2023 Infrastructure Investment Programme
2023 Infrastructure Investment Programme
DISTRIBUTED BY VERITAS
e-mail: [email protected]; website: www.veritaszim.net
Veritas makes every effort to ensure the provision of reliable information,
but cannot take legal responsibility for information supplied.
Contents
INTRODUCTION ...............................................................................................9
2022 Infrastructure Investment Summit........................................... 11
PROGRESS ON 2022 INFRASTRUCTURE DELIVERY.................................14
2023 INFRASTRUCTURE INVESTMENT PLAN............................................17
Value For Money and Public Sector Investment Programme........ 18
2023 Infrastructure Funding Mix.......................................................19
DIGITAL ECONOMY........................................................................................20
Digital Infrastructure..........................................................................22
E-Government.....................................................................................23
Mining Cadastral System...................................................................25
Digital Entrepreneurship....................................................................26
Zim-Digital Migration Project.............................................................26
Integrated Electronic Case Management System ..........................27
Development Projects Management Information Systems............ 28
ENERGY..........................................................................................................28
Independent Power Producers .........................................................31
Rural Electrification Programme......................................................31
TRANSPORT...................................................................................................33
Roads ..................................................................................................34
Beitbridge–Masvingo–Harare Road.....................................................36
Mbudzi Traffic Interchange...................................................................37
Bridges and Other Roads.....................................................................39
Rural Feeder Roads.............................................................................40
Emergency Roads Rehabilitation Programme II.................................. 41
Aviation...............................................................................................47
Rail ......................................................................................................48
Border Posts.......................................................................................49
WATER AND SANITATION..............................................................................54
Dam Construction.............................................................................. 55
Borehole Drilling................................................................................. 60
3
Rural WASH......................................................................................... 61
Rural Development Programme........................................................61
Water Supply Schemes for Small Towns and Growth Points........ 62
HEALTH AND WELL-BEING...........................................................................64
Central and Quinary Hospitals..........................................................68
Provincial Hospitals...........................................................................69
District Hospitals and Mission Hospitals.........................................70
Primary Health Care...........................................................................71
Ambulances & Medical Equipment...................................................71
HUMAN CAPITAL DEVEPOPMENT AND WELL-BEING...............................72
Basic Education..................................................................................72
Tertiary Education..............................................................................73
High Performance Computing Center Phase II................................ 79
Modernisation of Public Service Academy Institutions..................80
HOUSING DELIVERY......................................................................................81
Residential Accommodation.............................................................82
Institutional Housing .........................................................................85
Civil Service Housing Fund...............................................................91
FOOD AND NUTRITION .................................................................................92
Irrigation Development......................................................................92
Animal Disease Prevention and Control..........................................98
CLIMATE CHANGE MAINSTREAMING.........................................................99
DISASTER RISK MANAGEMENT.................................................................102
DEVOLUTION................................................................................................103
YOUTH AND WOMEN EMPOWERMENT..................................................... 116
Women Empowerment..................................................................... 116
Youth Empowerment........................................................................ 119
PUBLIC INVESTMENT MANAGEMENT....................................................... 119
Project Preparation Development Fund.........................................121
ANNEXURES.................................................................................................123
4
FOREWORD
In addition to policy reforms meant to create the right conditions for private
sector participation in public infrastructure provision, Treasury will deepen policy
reforms as part of the fiscal consolidation measures towards Public Investment
Management that addresses current bottlenecks in the infrastructure sector.
Such reforms will include the development of a strong conceptual framework for
mainstreaming climate change into the different phases of infrastructure projects,
addressing weaknesses in procurement processes, contract management,
value for money and other project delivery challenges.
5
Whilst investments in new capacity remains critical in order to meet increasing
demand for services, maintaining current assets will also ensure public
infrastructure assets are more durable, economical and sustainable over time.
I therefore commend the 2023 Infrastructure Investment Programme to public
entities, private sector, civil society and cooperating partners as well as other
stakeholders as it provides a clear link between the NDS1 goals and objectives
and the Budget.
November 2022
6
PREFACE
Noting that public procurement constitutes a large share of the economy, how
and where Government procures goods and services impacts the behaviour of
economic agents and promotes responsible business practices.
In this regard, enforcing the value for money principle on all transactions will
result in Government getting fair value prices for all goods and services procured.
7
Government will, therefore, monitor every step of the project life cycle, from
appraisal, prioritisation and selection, financing, procurement, construction as
well as operations and maintenance, to ensure that due process is followed and
costs are justifiable and sustainable and where necessary, remedial action will
be taken.
G. T. Guvamatanga
SECRETARY FOR FINANCE AND ECONOMIC DEVELOPMENT
November 2022
8
INTRODUCTION
3. For the economy to integrate with other economies both regional and
international, appropriate infrastructure in the form of roads, aviation,
railways, information and technology and power, as well as their efficient
operation, is required.
with large cost overruns and long delays in construction. Even as the
9
projects are completed, they have low returns to communities after
10
• Implementation of cost reflective but economically sustainable tariffs;
8. The inaugural Infrastructure Summit that was held in Victoria Falls during
construction industry.
11
as critical in crowding in additional private sector funding to address the
11. The following were some of the recommendations from the Summit:-
12
• The need for cost reflective tariffs and measures to close revenue
infrastructure development.
13. The infrastructure architecture will be improved with each project being
assets.
13
16. Enforcement of best practices in costing and contract management of
where they deliver better value for money in order to crowd in additional
funding for projects.
18. Out of the 2022 Revised Capital Budget of ZWL$507.3 billion which
14
19. The table below provides a summary of the deployment of the resources
Devolution 16,491,454,625
15
• Harare-Masvingo-Beitbridge Road Upgrading project that has seen
expected to come on stream before year end and Unit 8 during the
69% with the entire dam project now targeted for completion during
Programme;
of residence;
16
21. Notable developments have also been realised on the construction and
24. Resource outlays under the 2023 National Infrastructure Investment Plan
will prioritise on-going and stalled projects over new projects in order
to ensure sustainability of our interventions under the difficult global
and domestic financial conditions. Priority will also be accorded to the
25. Costs for projects and allocations thereof during 2023 will be based
on consideration of technical engineering designs, prevailing market
17
26. Due consideration has also been aligned to the technical capacity of
that should enable project managers to plan and execute the projects.
develop a robust monitoring and evaluation plan for each of the targeted
projects under their purview that allows for multi stakeholder dialogue and
18
on costings of projects, programmes including equipment procurement
with the objective to ensure value for money in all public procurement.
31. The thrust by Government is clear that all fiscal outlays on projects
country.
32. In this regard, Government will monitor every step of the project life
cycle for all major infrastructure projects, to ensure that due process is
34. In order to achieve the set targets and ensure that citizens benefit
35. The Overall support towards the 2023 Development Budget including
19
• Tax revenues ZW$490.8 billion;
36. The table below shows the distribution of the infrastructure outlay
Housing and
49,931,976,050 49,931,976,050
Social Amenities
Primary and
Secondary 4,180,000,000 4,180,000,000
Education
Water and
30,365,402,000 30,365,402,000
Sanitation
DIGITAL ECONOMY
37. The ICT sector is the bedrock in the establishment of a digital economy,
20
38. In our context, paramount is the need to bridge the digital gap between
the rural communities and the urban communities, necessitating the need
39. Government has, during the course of the year, achieved the following
Centres;
40. To fully benefit from the rapid growth in ICTs and unlock the digital
21
infrastructure, digital skills, financial services and entrepreneurship will
need to be upscaled.
41. The overall support towards the ICT sector of ZWL$56.7 billion during
billion having been set aside for various e-Government programmes and
Digital Infrastructure
backbone only connects major cities and urban areas, with the rural
44. Through the Universal Services Fund (USF), POTRAZ has channelled
22
Community Information Centres. These interventions are consistent with
mobile networks, 83.9 percent for 3G networks, and 34.9 percent for
services.
E-Government
47. Government digital platforms, such as the PFMS, the HRMIS, and the
48. Most MDAs have established their own digital platforms, operating largely
23
49. Through the e-Government Standards Development Technical Working
among the various MDAs, and optimise on the available technical skills
across government.
24
Project Name Implementing Targeted works Budget
Entity Provision
(ZWL$)
PFMS Kiosk Min of ICT Provision of access to government Public 175,000,000
Finance System to remote users who don’t
have access to the system
Last Mile Min of ICT Provision of connectivity to the PFMS 290,000,000
Connectivity platform remote users
52. The system has since been successfully rolled out in Manicaland
Province and is expected to be fully operational in other provinces during
ZWL$1.6 billion has been set aside under the 2023 National Budget for
that purpose.
25
Digital Entrepreneurship
54. The country has potential for the development of digital entrepreneurship,
57. In the region, Zimbabwe is among the countries which are yet to fully
digitalise the broadcasting services. As a way of deriving benefits from
the initial investment, in 2022, 50 000 set top boxes were purchased,
now awaiting pre-shipment inspection with US$504,000 being disbursed
towards high end upgrade, which is expected to enable households to
enjoy the new digital broadcasting services This may be mitigated by
smart TVs that now come with “in-built capacity” to receive digital signals.
This should be the way forward.
58. To ensure that the society continue to reap the benefits from the project
investments, ZWL$1.5 billion has been provided for in the 2023 National
26
Budget targeting the construction of base stations, installation of radio
justice with consistency and collective effort by all justice delivery players.
60. Key to note is that, once fully embraced and operationalised, the system
corrupt activities.
61. Phase 1 of the project has been completed and commissioned by His
27
Development Projects Management Information Systems
65. To date system installation and user acceptance training have since
been completed whilst the entire system is expected to be operational in
ENERGY
66. The sector is key to sustainable economic growth and development and
hence the need to promote the management of both renewable and now
28
68. In this regard, our strategic objective under the sector remains centered
power supply.
70. Kariba Power Station contributed 67.24%, Hwange Power Station added
26.94% whilst the Small Thermals only contributed 1.40% to the total
71. The table below indicates electricity generation for the country.
Installed Capacity
Plant Actual Generation (GWh) 2023 Target (GWh)
(MW)
Hwange 920 1,896 9,108
Harare 120 34 84
Bulawayo 135 15 84
29
infrastructure at the same time increasing private sector participation
Installed steam turbine and generator for unit 7 Cooling tower for units 7 & 8
74. The overall progress of the project as at end of September 2022 stood at
94.57% with Commissioning and Synchronising works remaining.
76. During 2023, an amount of US$472 million will be injected on the project
from the China Exim Bank loan facility to support ongoing works, with an
30
additional ZWL$20.1 billion being mobilised by the parastatal for local
works whilst ZWL$3 billion will be channeled from the fiscus towards
78. ZERA has licensed more than 60 IPPs in the renewable energy space,
with a capacity of around 2000MW, however, off take of the projects
has been low owing to viability challenges. With the technical assistance
of the African Legal Support Facility (ALSF) Government is working to
improve the bankability of IPP projects, reduce currency related risks
31
81. Rural Electrification Programme has been a topical issue in as far as
trying to improve access to electricity for the rural population mainly
through solar grid and mini grid extensions as well as biogas projects.
82. To date, 437 solar grids, 430 solar micro-grids, 1 community solar and 89
biogas digesters have been installed.
83. For the year 2023, a combined allocation amounting to ZWL$19.3 billion
will be availed (ZWL$18.3 billion from Rural Electrification Fund) and
(ZWL$1 billion from the fiscus) to accelerate electricity transmission and
off-grid solutions to rural areas in order to improve electricity access.
84. This intervention will also help rural schools to cope up with education 5.0
that focuses on innovation and industrialisation a catalyst for achieving
Vision 2030.
85. The table below indicates the targeted interventions under the
programme.
32
Rural Rural
Electrification Targeted Scope Fiscus Electrification Total Resources
Programme Fund
89 Institutional Biogas
Biogas Digesters constructed 282,560,000 282,560,000
TRANSPORT
88. Therefore, priority is on ensuring road, rail and air services are seamlessly
connected within the country as well as the region. This will enhance
33
economic competitiveness while facilitating domestic, regional as well
as international trade.
89. The focus in the sector will also include the harmonization of traffic signs
to meet the agreed uniform signage in line with SADC agreed standards.
91. Such a framework is already being considered for rolling out to other
92. Overall support towards the transport sector during 2023 amounts to
Roads
regard, support has mainly been targeted at the upgrading of the Harare-
34
Masvingo-Beitbridge Road and rehabilitation of other trunk roads linking
94. Lack of routine maintenance for extended periods has invariably led
the form of long travelling hours, high vehicle operating costs and road
carnage.
vehicles now transport more than 90% of cargo in and out of Zimbabwe
thus, putting pressure and damage to the road network as well as causing
congestion.
96. Going forward, policy measures are being pursued to ensure road
roads across the country. To make meaningful progress, this will require
35
98. The 2023 National Budget is therefore, setting aside ZWL$194.8 billion
towards interventions in the road sector, covering construction upgrading
and rehabilitation.
98. The 2023 National Budget is therefore, setting aside ZWL$557.8 billion towards interventions
in Beitbridge–Masvingo–Harare Road and rehabilitation.
the road sector, covering construction upgrading
99.
the country is expecting over 100 international freighters ferrying different
The widening, reconstruction and rehabilitation of the 580km Beitbridge-Harare Highway is a
minerals
critical and industrial
component output Corridor
of the North-South to global
as destinations
the country is through
expecting the
over highway
100
daily. freighters ferrying different minerals and industrial output to global destinations
international
through the highway daily.
100. Implementation of the targeted works is progressing well with a total of
355km having
100. Implementation been
of the opened
targeted works istoprogressing
traffic whilst the
well with remaining
a total section
of 355km having is now
been
opened to traffic
targeted forwhilst the remaining
completion sectionthe
during is now targeted
year 2023.for completion during the year
2023.
101. In support of the target to complete the entire stretch by 2023, an amount
101. Inof
support of the target
ZWL$43 to has
billion complete the set
been entireaside
stretchfor
by 2023, an amount of ZWL$43 billion
the project.
has been set aside for the project.
36
Part of the 20km Masvingo Urban along Harare-Masvingo-Beitbridge road
Section of the completed Beitbridge-Harare Road
37
38
Mbudzi Interchange Bridge
105. The year 2023 will also see the construction, rehabilitation and upgrading
39
• Construction of 10 km on Harare-Kanyemba starting with the missing
40
Government through the District Development Fund (DDF) is regravelling
and maintaining rural feeder roads. This has seen works covering over
107. The 2023 Budget will continue to deepen investments in rural road
108. The commuting public is now realizing the fruits from the ongoing roads
2021. This noble intervention has since resulted in cost savings in vehicle
with ZWL$30.7 billion being disbursed from the budget and ZWL$15.2
41
• 184 wash aways reclaimed;
attended to.
111. The above progress has seen attainment of specific milestones, through
the respective Road Authorities, among others, as indicated below:
42
Ø Primmed 2km of Tipperary Road in Shamva;
is still in progress;
2km stretch;
Tsholotsho;
in progress;
43
̧
44
Camperdown Road resurfacing completed on 2km stretch
45
Current works at Harare-Mutare Road Dualisation Project - Melfort section
road network.
113. In order to ensure value for money in the implementation of works under
46
Emergency Road Rehabilitation Programme II
Road Fund
Sub-total 84.5
Fiscus
Sub-total 70.5
Aviation
following works:
and scanners.
47
116. The expected date of completion for the new terminal buildings is May
immediately.
117. The project involves the construction of a new airport terminal, and
118. On completion, the airport will be a game changer as this will handle
of 2.5 million being handled by the existing facilities. With no doubt, the
airport will become one of the regional aviation hubs that should attract
Rail
120. Rail infrastructure network remains key towards the provision of bulk
48
121. Concern is however on the current network challenges associated with
123. Ensuring that NRZ recovers capacity has, therefore, become very
124. Under the initial NRZ Recapitalisation phase, funding options are being
the recovery.
Border Posts
49
126. Already, works under the second phase of the expansion and
connectivity.
127. The project scope of modernization of the Beitbridge Border Post includes
upgrade of the entire border post commercial facilities (freight terminal,
bus terminal, pedestrian terminal), Information Communication and
Technology infrastructure, construction of a number of social projects to
improve the town of Beitbridge infrastructure such as a fire station, plant
and animal quarantine facility, residential buildings, a sewage dam, and
50
Megalitres reservoir superstructure is awaits roofing and other ancillary works
51
Staff Houses and road under construction at Beitbridge Border Post
Border Post, the port of entry linking Zimbabwe and Mozambique, to the
52
Beitbridge border post warehouse
131. Works to align the country’s border at Kazungula with Botswana and
as world class roads that meet international standards and eliminate all
53
and major roads linking all border posts must be made to international
standards.
133. Water is a critical enabler for different sectors of the economy and a
basic human right essential for improving the standard and quality of life
coverage and limited access to water with only 63% of the population
water infrastructure;
54
• Poor billing and low collection efficiency which undermine revenue
droughts;
137. In view of the above, provision of clean and safe water is at the heart
138. Government’s focus under this sector has been towards dam construction,
Dam Construction
55
140. Specifically, an amount of ZWL$2.6 billion was channeled towards the
Chivhu dam
and now at 69%. The availed resources enabled the contractor to cast
concrete on the dam wall to a height of 31m out of the target of 72m,
56
Construction of Gwayi Shangani Dam
143. While priority will be accorded to key interventions that will mitigate the
purposes;
57
water supply development approach already adopted by Government;
and
sectors.
144. In view of the above, the 2023 Budget makes a provision of ZWL$30.4
147. Government will also facilitate ongoing works at other dam construction
148. The Table below indicates the specific allocations and works targeted
during 2023.
58
PROJECT LOCATION PROGRESS 2023 TARGETED WORKS 2023 BUDGET
NAME (%) ALLOCATION
Gwayi-Shangani Matebeleland 69% Construction of 46m 6,297,000,000
Dam North
of the dam to reach full height of
72m, construction of outlet works,
and apron concrete placing.
Bulawayo Pipe- Matebeleland 5% Construction of two pump houses, 2,798,000,000
line North and laying of 104km of pipeline.
Muchekeranwa Mashonaland 0% Establishment of Engineer’s camp 600,000,000
Pipeline (Harare East and commencement of pipeline
East Water Aug- construction
mentation)
Semwa Dam Mashonaland 41.6% River diversion works, construc- 2,897,000,000
Central tion of the cofferdam, main dam
excavations, and main dam concrete
placing.
Tuli Manyange Matebeleland 34% Saddle dam construction, excava- 1,797,000,000
Dam South tions of main dam, concrete placing,
and construction of outlet works.
Kunzvi Dam Mashonaland 17% Finalisation of site establishment, 2,098,000,000
East cut off trench excavation, main
dam excavations, and main dam
construction.
Ziminya Dam Matebeleland 9% Site establishment, excavation of 1,123,000,000
North core trench, river diversion works,
construction of main dam, and spill-
way construction.
Vungu Dam Midlands 3% Completion of site establishment, 1,498,000,000
excavation of core trench, outlet
works excavations, and construction
of main dam.
Dande Dam Mashonaland 20% Completion of hard excavations, 600,000,000
Central grouting of main dam, backfilling,
and blasting of 7km tunnel.
Mbada Dam Mashonaland 13% Completion of site establishment, 600,000,000
Central access road construction, founda-
tion excavations, and main dam
construction.
Defe Dam 0% Preliminary works including detailed 1,000,000,000
designs, procurement and site estab-
lishment.
Bindura Dam Mashonaland 38% Main dam grouting, outlet works 400,000,000
Central establishment, and construction of
main dam.
Grand Total 21,708,000,000
59
149. Noting the number of existing idle water bodies in the country including
Tugwi-Mukosi, Marovanyati, and Muchekeranwa dams, a deliberate
be undertaken.
150. In this regard, an amount of ZWL$42.5 billion has been set aside towards
Borehole Drilling
(ZINWA 40 and DDF 10) were procured with 10 under ZINWA having
rigs have already commenced work and to date 270 boreholes have
152. Moreover, a total of 747 boreholes (ZINWA 275, DDF 230, and
153. With regards to rehabilitation works, a total of 4,788 hand pumps have
60
Rural WASH
154. Adaptation to the effects of climate change and climate variability has
155. In view of sanitation and hygiene, four hundred and seven (407) villages
have been triggered for behavior change and for the attainment of an
Open Defecation Free (ODF) status with community sanitation & hygiene
157. In line with the focus of NDS1 on rural development, the Government
61
158. The programme has a target of drilling of 8,600 boreholes which will be
another 2,500 boreholes with solar pumps in order to empower our rural
communities.
160. In order to support the above interventions, the 2023 Budget makes a
161. In line with the thrust of “leaving no one behind”, focus during 2023 is
62
PROJECT 2023 PLANNED WORKS 2023 BUDGET
NAME ALLOCATION
Dema Water Supply and install pump sets, construction of 200mm, raw water 74,717,000
Supply abstraction pumping main, completion of a 50m³/h radial filter and
sedimentation unit, backwashing system & sump, pumping main to Dema,
Construction of 1000m³ tank.
Nyanga Construction of a new treatment plant (50m3/hr). 19,925,000
Water Supply
Hauna Water Completion of 3 500km of 200mm PVC clear water main from the 54,793,000
Supply treatment works to Hauna, completion of twin 75m³/h radial filter and
sedimentation, completion of upholding weir.
Filabusi Completion of construction of a new treatment plant (50m3/hr), upgrade 44,830,000
Water Supply clear water pumps, and construction of 2 880 reinforced concrete
reservoir.
Colleen Bawn Construction of a new sedimentation tank and filter tank (100m3/hr), 149,435,000
Water Supply installation of new raw water pumps, laying of pumping main of 315mm
diameter and PVC pipes and construction of clear water sump.
Parirewa Construct 1000m³ Tank, reticulation Extension. 99,623,000
Water Supply
Inyathi Water Supply and install pump sets, completion of clear water main, clear water 24,906,000
Supply pumping main, and installation of elevated tanks at booster station.
Vic Falls Construction of 100m3/hr new treatment plant, sedimentation and 2 filter 24,906,000
Airport Water tanks and 250m3 sump, electrification and transformer upgrading.
Supply
Mataga Water Construction of 2 x 60m³/h new treatment plant filter and sedimentation 64,755,000
Supply unit, and construction of 1 000 reinforced concrete reservoir.
Mberengwa Construct raw, clear water and water pump house, supply and install pump 134,491,000
Water Supply sets, construct a 150m³/h reinforced concrete filter and sedimentation unit,
and construct 500m³ brick reservoir.
Jerera Water Construction of a new treatment plant 50m3/hr sedimentation and filter 49,812,000
Supply unit, and supply and install water pump sets.
Mhangura Construction of raw water pump house, reticulation of Damba and 79,699,000
Water Supply Chebanga high density, construction of sewer trunk mains, construction of
waste water stabilisation ponds, and construction of 1 000m3 RC reservoir
Goromonzi Construction of 150m3/hr reinforced concrete sedimentation and filter 174,340,000
Water Supply unit, supply and install pump sets, construction of 500m3 brick reservoir at
Chinyika school, and construction of 2 280m3 reinforced concrete reservoir
at Goromonzi Centre.
Lutumba Construction of 20km pumping main from Beitbridge Lutumba, 500 m3 498,116,000
Water Supply reservoir, and booster pump station.
Nyabira Construct raw, clear and booster station pump houses, supply and install 547,928,000
Water Supply raw water pump sets, construction of 450mm raw water pumping main,
7km long of 315mm clear water pumping main, and 15km of 200mm from
Nyabira to New Parliament.
63
PROJECT 2023 PLANNED WORKS 2023 BUDGET
NAME ALLOCATION
Checheche Construct 100 m3 new treatment plant sedimentation tank, filter tank and 74,717,000
Water Supply 250m3 sump, 1.6km raw water pumping main, 6.5km clear water pumping
main, 13km reticulation main, Supply and install water pump sets,
Construction of 2 280 reinforced concrete reservoir.
Murambinda Construction of 250m3 clear water sump, construction of booster pump 24,907,000
Water Supply house, supply and install booster pumping plant, trench, lay 3km of
reticulation main, and construction of 2 280m3 reinforced concrete tank
Grand Total 2,142,000,000
165. The global Covid 19 pandemic, which has since subsided, presented
an opportunity for our health delivery sector to reflect on its efficiencies
and capacities in infrastructure, prerequisite curative and diagnosis
equipment, and rapid response services. Government has, therefore,
over the past 2 years invested significantly in health infrastructure, medical
equipment and ambulances, covering all levels of care, increasing its
readiness for any future pandemics.
166. On 13th May 2022, His Excellency, President E.D Mnangagwa presided-
over the ceremonial opening of the NMS-built Stoneridge Health Centre,
that will see the construction of thirty 22-bed Health Centres Facility.
167. Significant progress has been made on Cowdry Park Health Centre
in Bulawayo and is expected to be completed by year-end, whilst
64
preparatory works are underway for other facilities in Mberengwa and
Chimanimani.
Manyame Hospital
65
systems.
machines.
172. The rehabilitation and expansion of wards, kitchens, and laundry facilities
66
173. The renovations of two medical residential suites at Mpilo Central
Hospital were completed during the first half of 2022 and whilst three
before year-end.
and an administration block. Also under construction are junior staff flats,
Central Hospitals now connected. The System is now being rolled to all
176. As the country accelerates progress towards ending AIDS and public
antiretroviral therapy center that will cater for over 3 500 people who are
177. During the year 2023, public health investment thrust will mostly
be focusing on consolidating and strengthening the critical health
67
interventions which have received lesser attention in the past two years,
as the country concentrated mainly on the Covid 19 pandemic. This
rejuvenation drive will ensure the full utilisation of excess capacities and
COVID-19 fight.
blood banks and storage facilities, expansion of dental units and support
179. Our Central hospitals have transited into lower entry-point, mainly due
Covid 19 emergencies and some inefficiencies that had crept into the
180. In this regard, the 2023 Budget makes a provision of ZW$19.8 billion
68
Development and related stakeholders, is establishing a stand-alone
Provincial Hospitals
and absence of district hospitals within these major urban centres. In this
regard, the 2023 Budget proposes to avail ZW$792 million for the pre-
184. The completion of Lupane Provincial Hospital under phase 1, which has
services, ZW$3.5 billion will be channelled towards the final touches and
69
Casualty Block Outpatients Block
185. District hospitals, being the mainstay of the health referral system, play
a critical role in ensuring that quality health services are delivered closer
187. In addition, mission hospitals have played a crucial role in the provision
of medical services in some rural areas, where Government, is yet to
establish comprehensive secondary care facilities. In this regard, an
amount of ZW$154 million will be allocated to selected 5 faith-based
hospitals in 2023.
70
Primary Health Care
188. In line with leaving no-one and no place behind philosophy, Central
and Local Governments, in 2023, will continue to roll out more primary
health facilities aimed at ensuring that all settlements are within the
recommended 5-kilometre radius to health services.
189. Government in 2023, will spearhead the completion of the rural health
centre projects through an allocation of ZWL$9.3 billion as indicated in
the table below:
190. Local Authorities are urged to continue developing rural health centres
71
HUMAN CAPITAL DEVEPOPMENT AND WELL-BEING
Basic Education
Ministerial Committee.
193. Already under the programme, preparatory works such as school site
establishment and clearance have been completed and tendering
modern institutions.
such as repair of windows and blown away roofs done on 230 classroom
72
196. Government will also prioritise investments towards the ICT services and
in the country.
197. In this regard, the 2023 National Budget will allocate ZWL$600 million
to source the required ICT equipment for all schools as part of the
digitization drive.
198. Riding on the Rural Electrification Programme, the 2023 Budget will
Tertiary Education
199. The 2022 National Budget kick started the implementation of Gender
200. In line with this thrust, Bindura University of Science Education has
73
might be susceptible to abuse if they fail to secure decent accommodation
201. Additionally, priority by Government under the sector has been towards
74
Simon Mazorodze School of Medical and Health Sciences, Great Zimbabwe University
203. Consistent with the NDS1 strategic objectives, the focus during 2023
75
2023 Allocation
Name of Institution Project
(ZWL$)
State Universities
Male halls of residence 700,000,000
Bindura University of Science Education Industrial Park 50,000,000
Innovation Hub 80,000,000
Sub Total 830,000,000
Faculty of Humanities 800,000,000
Lupane State University Industrial Park 50,000,000
Innovation Hub 80,000,000
Sub Total 930,000,000
Student Admissions 200,000,000
Manicaland University of Applied Halls of Residence 360,000,000
Sciences Industrial Park 50,000,000
Innovation Hub 80,000,000
Sub Total 690,000,000
Pathology Laboratory 400,000,000
Construction of faculty of Law 300,000,000
Midlands State University Industrial Park 50,000,000
Innovation Hub 80,000,000
Halls of Residences 320,000,000
Sub Total 1,150,000,000
Industrial Park 50,000,000
Chinhoyi University of Technology Innovation Hub 80,000,000
Engineering workshops Phase 1 300,000,000
Sub Total 430,000,000
Library 600,000,000
National University of Science and Students Service Centre 500,000,000
Technology Industrial Park 50,000,000
Innovation Hub 80,000,000
Sub Total 1,230,000,000
Rehabilitation of infrastructure 100,000,000
Lecture Block 150,000,000
Gwanda State University Mining Lab 150,000,000
Industrial Park 50,000,000
Innovation Hub 80,000,000
Sub Total 530,000,000
Teaching Hospital 100,000,000
Great Zimbabwe University Industrial Park 50,000,000
Innovation Hub 80,000,000
Sub Total 230,000,000
Rehabilitation of infrastruc-
50,000,000
ture
Harare Institute of Technology Laboratory Plaza 200,000,000
Industrial Park 50,000,000
Innovation Hub 80,000,000
Sub Total 380,000,000
76
2023 Allocation
Name of Institution Project
(ZWL$)
Students Affairs Building 200,000,000
Halls of residence 200,000,000
University of Zimbabwe
Industrial Park 50,000,000
Innovation Hub 80,000,000
Sub Total 530,000,000
Office block 150,000,000
Marondera University of Agriculture
Industrial Park 50,000,000
Sciences and Technology
Innovation Hub 80,000,000
Sub Total 280,000,000
Administration, Teaching and
100,000,000
Learning Block
Zimbabwe Open University
Multipurpose Hall 100,000,000
Innovation Hub 80,000,000
Sub Total 280,000,000
77
2023 Allocation
Name of Institution Project
(ZWL$)
Construction of new classroom
Construction of classroom blocks 815,000,000
blocks
Rehabilitation of schools Rehabilitation of infrastructure 415,000,000
Sub total 4,180,000,000
207. Notable progress has been achieved with the construction of two blocks
[B3 and B1] having been completed and now ready for occupation before
end of 2022.
208. Upon completion, the project will provide a commercial centre on the
ground floor of each block that should allow the operationalisation of
78
Bulawayo Student Accommodation Complex Completed Block
209. Under the same arrangement of crowding in private sector and institutional
investors on infrastructure projects, the year 2023 will see the construction
would entail increasing the computing power and storage capacity for
79
211. Phase II shall address the development of meteorological monitoring,
214. To this end, the 2023 Budget has set aside ZWL$2 billion to support the
planned modernization programmes as indicated in the table below.
PROJECT ALLOCATION
(ZWL$)
Equipment for training centres and academies 345,000,000
Rehabilitation of training centres
Domboshava 120,000,000
Highlands 90,000,000
Elangeni 100,000,000
Rowa 90,000,000
Toronto 100,000,000
80
Inyati 100,000,000
Eskoveni 100,000,000
Bikita 90,000,000
Senga 100,000,000
Murewa 90,000,000
Chinhoyi 120,000,000
Alford 100,000,000
Zimbabwe Institute of Public Administration and Management 473,000,000
TOTAL 2,018,000,000
HOUSING DELIVERY
215. In line with the Zimbabwe National Human Settlement Policy aimed at
construction of 225 000 new housing units drawing funding from both
the public and private sector as well as international funders by the year
2025.
216. This thrust entails densification of settlements that include the creation of
citizens and the use of alternative building technologies and designs that
confirm to climatic changes shocks and generally speak to modernity.
housing backlog.
81
218. Supported projects range from the construction of residential flats,
Residential Accommodation
Dzivarasekwa.
220. In this regard, the initial four blocks of flats for Senga and Marondera
82
Block of flats under construction in Marondera
221. The focus during 2023 will continue to be on ensuring that our settlements
are well organized whilst at the same time having the requisite
infrastructure that defines a properly structured settlement.
222. Given the above and also taking into consideration settlements such
as Caledonia, Harare South and Garikai/Hlalani Kuhle which were
developed without onsite and offsite infrastructure, among other ancillary
services, Government will continue to work with our institutions of higher
learning to develop settlement plans for such areas in fulfillment of the
agenda of regularising illegal settlements.
83
224. Already, the Infrastructure Development of Zimbabwe working with a
225. The same arrangement will be undertaken in Gwanda which will involve
square metres.
challenges.
84
Completed Binga Flood Victim house
Institutional Housing
228. Construction of the New Parliament Building through a grant from the
• Landscaping;
85
229. Completion of the remaining works will pave way for occupation for both
231. Construction of the four blocks have been completed with outstanding
works including installation of Telone cables, substation dressing, laying
of cables from feeder pillar to the substation, installation of gutters and
completion of sunscreens as well as balustrading.
86
Lupane Provincial Composite Office Block
232. The focus during 2023 will be on completion of ongoing works at various
composite offices including Mutoko and Siakobvu District Composite
Offices, among other projects countrywide.
234. Critical interventions were also undertaken towards prison and court
infrastructure resulting in the completion of Lupane Magistrates Court,
Chikurubi female open prison as well as rehabilitation and upgrading
87
of various buildings under the same that are now at different stages of
completion.
88
Gwanda Magistrates Court under construction
court and prison infrastructure in order to improve the face of the existing
238. Below is a pictorial view of the works that were undertaken at Dzivarasekwa
in 2022:—
89
Housing Units at Dzivarasekwa under construction
240. Resources amounting to ZWL$3.3 billion is being set aside for these
90
243. In order to upscale our intervention under this noble programme,
ZWL$3.1 billion has been set aside in support of the already identified
cantonment areas.
244. In honour of the fallen veterans of Africa’s liberation wars and as a way of
245. In this regard, foundation works mainly targeting excavations have since
246. The 2023 Budget has therefore, made an allocation of ZWL$4.9 billion
capitalize the revolving Housing Loan Schemes for both Senior and
91
248. The 2023 National budget is allocating resources amounting to ZWL$7.5
billion towards resourcing both the Senior Officers Housing Scheme and
249. Government, through the institutional set ups for both senior officers and
junior officers will work on measures that should ensure full recoveries
Irrigation Development
250. Improved food security and nutrition remains at the core of Government’s
interventions towards the same have mainly been focused on the National
following:
92
target of 1 592 ha have been completed and construction works are
iii. Pedstock Center Pivot Facility where a total of 61 pivots have been
targeted 2 900ha;
93
Maize crop under a 50ha centre pivot at Mtorazeni Farm, Muzarabani District
252. The 2023 Budget has set aside ZWL$55.3 billion towards irrigation
below:
94
Project Name Potential Targeted Fiscal Resources Development Special
Hectarage Hectarage (ZWL$) Partner Drawing
Support (ZWL$) Rights (US$)
Operations and 15,000.00 10,000.00 1,620,000,000
Maintenance
of Irrigation
Schemes
Pedstock Irriga- 2,900.00 880.00 1,056,000,000
tion Equipment
Facility
Upgrading of 20,000,000
Fels Demonstra-
tion Center
Upgrading and 5,000,000
Rehabilitation
of Irrigation
Demonstration
Plots
Off-grid Small- 100,000,000
holder Farmer
Led Irrigation
Systems
Grand Total 70,786.00 23,788.00 27,965,120,000 14,608,094,000 20,000,000
as follows:
95
Ø Operations and maintenance of irrigation schemes.
254. Under the Green Climate Fund, a total of US$3 million will be availed
255. In addition, through the support from International Fund for Agricultural
96
SDR Support towards Irrigation Development
PROVINCE NAME OF IRRIGATION SCHEME TARGETED TARGETED WORKS
HECTRAGE
Mash Central Morefields Irrigation Scheme 170 Turnkey Supply, Delivery
and Installation of Pumping
Units,3 Centre Pivots covering
140ha, 315kva Transformer
and Infield equipment for
a semi portable sprinkler
irrigation on 30ha
Mwenje Irrigation Scheme 100 Supply and Installation of an
800m PVC pipeline
Mat North Bubi-Lupane Extension Irrigation 200 Turnkey Supply and
Scheme Construction of Pumping
Station, Pipeline, Centre
Pivots and Related Ancillary
Equipment
Manicaland Murambinda Irrigations Scheme 200 Turnkey Supply and
Construction of Pumping
Station, Pipeline, Centre
Pivots and Related Ancillary
Equipment
Ruti Irrigation Scheme 80 Construction of a Solar
Pumping Station, Pipeline,
Storage Tanks and Drag
Horse Sprinkler Irrigation
Upper Lesapi irrigation Scheme 130 Turnkey Supply and
Construction of Diversion Weir,
Conveyance Canal, Booster
Pumping Station, Pipeline,
Centre Pivots and Related
Ancillary Equipment
Mash West Muzvezve Irrigation Scheme 200 Turnkey Supply and Con-
struction of Pumping Station,
Pipeline, Centre Pivots and
Related Ancillary Equipment
Riversdale 110 Turnkey Supply and Con-
struction of Pumping Station,
Pipeline, Centre Pivots and
Fencing
Mat South Mtshabezi Irrigation Scheme 100 Extension of the existing
project by installation of
centre pivots
Smith Block Irrigation Scheme 150 Turnkey Supply and
Construction of Mainline,
Night Storage Dam, Booster
Pumping Station, Pipeline,
Centre Pivots and Fencing
97
PROVINCE NAME OF IRRIGATION SCHEME TARGETED TARGETED WORKS
HECTRAGE
Masvingo Nyahombe Irrigation Scheme 60 Turnkey Supply and
Construction of Pumping
Station, Pipeline and Infield
Irrigation Equipment
Munjera (Ruti) Irrigation Scheme 100 Turnkey Supply and
Construction of Pumping
Station, Pipeline and Infield
Irrigation Equipment
Gororo Irigation Scheme 150 Turnkey Supply and
Construction of Pumping
Station, Pipeline and Infield
Irrigation Equipment
Midlands Chaora Block Irrigation Scheme 230 Construction of a Pumping
Station, 2,9km Mainline,
Night Storage Reservoir,
Booster Pump Station, Infield
Pipelines, Centre Pivots and
Fencing
Mutange Irrigation Scheme 134 Completion of land Clearing
on 60ha and Transformer
upgrading
Mabwematema Irrigation Scheme 640 Turnkey Supply and Con-
struction of Pumping Station,
Pipelines and Infield Irrigation
Equipment on various blocks
Mash East Mutawatawa Irrigation Scheme 100 Turnkey Supply and Con-
struction of Pumping Station,
Pipeline and Infield Irrigation
Equipment
Total 2,714
257. The list of irrigation schemes to be supported through the fiscus is shown
in annexure II
98
259. The country has a total of 4,099 dip tanks out of which 3,969 are
functional, with 400 having been rehabilitated during 2022 and targeted
260. An amount of ZWL$590 million has been set aside targeting construction
of 40 dip tanks and rehabilitation of 500 dip tanks across the country.
and the outbreaks of diseases such as anthrax and foot and mouth, an
amount of ZWL$514.2 million has been set aside targeting fencing of the
262. A changing climate and the resulting more extreme weather events are
99
the environment, human health, agriculture, food security, economic
264. The 2022 Budget laid a strong foundation for creating a more climate-
265. As the world emerges from the Covid 19 pandemic, the 2023 Budget will
economic conditions.
268. To this end, the 2023 National Budget has streamlined ZWL$182.1 billion
100
Sector Programme/Project Allocation (ZW$)
Energy Electrification of rural areas and mini-grid solar projects 1,000,000,000
269. The National Adaptation Plan (NPA), expected to be launched later this
table below:
101
PROGRAMME TARGETED ACTIVITIES PARTNERS AMOUNT (US$)
Zimbabwe Resilience Hazard maps in Southern European Union,
Building Fund Zimbabwe, transformative UNDP and the 88,400,000
adaptation and disaster Governments of
risk management (DRM), Sweden and the
solarized water provision, United Kingdom
climate-smart agriculture,
and post-harvest
processing.
Support to Zimbabwe Improve Government World Bank
Recovery and Resilience systems and develop 2,000,000
capacity for DRM in
Cyclone-affected provinces,
national DRM operational
guidelines, and training
curriculum.
Idai Recovery Project The early and medium-term World Bank, UNOPS
resilient disaster recovery and Cordaid 72,000,000
and the rehabilitation
of critical community
infrastructure.
Smallholder Irrigation Improve climate-resilient IFAD 52,034,000
Revitalization Programme crop production in
Manicaland and Masvingo
Provinces.
Smallholder Agriculture Designing climate-smart IFAD 67,440,000
Cluster Project and nutrition-sensitive
investments
TOTAL 317,334,000
271. Opportunities lie in the private sector, where corporates can not only
reduce their own risks from the impacts of climate change but also take
advantage of new markets and businesses in the adaptation space.
102
preparedness, recovery and resilience building through capitalisation of
Disaster Risk Management structures up to village level.
DEVOLUTION
275. The year 2023 marks the fourth year since the fiscus started allocating
resources to the lower tiers of Government through the 5% Inter-
Governmental Fiscal Transfers as enshrined in the Constitution.
103
with the main focus being on construction and rehabilitation of roads,
schools, clinics and boreholes, as well as procurement of equipment
among others.
278. During the year 2022, resources amounting to ZWL$16.7 billion have so
far been disbursed as indicated in the table below.
2022 DISBURSEMENTS TO
PROVINCE 2022 BUDGET SEPTEMBER
Provincial Councils 5,913,904,100 7,740,810
Sub-Total 5,913,904,100 7,740,810
279. The overpricing of goods and services by contractors did not spare
the devolution programme. In this regard, it affected the coverage of
280. Outlined below is also the picture collage of selected completed and
104
Key project milestones through devolution
Province Local Name of Project Pictures
Authority
105
Province Local Name of Project Pictures
Authority
106
Province Local Name of Project Pictures
Authority
107
Province Local Name of Project Pictures
Authority
108
Province Local Name of Project Pictures
Authority
109
Province Local Name of Project Pictures
Authority
110
Province Local Name of Project Pictures
Authority
111
Province Local Name of Project Pictures
Authority
112
Province Local Name of Project Pictures
Authority
113
Province Local Name of Project Pictures
Authority
281. Whilst notable progress has been witnessed in the implementation of the
Transfer Administrative Manual that should see the review of the current
formula and come up with the one that brings fairness in terms of resource
fiscal grant.
114
284. To ensure smooth implementation of programmed works, capacity building
285. Pursuant to the above, the 2023 National Budget will provide resources
Operational Capital
Grant Grant Total Grant Total Grant Total Grant
Entity (ZWL$) (ZWL$) (ZWL$) (ZWL$) (ZWL$)
Provincial
Councils 7,820,146,000 11,730,217,000 19,550,363,000 28,267,244,000 34,050,069,000
Local Authorities
Bulawayo
Metropolitan Province 508,851,000 4,579,661,000 5,088,512,000 7,357,317,000 8,862,454,000
Manicaland
Province 2,138,036,000 19,242,333,000 21,380,369,000 30,913,194,000 37,237,319,000
Mashonaland
Central Province 1,819,790,000 16,378,118,000 18,197,908,000 26,311,776,000 31,196,021,000
Mashonaland
East Province 1,832,173,000 16,489,560,000 18,321,733,000 26,490,805,000 31,910,214,000
Mashonaland
West Province 2,287,095,000 20,583,843,000 22,870,938,000 33,068,356,000 39,833,379,000
Matabeleland
North Province 1,559,895,000 14,039,061,000 15,598,956,000 22,954,033,000 27,804,923,000
Matabeleland
South Province 1,462,195,000 13,159,756,000 14,621,951,000 21,141,412,000 25,466,461,000
115
2023 Estimates Indicative Estimates
2024 2025
Operational Capital
Grant Grant Total Grant Total Grant Total Grant
Entity (ZWL$) (ZWL$) (ZWL$) (ZWL$) (ZWL$)
Midlands
Province 2,373,402,000 21,360,615,000 23,734,017,000 34,316,252,000 41,836,568,000
Masvingo
Province 1,877,944,000 16,901,506,000 18,779,450,000 27,152,608,000 32,707,409,000
Harare
Metropolitan
Province 1,735,943,000 15,623,485,000 17,359,428,000 24,699,443,000 29,595,893,000
286. Priority under the devolution thematic area will continue to support
authorities.
Annexure I.
Women Empowerment
116
• Funding of women’s projects through the women Development Fund
entrepreneurs,
business associations.
and 957 men which resulted in the creation of 11 700 jobs and livelihoods
290. In addition, to date 85 projects have been funded through the Women
women. The year 2022 also witnessed a total of 4 000 women who were
117
exposed to markets through participation at shows, fairs and exhibitions
is almost complete and this will benefit 125 women as owners of this
project.
literacy and other skills such as business, technical, life, leadership and
118
293. The focus during 2023 will be on recapitalisation of the Zimbabwe
Women’s Micro Finance Bank and funding of 9 150 women ‘s projects
through disbursement of funding from the Bank, supporting 120 projects
through the Women Development Fund, capacity building of 350 000
female enterprises, promotion of market access for 3 000 women including
participation and registration of women on digital platforms among others.
294. To this end, the budget is setting aside resources amounting to ZWL$3
billion targeting the capitalisation of the Zimbabwe Women Micro Finance
Bank and ZWL$3 billion for SMEDCO.
Youth Empowerment
119
298. The above thrust is necessitated by recent project delivery inefficiencies
which include cost and time overruns emanating due to poor early project
development processes coupled with institutional weaknesses.
299. There is, therefore, need to upscale requisite public investment management
• Pre-feasibility study;
• Feasibility study;
resources.
120
• Strengthening of Monitoring and Evaluation systems within MDAs for
302. This, therefore, calls for MDAs to abide with the dictates of the Zimbabwe
303. Going forward, Treasury will be cautious on its decision to fund submitted
121
305. Ordinarily, the purpose of the Fund is to finance project development
306. Notwithstanding the existence of this Fund since 2017, resource uptake
funding requirements.
307. In view of the above, the 2023 budget will target capacitation of the fund
122
ANNEXURES
Annexure I: Inter-Governmental Fiscal Transfers Allocation
ANNEXURE I: 2023 INTERGOVERNMENTAL FISCAL TRANSFERS
Indicative Estimates
2022 Estimates 2023 Estimates 2024 2025
Operational Capital Grant Total Grant Total Grant Total Grant
Ref Entity Grant (ZWL$) (ZWL$) (ZWL$) (ZWL$) (ZWL$)
PROVINCIAL
A COUNCILS
C LOCAL AUTHORITIES
BULAWAYO
METROPOLITAN
PROVINCE
1 Bulawayo City Council 1,348,383,000 508,851,000 4,579,661,000 5,088,512,000 7,357,317,000 8,862,454,000
MANICALAND
PROVINCE
2 Mutare City 517,800,100 195,407,000 1,758,659,000 1,954,066,000 2,825,320,000 3,403,316,000
3 Chipinge Town Council 263,616,900 99,483,000 895,350,000 994,833,000 1,438,398,000 1,732,660,000
4 Rusape Town Council 245,230,000 92,544,000 832,899,000 925,443,000 1,338,070,000 1,611,808,000
5 Makoni RDC 748,988,800 282,652,000 2,543,872,000 2,826,524,000 4,086,781,000 4,922,842,000
6 Chipinge RDC 825,487,000 311,521,000 2,803,691,000 3,115,212,000 4,504,186,000 5,425,638,000
7 Mutasa RDC 590,623,000 222,889,000 2,005,998,000 2,228,887,000 3,222,676,000 3,881,961,000
8 Nyanga RDC 502,315,400 189,563,000 1,706,066,000 1,895,629,000 2,740,830,000 3,301,540,000
9 Buhera RDC 730,010,900 275,490,000 2,479,413,000 2,754,903,000 3,983,227,000 4,798,103,000
10 Chimanimani RDC 521,832,400 196,928,000 1,772,354,000 1,969,282,000 2,847,322,000 3,429,819,000
11 Mutare RDC 719,592,700 271,559,000 2,444,031,000 2,715,590,000 3,926,384,000 4,729,632,000
Sub-total 5,665,497,200 2,138,036,000 19,242,333,000 21,380,369,000 30,913,194,000 37,237,319,000
MASHONALAND
CENTRAL PROVINCE
12 Bindura Municipality 293,693,000 110,833,000 997,501,000 1,108,334,000 1,602,506,000 1,899,978,000
13 Mvurwi Town Council 253,322,300 95,598,000 860,385,000 955,983,000 1,382,226,000 1,638,808,000
14 Pfura RDC 671,738,100 253,500,000 2,281,497,000 2,534,997,000 3,665,271,000 4,345,654,000
15 Muzarabani RDC 533,021,300 201,151,000 1,810,358,000 2,011,509,000 2,908,376,000 3,448,257,000
16 Mazoe RDC 678,944,500 256,219,000 2,305,973,000 2,562,192,000 3,704,592,000 4,392,274,000
17 BinduraRDC 478,988,300 180,760,000 1,626,839,000 1,807,599,000 2,613,549,000 3,098,701,000
18 Chaminuka RDC 502,925,700 189,793,000 1,708,140,000 1,897,933,000 2,744,161,000 3,253,559,000
19 Mbire RDC 449,563,500 169,656,000 1,526,900,000 1,696,556,000 2,452,996,000 2,908,344,000
123
ANNEXURE I: 2023 INTERGOVERNMENTAL FISCAL TRANSFERS
Indicative Estimates
2022 Estimates 2023 Estimates 2024 2025
Operational Capital Grant Total Grant Total Grant Total Grant
Ref Entity Grant (ZWL$) (ZWL$) (ZWL$) (ZWL$) (ZWL$)
20 Guruve RDC 523,944,000 197,725,000 1,779,526,000 1,977,251,000 2,858,843,000 3,389,530,000
21 Rushinga RDC 436,048,700 164,555,000 1,480,999,000 1,645,554,000 2,379,256,000 2,820,916,000
Sub-total 4,822,189,400 1,819,790,000 16,378,118,000 18,197,908,000 26,311,776,000 31,196,021,000
MASHONALAND
EAST PROVINCE
22 Marondera Municipality 246,166,000 92,898,000 836,078,000 928,976,000 1,343,176,000 1,617,958,000
23 Manyame RDC 422,823,800 159,564,000 1,436,080,000 1,595,644,000 2,307,091,000 2,779,070,000
124
ANNEXURE I: 2023 INTERGOVERNMENTAL FISCAL TRANSFERS
Indicative Estimates
2022 Estimates 2023 Estimates 2024 2025
Operational Capital Grant Total Grant Total Grant Total Grant
Ref Entity Grant (ZWL$) (ZWL$) (ZWL$) (ZWL$) (ZWL$)
125
ANNEXURE I: 2023 INTERGOVERNMENTAL FISCAL TRANSFERS
Indicative Estimates
2022 Estimates 2023 Estimates 2024 2025
Operational Capital Grant Total Grant Total Grant Total Grant
Ref Entity Grant (ZWL$) (ZWL$) (ZWL$) (ZWL$) (ZWL$)
78 Tongogara RDC 408,888,400 154,306,000 1,388,750,000 1,543,056,000 2,231,054,000 2,687,477,000
79 Chirumanzu RDC 419,661,000 158,371,000 1,425,338,000 1,583,709,000 2,289,834,000 2,758,281,000
Annexure II: 2023 Irrigation Schemes Being Supported Through the Fiscus
NAME OF PROJECT PROVINCE DISTRICT 2023 ALLOCATION
(ZWL$)
Zhove irrigation (Kuwait Fund) Matebeleland South Beitbridge 300,000,000
Calsvale Matebeleland North Umguza 90,000,000
Bengura irrigation Masvingo Bikita 72,000,000
Maparu Velvekia irrigation Mashonaland Central Muzarabani Centenary 380,000,000
Masembura irrigation Mashonaland Central Bindura 120,000,000
Hiltop irrigation Matebeleland North Umguza 72,000,000
Mwenje irrigation Mashonaland Central Mazowe 120,000,000
Chinehasha irrigation Mashonaland Central Mazowe 144,000,000
Gwayi Shangani irrigation Matebeleland North Lupane Hwange 1,920,000,000
Marovanyati irrigation Manicaland Buhera 480,000,000
Manyuchi irrigation Masvingo Mwenezi 192,000,000
Mola irrigation Mashonaland West Kariba 96,000,000
Mopani irrigation Mashonaland West Sanyati 96,000,000
Bulawayo Kraal Matebeleland North Binga 720,000,000
126
NAME OF PROJECT PROVINCE DISTRICT 2023 ALLOCATION
(ZWL$)
Ruti Irrigation Manicaland Buhera 150,000,000
Nyabango irrigation Mashonaland West Chegutu 235,200,000
Gororo irrigation Masvingo Chivi 360,000,000
Riversdale irrigation Mashonaland West Chegutu 264,000,000
Temperly irrigation Mashonaland West Makonde 240,000,000
Smith Block irrigation Matebeland South Matobo 360,000,000
Mufusirwa irrigation Masvingo Bikita 144,000,000
Chilonga irrigation Masvingo Chiredzi 120,000,000
St Josephs irrigation Masvingo Chiredzi 60,000,000
Famona irrigation Matebeleland North Bubi 72,000,000
Maparo Irrigation Mashonaland Central Muzarabani 480,000,000
Makwe irrigation Matebeleland South Gwanda 72,000,000
Chemahororo irrigation Midlands Gokwe 52,800,000
Kachuta irrigation Mashonaland Central Guruve 150,000,000
Low Lands irrigation Masvingo Gutu 150,000,000
Mtshabezi irrigation Matebeleland South Gwanda 240,000,000
Mahute irrigation Mashonaland West Hurungwe 192,000,000
Bita irrigation Mashonaland East Hwedza 384,000,000
Mhakwe irrigation Mashonaland East Hwedza 60,000,000
Igogo Takawira irrigation Midlands Kwekwe 129,600,000
Musena Youth irrigation Midlands Mvuma 72,000,000
Bubi-Lupane irrigation Matebeleland North Lupane 332,000,000
Upper Lesapi irrigation Manicaland Makoni 312,000,000
Muzhwi irrigation Masvingo Masvingo 240,000,000
Bambanani irrigation Midlands Gweru 96,000,000
Bonchance irrigation Mashonaland East Marondera 288,000,000
Nyika irrigation Masvingo Bikita 57,600,000
Vuka irrigation Mashonaland Central Muzarabani 240,000,000
Nyambudzi irrigation Mashonaland Central Mbire 120,000,000
Milsonia irrigation Midlands Kwekwe 48,000,000
Gwingwizha irrigation Mashonaland Central Mazowe 72,000,000
Nyarumwe irrigation Mashonaland Central Mazowe 60,000,000
Chaora block irrigation Midlands Mberengwa 552,000,000
Kanyemba irrigation Mashonaland Central Mbire 538,800,000
Everton irrigation Mashonaland Central Mt Darwin 120,000,000
Sommerset irrigation Mashonaland East Marondera 96,000,000
Mpudzi irrigation Manicaland Mutare 96,000,000
Nyazvikatsi irrigation Mashonaland East Mutoko 72,000,000
Nyambiri irrigation Mashonaland East Seke 144,000,000
Chigara BBH irrigation Mashonaland East Seke 144,000,000
Nyanyadzi irrigation Manicaland Chimanimani 450,000,000
Nyaje irrigation Midlands Gokwe 24,000,000
Laverstork/Ena Vante irrigation Manicaland Mutare 624,600,000
Chikwezvero irrigation Mashonaland East Chikomba 84,000,000
Lapachi irrigation Masvingo Mwenezi 156,000,000
Muzvezve Village 13 irrigation Mashonaland West Ngezi 240,000,000
Chimhanda Extension irrigation Mashonaland Central Mt Darwin 120,000,000
Gowe irrigation Mashonaland West Sanyati 173,000,000
Seke Sanyati irrigation Mashonaland West Sanyati 144,000,000
Chipoli D irrigation Mashonaland Central Shamva 154,000,000
Nhema irrigation Masvingo Zaka 72,000,000
127
NAME OF PROJECT PROVINCE DISTRICT 2023 ALLOCATION
(ZWL$)
Mushaya irrigation Masvingo Zaka 84,000,000
Mabwematema irrigation Midlands Zvishavane 220,000,000
Mutema Taona irrigation Manicaland Chipinge 96,000,000
Mbuya Nehanda Irrigation Mashonaland West Ngezi 720,000,000
(Dorreen’s Pride) irrigation
Karoi irrigation Mashonaland Central Mbire 60,000,000
Biri Irrigation Midlands Mberengwa 282,998,704
Ndiyadzo irrigation Manicaland Chipinge 96,000,000
Lilstock irrigation Mashonaland Central Bindura 140,000,000
Save/Taziwa irrigation Manicaland Chimanimani 72,000,000
Muchekeranwa irrigation Mashonaland East Marondera 144,000,000
Dendere irrigation Masvingo Chiredzi 100,000,000
Katsvenzve irrigation Mashonaland West Zvimba 144,000,000
Morefields irrigation Mashonaland Central Bindura 126,000,000
Emojeni irrigation Mashonaland West Chegutu 120,000,000
Makoshe irrigation Matebeleland South Gwanda 24,000,000
Tugwi Mushandike irrigation Masvingo Masvingo 439,440,648
Portlet irrigation Mashonaland Central Makonde 100,000,000
Osborne irrigation Manicaland Mutate 200,000,000
Mambale irrigation Matebeleland South Matobo 135,000,000
Presidential Drip Irrigation 1,192,000,000
Systems
128
Annexure III: 2023 Priority Infrastructure Projects by Province
2023 TOTAL
PROVINCE DISTRICT PROJECT NAME RESOURCES
ZWL$
129
2023 TOTAL
PROVINCE DISTRICT PROJECT NAME RESOURCES
ZWL$
Harare Munhumutapa Building 3,077,572
African Regional Labour Administar-
Harare 218,000,000
tion Centre (ARLAC)
Harare Northcot Children’s Home 75,000,000
130
2023 TOTAL
PROVINCE DISTRICT PROJECT NAME RESOURCES
ZWL$
National Pharmacetical Company
Harare
Storage facilities 264,064,000
Chitungwiza Central Hospital Reha-
Chitungwiza
bilitation 15,882,000,000
Sally Mugabe Central Hospital Ren-
Harare ovation of adult hospital, wards and
528,000,000
kitchens
Sally Mugabe Central HospitalMaterni-
Harare ty theatre extension
660,000,000
131
2023 TOTAL
PROVINCE DISTRICT PROJECT NAME RESOURCES
ZWL$
Student hostel at Msasa Industrial
Harare
Training College 100,000,000
Rehabilitation of infrastructure at Bel-
Harare
vedere Teachers College (On-going) 50,000,000
Harare Caledonia
100,000,000
Harare Hatcliff
100,000,000
132
2023 TOTAL
PROVINCE DISTRICT PROJECT NAME RESOURCES
ZWL$
Sub-Total
- - 61,694,245,790
133
2023 TOTAL
PROVINCE DISTRICT PROJECT NAME RESOURCES
ZWL$
Buhera Murambinda-Birchenough
1,800,000,000
Mutare Odzi-Marange-Msasa
720,000,000
Manicaland-Mas-
Masvingo - Mutare Road
vingo 1,100,000,000
Victoria Chitepo Provincial Hospital
Mutare
Theatre and Wards 66,000,000
Mutare Equipment
20,000,000
Manicaland State University of
Mutare Applied Sciences (MSUAS) - Student
260,000,000
Residence
134
2023 TOTAL
PROVINCE DISTRICT PROJECT NAME RESOURCES
ZWL$
Female Hostel at Marymount
Mutare
Teachers’ College 100,000,000
Rehabilitation of infrastructure at
Mutare Urban
Mutare Teachers’ College (On-going) 50,000,000
Rehabilitation of infrastructure at
Mutare Urban
United College of Education (On-going) 50,000,000
Baobab Project at Mutare Teacher’s
Mutare Urban
College 50,000,000
B Tech Block at Mutare Polytechnic
Mutare
(On-going) 100,000,000
Mutare Gimboki
100,000,000
Sub-Total
10,470,079,234
Mashonal-
Mazowe Mazowe Training School
and Central 3,350,000,000
Kanyemba Special Service District
Mbire
Office 161,000,000
Kanyemba Special Service District
Mbire
Office 56,000,000
135
2023 TOTAL
PROVINCE DISTRICT PROJECT NAME RESOURCES
ZWL$
Marondera Provincial offices (Animal
Marondera
Extn Services) 109,005,000
136
2023 TOTAL
PROVINCE DISTRICT PROJECT NAME RESOURCES
ZWL$
Bindura Provincial Hospital Theatre
Bindura
and Wards 528,000,000
137
2023 TOTAL
PROVINCE DISTRICT PROJECT NAME RESOURCES
ZWL$
Sub-Total
18,981,465,152
Mashonal-
Mutoko Nyamuzizi Bridge
and East 200,000,000
Beatrice National Rehabilitation
Beatrice
Centre 115,000,000
138
2023 TOTAL
PROVINCE DISTRICT PROJECT NAME RESOURCES
ZWL$
chikomba Chikomba
210,000,000
Sub-Total
18,984,412,472
139
2023 TOTAL
PROVINCE DISTRICT PROJECT NAME RESOURCES
ZWL$
Mashonal-
Chinhoyi Chinhoyi
and West 189,000,000
Zvimba Katsvenzve
144,000,000
140
2023 TOTAL
PROVINCE DISTRICT PROJECT NAME RESOURCES
ZWL$
Emojeni
- 120,000,000
Chinhoyi Crowlands
1,000,000,000
141
2023 TOTAL
PROVINCE DISTRICT PROJECT NAME RESOURCES
ZWL$
Construction of Chegutu Magistrate
Chegutu
Court 40,000,000
Sub-Total
15,699,192,377
Chiiredzi Dendere
100,000,000
142
2023 TOTAL
PROVINCE DISTRICT PROJECT NAME RESOURCES
ZWL$
Tugwi mashandike
- 639,440,648
143
2023 TOTAL
PROVINCE DISTRICT PROJECT NAME RESOURCES
ZWL$
Victoria Falls Special Service District
Victoria Falls
Offices 490,000,000
144
2023 TOTAL
PROVINCE DISTRICT PROJECT NAME RESOURCES
ZWL$
145
2023 TOTAL
PROVINCE DISTRICT PROJECT NAME RESOURCES
ZWL$
146
2023 TOTAL
PROVINCE DISTRICT PROJECT NAME RESOURCES
ZWL$
Sub-Total
470,375,505,252
Matabele-
Gwanda Esigodini District Office
land South 189,000,000
147
2023 TOTAL
PROVINCE DISTRICT PROJECT NAME RESOURCES
ZWL$
Makoshe
- 24,000,000
Mambale
- 135,000,000
Matopo Bulawayo-Khami
2,000,000,000
Bulilima Plumtree-Madlambuzi
1,300,000,000
148
2023 TOTAL
PROVINCE DISTRICT PROJECT NAME RESOURCES
ZWL$
Gwanda State University - Rehabilita-
Insiza
tion of infrastructure (On-going) 100,000,000
149
2023 TOTAL
PROVINCE DISTRICT PROJECT NAME RESOURCES
ZWL$
Sub-Total
22,285,140,824
150
2023 TOTAL
PROVINCE DISTRICT PROJECT NAME RESOURCES
ZWL$
Vungu Maboleni
20,000,000
Sub-Total
8,459,691,366
151
2023 TOTAL
PROVINCE DISTRICT PROJECT NAME RESOURCES
ZWL$
National Mortuaries
330,000,000
152
2023 TOTAL
PROVINCE DISTRICT PROJECT NAME RESOURCES
ZWL$
General Rehabilitation of Mission
Hospitals (St michaels, Zhombe, All
National
Souls,Tshelanyemba, Rusitu, St Lukes, 33,000,000
Mogenster,Marymount )
153
2023 TOTAL
PROVINCE DISTRICT PROJECT NAME RESOURCES
ZWL$
ZPCS - Computerisation project -
National
ZPCS 150,000,000
National Biogas
1,000,000,000
Sub-Total 107,871,380,999
154