Division 13 Specification
Division 13 Specification
The information in this section on general discussion is crucial for the installation of successful
very specific end-use in building projects. The problems stem from the underlying structure of the
project, along with the process of production and installation, and the long-term success of those
project components. This section projects tend to require professional insight and construction
expertise, making them more expensive to design and build than standard projects.
The contractor has to verify that he has inspected and examined the proposed project
site, its surroundings, and any existing infrastructure and facilities related to the
execution of the work at his own expense, and that he has obtained all of the information
deemed necessary for the proper execution of the work covered by these terms of
reference.
Contractor must ensure that all construction, restoration of impacted areas, testing, and
commissioning work is completed swiftly and effectively.
The contractor must produce comprehensive reports, including technical analyses, maps,
and details about the site's current state and suggested changes.
The contractor must take into account the academic calendar and crucial dates.
dates and occasions in order to synchronize his work schedule with the school's academic
calendar in order to avoid unnecessary disruption of school activities due to construction
activities such as water and power supply closures and non-use of existing roadways
All works conceived and built must be assured to integrate smoothly into the overall
system general design requirements.
B. SCOPE OF WORK
1. Prefabricated insulated rooms with wall and ceiling panels. Floor panels where
scheduled.
2. Doors, frames and hardware.
3. Controls and instrumentation.
4. Electric outlets and lighting.
The Contractor shall be responsible for confirming the total number and sizes of units.
Furnish and install at the locations shown in the architectural plan.
A. General
1. Design and construct rooms using modular panel sections to allow for future
expansion and ease in disassembling for relocation.
2. Units shall include control circuits, temperature conditioning and circulation systems,
ductwork and mechanical and electrical equipment to meet performance criteria
specified.
1. Design system to meet specified uniformity and control tolerances and to rapidly
adjust to internal temperature loads.
2. Uniformity is defined as measured variation in temperature between any two points in
work space.
3. Temperature control is defined as temperature variance above or below setpoint, as
measured at control sensor over a 24-hour period.
1. System shall provide accurate control of relative humidity over specified range.
C. Prevent Condensation
QUALIFICATIONS
REGULATORY REQUIREMENTS
A. Conform to ICC IBC for flame spread 75 and smoke developed rating of 450 for
insulation.
B. Hardware shall comply with barrier free design requirements.
C. Design structural roof system under direct supervision of a registered Professional
Structural Engineer.
D. Operating Equipment: Conform to UL requirements.
E. Control Panel: Comply with NFPA 70 and NFPA 79
MAINTENANCE SERVICE
A. Provide 12 Months Maintenance Service
PRODUCTS
MANUFACTURERS
A. Have more than 10 years’ experience manufacturing cold rooms for scientific and clean
storage.
B. Have a good reputation for prompt service in the National Capital Region.
C. Insulation
D. Door Construction
E. Ceiling Access
F. Closure Trim
1. Same material and finish as exterior panels, between room units and
building walls.
F. Access Ports
1. Field cut and sealed; size as required for room services.
2. Coordinate with other trades for size, shape, and location.
G. Ramps
FINISHES
A. Exterior Surfaces
1. Exposed Wall Surfaces - All rooms shall have 0.794 mm (22 gauge)
smooth galvanized steel or Galvaneal, factory finished with baked white
acrylic enamel.
2. Concealed Wall Surfaces - Embossed aluminum, 0.8 mm (0.032 inch)
thick, mill finish.
B. Interior Surfaces
EXECUTION
INSTALLATION
TESTS
A. Perform the tests for each controlled environment room and provide everything
required. Notify the Contracting Officer 10 days before performing the tests.
B. Tests shall be performed in the presence of a manufacturer's representative.
C. Start-Up and Operational Tests
1. Start up and initially operate the systems upon completion of the
installation of the equipment and refrigerant piping. Adjust the safety and
automatic controls to place them in operation and sequence. Record
manufacturer's recommended readings hourly. Operational tests shall
cover a period of not less than 24 hours.
D. Performance Tests
1. Upon completion of the operational tests the systems shall be
performance tested. Test duration shall not be less than 8 hours.
2. Tests shall include the following information to be in the report with
conclusions regarding the adequacy of the systems:
a. Time, dates and duration of tests.
b. Inside dry-bulb and wet-bulb temperatures maintained in each room
during the tests employing recording instruments calibrated before
the tests.
c. Outside dry-bulb and wet-bulb temperatures obtained from recording
instruments calibrated and checked hourly with a sling psychrometer.
d. Evaporator and condenser entering and leaving temperatures taken
hourly with the compressors in operation.
e. The make, model and capacity of each evaporator and condensing
unit.
f. Voltmeter and ammeter readings for condensing units and
evaporators.
OPERATING INSTRUCTIONS
A. Provide a framed and glassed control chart indicating a layout of the refrigeration
systems, including piping, valves, wiring, and control mechanisms.
B. Install control chart where directed. Submit printed instructions covering the
maintenance and operation of refrigeration equipment.
C. Tag shutoff valves in accordance with the printed instructions.
D. Provide special tools as necessary for repair and maintenance of the equipment.
CLEANING
A. Upon completion of the work and at a time designated by the Contracting Officer,
provide for the instruction of Owner’s personnel in the operation and
maintenance of each refrigeration system.
B. The period of instruction shall be for not less than one 8-hour working day.