Renovation Work Programme Example 2

Typical renovation construction work programme to built a laboratory testing workshop including plumbing works, electrical and cabling works, fire system protection, redo flooring and wall finishes, setting up of partition and HVAC

Uploaded by

adrii.pmc
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
75 views

Renovation Work Programme Example 2

Typical renovation construction work programme to built a laboratory testing workshop including plumbing works, electrical and cabling works, fire system protection, redo flooring and wall finishes, setting up of partition and HVAC

Uploaded by

adrii.pmc
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Desmet Ballestra @ Wisma Comcorp, Glenmarie

November 2022 December 2022


Task name Start date End date
07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26

08/11/2022 19/11/2022 Today

1 Mobilisation of work 08/11/2022 19/11/2022 Mobilisation of work 08/11/2022 - 19/11/2022

1.1 Purchase of Workmen Compensation and … 10/11/2022 10/11/2022 P…

1.2 Produce shop drawings/ carpentry details … 08/11/2022 12/11/2022 Produce shop drawin…

1.3 Mobilisation of tools and equipments, ie sc… 10/11/2022 12/11/2022 Mobilisation…

1.4 Daily cleaning 10/11/2022 19/11/2022 Daily cleaning

1.5 Erection of hoarding from cargo lift to mai… 15/11/2022 15/11/2022 Er…

2 Demolition works 10/11/2022 19/11/2022 Demolition works 10/11/2022 - 19/11/2022

2.1 Demolition of partition of existing conferen… 10/11/2022 12/11/2022 Demolition …

2.2 Demolition of existing lower cabinet in fron… 15/11/2022 15/11/2022 D…

2.3 Demolition of main entrance door frame 15/11/2022 16/11/2022 Demoli…

2.4 Demolition of 2'x4' ceiling at new lab and … 14/11/2022 14/11/2022 D…

2.5 Disposal of rubbish into roro bin 11/11/2022 19/11/2022 Disposal of rubbish into roro bin

3 Gypsum board partition 14/11/2022 19/11/2022 Gypsum board partition 14/11/2022 - 19/11/2022

3.1 Site marking 14/11/2022 14/11/2022

3.2 Male Surau 15/11/2022 17/11/2022 Male Surau 15/11/2022 - 17/11/2022

3.2.1 Erection of internal metal stud 15/11/2022 16/11/2022 Erectio…

3.2.2 Closing one side of gypsum partition for… 15/11/2022 16/11/2022 Closin…

3.2.3 Skim coating 17/11/2022 17/11/2022 S…

3.3 Filing room and new walkway area 15/11/2022 19/11/2022 Filing room and new walkway area 15/11/2022 - 19/11/2022

3.3.1 Erection of internal metal stud 15/11/2022 16/11/2022 Erectio…

3.3.2 Closing of one side of partition 17/11/2022 18/11/2022 Closin…

3.3.3 Closing another side of partition 19/11/2022 19/11/2022 C…

3.3.4 Skim coating 19/11/2022 19/11/2022 S…

3.4 New office room 15/11/2022 19/11/2022 New office room 15/11/2022 - 19/11/2022

3.4.1 Erection of internal metal stud for new … 15/11/2022 16/11/2022 Erectio…

3.4.2 Closing of one side of partition 18/11/2022 19/11/2022 Closin…

3.4.3 Closing another side of partition 19/11/2022 19/11/2022 C…

3.4.4 Skim coating 19/11/2022 19/11/2022 S…

3.4.5 Main entrance 15/11/2022 17/11/2022 Main entrance 15/11/2022 - 17/11/2022

3.4.5.1 Erection of internal metal stud for bo… 15/11/2022 16/11/2022 Erectio…

3.4.5.2 Closing of one side of box up 17/11/2022 17/11/2022 Cl…

3.4.5.3 Closing another side of box up 17/11/2022 17/11/2022 Cl…

4 Ceiling finishes works 17/11/2022 19/11/2022 Ceiling finishes works 17/11/2022 - 19/11/2022

4.1 Erection of internal metal stud at lobby 17/11/2022 19/11/2022 Erection of …

4.2 Closing of ceiling plasterboard 17/11/2022 17/11/2022 Cl…

5 Electrical works 16/11/2022 19/11/2022 Electrical works 16/11/2022 - 19/11/2022

5.1 Filing room 16/11/2022 16/11/2022 Filing room 16/11/2022 - 16/11/2022

5.1.1 Pulling of wires in between drywall for p… 16/11/2022 16/11/2022 P…

5.2 Lift lobby, new drinks area and new dis… 16/11/2022 17/11/2022 Lift lobby, new drinks area and new discussion area 16/11/2022 - 17/11/2022

5.2.1 Wall hacking to receive conduit 16/11/2022 17/11/2022 Wall h…

5.2.2 Install conduits and pulling cables 16/11/2022 16/11/2022 In…

5.3 New printer and plotter area 18/11/2022 19/11/2022 New printer and plotter area 18/11/2022 - 19/11/2022

5.3.1 Install conduits and pulling cables 18/11/2022 19/11/2022 Install …

6 Glazing works 17/11/2022 19/11/2022 Glazing works 17/11/2022 - 19/11/2022

6.1 Dismantle existing glass doors 17/11/2022 17/11/2022 Di…

6.2 Measurement for glass partition 18/11/2022 18/11/2022

6.3 Off site fabrication for glass partition 18/11/2022 19/11/2022 Off sit…

7 Plumbing works 14/11/2022 15/11/2022 Plumbing works 14/11/2022 - 15/11/2022

7.1 Hacking for new pipeline to ablution area … 14/11/2022 14/11/2022 H…

7.2 Laying pipes 15/11/2022 15/11/2022 L…

8 Masonry works 16/11/2022 16/11/2022 Masonry works 16/11/2022 - 16/11/2022

8.1 Erection of brick wall for ablution area 16/11/2022 16/11/2022 Er…

9 Tiling works 15/11/2022 15/11/2022 Tiling works 15/11/2022 - 15/11/2022

9.1 Purchase of tiles for ablution area and ne… 15/11/2022 15/11/2022