0% found this document useful (0 votes)
21 views

Cable Diary

Cable Diary

Uploaded by

UNIVERSAL CHANEL
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
21 views

Cable Diary

Cable Diary

Uploaded by

UNIVERSAL CHANEL
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2

Saudi Electricity Project ‫شركة الكهرباء السعودية لتطوير المشاريع‬

Development
‫إدارة ربط مشاريع الطاقة المتجددة‬
R. E. Interconnection Projects
Department
‫الغربية‬- ‫ربط مشاريع الطاقة المتجددة‬
R. E. Interconnection Projects - ‫والجنوبية‬
WOA&SOA

Cable Diary
CONTRACT NO: CONTRACTOR:
PROJECT NAME: SECTION:
CABLE TYPE: CABLE MANUFACTURER:

Sub Station Breaker No. Joint Bay No. Drum Detail Cutting Length in
(M)
Name of Section No. Section Phase Actual Cable
Date Laid
Circuit Length Length in (M)
From To From To From To Number Length in (M) From To

270 Red
270 Yellow
270 Blue
C1 270 Red
270 Yellow
270 Blue
270 Red
270 Yellow
270 Blue
C2
270 Red
270 Yellow
270 Blue
270 Red
270 Yellow
270 Blue
C3
270 Red
270 Yellow
270 Blue
270 Red
270 Yellow
270 Blue
C3
270 Red
270 Yellow
270 Blue

'
‫شركة الكهرباء السعودية لتطوير المشاريع‬
Saudi Electricity Project Development
R. E. Interconnection Projects Department ‫إدارة ربط مشاريع الطاقة المتجددة‬
R. E. Interconnection Projects - WOA&SOA ‫الغربية‬- ‫ربط مشاريع الطاقة المتجددة‬
‫والجنوبية‬
PROSECT TITLE: 380KVA UGC CONNECTION RELATING TO INTEGRATION OF SHUAIBA PV POWER PLANT
CONTRACT NO. 44000016438 J. O. NO.
CONTRACTOR CEPCO CIRCUIT

INSPECTION REQUEST FOR INTREM MEASURMENT; FINAL MEASURMENT;

INSPECTION REQUEST NO. RE-INSPECTION REQUEST NO.


TIME:______________ DAY:_______________ DATE:________________
PLACE / LOCATION :_______________________________________________________________________________________
REFERENCE DRAWING NO. :_______________________________________________________________________________________
REFERENCE SPECI FICATION :_______________________________________________________________________________________
From_____ to______ Length : (m) Trench Cross Section Size:______X______

I hereby confirm that the mentioned Work was checked by the Contractor and found to comply with SEC Requirements

CONTRACTOR'S QA/QC ENGINEER SIGNATURE:___________________________

CONTRACTOR'S QA/QC ENGINEER NAME :_______________________________


TEL:______________________________ FAX:___________________E-MAIL:_______________________________ DATE:__________

APPLICABLE STANDARD : ....................................................


INSPECT / VERIFY CONTRACTOR SEC OBSERVATION
LOCATION
TRENCH CROSS SECTION
LENGTH OF OPEN TRENCH
NO OF HDD IN TH E ROUTE
TOTAL LENGTH OF HDD
DUCT BANK CONCRETE QUANTITY

APPROVED ROUTE & TRENCH S CROSS SECTION AT EACH ROAD TO BE ATTACHED, EXECUTED WORK SHALL BE INDICATED IN
DIFFERENT COLOUR,HDD & DUCTBANK LOCATIONS SHALL BE INDICATED in the DRAWING SKETCH SHOWING THE HDD LENGTH TO
BE INCLUDED

COMMENTS :_________________________________________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________________
SEC INSPECTOR NAME:________________________________________________
DATE:___________________ TIME:________________ SIGNATURE:_______________________
TEL :___________________ FAX :_______________ E-MAIL:___________________________

APPROVED APPROVED WITH COMMENTS NOT APPROVED, REDO


_______________________________________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________
_________________________________________________________________________________
SEC PROJECT ENGINEER NAME :_________________________________________________
DATE:___________________ TIME:________________ SIGNATURE:_______________________
TEL :___________________ FAX :_______________ E-MAIL:___________________________

Contractor Should at all Time Make Sure That All Necessary Work Permits are Obtained Before Execution of Work and to Make Sure That all Neccessary Coordination
with Other Related Stakeholders are Made Before Hand.

Contractor shall submit the Inspection Request at least 24-hours prior to the inspection time.

You might also like