0% found this document useful (0 votes)
17 views3 pages

SAIC M 1001rev4

SAIC-M-1001rev4

Uploaded by

Enrique Ga
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
17 views3 pages

SAIC M 1001rev4

SAIC-M-1001rev4

Uploaded by

Enrique Ga
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - March 2010) Rev 4 31-Mar-10

SAIC NUMBER DATE APPROVED QR NUMBER


SAUDI ARAMCO INSPECTION CHECKLIST
Fence and Gate Components Receiving Inspection- Types I -
SAIC-M-1001 31-Aug-11 CIVIL-
V Fences
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.

LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.

SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?

SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

A General Fence Components Receiving Inspection

Saudi Aramco Security Fencing Type I shall be used for all facilities SAES-M-006
A1
where security is of concern. Sec. 4.3

Use of Reclaimed material is not permitted unless written approval is SAES-M-006


A2
obtained from Proponent Organization. Sec. 4.2

Galvanized fabric and hardware shall be used for all inland locations SAES-M-006
A3
(more than 1.5 km from the sea). Sec. 4.5

Vinyl-clad fabric, barbed wire, tension wire, tie wire and gate infilling shall SAES-M-006
A4
be used on all locations within 1.5 km from the sea. Sec. 4.5

Types of Saudi Aramco fencing and their appurtenances:


Fence Height Top Brace Post Barbed Wire Number Continuous
Type Fabric Rail For Each Number of of Barbed Concrete
(mm) Line Post Arms Wires Anchor SAES-M-006
A5 I 2.4m Yes Yes 2 6 Yes Sec. 4.9
II 2.4m Yes Yes 2 6 No Table 1
III 2.4m No No 2 6 No
IV 2.4m No No 1 3 No
V 2.4m No No 0 0 No

B Gates and Components Receiving Inspection

Applicable Gate Sizes:


Fence Gate Walk/ Width Overall Gate Frame Gate Post
Type Type Drive opening Height Extensions O.D.(mm)
I,II,III,IV,V A Walk 1.2m 2.45m No 73
SAES-M-006
B Drive 4.0m 2.8m Yes 102
B1 Sec. 4.10
I,II,III,IV C Drive 7.3m 2.8m Yes 102
Table 1
V D Drive 4.0m 2.45m No 102
E Drive 7.3m 2.45m No 102

Note: Width opening is measured from inside to inside of the gate posts.

SASD-AB-
B2 Gates shall be framed with a minimum of 48mm O.D. steel pipe.
036679 Sht. 1

Page 1 of 3
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - March 2010) Rev 4 31-Mar-10
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Fence and Gate Components Receiving Inspection- Types I -
SAIC-M-1001 31-Aug-11 CIVIL-
V Fences
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

SASD-AB-
B3 Gates shall have 10 mm diameter adjustable diagonal tension rods.
036679, Sht. 1

Gates shall be equipped with attachments for padlocking, the padlock to SASD-AB-
B4
be accessible from both sides of the gate. 036679, Sht. 1

Gates shall be equipped with 35mm diameter plunger rod for each gate SASD-AB-
B5
leaf. 036679, Sht. 1

Gate leaves shall be equipped with a plunger rod receiver and open-gate SASD-AB-
B6
holders. 036679, Sht. 1

Tee with truss rod connections are required on gates over 1850mm with SASD-AB-
B7
900mm to 1550 mm panels. 036679, Sht. 1

SASD
Materials for Saudi Aramco Security Fencing & Gates comply with SASD
B8 AE-036881,
AE-036881, Sheet 1 to Sheet 9
Sht. 1 to Sht. 9
SASD
Materials for Saudi Aramco Type II Fence & Gates comply with SASD
B9 AE-036882,
AE-036882, Sheet 1 to Sheet 9
Sht. 1 to Sht. 9
SASD
Materials for Saudi Aramco Fence Type III & Gates comply with SASD
B10 AE-036883,
AE-036883, Sheet 1 to Sheet 8
Sht. 1 to Sht.8
SASD
Materials for Saudi Aramco Fence Type IV & Gates comply with SASD
B11 AE-036884,
AE-036884, Sheet 1 to Sheet 8
Sht. 1 to Sht.8
SASD
Materials for Saudi Aramco Fence Type V & Gates comply with SASD
B12 AE-036904,
AE-036904, Sheet 1 to Sheet 8
Sht. 1 to Sht.8

C Fence Post Receiving Inspection

Post Lengths: Length of Posts (mm)


Fence Type: I II III IV V
Walk Gate 3400 3400 3400 3400 3400 SAES-M-006
Drive Gate 3900 3900 3900 3900 3900 Sec. 4.11 Table 3
Line 3400 3400 3400 3400 3400 & SASD-AC-
C1
Corner/End 3400 3400 3400 3400 3400 036680 Sht. 1
Brace 2900 2900 2900 2900 2900

Note: Post Lengths (Heights) are subject to a +/- 12mm tolerance; These
lengths include 975 mm extension in the footing.

D Fencing Fabric and Fittings Receiving Inspection

Wire fencing fabrics shall be 2.400 (+/- 12mm) meter high, have a 50mm
diamond mesh, the top and bottom selvages shall be machine twisted SASD
D2 with the wire cut to form a barbed wire finish, Vinyl Clad or Galvanized, AE-036881
meeting SAMS Number 12-679-440 or 12-679-410; Standard roll lengths Sheet 4
15m.

Page 2 of 3
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - March 2010) Rev 4 31-Mar-10
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Fence and Gate Components Receiving Inspection- Types I -
SAIC-M-1001 31-Aug-11 CIVIL-
V Fences
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

Galvanized Tension wire shall be used top and bottom in type III, IV and SASD AB-
V fencing and at the bottom only for type II fencing; shall be SAMS 036677, AE-
D3 Number 12-711-585, having a minimum of 4.5mm nominal wire 036882 to
diameter, galvanized with not less than 244g/m 2 of zinc. 036884 & AE-
(SASD AB-036677, AE-036882 to 036884 & AE-036904) 036904
Vinyl-Clad Galvanized Tension wire shall be used top and bottom in type
SASD AB-
III, IV and V fencing and at the bottom only for type II fencing; shall be
036677,
SAMS Number 12-711-585, having a minimum of 3.55mm nominal core
D4 AE-036882 to
wire diameter, galvanized with 244g/m 2 of surface area with additional
036884
PVC or Vinyl coating. (SASD AB-036677, AE-036882 to 036884 & AE-
& AE-036904
036904)
SASD AB-
Galvanized Tie Wire 3.0mm minimum nominal diameter shall be
036677,
provided in 250mm lengths + 10mm long, with 244 g/m 2 galvanization,
D5 AE-036882 to
meeting SAMS number 12-711-600. (SASD AB-036677, AE-036882 to
036884
036884 & AE-036904)
& AE-036904
Vinyl-Clad Tie Wire 2.65mm core wire minimum nominal diameter shall
SASD AB-03667,
be provided in 250mm lengths + 10mm long, with 85.4 g/m 2
AE-036882 to
D6 galvanization, with a top coating of either 0.2mm (8mil) of fusion bonded
036884
PVC or 0.5mm (20mil) of extruded Vinyl; SAMS number 12-711-600.
& AE-036904
(SASD AB-03667, AE-036882 to 036884 & AE-036904)

REMARKS:

REFERENCE DOCUMENTS:
1- SAES-M-006 -- Saudi Aramco Security and General Purpose Fencing, 16 September 2008
2- SASD-AA-036678 Rev. 1 -- Saudi Aramco Security and General Purpose Fencing Post and Fabric Details, 01 May 1990
3- SASD-AB-036677 Rev. 2 -- Saudi Aramco Security and General Purpose Fencing, An Overview (Architectural), 01 April 1990
4- SASD-AB-036679 Rev. 1 -- Saudi Aramco Security and General Purpose Fencing Gate Details, 01 May 1990
5- SASD-AC-036680 Rev. 3 -- Saudi Aramco Security and General Purpose Fencing Footing Details, 01 April 1997
6- SASD-AE-036881 Rev. 4 -- List of Material for Saudi Aramco Security Fencing, 01 November 1993
7- SASD-AE-036882 Rev. 4 -- List of Material for Saudi Aramco Type II Fencing, 01 November 1993
8- SASD-AE-036883 Rev. 4 -- List of Material for Saudi Aramco Type III Fencing, 01 November 1993
9- SASD-AE-036884 Rev. 4 -- List of Material for Saudi Aramco Type IV Fencing, 01 November 1993
10- SASD-AE-036904 Rev. 3 -- List of Material for Saudi Aramco Type V Fencing, 01 December 1993

Contractor / Third-Party Saudi Aramco


Construction Representative* PMT Representative
Work is Complete and Ready for Inspection: T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Inspector PID Representative


Performed Inspection Work / Rework May Proceed T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Supervisor Proponent and Others


Quality Record Approved: T&I Witnessed QC Record Reviewed Work Verified
Name, Organization,
Name, Sign and Date:
Initials and Date:

*Person Responsible for Completion of Quality Work / Test Y = YES N = NO F = FAILED