CHAPTER 4 Management Report
CHAPTER 4 Management Report
Pasto
4-1 Introduction
PERT and CPM were developed independently in the later part of 1950's.
PERT and CPM are networks, a technique used for planning and coordinating large scale
projects.
- The use of PERT began in 1958 through joint efforts to speed up the Polaris Missile project.
-The concept was formulated by the research team and is then called Program Evaluation and Review
Technique, which is simply called PERT.
-The use of PERT in this large scale project was proven successful in shortening the length of the project
completion time.
-Began in 1956
-Developed by J.E. Kelly of the Remington Rand Corp, and M.R. Walker of Du Pont
CPM was designed as a tool for planning, scheduling, and control of construction work.
PERT was developed as a result of looking for an improved method of planning and evaluating progress
of a large-scale research and development program.
Although PERT and CPM were developed independently, they have a great deal in common.
For practical purposes, the two techniques are the same. Thus, comments and procedures described will
apply to both PERT and CPM project analysis.
A person in charge of each work and the project manager know what is supposed to happen and when it
is supposed to happen.
Fc
4-2 PERT/CPM Project Requirements
In all major projects of the government, PERT and CPM network are a mandatory requirement.
Under Presidential Decree (PD) 1594, Prescribing Policies, Guidelines, Rules and Regulations for
government infrastructure contracts
- Estimates of work items, quantities, costs and PERT/CPM analysis of project activities.
On January 27, 1968, President Ferdinand E. Marcos issued Memorandum Circular No. 153
- Heads of departments and chiefs of bureaus and offices must change old Gantt Chart system to
PERT/CPM network.
On June 19, 1968, the Executive Committee for Infrastructure Program implemented the Presidential
Order in a letter to all implementing agencies to wit:
"Your attention is invited to a Presidential Order requiring the preparation of a PERT/CPM diagram for
every major project prior to their actual construction."
Section 6 of R.A 5979 requires the application of PERT/CPM technique to all projects with an estimated
cost of P100,000 or more.
Aprilyt
With the use of PERT/CPM, the project manager can easily obtain the following informations:
3. Determine which activities are the most critical to timely project completion.
4. Determine how long any activity can be delayed without lengthening the project.
1. Planning
2. Scheduling
3. Control-Monitor
Planning
Planning is defined as determining the relationship between the work operation and the sequence in
which they are to be performed.
Tidoso
Each work operation can be performed in different ways at different costs and in different time
duration.
However, there is a danger that shortening a single operation may only increase project cost but may
not shortened construction time considering that other operations have not been shortened.
3. It gives a time leeway or float available for each of the non-critical work operations
9. Any claim if any, for additional payment will be understood both by the owner and the contractor.
10. In case of serious delay, the network can be revised at that stage
Christian
In any project construction undertakings, planning is the most important consideration which includes:
1. Gathering of all the necessary input data to make the PERT/CPM work.
3. The contractor can seek assistance for the accomplishment of his work particularly the gathering of
data
4. The contractor has the complete perception, experiences, resources, and interest in getting the
project done
6. If the contractor wants an effective approach and use of the construction management, he must do it
himself.
7. By performing the work personally, one obtains intimate first hand knowledge
SCHEDULING
Scheduling is defined as the process of translating the arrow diagram into timetable of calendar days.
The PERT/CPM schedule shows the relationships between the operations and the leeway limitations.
Job control through the use of PERT/CPM gives the management a reliable system identifying job
problems within days instead of months.
Kuya Jaren
The PERT/CPM diagram should be updated periodically to account for:
1. Time discrepancies
2. Deliveries
3. Weather
4. Change orders
Life
Planning Phase
3. Cost estimates of the activities for monitoring cost, cash Bow requirements
4. Resource estimates
Schedule Phase
3. A Resource Analysis
4. A Cash Requirement
Kuya Say
The Control Monitor Phase uses actual data which includes:
2. Revised schedules
1. Unbalanced organization