PPC Unit 5 KMSR
PPC Unit 5 KMSR
Sivaram kotha
Topics:
Definition & Objectives of Scheduling.
Scheduling Terminology
Scheduling Techniques
Definition & Objectives of Line balancing
Terms Used in Line Balancing
Procedure of Line Balancing
Methods/Heuristics of Line Balancing
Definition & Objectives of Scheduling
“ It is defined as arrangement of the jobs in the order of
their priority by fixing time and date when each job is to be
completed.”
• It decides when the work has to start and to end in a
particular day.
• It is one of the important planning function in PPC.
• Scheduling is the final stage in the production planning. It is
the stage at which all the production activities are
coordinated and projected on a time scale. A production
schedule is infact a timetable representing what machine or
department should be doing what and when.
Objectives / policies of Scheduling
• Customer satisfaction
-The prepared schedule should meet the delivery dates of a customer to get
repeated orders.
• Cost optimization
-An ideal schedule should avoid the early or late completion of job.
-Early completion of job increases the cost of carrying work in progress
and finished goods inventory in the organization.
-Late completion of job leads to under utilization of man and machines.
• Increase the efficiency by minimizing the under utilization of the capacity.
• Reduce variances in the transformation process
-There are two major issues during transformation process:
1. Over loading at work center (Job waiting)
2. Lack of sufficient load on the ideal machine.(Machine waiting)
• Employ Focus/skill on Scheduling
Some times scheduler should plan based on the availability of key employ.
Scheduling Terminology
Processing time or Performance time (tj):
It is a time required to process the job “j” which include
both processing time and machine set-up time.
Due date (Dj):
It is a committed time/date at which job “j” is to be
completed.
Completion/Flow Time(Cj or Fj):
• Amount of time at which job “j” spends in a production
system.
• It is a time at which job “j” completed in a sequence.
Cj or Fj = Cj -1+ tj
Job A B C D
Ex:
Processing Time (tj) 10 8 5 15
Due date(Dj) 15 11 6 17
Critical Ratio(CRj ) 1.5 1.37 1.2 1.13
A Roll dough 60 -
C Sprinkle cheese 35 B
D Add sausage 25 C
E Add pepperoni 35 C
F Add mushroom 22 C
H Add label 23 G
• Line efficiency
• Smoothing index
GATE Qns
1. In an assembly line for assembling toys, five
workers are assigned tasks which take times
of 10, 9, 7, 9 and 8 min respectively. The
balance delay for line is
A) 43.3% B) 14.8% C)14% D)6.3%
2. If the number of workstations are 5, cycle
time 20 min. And total work content is 80
min. what will be the value of balance delay
and line efficiency in percentage?
A) 30,70 B) 20,80 C) 80, 20 D) 70,30
GATE Qns
3. A line balancing analysis resulted in a
procedure grouping as shown below:
Work centre Time(min) Activity number
A 1.4 1,2
B 1.1 3,5,6
C 0.9 4,7
D 1.6 8,10,11
E 1.5 9
Follow-up :
• The follow-up phase is the most important step of
production control.
• This function is carried out by “follow-up man”.
• The follow-up men will check continuously whether the
planned activities are carried out at planned place, time and
with planned material or not.
• They act as intermediaries between various departments.
Follow-up Contd.
• The follow-up phase consist of :
1. Progress Reporting
(a) Data collection (b) Data interpretation
2.Corrective action
(a) Expediting (b) Replan.
• Data collection : The data about the progress of the work should
be collected. The collected data may include
(i) Job identification (order number and identification number)
(ii) time of report
(iii) completion of work
- This collected data may be transmitted by
(i) Written system
(ii) Oral system(telephone, radio etc)
(iii) Electronic system.
Follow-up Contd.
Data interpretation :
• Includes comparing the actual data with the planned data to
find the deviations.
• These deviations can be occurred due to
- shortage of tools & materials,
- equipment breakdown,
- excessive rejection,
- accumulation of in process inventory and
- errors in planning,
- labor turn over & mass absentees, lack of necessary
instructions, late starting of work, unexpected rush orders
change in priority of orders.
Follow-up Contd.
Expediting
• PPC function requires the function “Expediting”, when the actual
progress of the work is lagging behind the planned work.
• It is necessary when the delays and interruptions are causing
delay in meeting the delivery dates.
Expediting function may include the following ways to rush up jobs
for it’s timely completion.
• Change in priority from low priority to delayed production
orders.
• Engaging additional personnel and equipment.
• Sub contracting the workers with in the organization or from the
outside.
• Hiring capacity to rush up the jobs.
Expediting Contd...
• Overtime working.
• Overlapping the remaining operations by reducing the cycle
time at each work station.
• Job splitting
• Alternative routing
• Increasing speeds and feeds.
Reasons for Existence of Control function
• Delay in supply of raw materials to the production shop.
• Excessive absenteeism of workers causing idling of
machines and upsetting the production schedule.
• Change in design specifications and route cards or process
plans.
• Change in delivery schedule demanded by customers.
• Break-down of machines, tools and equipments.
• Break-down of tools, jigs and fixtures
• Error in design drawings and process plans.
Applications of Computers in PPC
“Use of computers can supply the relevant information in
Production Planning and Control”.
1. Simple stock control and reordering problem.
2. Order analysis problem
3. Scheduling problem
4. Operation details and Bill of materials problem
5. Capacity loading problem
6. Work order documentation problem
7. Integration of production control and other control
functions.