CHAPTER 4 Management Notes
CHAPTER 4 Management Notes
PERT is a Program Evaluation and Review Network diagram defined and focused
Technique attention on the job to be accomplished.
CPM is the Critical Path Method. Schedule derives the earliest and the latest
times for their start and finish.
-The concept was formulated by the research Although PERT and CPM were developed
team independently, they have a great deal in
common.
-The use of PERT in this large scale project was
proven successful in shortening the length of PERT originally stressed probabilistic activity
the project completion time. time estimate because the field in which it was
developed was typified by high uncertainty. In
CPM is the Critical Path Method. contrast, CPM originally made no provisions for
-Began in 1956 variable time estimates.
-Developed by J.E. Kelly of the Remington Rand Thus, comments and procedures
Corp, and M.R. Walker of Du Pont described will apply to both PERT and
CPM project analysis.
-Advanced scheduling and cost control
methods.
PERT/CPM is a control tool for defining the On January 27, 1968, President Ferdinand E.
parts of construction job and then putting them Marcos issued Memorandum Circular No. 153
together in a network form. It serves as an aid which provides that:
to the construction manager but it does not
make decision for him nor does it guarantor "In order that the performance discipline on the
good management PERT/CPM only serves the field could be controlled and easy reporting
project manager to see the whole picture of the system could be made to facilitate the
entire job. monitoring, evaluation, inspection completion
of infrastructure pro- jects, all heads of
PERT/CPM encourages periodic re-evaluation departments and chief of bureaus and offices
and providing an accurate measure of progress. concerned are hereby required to change the
old system of preparing the work programs of
Thus, a person in charge of each work said projects from the Gantt Chart (Bar Type) to
and the project manager know what is the PERT/CPM network. Strict herewith is
supposed to happen and when it is enjoined."
supposed to happen.
Summary: Heads of
departments and chiefs of
bureaus and offices must
4-2 PERT/CPM Project change old Gantt Chart system
Requirements to PERT/CPM network.
SCHEDULING
Planning Phase
4. Resource estimates
PERT/CPM – it gives the management a reliable 5. Trade indicators (responsibility) for activity
system identifying job problems within days grouping.
instead of months.
Schedule Phase
The PERT/CPM diagram should be updated
periodically to account for:
1. The schedule of activities
1. Time discrepancies
a. The Critical Activities
2. Deliveries
b. The Earliest Start date
3. Weather
c. The Earliest Finish date
4. Change orders
d. The Latest Start date
5. Unexpected events or conditions.
d. The Latest Finish date
CONTROLLING AND MONITORING
e. The Float
1. The contractor is supplied with time status
reports 2. A Bar Chart or a Time Scaled Network
3. A Resource Analysis
4. A Cash Requirement
2. Revised schedules
1. Unbalanced organization