Mitigation
Mitigation
AIR QUALITY
- Water or dust palliative(screen) should be applied to exposed soil surfaces at the construction
site(s) and equipment as frequently as necessary to control fugitive dust emissions.
- Soil binder should be spread on any unpaved roads used for construction purposes, and all
construction parking areas.
- Trucks should be washed off as they leave the construction site(s), as necessary, to control
fugitive dust emissions.
- Construction equipment and vehicles should be properly tuned and maintained. Low sulfur fuel
should be used in all construction equipment.
- Track-out reduction measures such as gravel pads should be used at access points to minimize
dust and mud deposits on roads affected by construction traffic.
- Transported loads of soils and wet materials should be covered prior to transport, or adequate
freeboard (space from the top of the material to the top of the truck) should be provided to
reduce deposition of particulate during transportation.
- Dust and mud that are deposited on paved, public roads due to construction activity and traffic
should be removed to decrease particulate matter.
- To the extent feasible, construction traffic should be routed and scheduled to reduce
congestion and related air quality impacts caused by idling vehicles along local roads during
peak travel times.
- Grading and earth moving should be suspended when wind gusts exceed 25 mph unless the soil
is wet enough to prevent dust plumes.
WASTE
- Soil sampling should be conducted in areas within the Area proposed to be disturbed and/or
excavated prior to soil export, reuse, or disposal to characterize the soil for the presence of
hazardous materials (e.g., metals, petroleum hydrocarbons, volatile organic compounds,
pesticides, etc.).
- Prior to renovation or demolition of existing structures, surveys should be conducted to
evaluate the presence, locations, and quantities of hazardous building materials.
- Prior to commencement of excavation activities, a Site and Community Health and Safety Plan
should be prepared to manage potential health and safety hazards to workers and the public.
- Prior to commencement of excavation activities, a Soil Management Plan should be prepared to
address the notification, monitoring, sampling, testing, handling, storage, and disposal of
contaminated media or substances that may be encountered during construction activities.
- Prior to commencement of excavation activities, a Groundwater Management Plan should be
prepared to address the notification, monitoring, sampling, testing, handling, storage, and
disposal of potentially contaminated groundwater.
- Contract specifications should include references to the potential to encounter contaminated
soil, groundwater, or other regulated wastes during construction activities.
- If contaminated soil is present, appropriate abatement actions should be implemented in
accordance with applicable regulatory requirements.
NOISE
- Construction vehicles and equipment noise would be reduced using properly sized and
maintained mufflers, engine intake silencers, and engine enclosures.
- Equipment could also be turned off when not in use and activities could be confined to
between 7 am and 7 pm.
- Where sheet piles are needed and soil conditions allow, vibratory pile drivers would be used
instead of impact pile drivers.
- Stationary construction equipment would be located away from sensitive receptors, such as
residences, where possible.
- Where this is not possible or where noise impacts are still substantial, portable noise barriers
could be placed around equipment with the opening directed away from sensitive receptors.
- Construction specifications would provide that noise levels for scrapers, pavers, graders, and
trucks should not exceed 90 dBA, and pile drivers should not exceed 95 dBA at 15M as
measured under the noisiest operating conditions.
- For all other equipment, specifications would provide that noise levels should not exceed
85 dBA.
- Substituting hydraulic or electric models for impact tools such as jack hammers
and pavement breakers would further reduce construction noise.