can make identifying these scenarios easier.
General requirement
Page | 127
The company should assess the potential for emergency situations that impact on
Safety Health and the Environment (SHE) and develop a procedure(s) for an effective
response(s). This may be a stand-alone procedure(s) or be combined with other
emergency response procedure(s). The company should periodically test its emergency
preparedness and seek to improve the effectiveness of its response activities and
procedure(s).
NOTE Where the procedure is combined with other emergency response procedure(s),
the company needs to ensure that it addresses all potential SHE impacts and should
not presume that the procedures relating to fire safety, or environmental emergencies,
etc., will be sufficient.
WASTE MINIMISATION
Page | 128
SPILLAGE AND RELEASE CONTROL MEASURES
Overfills, vehicle accidents, and tank and piping failures can lead to releases during
waste storage and handling. Mitigation measures, including physical protection, overfill
protection, tank integrity, and secondary containment (banded areas) for tanks are
some of the general mitigation measures. Recommended measures include:
Spill Kits and hazmat clean-up materials should always be available on site;
Conduct regular training and exercises for site staff regarding emergency
procedures;
Provide sufficient fire extinguisher to control accidental fires
In line with the Environmental management regulations and good international practice
measures to adequately mitigate release of emissions and escape of pollutants into the
environment, Surface waste, groundwater, soil and air must be put in place and
implemented. Such recommended measures include:
Although it is not anticipated that this proposed mining will have significant potential
for air emission release, the following measures should be considered and assessed:
1. Appropriate engineering controls (Best Available Technologies) must be in place;
2. Complaints of potential air quality risks and concerns must be recorded and
investigated.
Page | 129
WATER POLLUTION CONTROL MEASURES
Although it is not anticipated that this proposed mining will not have significant
potential for water pollution risks, the following measures should be considered and
assessed for possible implementation:
Although it is not anticipated that this mining will have significant potential for soil
contamination risks, the following measures should be considered and assessed:
Training
There are a number of regulations, guidelines, standards which requires that the
employer develop and implement a written emergency response plan to handle possible
emergencies before performing hazardous waste site operations. The permit Holder for
the waste disposal site in this case, the company Health and Safety officer must, develop
an emergency preparedness and response or action plan complying to ensure the safe
evacuation of personnel.
The Emergency Preparedness and Response Plan must be commensurate with the risks
of the mining and at the minimum include the following elements:
Administration
Pre-emergency planning,
Emergency recognition and prevention,
Emergency medical and first-aid treatment,
Methods or procedures for alerting on-site employees,
Safe distances and places of refuge,
Site security and control,
Personal protective and emergency equipment,
Evacuation routes and procedures. and Training and Awareness
Page | 131
In addition to the above requirements, the plan must include site topography, layout,
prevailing weather conditions, and procedures for reporting incidents to local
authorities, the South Africa Police Services (SAPS), and regulating agent i.e. DEA and
Department of Labour etc.
The procedures must be compatible with and integrated into the operational
management plan of the site. The plan requirements also must be rehearsed regularly,
reviewed periodically, and amended, as necessary, to keep them current with new or
changing site conditions or information.
Policy
The emergency response plan should be implemented in line with the company’s Safety,
Health and Environment Policy.
Distribution
This Plan and procedures contemplated in this plan must be distributed to all personnel
working on the site.
Definitions
The procedures must be compatible with and integrated into the operational
management plan of the site. The plan requirements also must be rehearsed regularly,
reviewed periodically, and amended, as necessary, to keep them current with new or
changing site conditions or information.
Organogram
The organogram described in the EMP shall apply to the emergency response plan.
Personnel roles and responsibilities
The Roles and Responsibilities described in the EMP shall apply to the emergency
response plan.
Communication procedures
The communication lines established in the EMP shall apply to the emergency response
plan.
First-Aid Calls
Page | 132
The company’s Safety Health and Environment officers must ascertain that all
emergency contact numbers (first aid officers, ambulances, fire brigade, police,
hospital etc) are conveniently posted at several site notice boards in order to assist in
the event of an emergency.
Training and Awareness
Facilities: Will be either left for future users or sold for removal. Soil will be
decontaminated and the site rehabilitated. This will be done on a case by case
basis in consultation with stakeholders and the area will be restored to as
much of the natural condition as it was before the construction phase ;
Ensure that all areas are stable and there is no risk of erosion;
Prevent the alien plant invasion on site until the area is in a stable condition;
Page | 133
Ensure that no degradation in land capability remains; and
The Landowner, Interested and Affected Parties have been consulted on the closure
objectives and rehabilitation during the consultation period.
Page | 134
33. Explain why it can be confirmed that the rehabilitation plan
is compatible with the closure objectives.
The closure plan will assist company to achieve the following objectives:
Ensure shareholder value is preserved;
Ensure that stakeholders’ needs, concerns and aspirations are taken into
account when considering closure;
Comply with relevant or applicable legislative requirements;
Limit or mitigate adverse environmental effects to an extent that it is
acceptable by all parties;
Ensure land is rehabilitated to, as far as is practicable, it’s natural state, or to
a predetermined and agreed standard or land use which conforms to the
concept of sustainable development.
Page | 135
are no leaks which would result in loss of water and that they are functioning
optimally.
The groundwater flow dynamics will be calibrated every two years with
updated monitoring data. This will assist with management and long term risk
prediction and management.
The environmentalist/consultant/mine manager will be responsible for
inspection of sites and keeping records of all monitoring activities.
All incidences and issues will be recorded, as will the actions taken to address
issues.
Page | 136
38. Environmental Awareness Plan
38.1 Manner in which the applicant intends to inform his or her employees of any environmental risk which
may result from their work.
The successful implementation of the EMP is dependent on training and awareness of all
personnel working on the drilling site. The environmental awareness plan aims at:
Promoting general environmental awareness amongst all employees;
Informing all personnel of environmental policies, procedures and programmes
applicable to the mining activities;
Providing general training on the implementation of environmental management
actions; and,
Providing job specific environmental training to ensure the protection of the
environment.
38.2 OBJECTIVES
Inform employees and contractors of any environmental risks which may result from
their work, and
Inform employees and contractors of the manner in which the identified possible risks
must be dealt with in order to prevent degradation of the environment.
In general, the purpose of implementing an Environmental Awareness Plan is to
optimize the awareness of those partaking in the mining and related activities which
have the potential to impact negatively on the environment (e.g. spillages form dirty
water dams), and in doing so, promote the global goal of sustainable development.
Page | 136
38.3 RESPONSIBILITY FOR IMPLEMENTING THE EMP
The environmental management plan will ensure environmental commitments are adhered to
and will be used to evaluate the effectiveness of mitigation measures.
Ensure that project- related activities are in compliance with the Environmental
Management Programme, contingency plans, tender specifications and approval
conditions, contract provisions or specifications during mining works,
Be responsible for all environmental field work, programme, and monitoring,
In case of an environmental emergency, a site supervisor must report it to an ECO and
then a decision will be made to not have the authority to stop a project.
Ensure that any mitigation and environmental management measures required to
protect the environment during work stoppage follows these environmental
regulations,
Be responsible for addressing on-site environmental issues as they emerge.
Record instance of non-compliance, contingency response and work stoppage
relating to environmental issues.
Maintain records of all communication
Page | 137
suppliers have to give assurance that they understand the Environmental Management
Programme and that they undertake to comply with its conditions.
The workforce, contractors are not informed about the environment and need to be informed
of key elements that the EMP strives to manage:
- Description of the environment and sensitive features;
- Explain simple key concepts;
- Introduce the environment of proposed works area and adequate management
Thereof;
- Provide examples of environmental degradation and pollution sources
- Explain the roles and responsibilities of the contractors, employees in managing the
environment;
- Devise basic principles to manage the environment
- Indicate laws applicable to the management and protection of the environment;
- Indicate day to day preventative measures to assist elimination of pollution and
degradation (presentation is better than cure)
All senior and supervisory staff members shall familiarize themselves with the full contents of
the EMP. They shall understand and know how to implement the control measures of the EMP
and shall be able to assist other staff members in matters relating to the EMP. Senior
and Supervisory personnel are to be identified and presented to the workforce, contractors
during training.
The applicant will as soon as possible, but within 48 hours, report to the Environmental
Consultant on:
Difficulties encountered with carrying out the EMP control measures
Areas of non-compliance, or amendments that may be required to any of the
EMP control measures
Within 24 hours of becoming aware of any environmentally related problems (such as spillages
and an environmental complaint or claim; an incident of non-compliant the
Page | 138
environmentally related incident), the project manager/geologist should be notified and
the following documented:
Nature and cause of the problem
Parties responsible for causing the problem
Immediate actions taken to stop/reduce/contain the causes of the problem. It should
be emphasized that the ECO/geologist/project manager shall be given the
responsibility to inventory all the environmental aspects of the mining activities.
These shall include the following:
Documentation for specific environment-related activities, such as lists of spill
response, incidence reporting.
Ensure that project-related activities are in compliance with contingency plans,
regulatory permits and approval conditions, contract provision or specifications.
Be responsible for providing environmental information for staff, and for making sure
that all personnel and contractors understand the terms and conditions in all
regulatory permits and approvals and the environmental management programme
and also incident contingency plans before commencement of the work.
Be responsible for addressing on-site environmental issues, as they emerge
Maintain required records for environmental monitoring programs.
Maintain a photographic record of prior to, and during, construction activities
that have the potential to adversely affect resources of other environmental features.
38.8 CONCLUSION
Please refer to the impact assessment above (Also attached to this report).
Page | 139
40. Specific information required by the competent authority
(Among others, confirm that the financial provision will be reviewed annually).
Specific information requirements have not been stated by the competent authority to date and
the financial provision will be reviewed annually.
Page | 140
41. UNDERTAKING
P.M
Name of company
Date:
18/08/2022
______________________________
Page | 141
Page | 142
42. APPENDIXES
Page | 143
Page | 144