Measurement and Billing
Measurement and Billing
Introduction
Like most businesses, construction depends on cash flow. As a result, terms of and
procedures for payment are of extreme interest to all concerned.
Most contracts specify the procedures for submitting an application for payment and specify
when the owner must pay the contractor. The same is true of contracts between general
contractors and subcontractors. Many sub-contracts have “pay when paid” (or the harsher
“pay if paid”) clauses which means that subcontractors will be paid when the owner pays the
GC (or within a reasonable period).
Progress payment, also known as interim payment, is a payment made to a contractor during
the construction process for work that has been completed or for materials that have been
delivered to the site. Progress payments are typically made on a regular schedule, such as
monthly or at certain stages of the project, and they are usually based on the percentage of
work completed or the value of the materials delivered.
Methods of payment
Several methods of payment are available for construction work, depending on the project
delivery method, the owner’s financial conditions, and the arrangements made for payment
and payment frequency. The most common method of payment in commercial building
construction in the traditional owner-contractor contract, is by monthly progress payments,
which are partial payments for work completed during a portion, usually a month, of the
construction period. By agreement, this payment frequency can be modified. In India, there
are several payment processes available for construction projects. Some common methods
include:
1. Advance Payment: This is a payment made by the client to the contractor before the
work begins.
2. Running Account: This is a payment made to the contractor as the work progresses. It
the standard approach for progress payments. Typically, the general contractor is paid
monthly for all work completed during that billing period.
3. Retention Money: This is a percentage of the contract value that is withheld by the
client as a guarantee for the satisfactory completion of the work.
4. Payment against Performance Guarantee: This is a guarantee provided by a bank or
financial institution to the client, assuring the satisfactory completion of the work by
the contractor. Usually, retention amount is released by client in lieu of Performance
Bank Guarantee.
5. Milestone Payment: This is a payment made by the client to the contractor based on
the completion of specific milestones in the construction project. For example,
completion of the foundation, closing in the structure, or completing a floor might all
generate payments. The milestones are determined and agreed to at the time the
construction contract is signed.
6. Final Payment: This is the final payment made by the client to the contractor after the
completion of the work.
As the monthly progress payment is the most common method of payment, typical building
construction projects, our discussions will primarily deal with procedures concerning these
periodic payments.
Progress Payments
Progress payments reflect payment for the work in place and material delivered during the
applicable period. Under the progress payment method, an estimate of the work complete is
made and payment is made for that amount. Most contracts deduct an amount for retainage
(Retention Amount) from the amount earned during the period. Retention is an amount held
by the owner until the final completion of the contract. It can be held for a number of reasons,
depending on the owner and the owner’s contracting rules. In some cases, retention is held by
the owner to complete the project, if necessary. Some owners, particularly public owners,
retain an amount as a reserve fund to cover materialman and subcontractor liens on the
project. Varying amounts of retainage are held by owners, usually 5 or 10 percent. This
amount is expressed in the contract documents and is established in the agreement between
the owner and contractor. Some contracts do not retain funds, as the performance bank
guarantee is intended for the same purpose as retention. When retention is held, it is normally
released in the final payment, when the contract requirements are completed.
Material delivered to the site, even when not actually incorporated into the work, is usually
included in the progress payments. Special care is normally taken to inventory the material
stored at the jobsite. Some owners will also include material stored away from the jobsite in
the progress payment, with special provisions. It is necessary to assure the owner that the
material is insured and will be installed during the project. Some reluctance may occur on the
owner’s part in paying for material stored off-site that could be used for other projects. The
owner’s primary concern with stored material is whether it will actually be incorporated into
the project.
Varying method of inspection and verification are done by the owner to determine accuracy
of the payment request. This verification process, also referred as Bill Certification, can vary
from a meticulous measurement of work in place and material stored to an approximation of
the percentage completed for the activities. Owners and their agents, such as architects,
engineers and construction managers, are concerned that the proper amount be paid, without
overpayment.
The actual payment period varies from contract to contract. The frequency of payment is
generally on a month, or 30-day, basis, but the actual cutoff dates can vary. Generally, the
payment period extends from the first to the last day of the month. There are however, many
variations regarding the exact start and cutoff date, depending on the owner’s processing
requirements. If the owner requires the verified payment on the first day of the month, the
actual cutoff dates may be twentieth day of the month to facilitate compilation and review the
progress payment request. This type of payment period is relatively easy to incorporate into
the project procedures however each supplier and subcontractor must be made aware of the
cutoff dates used for the project.
Example:
A) CPWD progress payment procedure
The Central Public Works Department (CPWD) is responsible for the construction and
maintenance of government buildings in India. The CPWD has a specific procedure for
progress payments to contractors. The procedure is as follows:
1. The contractor submits an invoice for the work completed to the CPWD, which is
then examined by the CPWD's Engineer-in-Charge (EIC) and the Assistant Engineer
(AE).
2. The EIC and AE assess the work completed and certify that it is in accordance with
the contract and the approved drawings.
3. The EIC and AE then calculate the value of the work completed based on the
Schedule of Rates (SOR) and the approved drawings.
4. The EIC and AE then prepare a certificate of the value of the work completed and
submit it to the CPWD's Executive Engineer (EE).
5. The EE then approves the certificate of the value of the work completed and forwards
it to the CPWD's Chief Engineer (CE).
6. The CE then approves the certificate of the value of the work completed and forwards
it to the CPWD's Director General (DG) for final approval.
7. Once the DG approves the certificate of the value of the work completed, the CPWD
will release the payment to the contractor.
8. The contractor should also submit a statement of account, including the work carried
out, the value of work completed, the amount paid and the balance remaining.
It is important to note that the payment is made based on the work completion percentage,
and the payments are made on the certification of the executive engineer and the chief
engineer.
Additionally, retention money is also held back by CPWD, it is generally 10% of the bill
amount and is released only after the defects liability period (DLP) is over.
First and Final Bill Payments (Form No. 24)
Form No. 24 is used for making payments both to contractors for work and to suppliers. A
single form may be used for making payment to several payees, if they relate to the same
work (or to the same head of account in the case of supplies) and are billed for at the same
time. Specimen of First and Final bill form is as mentioned below:
The construction progress payment procedure can differ between government and private
construction projects in a few ways:
Table 1: Difference between Government (Public) construction project and Private
construction project payment procedure
Government (Public) construction project Private construction project
1. Government projects typically have 1. In private construction projects, the
more strict regulations and payment process is often more
procedures in place for progress flexible and can be negotiated
payments, which can include between the contractor and the
specific forms that need to be filled client. The payment terms are
out and submitted, and detailed usually included in the contract and
documentation that needs to be can be based on a variety of factors,
provided to support payment claims. such as the completion of specific
2. In government projects, payments milestones, the submission of
are often made on the basis of the invoices, and the client's cash flow.
work done, as per the schedule of 2. In private construction projects,
rates, which is a document that lists payments can be made on mutually
the rates for different types of work. pre-decided (as per contract terms)
The schedule of rates is usually based on the work done, material
prepared by the government agency supplied, keeping in mind the agreed
in charge of the project, and it is Bill of Quantities (BOQ).
binding on the contractor. 3. In private construction projects the
3. Government projects may also have payment process may not be as
a formal system for approving strictly regulated as in government
payments, which can involve projects, which can allow for more
multiple levels of review and flexibility and faster payments.
approval. This can slow down the However, this also means that there
payment process and make it more may be a higher risk of disputes and
complex. disagreements between the
contractor and the client.
It's important to note that the payment process may vary depending on the specific laws and
regulations of the region, and the contract agreement between the parties involved in the
project.
Common Disputes related to progress payments
Some common disputes that can arise in relation to construction progress payments include:
1. Disagreements over the value of work completed: This can happen when the
contractor and the client disagree on the amount of work that has been completed and
the associated costs.
2. Delays in payment: This can happen when the client is slow to approve and make
payments, causing financial difficulties for the contractor.
3. Disputes over the quality of work: This can happen when the client is not satisfied
with the quality of the work and refuses to make payments until the issues are
resolved.
4. Disputes over change orders: This can happen when the client requests changes to the
scope of work and the contractor is not willing to make the changes without additional
compensation.
5. Retention money disputes: This can happen when the client hold back a percentage of
the payment and release it after a certain period of time, and the contractor disputes
the release of the retention money.
The R.A. bill computation is shown in Table B. The computation for cash inflow for the
contractor is shown in Table C.
Reconciliation
Payment to be received for work done Rs. 76,25,000
Less TDS at 2% (-) Rs. 1,52,500
Less advance payment (-) Rs. 5,00,000
Less materials issued by owner (-) Rs. 3,20,000
Actual payments to be received Rs. 66,52,500
Actual payments made Rs. 11,37,000 + Rs. 20,83,000 + Rs. 17,53,000 + Rs. 9,17,000 +
Rs. 7,62,500 = Rs. 66,52,500 (Hence, reconciled)
The cash inflow diagram for the contractor is as shown in Figure 4.
Table C. Computation of Cash inflow
A contractor is also supposed to pay to his subcontractors, suppliers for the materials, and
labour for the work done during a month. These factors are taken into account while
preparing the cash outflows of a contractor. The computation for cash-flow diagram is
performed in Table D.
Based on the above computation, the cash outflow diagram for the contractor is shown in
Figure 5.
Table Computation for cash outflows
Net cashflow is calculated using Net cashflow = (Cash inflow – Cash outflow) and the net
cashflow diagram for contractor is shown in Fig. 6.
Fig.6. Net cashflow diagram for the contractor
Additional readings:
Mincks, W. R., & Johnston, H. (2016). Construction Jobsite Management. Chapter 17 – Progress
Payments. Cengage Learning.
Jha, K. N. (2015). Construction Project Management: Theory and Practice. Pearson Education India.