Utility Solar Station Feasibility Study
Utility Solar Station Feasibility Study
XXXX Station
100MW Solar PV Plant Project Feasibility Study Report
LEGAL INFORMATION
By accepting this certain document of CORPORATION you agree to the following terms. If you do not
agree to the following terms, please notice that you are not allowed to use this document.
Copyright © 2022 CORPORATION. Any rights not expressly granted herein are reserved. This
document contains proprietary information of CORPORATION. Any reproduction, transfer,
distribution, use or disclosure of this document or any portion of this document, in any form by any
means, without the prior written consent of CORPORATION is prohibited.
and are registered trademarks of XX CORPORATION. company name, logo and product names
referenced herein are either trademarks or registered trademarks of CORPORATION. Other product
and company names mentioned herein may be trademarks or trade names of their respective owners.
Without the prior written consent of CORPORATION or the third party owner thereof, anyone’s access
to this document should not be construed as granting, by implication, estoppel or otherwise, any
license or right to use any marks appearing in the document.
The design of this product complies with requirements of environmental protection and personal
security. This product shall be stored, used or discarded in accordance with product manual, relevant
contract or laws and regulations in relevant country (countries).
This document is provided “as is” and “as available”. Information contained in this document is subject
to continuous update without further notice due to improvement and update of CORPORATION’s
products and technologies.
I
100MW Solar PV Plant Project Feasibility Study Report
Revision History
Author
Prepared
Date Document Version Reviewed by Approved by
by
2014-9-18 V1.00
100MW Solar PV Plant Project Feasibility Study Report
TABLE OF CONTENTS
1 Introduction..................................................................................................... 1
III
100MW Solar PV Plant Project Feasibility Study Report
V
100MW Solar PV Plant Project Feasibility Study Report
13 Environment Protection and Soil & Water Conservation Design ............ 138
13.1 Environment Protection Design..................................................................... 138
13.1.1 Main Impact on Environment ........................................................................ 138
13.1.2 Design and analysis of environmental impact during operation period .......... 143
13.1.3 Conclusion and Suggestion of Environment Protection Design ..................... 147
13.1.4 Environment Protection Design..................................................................... 148
13.2 Design of Water and Soil Conservation ........................................................ 149
13.2.1 Types of Soil and Water Loss and Current Situation ..................................... 149
13.2.2 Prediction of Water and Solid Erosion........................................................... 149
13.2.3 Control Measures for Water and Soil Erosion ............................................... 150
13.2.4 Responsibility Scope and Control Division of Soil and Water Loss Prevention
151
13.2.5 Prevention Measures of Area Division .......................................................... 153
13.2.6 Analysis and Evaluation of Soil and Water Conservation for the Main
Engineering .................................................................................................. 157
13.2.7 Water and Soil Conservation Design ............................................................ 158
100MW Solar PV Plant Project Feasibility Study Report
VII
100MW Solar PV Plant Project Feasibility Study Report
FIGURES
IX
100MW Solar PV Plant Project Feasibility Study Report
TABLES
XI
100MW Solar PV Plant Project Feasibility Study Report
1 Introduction
With the increasing depletion of global energy resource and rising continuing of
global energy prices, as well as increasing impact of the environmental
pollution of traditional fossil, various governments and enterprises continuously
strengthen the clean energy and energy-saving technology investment and
development; while solar energy as a green, renewable, huge potential of
clean energy, has become the focus of global concern, is the new driving force
for economic development.
With the rapid development of society, the demand for electricity is growing
fast, while photovoltaic power solutions is one of the important ways to
effectively ease the power supply tension; while governments tax breaks and
subsidies, declining electricity costs provides a solid foundation for the
development of photovoltaic power generation market provides. More and
more countries have begun to implement "Project Sunshine." The figure is the
forecast data of global solar capacity between 2013-2015 from IMS report.
Global solar power development is very rapid.In 2013, the new global PV
installed capacity is nearly 37GW, of which China's installed capacity is nearly
12GW, accounting for nearly 30% share.China is in the forefront in the field of
photovoltaic applications, and it also laid a solid foundation for Chinese
enterprises to move towards global photovoltaic field. From 2014 to 2015, the
global PV installed capacity will continue to maintain two-digit growth rate.
1
100MW Solar PV Plant Project Feasibility Study Report
2 Comprehensive Description
The Republic of Zimbabwe, covering an area of more than 390,000km2, is a
landlocked country located in the south east of the Africa. It is to the west of
Mozambique and borders the South Africa at the south and the Botswana and
Zambia at the west and the northwest. It boards the Mozambique at the east,
Botswana at the southwest and connects with the South Africa at the south in
some part with the Limpopo River as the border. Most part of Zimbabwe is
plateau, with an average elevation of more than 1,000m. Its terrain can be
divided into three kinds including high-level prairie, middle-level prairie and
low-level prairie.
PV power plant project is proposed to be built about 10~15km from the south
of Munyati city. Its geographic coordinates are between the east longitude
29.79°, and south latitude 18.67°. It is close to towns, and transportation is very
convenient. The supporting projects include a 132kV step-up station, a 33kV
switchgear, complex building, 100 sets of photovoltaic arrays, road works, etc.
For this project, a line of 132kV, 10~15km in length will be set up to connect it
to a 132kV substation in thermal power plant. The above is only the primary
recommendation. The determination of grid connection point will be subject to
100MW Solar PV Plant Project Feasibility Study Report
the final approval documents from the competent authority of local grid. As the
bid for invitation does not provide the accurate data for climate, geographical
position, geology and power grid, this feasibility study report will be based on
the conventional assumption in these respects, therefore, there might be some
errors between the plan and the expense budget.
The content of the feasibility study includes: solar resource analysis, geology of
the project, project task and size, overall scheme design of the system and
generation capacity calculation, electrical design, civil project, construction
method, environmental impact assessment, and energy saving and
consumption reduction analysis after the building of PV power plant, project
investment estimate and fund raising scheme, etc.
3
100MW Solar PV Plant Project Feasibility Study Report
2、The project design shall consider the impact of metrological factors on the
operation efficiency of PV power plant, such as air temperature, wind speed,
floating dust, so as to take the preventive measures.
The gravel layer of the site stratum is evenly, continuously, compactly and
stably distributed, with good physical mechanics properties. The characteristic
value of the foundation carrying capacity fak=150kPa.
3. The site soil is slightly corrosive to concrete structure, and the rebar in
reinforced concrete structure. In accordance with relevant provisions of
international standards, corresponding anti-corrosive measures shall be taken.
4. The site has no adverse geological phenomenon like debris flow, slide
landslide and Karst.
5. The above is not based on survey and therefore is only our assumption.
There may be difference between the civil project and the physical presence.
100MW Solar PV Plant Project Feasibility Study Report
2.4 Electricity
The planned capacity of PV power plant is 100MWp, and will be finished in one
phase. For this project, a line of 132kV, 10~15km in length will be set up. The
above is only the primary recommendation. The determination of grid
connection point will be subject to the final approval documents from the
competent authority of local grid.
The PV power plant adopts only one 132kV overhead line which is of the lead
type LGJ-300, 10~15km in length.
dispatch and operation. The real-time date and information collected by the
station will be sent to the superior dispatch center after data processing.
There are two parts of matched construction: production and living area, and
photovoltaic array area. The 33kV switch station, complex building, arrival
roads, etc. are built in the production and living area. The photovoltaic array
area includes solar PV array, box-type substation, inverter room, cable trench,
etc. The solar PV array generates power adopting one 1MWp sub-system, and
there are 100 units. According to the site terrain, the area is arranged in a
rectangular shape, the production and living area is located at the west of the
photovoltaic array area, and the entrance and exit of the power plant is located
in the west of the management area, and is connected with the roads outside
the site. The total land occupation area of the power plant is 1, 5000, 000m2.
The complex building has one floor, and there is centralized control room,
office room, meeting room, communication room, activity room, kitchen, dining
hall, water pump room, mechanical overhauling shop, gasoline room, garage,
staff dormitory, etc.
The firefighting design follows the policy of “people oriented, prevention first,
and firefighting combined”, and is based on “self prevention and self rescue”.
During arrangement, the firefighting access is considered, so the rescue
personnel and the mechanical equipment can pass through when the fire
occurs. The process design, material and equipment selection, plane
arrangement and firefighting access are implemented in accordance with
relevant firefighting regulations. The equipment adopts the fireproof equipment
(including cables). The advanced fireproof technology and novel fireproof
material are adopted, so as to realize the purposes of safety, convenient use,
economy and reasonableness.
100MW Solar PV Plant Project Feasibility Study Report
The traffic roads in the photovoltaic power plant are arranged in the combining
way of construction roads and overhauling roads.
To fully utilize the human and management resources, realize the specialized,
standard, specified and modern construction management, and improve the
overall business management level and economic benefits, the construction
party is responsible for fully managing the project. In the operation period, the
whole photovoltaic power plant is uniformly managed, the staffing is minimized,
and the management efficiency is improved.
7
100MW Solar PV Plant Project Feasibility Study Report
The 33KV switch station is designed in accordance with the principle of “few
people on duty”. After the electrical and mechanical equipment of the
photovoltaic power plant (including 33kV switch station) enters the stable
operation period, the 33kV switch station can be managed in accordance with
the principle of “unmanned watching, and few people duty”.
The area of the project has fewer human activities, and has no natural
protection areas, traveling development areas and other environment sensitive
areas, and the ecological environments basically belongs to the primary state.
Some building garbage and living garbage may be generated in the building
process. Certain damage and influence on the local plants, ground surfaces
and soil layers can be caused due to treading by construction personnel and
rolling by construction machinery. Since the construction period is short, the
construction personnel are dispersive and various environment protection
measures are taken in the construction project, the influence on the local
ecological environment is minimized.
The main prevention objects of labor safety include fire, explosion, electrical
damage, mechanical damage and falling damage, and the main prevention
objects of industrial sanitation include noise, vibration, temperature, humidity,
dust, dirt, poison, corrosion, electromagnetic irradiation, lighting, illumination,
etc. After the project is built, according to the specifications and regulations,
the advanced production system is established, and the relevant costs for
safety education and training of production and operation personnel, and other
relevant costs for production safety and accident prevention are determined.
The safety and sanitation management organization must uniformly consider
the whole production and management organization and personnel
arrangement of photovoltaic power plant. After the project generates power
and is put into service, one set of complete safety and sanitation management
organization, systems and measures must be established, so as to ensure the
smooth operation of the photovoltaic power plant, and reach the safety
production.
The safety and sanitation management organization for the photovoltaic power
plant is set, and is responsible for the education, training and management of
safety and sanitation after the project is put into service. The safety personnel
of production department are determined, with one part-time personnel for the
daily labor safety and industrial sanitation works.
The solar energy is the green clean energy source. This project belongs to the
renewable energy source development project, meets the industry policies,
simultaneously meets the social sustainable development, and is obvious in
environment benefits and social benefits. This project adopts the advanced
and feasible electricity-saving, water-saving and raw material-saving measures,
reasonably utilizes the energy sources and resources, and strictly implements
9
100MW Solar PV Plant Project Feasibility Study Report
In accordance with the total radiation data of Munyati Metrological Station, the
average annual radiation of Munyati area in the past twenty years is
2128.1kWh/m2.The Munyati area falls in the area with rich solar resource.
The project design shall consider the impact of metrological factors on the
operation efficiency of PV power plant, such as air temperature, wind speed,
floating dust, so as to take the preventive measures.
11
100MW Solar PV Plant Project Feasibility Study Report
4 Project Geology
4. Find the distribution of foundation sustaining layer and main stress layer
inner soil layers, evaluate the bearing capability and deformation
characteristic, and provide the usable bearing capability and deformation
characteristic.
The content of the project includes: solar resource analysis, geology of the
project, project task and scale, overall scheme design of the system and
generation capacity calculation, electrical design, civil project, construction
method, environmental impact assessment, and energy saving and
consumption reduction analysis after the building of PV power plant, project
investment estimate and fun raising scheme, financial evaluation, etc.
Munyati PV power plant project is proposed to be built about 10~15km from the
south of Munyati city. As it is not far from Munyati city, transportation is very
convenient. The supporting projects include a 132kV step-up station, 33kV
switchgear, complex building, component bracket installation and foundation,
road repairs, etc.
This project will build a 132kV line with a length of 10~15km which is
connected into the 132kV boosting station in opposite thermal power plants.
The above is only the primary recommendation. The determination of grid
connection point will be subject to the final approval documents from the
competent authority of local grid.
100MW Solar PV Plant Project Feasibility Study Report
Solar PV power plant usually divided into independent solar PV systems and
grid solar PV power systems. Grid PV power generation system is connected
to the power system, generally divided into centralized and distributed,
centralized grid power average amount is larger, usually in the hundreds of
kilowatts to megawatts magnitude, and distributed grid system capacity is
small, usually in a few kilowatts to tens of kilowatts. This project belongs to
large centralized grid PV power plant. In centralized grid PV power plant, solar
energy through solar PV modules array convert into direct current and
converted into low voltage three-phase alternating current (AC) by inverter (DC
- AC), and then through the booster transformer convert to meet the
requirements of the public power grid voltage alternating current (AC), and
direct access to the public grid.
15
100MW Solar PV Plant Project Feasibility Study Report
For solar module selected, first for most consideration is the industry trend,
technology maturity, operation reliability, future technology development trend
of the commercialized solar module. However the other consideration as the
natural environments, construction conditions, traffic transportation conditions
around solar station. Selection also involves the technical, economy
parameters. The solar module which suitable for the centralized large
grid-connected solar power plant is selected which will of course adhere to the
international standards.
At present, according to the raw materials, the solar modules are classified
into:
Thin film solar module: non-crystalline silicon thin film cell (α-Si), polycrystalline
thin film solar PV module, chemical semiconductor thin film solar PV module
and nano crystalline thin film cell.
At present, the solar cells are mostly made of crystalline silicon material, along
with the increased production capacity and investment of the crystalline silicon
cell. The solar power generation industry is abruptly developed; the yearly
solar module production has reached 40,000MWp, more and more solar power
plant being built.
The crystalline silicon solar module is the solar device with leading role in
the 21st century, and is continuously developed to the goal of higher
efficiency and lower cost.
The non-crystalline silicon thin film cell has the most shares in the market.
There are the following characteristics:
ii. The consumed power in the manufacturing process is little, and the
energy compensation time is short.
iv. The weak light effect is good, the temperature coefficient is low, and
the power generation amount is much.
The scaled production of CdTe and CIGS cells in the thin film solar
modules is limited due to the hypertoxicity of raw material or lacking of
raw material, so they are still in investigation.
Copper
Categories Mono-crystalline Polycrystalline Non-crystalline Cadmium
indium
Silicon Silicon Silicon Telluride
dieseline
Commercial 12% -
16% - 17% 15% - 16% 8% - 10% 13% - 16%
Efficiency 15.5%
Laboratory
25% 20.4% 12.8% 20.4% 20.8%
Efficiency
Thickness of
Thickness of Thickness of
Assembly Lamella Lamella Lamella
frame frame
Layer
Scale of
Formed Formed Formed Formed Feasible
Production
Neutral,
Environmental Yes (using except
Neutral Neutral Neutral
Issue cadmium) Using
Cadmium
Energy
Compensation 2~3 years 2~3 years 1~2 years 1~2 years 1~2 years
Time
Cadmium
and Indium is
Major Material
Medium Medium Abundant telluride expensive
Source
are rare rare metal
metals
Manufacturing
Medium Medium Low Low Low
Cost
Good
High Good
High Efficiency Good Weak Weak Light
Key Efficiency Weak Light
Matured Light Effect Effect
Advantages Matured Effect
Technology Low Cost Lower
Technology Low Cost
Cost
19
100MW Solar PV Plant Project Feasibility Study Report
mono-crystalline silicon cell is smaller than that of the polycrystalline silicon cell.
The difference between the electric performances, service lives, etc. of the two
types of cell assemblies is little. If only the technical property is taken into
consideration, in the practical application process, both mono-crystalline solar
module and polycrystalline silicon solar module can be selected. Since the
crystalline silicon cell has the characteristics of sufficient productivity, matured
manufacturing technology, stable product performance, long service life, and
higher photoelectric conversion efficiency, the crystalline silicon cell is widely
applied to the grid-connected photoelectric power plant project.
The Amorphous Silicon cell has lower efficiency, large land occupation area
and instability. Along with the development of technology and market, since the
manufacturing technology is relatively simple, the high-temperature process is
not required and the performance is higher than that of the crystalline silicon
cell under the weak light condition, and the Amorphous Silicon silicon cell
occupies certain shares at market.
Along with the technology advancing of solar industry and market development,
the competitiveness among the module manufacturers is increased, and the
market price is reduced. Taking 10MWp capacity of China using fixed
installation type as example, the price of the polycrystalline silicon module is
USD0.95/Wp, the price of the Amorphous Silicon module is USD0.89/Wp. The
primary comparison of the direct costs of these two type solar modules is as
shown.
Polycrystalline Amorphous
Items
Silicon Module Silicon Module
Array area (unit:10,000 m2) 15 23
Note: 1) The land cost is based on free allocation. 2) The data in the table is
only primarily calculated in China market.
The polycrystalline silicon module has multiple power item, they’re from 5Wp to
300Wp. Since the installation capacity of this project is 10MWp, the land
occupation area is wide and installation amount is high. So the module with
larger power is adopted, in order to reduce the land occupation and installation
amount.
Here we take 175Wp, 250Wp and 290Wp models of one manufacture for
example. The comparison of three polycrystalline silicon module is as shown in
below Table. The comparison of different polycrystalline silicon module is as
shown below.
From above table, it’s required less quantity of 250Wp and 290Wp assemblies
comparing with 175Wp module. It means that the number of connecting points
is less, the construction schedule is fast, the fault rate is reduced, the contact
resistance is little, the usage amount of cables is less, and the integral loss of
the system is relatively reduced.
21
100MW Solar PV Plant Project Feasibility Study Report
Module certified to withstand extreme wind (3800 Pascal) and snow loads
(5400 Pascal) .Compatibility to different inverter designs.
Item Description
Maximum rated power (Pmax) at
250Wp
STC
Rated power tolerance 0/+5%
Maximum operating voltage (Vmp) 30.7VDC
Maximum operating current (Imp) 8.15 A
Electrical
Open circuit voltage (Voc) 37.4VDC
characteristics
Short circuit current (Isc) 8.63A
Maximum system voltage 1000Vdc
Conversion efficiency 15.4%
Minimum efficiency at 200 W/m² 95.5% or higher of STC
(25°, AM 1.5) efficiency
Power temperature coefficient
-0.44%/oC
Tc-Pm
Temperature Current temperature coefficient
+0.055%/oC
characteristics Tc-Isc
Voltage temperature coefficient
-0.33%/oC
Tc-Voc
Solar Cell Polycrystalline silicon
Mechanical Cell dimensions (L × W) 156 × 156mm
characteristics Number of cells 60 (6 ×10)
Module dimensions (L × W × D) mm 1640×992×35
23
100MW Solar PV Plant Project Feasibility Study Report
When the solar power plant is designed, the operation method of solar array
has larger influence on the received radiation amount. The operation methods
of solar array include fixed installation type and automatic tracing types. The
automatic tracing types include the single-axis tracing system and the
double-axis tracing system. The single-axis tracing (horizontal single-axis
tracing and inclined single-axis tracing) system traces the sun track from east
to west at the fixed inclining angle, and the double-axis tracing (full tracing)
system changes the azimuth and tilt angle along with the change of seasonal
position of sun track.
100MW Solar PV Plant Project Feasibility Study Report
For the automatic tracing type system, the inclining surface can furthest
receive the sun radiation amount, so as to increase the power generation
amount. According to the primary calculation, if the horizontal single-axis
tracing type is adopted, the theoretical power generation amount is improved
by 15% to 20% (under the ideal condition that the tracing system is free from
shielding from sunrise to sunset). If the inclined single-axis tracing method is
adopted, the theoretical power generation amount is improved by 25% to 30%.
If the double-axis tracing method is adopted, the theoretical power generation
amount is improved by 30% to 35%. While the practical working efficiency of
the system is smaller than the theoretical value, because of many reasons,
such as mutual projection shade of the solar modules, difficult synchronizing of
tracing brackets, etc. The investment of the double-axis tracing method is
greatly higher than the single-axis system, and the land occupation area is
relatively higher.
Land occupation
1.6 2.1 3.2 3.3
area (unit:10000m2)
Increase of direct
100 111 114 122
investment (%)
25
100MW Solar PV Plant Project Feasibility Study Report
Single-point or
Multi-point Multi-point Multi-point
Point of support Multi-point
support support support
support
From the data in the table, the fixed type and the automatic tracing type
respectively are different in that the fixed type has lower investment, the
bracket system is basically free from maintenance, and the land occupation
area is relatively less; while, the automatic tracing type has higher investment
and requires certain maintenance, the power generation amount is greatly
improved in comparison with the fixed type with optimum tilt angle, and the
electricity cost of the station power plant adopting the automatic tracing type is
reduced if the added cost of the post maintenance operation is not considered.
If the bracket manufacturing cost of the automatic tracing type is further
reduced, the advantage of increased power generation amount is more
obvious. Meanwhile, if the array synchronizing is well solved and the
maintenance workload is reduced, the automatic tracing type is more
competitive than the fixed installation type.
By primarily comparing the fixed type and the automatic tracing type, the scale
of the project is larger, the fixed type has lower investment, the bracket system
is basically free from maintenance, and the land occupation area is relatively
less; while, although the automatic tracing type increases certain power
generation amount, the primary investment is relatively higher, the certain
maintenance is required in the post operation process, and the operation cost
is relatively higher. In addition, the requirement on the electromechanical
control and mechanical transmission components is higher, the automatic
tracing type lacks the reliability verification of the practical application in the site
100MW Solar PV Plant Project Feasibility Study Report
6.3.2.1 Introduction
Mounting system is applicable for the PV array system on the open fields. The
steadiness and safety of this system is compliable with the structural
mechanics and construction acts.
For different foundation solutions, such as concrete with pre-buried bolt, direct
buried and ground screw, the system can be modified to install. Material used
include hot galvanized steel and anodized aluminum alloy, with great
anti-corrosive suitable for outdoor using.
6.3.3.1 Features
Easy Installation
Excellent Duration
For Outdoor using, all the material selected with high class
27
100MW Solar PV Plant Project Feasibility Study Report
anti-corrosion protection.
Great Flexibility
Item Detail
Install Site Open Field
Color Natural
W 0=V02/1600=40X40/1600=1KN/M2
W k= W 0βzμzμs
W 0:1 KN/M2
μs1=-1.355
μs2=-0.555
μs3=1.355
29
100MW Solar PV Plant Project Feasibility Study Report
μs4=0.555
The installation tilt angle of solar array has higher influence on the solar power
generation. When the tilt angle of fixed module is optimum, the annual
electricity generation amount is maximized. It is shown the horizontal
irradiation of this region in one year from NASA.
100MW Solar PV Plant Project Feasibility Study Report
200
150
100
50
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
While there is tilt angle, the absorbed solar energy is better. The calculation is
below:
R b = S × [sin(A + B) / sin A] + D
D -----scattering radiation
Herein give tilt angle and yearly irradiation yield of above three solar radiation
data via PVsyst calculating, detail see following figures.
31
100MW Solar PV Plant Project Feasibility Study Report
From above Figure, 21o tilt angle has the maximum irradiation on the pane, so
we choose the 21o tilt angle for the preliminary analysis. The average
irradiation is correspondingly 2287.5kWh/m2/annual.
Vdcmax
S=
Voc × [1 + (t − 25) × K v ]
For this solar station, it uses 1MW containerized inverter, the maximum input
DC voltage of inverter is 1000Vdc, the open circuit voltage of 250W module is
37.4Vdc, so max module quantities in series
=1000/37.4/[1+(-10-25)*(-0.32%)]=24.
Solar modules are arranged in multiple forms in one unit, but in order to
simplify the wiring, reduce cable quantity and lower the construction complexity,
250Wp module arrangement is analyzed on the basis of project calculation.
Vertical layout in one line and one row as follows.
For above layout, an array includes two stings with 40pcs 250Wp solar
modules, its length is 20.2m, width is 3.1m.
Solar module arrays must be considered the shadow shading problems of front
and back rows, and calculated and determined the distance between arrays or
the distance between solar module arrays and buildings. In order to avoid the
33
100MW Solar PV Plant Project Feasibility Study Report
power loss, considering the winter solstice day as early as 9:00 to 15:00 solar
module should not have shelter, the calculation formula is as follows:
D=cosβ×H/tan[arcsin(0.648cosφ-0.399sinφ)]
Components after 21°tilt,In order to avoid the shadow block, calculated the
distance is 1420mm between the front and rear row of the array in the
installation, so we suggest the distance is 1450mm, and the array pitch is
4550mm.
About 450 acres lands will be provided for this 100MWp PV power plant project.
In our proposal, 420 acres area is needed, and the plant includes PV arrays,
Inverters, Transformers, 33kV distribution room, 132kV step-up station,
complex building, access road, fence and gates.
PV arrays are divided into twenty 1MWp sub-array, and each sub-array’s
layout is similar. 1MW Inverter and Transformer will be installed on the north or
100MW Solar PV Plant Project Feasibility Study Report
south side of sub-array in order to decrease the cable loss and shading loss. A
preliminary outline scheme of this project is as below.
35
100MW Solar PV Plant Project Feasibility Study Report
Items Parameters
PV array input voltage <1000
Elevation <2000
37
100MW Solar PV Plant Project Feasibility Study Report
The large and medium grid-connected solar power plant project generally
selects the large-capacity centralized grid-connected inverter. The output
power of the large-capacity centralized grid-connected inverter at the present
market is 100kW to 500kW. The larger the capacity of the inverter of the single
unit is, the lower the unit manufacturing cost is, and the higher the conversion
efficiency is. The capacity of the system in the project is 10MWp. By
considering the primary investment, project operation and maintenance, if the
single unit with small capacity is selected, the number of inverters is more, the
primary investment is relatively higher, the system loss is larger, and the post
maintenance workload is higher. In the large and medium grid-connected solar
power plant project, it’s necessary to select the grid-connected inverter with
large capacity as much as possible, so as to certainly reduce the investment,
and improve the system reliability. While, the capacity of the inverters of the
single unit is overlarge, and the power output of the power generation system is
severely affected when the inverter fails. Therefore, when the type is practically
selected, the comprehensive consideration should be made.
100MW Solar PV Plant Project Feasibility Study Report
The higher the conversion efficiency of the inverter is, the higher the
conversion efficiency of the solar power generation system is, the smaller the
loss of the total power generation amount is, and the higher the economy of the
system is. When the rated capacity of the single unit is the same, the inverter
with higher efficiency should be selected. When the large-capacity inverter is in
the rated load, the efficiency should not be less than 95%. When the rated load
is 10%, the conversion efficiency more than 90% should be ensured for
large-power inverter. The conversion efficiency of the inverter includes
maximum efficiency and European efficiency, wherein the European efficiency
is the weighting for the efficiencies of different power points, and can reflect the
comprehensive efficiency property of the inverter. The output power of the PV
system changes along with the sunlight intensity, so the inverter with higher
European efficiency should be selected.
The terminal voltage of solar PV module module varies with the sunlight
intensity and environment temperature, and the ID input voltage range of the
inverter is broad, so the generated energy during the shorter time before
sunrise and after sunset with weak sunshine solar irradiation can be used to
extend the time of power generation and increase the generated energy. If
under the sunset glow with smaller solar irradiance, the working voltage of
solar PV module module is lower while its temperature is higher, so if the DC
input voltage range is lower, it can increase power generation during this
period.
The output power of solar PV module modules varies from time to time, so the
resistance of the inverter at input terminal can adjust to the actual operating
characteristics of solar generation system, accurately track the maximum
power point, and ensure the efficient operation of solar generation system.
Output current has a low harmonic content and high power factor.
After the solar station is connected to the power grid, the harmonic voltage and
total harmonic current component shall meet the provisions of Power Quality
Utility Grid Harmonics, and harmonics in solar power plant is mainly from the
39
100MW Solar PV Plant Project Feasibility Study Report
inverter, so filtering measures must be taken to make the output current meet
the requirements of connection to the grid. It is required that the harmonic
content is lower than 3%, and the power factor of the inverter nears 1.
Technical Rules for Solar Power plant Connected to Power Grid provides that
the large and medium solar power plants must tolerate with the voltage
abnormality to some degree, and avoid that separation in case of abnormal
voltage in grid causes the loss of grid power. Thus, the on-grid inverter must
have LV endurance capacity, and it is required as follows:
Solar power plant must maintain the on-grid system operation for 1s when the
voltage in point of interconnection drops to the nominal voltage of 20%.
The voltage in point of interconnection of solar power plant can return to 90%
of nominal voltage within 3 seconds after voltage drop, and the PV power plant
can maintain the on-grid system operation.
When the voltage in point of interconnection of solar power plant is not lower
than 90% of the rated voltage, the solar power plant must maintain the on-grid
system operation uninterruptedly.
Relevant technologies of solar power plant connected to the grid requires that
large and medium solar power plant must own the ability to tolerate the
abnormal system frequency, and the response characteristics in case of
abnormal inverter frequency can ensure that the solar power plant continue
operate in case of the grid frequency deviation as shown below.
Frequency
Operating Requirement
Range
Less Than 48Hz Depending on Grid Requirements
48 - 49.5Hz When it is lower than 49.5Hz, it can operate for at least 10min.
The energy storage station shall be able to run 2 minutes continuously if the
frequency is higher than 50.2HZ each time, and also shall be able to stop
50.2 - 50.5Hz sending power to the grid within 0.2s with the actual operation time
determined by the grid dispatching institution; at this time, the grid energy
storage station in outage is not allowed to be in the grid.
Within 0.2s it can stop power supply to grid lines and forbid PV power plant
Above 50.5Hz
during shutdown from connecting to grid.
In case of disturbance, the inverter cannot allow connection to grid before the
grid voltage and frequency return to normal, and after the system voltage
frequency returns to normal, the inverter need a adjustable delay time before
reconnection to grid.
h. Protection Function
Based on the demand of power grid for solar power plant operation mode, the
inverter must have AC overvoltage and under voltage protection, over
frequency and under frequency protection, anti-islanding protection, short
circuit protection, AC and DC over current protection, overload protection,
reverse power protection, HT protection, etc.
The inverter should have multiple communication interfaces to collect data and
transmit it to the Control Room, and its controller should have the analog input
port connected to the external sensor to measure sunshine and temperature,
which is convenient for data treatment and analysis in power plant.
41
100MW Solar PV Plant Project Feasibility Study Report
In this project, we will take 1MW containerized inverter; it includes two above
SPI1500K-B 500kW inverters, two 500kW DC distribution cabinets, one
container and some accessories. This 1MW containerized inverter includes
following features:
ii. Adopts MPPT to control and track the maximum output power of PV
battery panels timely
iii. Sine wave output, automatically synchronize with grid, tiny current
harmonic, pollution-free and shock-free to the grid
vi. Equipped with big colorful screen, support Chinese and English
display setting, and touch operation
ix. Accept the dispatch of active power and reactive power for the grid
Parameters SPI1000K-B
Certificate CE,TUV(IEC62109-1/-2)
The 1MW containerized room and insides 500kW inverter appearance are
shown in following.
43
100MW Solar PV Plant Project Feasibility Study Report
Oil-immersed transformer has the advantage of high voltage level, wide range
using, the disadvantage is oil leaking, and causing environment pollution.
45
100MW Solar PV Plant Project Feasibility Study Report
Oil-immersed type transformer features low noise, low loss, rational structure,
high quality material, scientific design, strict production technology and
advanced test method. The product also has the following additional
advantages:
4. Nice appearance, small size, less installation space occupation and low
engineering cost.
Core:
The core is manufactured with high quality cold rolled grain-oriented silicon
steel of high magnetic conductivity, and 45° mitering and steps overlapping
structure is used for core production, thus to effectively reduce no-load loss
and no-load current.
HV winding:
LV winding:
Insulation Structure:
Tank:
47
100MW Solar PV Plant Project Feasibility Study Report
Phases (Ǿ) 3
HV winding
33000
(V)
Rated voltage
Ratings LV winding
315 , 315
(V)
HV: LI170AC 75
Insulation level
LV1~LV2:AC3-3kV
Top Oil 55
Temperature
Winding
Characteristics Rise (k) 60
Average
Earthing terminal
Lifting Lugs
Rating plate
Phases (Ǿ) 3
HV winding
132000
(V)
Rated voltage
Ratings LV winding
33000
(V)
Top Oil 55
Temperature
Winding
Characteristics Rise (K) 60
Average
Oil (Kg) -
Masses
Total (Kg) -
Earthing terminal
49
100MW Solar PV Plant Project Feasibility Study Report
Lifting Lugs
Rating plate
The solar irradiation and temperature data of local site from NASA are shown
in below figures.
Irradiation 190.6 171.6 182.3 169.8 162.4 141.9 155.3 181.0 194.1 205.5 188.7 184.8 2128.1
Average Temperature 22.7 22.5 22.4 21.1 18.4 16.1 15.9 18.9 23.0 24.6 24.5 22.8 21.1
From above tables, we can see that the solar resource is very rich in Munyati,
but hot weather will limit the efficiency of power plant.
Total Power100MW AC
According to NASA solar irradiation and other data, the annual production
of first year is 175445MWh, with a performance ratio of 76.7%
(1754kWh/kWp /Year).
51
100MW Solar PV Plant Project Feasibility Study Report
20000
18000 Monthly Yield
53
100MW Solar PV Plant Project Feasibility Study Report
2. The efficiency of solar module varies with the working temperature. When
their temperature rises, the module efficiency tends to decrease.
Considering that the monthly temperature and local annual average
temperature is 21°C, the temperature coefficient of polycrystalline solar
module at peak power is -0.44%/K, so the power loss coefficient caused
by working temperature of each month can be obtained. Based on above
description and calculation, the loss caused by module working
temperature is considered to be 8-10%.
5. Solar module pollution due to dust or accumulated snow can reduce the
module efficiency. In the site where this project is located, regular manual
washing is considered and the loss coefficient is 3%.
Solar module
Irradiation loss in morning and The low Irradiation in morning and night,
1%
night. inverter cannot startup
55
100MW Solar PV Plant Project Feasibility Study Report
Dust coverage loss of module 3%-5% Supposed PV module get regular cleaning
The result of simulation can reflect the general annual energy yield, but there
are many uncertain factors to affect the yield.
1. Meteorology
2. Soiling loss
Although the equipment in the PV plant get reliability more than 99.9%,
the PV plant still will get down due to equipment failure. In the period of
equipment maintenance, the yield will be affected.
Because grid failure can’t be forecasted, so the yield loss due to grid
100MW Solar PV Plant Project Feasibility Study Report
failure is uncertain.
5. Force majeure
The solar module has derating coefficient during using period. The derating
curve is shown in below figure.
57
100MW Solar PV Plant Project Feasibility Study Report
t:year,t=0,1,2…N
Total 3988568.4 /
59
100MW Solar PV Plant Project Feasibility Study Report
250Wp polycrystalline silicon panels are used in this project. 20 panels are
connected in serial as a branch. 100 branches are combined in parallel by 7
DC combiners as one unit and feeding DC power into one on-grid 500kW
inverter. In this project there are 200 identical units feeding power into 200
inverters.
In this project every two 500kWp inverters are connected to the LV terminals of
a three-winding transformers and together they form one sub-system. The DC
power is converted into AC and then stepped-up by the three-winding
61
100MW Solar PV Plant Project Feasibility Study Report
transformer. There are in total 100 sub-systems in this project, each has the
capacity of 1MWp. Every 1MWp sub-system consists of an inverter building
and a container type transformer station.
The 33KV system will be a single bus with two sections arrangement. About 20
pieces of KYN61 type indoor metal clad withdrawable cabinets are needed.
The short-circuit rating is assumed of 25kA due to the lack of information.
The 132kV system utilizes single bus configuration. The 132kV substation is
an outdoor AIS type, medium profile layout. It consists of four bays, namely two
transformer incoming bays (2x50MW), one outgoing OHL bay and one busbar
PT and SA bay. The short-circuit rating is assumed of 31.5kA due to the lack of
information.
For station power, two dry type, double-winding, OCTC, indoor type
33/0.4kV/630kVA transformers are utilized. The 400V station auxiliary power
system is a single-bus with two incoming configuration. The two incomings are
automatically transferred using ATS device.
100MW Solar PV Plant Project Feasibility Study Report
The final capacity of the RCE will be determined by the gird interconnection
study.
Due to the lack of information, for the bidding purpose the short circuit rating
25kV is taken for the 33kV busbar system.
Due to the lack of information, for the bidding purpose the short circuit rating
31.5kV is taken for the 132kV busbar system.
The actual short circuit rating can be determined with input from the power
company.
63
100MW Solar PV Plant Project Feasibility Study Report
Fire retardant copper core cable ZR-YJV22-0.6/1kV will be used for the LV
power cables.
Fire retardant copper core cable ZR-YJV22-33kV will be used for the MV
power cables.
8.2.3.1 PV array
The shades of the lightning rods have bad influence to the PV modules. In
consideration that the site location is not the lightning strike zone, the lightning
rods are not used in the PV array area. The direct strike protection is archived
by connecting the PV panels and the racks with the grounding grid.
An unified grounding grid will be designed for this project. The iron bars in the
PV concrete base, the vertical grounding electrodes and the grounding grid are
welded together. The electrodes in each sub-array are welded as grid, all
sub-arrays are interconnected together, and the grounding resistance should
be less than 4 Ohms.
To prevent the surge on the DC circuit, Surge arrestors are installed in the DC
combiner boxes, DC distribution panels, inverters and 33kV transformer
stations. The insulation coordination is based on 5kA rated discharge current
of the surge arrestors. This is in accordance with IEC 62305.
The Zinc oxide surge arrestors are installed at 132kV bus and incoming line
bay to prevent the lightning and operation overvoltage.
In this project, the 380/220V LV power system is common for lighting and
power system. The 400V station bus has two incoming feeders. The main
power supply is from the external 33kV public power grid. The back-up power
supply is from the 33kV bus in the PV station.
65
100MW Solar PV Plant Project Feasibility Study Report
Rated Capacity of the Auxiliary Transformer (KVA) = 0.8 * Total KVA = 148
In this project, a common LV power system is used for the lighting and
maintenance power and station power. According to the lighting design
regulations, the station lighting consists of the normal lighting and emergency
lighting. The PV inverter containers lighting power is taken from its own 380
distribution boxes. The station emergency lighting is connected to the DC
distribution cabinets. The emergency lighting is powered by the AC source
during normal operation. Under emergency conditions when the AC power is
lost, the emergency lighting transfer panel will transfer the power input from AC
100MW Solar PV Plant Project Feasibility Study Report
to DC. The emergency lighting and fixtures are installed in the office, central
control room. Independent small emergency lighting fixtures with batteries are
installed in emergency 33kV switchgear room。
Inverter container, Central control room and office: Ceiling fluorescent lamp;
Dormitory, corridor and stair hall: Ceil mounted energy saving lump;
The project facilities can be divided into two parts: complex building area and
PV array area. In complex building area there are 132 substation, 33kV
switchgear room, complex building and entrance road, etc. In the PV array
area, there are PV arrays, container type transformer stations, container type
inverter stations, cable ditches, etc. The PV array consists of 100 No. of 1mWp
units. According to the terrain conditions, the whole plant is in shape of a
rectangle. The entrance, complex building, substation are located in the west
of the station. The total land occupation is 1,500,000m2。
The total installed capacity of the project is 100MWp. Each sub-array has
1MWp capacity, one inverter station and one transformer station. To avoid
shading, the inverter station keeps enough distance with PV array. Each
inverter station contains two sets of 500kW inverters. The 1000kVA
transformer station is 1-2 meters away from the inverter station.
67
100MW Solar PV Plant Project Feasibility Study Report
There are 100 sets of 1MWp sub-arrays, between each array there is an 8
meters wide maintenance road. 0.8 meter wide maintenance road is kept
within the sub-array.
The protection and monitoring equipments are located in the electronics device
room. The SCADA is located in the central control room. The floor of the
central control room is raised anti-electrostatic tile. The control and computer
cables may be routed under the raised floor. In the electronic room, the
secondary system cabinets are arranged in three rows. Outdoor cable ducts
are arranged between substation and the complex building.
(1) The PV station is designed according to the unattended (or fewer operators
are required) philosophy.
(2) The supervisory system is based on the computer SCADA system, there
will be no conventional device or cabinets in the central control room.
The SCADA system in this project has the tele-control functions, it is able to
exchange information with the grid dispatch center.
The following analog data can be sent to dispatch center: current, voltage,
frequency, active power, reactive power, watt-hour and var-hour.
The following binary signal can be sent to dispatch center: The position change
signal of the circuit breakers, disconnectors, etc. will be sent to dispatch center
with priority. Additionally, the important device abnormal or alarm signals will
be sent out, as well as the protection initiation signals.
100MW Solar PV Plant Project Feasibility Study Report
The dispatch center will be able to control the grid connection breaker in PV
station remotely. The remote control action subjects to the operation rights and
interlocked by the protection interlocking.
The comprehensive automation of the substation, the main parts of which are
microcomputer protection and supervisory computer control system, and other
parts including intelligent devices and so on .
The supervisory computer control system with remote control function will
control and dispatch the substation according to the demand of dispatching
center, which collecting the processed many kind of real-time data and
information.
69
100MW Solar PV Plant Project Feasibility Study Report
The system is consisted of station control layer、network layer and wall. The
station control layer is the center of the substation, integration of supervisory,
metering, control and management, connecting with wall through fiber or
STD(Shielded Twisted Pair). The wall is arrayed different places, perform the
function of device supervisory and circuit breaker control even on the condition
of station control layer、network layer failure. The supervisory computer control
system commute with dispatching center through remote control station.
The station control layer is consisted of operator station, remote control station,
exchanger, communication management machine, printer, GPS clock.
Two IPC(Industrial Personal Computer) are used as station level control device,
and one is used as host/operator station and the other is used as operator
station. In addition, 1 printer and 1 set voice alarm system is included.
below:
a. the supervisory computer control system supervise and manage the
PV modules and inverters, the information such as operation data, fault
type, real-time power, electric power and so on is displayed on the
LCD screen. The electric power is injected into the electric network, the
operator can supervise and control the PV modules and inverters
through keyboard.
b. The local supervised device is set up to supervise the PV modules and
inverters, the above function is realized as well. The protection and
detection configuration of the PV modules and inverters is made by the
supplier of inverters, such as thermal protection, over-load protection,
grid fault protection and sensor fault signal. After the protection device
action, the outgoing circuit breaker of the inverter is switch off and send
the signal.
c. The remote control of the PV modules and inverters is realized at the
central control room, the computer have multi-level access
authorization control, the authorized operator can operate remotely.
The displayed information as below:
DC voltage, DC current, DC power, AC voltage, AC current, AC power,
inverter temperature, clock, frequency, power factor, current generated
power, daily electric energy production, accumulated electric energy
production, daily generated power curve graph. All the operation state
is supervised, and audible and visual alarm will show the device fault
with cause and time.
d. The line protection switch, ampere meter, voltmeter are settled in the
ACDB. The voltage and current signal and switch state are transferred
from communication control layer to station control layer, and will be
supervised by station operator.
There are 100 sets box-type transformer and 10 33kV switching rooms, on the
step-up side of each transformer there are load switch and plug-in fuse, on the
low side there are auto-air switch. There are indoor complete metal enclosed
circuit breaker. The load switch, auto-air switch, circuit breaker, no-load tap of
the transformer can be controlled locally, and be centralized supervised by
supervisory computer control system, the action signals will be transferred to
central control room.
71
100MW Solar PV Plant Project Feasibility Study Report
The protection device outlet adopt relay passive contact. Relay protection and
safety automatic device can meet the demand of reliability, alternatively,
sensitivity and quick-action.
For the fault and protection device action analysis, micro computer fault
recorder is settled in the solar PV station and used for 33kV busbar voltage,
line current and switch action.
100MW Solar PV Plant Project Feasibility Study Report
The main electric parameters are sent into the supervisory computer control
system. The electric measuring meter is not settled in the central control room
but in the switch cabinet. At the same time, the nonelectrical signal is sent into
the supervisory computer control system for real-time supervisory.
73
100MW Solar PV Plant Project Feasibility Study Report
The metering gateway is on the 132kV outgoing line of solar PV power plant
with one 0.2 level kWh meter and one 0.5 level varmeter with intelligent
multi-function. The testing point of performance test is at the 132kV outgoing
line of solar PV power plant too.
8.3.4.2 CT&PT
The secondary side of levels of bus voltage transformer set dedicated circuit for energy
metering, and section of its loop wire should ensure that the secondary voltage drop of
each power meter is not more than 0.2%Ue when it runs under maximum load. So
design capacity of 33kV / 88KV outgoing current transformer is level 0.2s, and
measuring is 0.5. Design capacity of voltage transformer is level 0.2, measuring is 0.5,
One set electric quantity acquisition and power quality monitoring device is
settled, communicate with electricity meter through RS485, collecting electric
quantity information of total substation. electric quantity acquisition device is
equipped with dialer and network port.
DC control power system including: one set 200AH storage battery, one set
floating charge/ equalization device, single busbar connection with DC220V
voltage level. The DC insulation monitoring device is settled on the busbar in
order to monitor DC system insulation and busbar voltage. The battery is
equipped with detecting device. The charging device adopt micro computer
controlled with automatic and manual mode, when the automatic mode is
repaired, change to manual mode automatically.
According to load of each device, UPS is settled to make sure that the power
supply of micro computer monitoring system and protection device is reliable.
100MW Solar PV Plant Project Feasibility Study Report
The UPS will supply NCS, gateway, fault recorder, remote electrical power
measurements system, line protection supervisor and printer and so on.
The power plant will be provided with a set of fire alarm system. The fire alarm
system adopts central alarm method. The system is including sensors, manual
push buttons, communication system and wiring system, interlocking control
and central control panel. The fire detection and alarm and the interlocking
control will share the same information bus. The central fire alarm panel is able
to show the alarm and detection zone, and is able to initiate the external
system.
The central fire detection panel will be located in the control room.
The fire detection sensor will be setup at central control room, electronic room,
switchgear room, main transformers, etc. The fire alarm system is powered by
the UPS system and/or station DC system.
A surveillance system will be provided for the substation, in order for the
operation management and for the security of the PV plant.
The scope of the surveillance is including the PV station entrance, the main
transformers, the outdoor switchgears, the complex building and the fence.
The cameras should have no blind area or blocking.
75
100MW Solar PV Plant Project Feasibility Study Report
To provide the adjustment, testing and calibration instruments for the testing
and calibration of the electrical devices.
8.4 Telecommunication
The communication method between substation and the grid operator is either
through dedicated digital communication network or using PLC (Power Line
Carrier) depending on the real site saturation.
100MW Solar PV Plant Project Feasibility Study Report
9 Civil Works
The supporting projects can be divided into two parts: production and living
area, photovoltaic array area. An 132kV step-up station, complex buildings,
arrival roads, etc. are built in the production and living area. The photovoltaic
array area includes PV module array, box-type substation, inverter room, cable
trench, etc. The PV module array adopt 1MWp as one grid-connected power
generation sub-unit, and there are 100 units. According to the site terrain, both
two areas are arranged in a rectangular shape. The production and living area
is located at the west of the photovoltaic array area, and the entrance and exit
of the power plant is located in the west of the management area, connected
with the roads outside the site. The total area of the power plant is
1,500,000m2.
The major buildings (structures) in the production and living area are complex
building, 33kV switchgear and fire pool. The complex building is located at the
south of production and living area, while the dispatching device will be
allocated at the east of the production and living area according to the direction
of outgoing line. The complex building is a one-storey building with central
77
100MW Solar PV Plant Project Feasibility Study Report
control room, office, kitchen, dining hall, cultural and sports activities room
dormitories, etc. The central control room will be supplied with monitoring
system operator station, DC screen, centralized monitoring system, PC system
telecontrol and communication equipment.
The photovoltaic array area includes PV array, inverter, and box –type
substation and overhauling passage way, thereinto, the PV array is made of
100 sets of 1MWp photovoltaic sub-systems. Each 1MWp photovoltaic
sub-system is installed with an inverter room, which is at the middle of the
photovoltaic array. There’re one inverter rooms in total. The box substation is
located at the both sides of inverter room. Both of the box-type substation and
inverter room are located at area between the photovoltaic arrays, resulting in
no shadow to the PV panel.
The entrance of station connects the external roads to the production and living
area directly. There’re internal crossing roads in the photovoltaic array area,
easy for installation and maintenance. The access road is 8m wide, and the
internal road is between 4m and 6m wide.
2、Combine the overall planning of the total layout of the power plant, fan out
from point to area and highlight the key points.
3、The both sides of entrance roads and surroundings of the complex building
will be planned with ornamental plants or fruit trees, hedgerow and grasslands
etc; plant ever-green trees and shrubs at the side of the complex building
facing leading wind in winter to resist cold winds. The landscaping shall echo
with the buildings to form an elegant building afforestation landscape.
100MW Solar PV Plant Project Feasibility Study Report
79
100MW Solar PV Plant Project Feasibility Study Report
The floor area of the production and living area (including 33kV switchgear and
complex building) is 2,000m². Layout the buildings and structures inside the
walls, with functions and styles fully combining the local condition of perennial
wind area with beautiful environment and considering the applicability of
production, living, operating and maintenance. On the basis of complete
functions and reasonable usage of investments, the design idea integrates
buildings with similar functions and allocates 33kV switchgear, complex
building and fire pool. The design integrates the production and living rooms
into a one-storey building to save land and energy consumption.
2.Control room
3.Relay room
5.33kV substation
6.Auxiliary facilities
(1)Fence
Choose 2.2m high iron gird wall of about 6000m long.The foundation structure
of can be concrete, but also can be pile foundation.
(2)Fence gates
(3)Plant road
The initially planned to take Mud road gravel road or gravel roads.
81
100MW Solar PV Plant Project Feasibility Study Report
Since the current data is not very adequate. From information that we get, the
foundation is the natural foundation, not backfill, so it is assumed that the
foundation bearing capacity values> 150Kpa, non-weak foundation.
Underground water level is in the ground 10 meters below. The areas occur
without snow and permafrost. According to the site investigation and regional
geological survey, no undesirable geological condition has been detected, thus
it is primarily determined as stable.
Design Parameters
Switch stationtwo, the PV array bracket and base two, living facilities two
The inverter rooms, totally 100, are scatteredly installed in the photovoltaic
array area as container using under-pillar concrete independent foundation,
covering 7.5m2 each.
3. Cable trench
Cable trench in field area dug straightly. Depth is greater than 1 m, and width is
greater than 1 meter. It facilitate to entry into the ditch for construction. After
the laying of cables, backfill direct burial.
Two sets of 50MVA transformer and two sets of reactive power compensation
device are used in the project. Reinforced concrete foundations are required
for both of them; 132kV taking out interval need to build an outdoor steel
structure, and poured reinforced concrete foundation.
83
100MW Solar PV Plant Project Feasibility Study Report
2. Fire Consumption
Within the production and living area, the type of building fire risk is III type and
fireproof grade is II grade. According to Code for Fire Protection Design of
Buildings (GB50016-2006) and Code for Fire Protection Design of Thermal
Power Plant and Substation (GB50229-2006),the fire fighting device can be
designed.
The drainage system uses rain and sewage separating system, where the rain
and sewage are discharged separately.
The water on proof of complex building adopts inner roof drainage type. The
outdoor rain is drained out of site through rainwater pipe network after
gathered in road gully. Concrete drainage path can be determined after
investigation.
The water in kitchen and toilet of complex building shall be drained to the
reinforced concrete septic tank. It shall transport the sewage by sewage truck
to the sewer pipe point in surrounding towns to dispose intensively and prevent
the power plant from pollution.
100MW Solar PV Plant Project Feasibility Study Report
The outdoor water supply pipe shall adopt PE pipe and be connected through
hot melting. When connecting the water supply pipe with metal pipeline and
value, it shall use steel-plastic transition joints or exclusive flanged joints.
The indoor water supply pipe shall adopt steel-plastic complex pipe and be
connected by special accessories.
The indoor sanitary sewer shall adopt UPVC drain pipe and bear glue joint.
Outdoor rainwater and sewage pipe shall adopt TTP-PVC double-wall and
waved drainage pipe, as well as rubber ring connector.
The central control room shall arrange unitary air-conditioner to meet the
requirements of process design.
2.2 Backfill
2.5 Corrosion
3 Line Project
3.2 Backfill
4 Ground engineering
4.2 Backfill
2.2 Backfill
2.3 Concrete
100MW Solar PV Plant Project Feasibility Study Report
3 Outdoor Project
3.1 Fence
3.2 Door
Ⅳ Traffic Engineering
1 Access Road
2 Pit road
Ⅴ Other works
1 Environmental Engineering
4 Flood protection
87
100MW Solar PV Plant Project Feasibility Study Report
10.1 Overview
3, "Fire Protection Regulation for Thermal Power Plant and Substation Design"
(GB50229-2006);
3, if the PV power plant near the fire station, by the society of fire power.
3, The wire section of wire and cable should not be too small, to avoid
overloading the fever, which would cause the fire. The fire fighting equipment
should use fire retardant cable.
4, The perfect anti surge protection facilities and grounding system should be
provided.
Integrated fire control and protection technology measures is applied for the
overall design in this project from various aspects including fire protection,
monitoring, alarm, control, fire, smoke, escape, and strive to reduce the fire
occuring rate. The fire can be put out in a short time, so that the fire loss can be
reduced to a minimum, while ensuring the safety evacuation.
The fire ring channel for the complex building and switch station design should
have a width of no less than 4m. the turning radius is larger than 7m, and the
slope is less than 3%. The fire channel connects to the road of field, complex
buildings and step-up station, and also connect to the main road outside the
local city.
The distance between the step-up station walls and the nearest cell array is
greater than 200m, the surrounding of complex buildings and 33kV power
distribution room walls is open, conforms to the specification requirements.
According to the standard, the configuration of the fire hydrant, sand box,
portable fire extinguisher and cart type fire extinguisher etc. should be provided
in the complex buildings, step-up station, 33kV power distribution room and
field.
Fire control power supply should use the variable power supply for the
transfomer station. The telephone shall be configued in the important place.
91
100MW Solar PV Plant Project Feasibility Study Report
The surrounding of the 33kV power distribution room, complex buildings (i.e.,
production and living building) and the step-up station locating in the project
area should be open. And their location selection should comply with fireproof
distance criterion.
From the above list of data analysis: the fire hazard of 33kV distribution room is
a class 3, and the relative fire resistance rating is Class 2.
100MW Solar PV Plant Project Feasibility Study Report
The fire resistance rating of the switch station building and building is class 2,
the design material selection should meet with the corresponding fire
resistance limit (H) hour.
93
100MW Solar PV Plant Project Feasibility Study Report
According to the "fire protection design of thermal power plant and substation
standard" (GB50229-2006) and "architectural fire standards" (GB50016-2006)
regulations, the distance between the complex building and distribution room is
greater than 10m, and the partition of control room and the adjacent room
should be firewall.
(2)、Door Selection
Th inner and outer decorative materials of complex buildings and 33kV power
distribution room should select the non combustible and flameresistant
In the control room, restaurant, conference room and hall entrance, the doors
should be aluminum alloy door. Garage selects the automatic upturning door,
and the rest rooms should select the solid wood door. The fence wall should
select the white paint iron grille fence walls, and the wall door should select the
electric telescopic door.
(3)、Flameresistant measures
Fire in the switch station most causes from the electrical equipments,
especially charged equipments. After wire and cable is in place, in the inner of
33kV power distribution room and complex buildings, where there is a wire or
cable passing through the floor, wall, fire clay or fire-proof bag should be used
for sealing up.
4、Fire Lane
100MW Solar PV Plant Project Feasibility Study Report
Complex buildings and switch station should layout annular concrete road for
fire control. The road width should be greater than 4m and connect to the field
area roads and the city traffic trunk.
Switch the station fire most from the electrical equipment especially is caused
by oil equipment. And the fire is difficult to be put out by water. Cart type or
portable chemical dry power fire extinguisher should be recommended for
switch station. These extinguishers can be stored for long periods, flexible and
convenient use, and does not need the professional team. The fire can be
extinguished by these equipments in a short time before the professional team
arrives .
For the important instrument rooms, the fire should not use foam or CO2 fire
extinguisher, and fire water is not favorable. Because this kind of facility could
destroy or pollute the unfire equipments. Using dry chemical fire extinguisher
can not generate fouling gas and would be good for these applciation.
(2)、The places including the entrance for outside cable into the room, the
entrance for cable shaft and the cable layers between the control room and the
active floor and the cable trench into the high voltage switch cabinet or low
voltage distribution screen should take flameresistant and seperating
measures to prevent fire widespread. The fire resisting limit of the fire
prevention materials should not be less than 1hour. Cable trench should divide
the fire partition. All paint and plugging materials must be approved by the
national accreditation, and the production licenses issued by the public security
department. The product is suitable for the cable with non-combustible or
flameresistant materials, and complies with the provisions of the fire resistance
time limit.
95
100MW Solar PV Plant Project Feasibility Study Report
(3)、All holes and entrance through the walls, from floor into the control room,
control cabinet, instrument panel and protective plate at the cable hole, must
use fire blocking material tight sealing.
The transformer should be arranged in a separate room. The room has not
open window, but with a fireproofing door of class 1. The ground should be
cement ground.
According to the the relevant provisions of "the code for design of building fire
extinguisher" (GB50140-2005), the portable ammonium phosphate dry powder
fire extinguisher should be provided in the main building rooms (inverter room,
wattless power compensation room, control room, dormitory area, restaurants
etc.).
All electrical equipment for fire control should have double power sources
independent or double loop power supply. The power supply can automatically
switch.
Water shall be pumped from wells into the 12m3 high water tank in the building
for use of production and life. Another pipeline connecting to 300m 3 fire water
pool, guarantee to meet the requirements of fire water supply.
The building fire risk in this project is Class 3, and fire resistance rating is class
two. According to the "architectural fire standards" (GB50016-2006)
regulations, the indoor fire hydrant water valume is 5L/s and the outdoor fire
hydrant water volume is 25L/s. If a fire duration is 2hour, a fire hydrant system
will require water volume of 216m3.
Outside the water pumping house, a 300m3 reinforced concrete pool will be
arranged fire control. The top of the fire water pool should be deeper than the
bottom of the tundra layer, the side wall should cover insulation benzene plate,
and the top of pool should cover the coal clinker for antifreezing design.
In order to improve the building fire facilities, the complex building should
equipe with fire hydrant system.
In the complex building and the surrounding of 33kV power distribution room,
the underground fire hydrant of ring network should be provided. The
configuration should include 2 sets of SX100-1.6 fire hydrant system, water
gun bore ф19 and tap with long 50m.
Power supply for fire water pump is the primary load. It should be designed
with double loop power supply, and the power should be directly from the 33kV
main power distribution cabinet. The emergency power should be from the
11kV security power supply. When the main power source failure, the 11kV
security power should automaticall switch and supply power in 3 seconds.
The main evacuation channels in the control room and 33kV power distribution
room should equip with evacuation directional signs and fire lighting lamp. And
the fire lighting lamp for evacuation directional signs should use DC battery
power supply with continuous illumination 20min, and the minimum illumination
is not less than 0.5LX. All accident lamp and direction sign lamp should cover
with glass or non combustion material for protection.
In important places, such as the control room and power distribution room, the
telephone communication equipment should be provided.
The 33kV power distribution room, the change room, control room, dining room,
pump room, bathrooms and others should equip with a mechanical exhaust
system to strengthen the ventilation. In the kitchen and storage tanks, there
should be the local ventilation system for air ventilation.
1, The oil reservoir should equip with separate exhaust system. The fan and
motor should select the explosion proof type; the inlet should use the
100MW Solar PV Plant Project Feasibility Study Report
fireproof outlet, and the system would automatically close when the air
temperature reachs 70 degrees.
2, When the fire occurs, it should stop the operation of ventilation systems in
the relevant parts.
The open flame heating is strictly prohibited. Each room should equipe with
safe and reliable electric heating with good performance of insulation.
99
100MW Solar PV Plant Project Feasibility Study Report
33kV Electrical
1.3 MF/ABC8 4
Distribution Room
Station Transformer
1.5 MF/ABC8 2
Room
Main Building
Electrical Distribution
2.1 MF/ABC8 1
Room
Box Transformer
3.1 MF/ABC8 20
Substation
10.8.1 Fire Control Design for Complex Building and 33kV Electrical
Distribution Room
The oil storage and battery room building should use the firewall with fire
resitance limit of greater than 4 hours and the fireproof door with fire
resistance limit of greater than 1.2hours for fire separation. 33kV power
distribution room should use the firewall with fire resistance limit of greater
than 4hours and the fireproof door with fire resistance limit of greater than
1.2hours for fire separation.
The decoration design of the production complex building should fully comply
with the provision in the "building internal decoration fire standards"
(GB50222-95) .
101
100MW Solar PV Plant Project Feasibility Study Report
1, The engineering construction road should connect to the road outside the
field, and be used as a vehicle field, which can also be used as the fire lane
and emergency evacuation routes.
2, The fire control power supply should be obtained from the special 33kV
power supply for construction. The cross-sectional areas of cable / wire and
wire should be selected according to the working current and short circuit
current selection with a certain margin.
3, The house for fire control pump should use the non-combustion materials for
building and locate in a safe place. Fire control pump should adopt special
electrical distribution line from the upper end of the total circuit breaker in the
construction site, in order to ensure the reliability of power supply.
5, The building area should be equipped with fire extinguishers, and with the
security pail for fire control, water storage tank (pool), yellow sand pool and
other facilities. Temporary wood house, oil paint house and machinery tool
house should have a suitable kind of extinguisher. The oil depots and storage
of dangerous goods should be equipped with a sufficient number of fire
extinguishers. No objects should exist around the fire control facilities, so as
not to block the passage.
6 The office, dormitory, kitchen, toilet, bathroom and other temporary facilities
should use the concrete hard bottom, brick wall, light steel roof truss,
temporary housing or active housing with profiled steel sheet roof, or container
type movable house.
100MW Solar PV Plant Project Feasibility Study Report
According to the fire regulations, the construction unit should establish fire
control organizations consciously, establish a complete organization
mechanism for fire protection, establish and implement the actual fire fighting
and emergency evacuation plan for the project, and do regular fire knowledge
training. The training includes:
1, the relevant regulations, safety institutions and safety protection rules for fire
control;
2, Fire control measures for fire hazard according to the unit and the position;
4, Knowledge and skill for reporting fire alarm, extinguish the fire hazard at the
beginning and self rescue and escape.
5, The control room, all kinds of oil warehouse and spare parts warehouse are
listed as key protection area. New staff in the key fire control position, must be
pre fire safety training, and pass the examination for fire control and safe
production rule before work.
The following personnel should receive special training for public security and
fire control by the security and fire control institutions and pass examination:
1) Strictly obey relevant law and regulations of state and local government,
relevant provision.
103
100MW Solar PV Plant Project Feasibility Study Report
6) Strictly comply with safety and protection procedure and safe operation
procedure, regularly organize safety meeting, conduct safety protection
education, perfect safety management system and implement safety
responsibility system.
The earth surface is mainly gravel soils and the whole construction area is
covered by forests. Without karst, landslide, collapse, debris flow and other
adverse geological processes, the site enjoys good stability and foundation
uniformity, and structure is stable in the project area.
Main materials required by this project are sand and gravel materials, cement,
steel, timber, oil plants, etc. Main building materials are guaranteed. Sand and
gravel materials can be purchased from Gweru which is 90 kilometers away
from the construction site or from sand stone factory near Munyati; cement can
be purchased from outside of Gweru which is 100 kilometres from the
construction site while steel need to be purchased form Harare, 210kilometres
from the site. Oil plants and life materials can be purchased from Kwekwe
which is only 20 kilometers from the site. If Kwekwe cannot afford or qualify, we
also can buy these things from Harare. Timber can be obtained locally, uproot
105
100MW Solar PV Plant Project Feasibility Study Report
trees can be handled on their own, and residual material can be given to the
local residents.
Construction water can be taken from the water channels, 1km away, which
flow around the construction site. Meanwhile, drill wells on the site and install
pumps to pump the under-ground water. Two ways can ensure the
construction water and maintenance of water.
4) The transportation is good; trucks can arrive at the construction site directly.
107
100MW Solar PV Plant Project Feasibility Study Report
4) Principles of partition scribing, to fan out from point to area and from near to
the distant: Divide the photovoltaic plant into production management area and
photovoltaic array area; and then carry out installation, debugging and
debugging of photovoltaic array area in batches. So that it can not only
promote construction efficiency, but also guarantee the photovoltaic power
plant putting into commercial operation in batches in advance.
The construction unit is required to build waste water pool for waster water
produced in construction to settle before being discharged, and to set mobile
toilet on the site to prevent sanitary sewage from being discharged.
Construction electricity is mainly from the nearby 33kV lines or from the 132kV
lines which is 2kilometres away from the site. Peak construction power load is
estimated to be 300kW. Therefore, a 400kVA transformer with output voltage
of 380V is considered for later plant power. Power for site construction of
foundation of support, box substation and inverter room is supplied by
diesel-oil electric generator wagon. Meanwhile, the construction electricity site
should be equipped with two 100kW diesel generators.
100MW Solar PV Plant Project Feasibility Study Report
Given project amount and construction period of photovoltaic plant, at least two
parts are under simultaneous construction. Construction power supply and
load is shown in table next:
109
100MW Solar PV Plant Project Feasibility Study Report
Reinforcement bar
3 JJM-3 Set 1 7.5 7.5
straightening machine
Reinforcement bar
4 GQ-40 Set 1 7.5 7.5
cutting machine
Reinforcement bar
5 GJB7-40 Set 1 3 3
bending machine
AC electric welding
8 Set 4 25 100
machine
Diehead threading
10 Set 1 4.5 4.5
machine
Total 236.9
The landscape of the site is forest, the surface is covered with gravel soil, and
the terrain is relatively flat. The partly smoothing project on the site is small.
After cutting down the trees, the timbers can be extracted voluntarily to be the
materials of the construction. The remaining wood can be given to local
residents.
The project site set a mechanical repair and replacement workshop and
comprehensive process system (including steel processing plants, wood
111
100MW Solar PV Plant Project Feasibility Study Report
Serial Specification
Equipment name Unit Quantity
No. & model
1 Concrete mixing plant HZS60 Set 1
Reinforcement bar
7 JJM-3 Set 1
straightening machine
Warehouses required for the project are laid out near Production of the living
area, mainly including cement warehouse, wood warehouse, reinforcement
warehouse, integrated warehouse, mechanical parking area and equipment
stack yard. The cement warehouse, wood warehouse and reinforcement
warehouse are located in the concrete system and processing plants
separately. Integrated warehouse includes temporary production and living
supplies warehouse, machinery parking area considers 10 units of
construction machinery, with a total floor area of 500m2.
113
100MW Solar PV Plant Project Feasibility Study Report
According to the overall layout of the construction and installation of the electric
field, it is need to build, examine and repair the roads of 10km, pavement width
is 8m(hard road is 4m). In the basis of full use of existing roads, rolling and
straightening some of the new-build roads can meet the construction
requirements. The main material is the local gravel, macadam, to match the
grade ingredients according to the need. Subgrade is crushed according to the
original pavement, surface course is paved with 30cm gravels and broken
stones as required by grading, and clay-bound pavement is formed to produce
the effect of dust fall and solidifying pavement.
100MW Solar PV Plant Project Feasibility Study Report
3 Warehouse 500
Totally 2500
The main construction works of this project include the support foundation
construction, 33kV substation and complex building construction,
transportation and installation of equipments, in-plant power transmission
communication construction, etc.
115
100MW Solar PV Plant Project Feasibility Study Report
Technical Preparation
2) Material Preparation
c) According to the design materials list and each small parts, small tools used
in construction process, some lists are required to be prepared such as List of
Materials Required for Construction, List of Tools Needed for Construction, List
of Security Measures Protect Tools, etc, formulating Site Construction Manual
to guide the construction. Prepare materials according to material list, consider
supply cycle, etc. for outsourced purchased parts, and prepare subscription
and contact with manufacturers in advance to avoid delaying construction
period.
b) Equipment and materials are put in storage. The materials and equipment
storage procedures are handled by the material staff;
5) Site Preparation
2 Senior engineer 30
3 Engineer 60
117
100MW Solar PV Plant Project Feasibility Study Report
4 technicians 900
5 labors 6000
Note: the major managers and senior engineers mainly come from china while
assistants are from Zimbabwe. Engineers, technicians and labors are all from
Zimbabwe.
7) Communication Preparation
When the project is officially started, the temporary constructed living facilities
on site shall be completed, and necessities is provided to meet the staff living
needs. Set dormitory, canteen and toilets in the site.
1) Foundation Excavation
is forbidden. The excavated soil and rock shall be piled up at the location
designated by the project engineering company as required.
e) After foundation pit is excavated and before pouring concrete at the cushion,
foundation pit shall be protected.
b) During rebar layout process, such as cable trunking should adopt the
method of adjusting rebar spacing for avoidance, and do not cut rebar and
damage the mechanical structure.
4) Template Engineering
119
100MW Solar PV Plant Project Feasibility Study Report
The template, mold, and nodes of different components should have sufficient
strength and rigidity to ensure to meet the requirements of size error, and the
inner surface of template and mold should be clean.
5) Concrete Pouring
All modules in this project adopt the fixed installation; module installation is
performed after the acceptance for PV modules bracket foundation, the
installation for the PV modules is divided into two parts: Bracket installation,
module installation.
Before installing the module, efforts should be made to inspect each module
according to the parameters of components, and the parameter values should
comply with the delivery indicators of products. General test items are: open
circuit voltage, short circuit current. Components of similar operating
parameters should be selected for the same sub-array. Components of equal
or similar rated operational current should be selected for cascading.
During installation, the module should be gently handled to prevent from hard
object scratching and glass surface impacting. Components installation
position on the bracket and terminal box arrangement should meet
construction design provisions. When the fixed surface of components doesn't
tally with the support surface, use iron gasket to level up and fasten screws. It
is strictly prohibited to make it consistent with the method of fastening
connection screws. The fixed bolts should be added with locking washer and
tightened.
Adopt cascading for cable connection of modules, tightly plug, reserve some
allowance for outgoing line.
121
100MW Solar PV Plant Project Feasibility Study Report
complete, and installation will not start until confirmation is made according to
manufacturer technology.
Structure construction uses steel scaffold, floor and ceiling use all-round
scaffold for formwork erection and pouring, and vibration of concrete uses
handheld vibrator for vibration.
In the process of concrete pouring, the template, bracket, embedded parts and
reserved holes should be observed, and deformation, displacement should be
dealt with in a timely manner to ensure the quality. For pouring of beams and
slabs combined with columns, wait for 1 to 1.5 hours after the pouring of
column, and then continue the pouring. Within 12 hours after completion of
pouring, the maintenance of concrete should be made, and shall not be
trampled or installed template and support before its strength meets the
regulations,
According to the current level and experience of design and construction and
the ordering situation for main equipment, the complex building and
photovoltaic array foundation starts to construct early, and the construction
machinery is required to meet the requirements of two project construction.
The planned construction period for this project is 12 months. The overall
target of construction period: All photovoltaic power plant equipment
installation and debugging is completed, all the photovoltaic arrays are
combined to the grid.
Under the premise of ensuring the above mentioned, the construction of other
project projects such as warehouses, temporary subsidiary building and
concrete foundation can be carried out simultaneously. Other parts of the
project can be operated with flow process in order to speed up the progress,
guarantee construction period.
Notes: This progress chart for construction is showed above; the schedule of
this project will be adjusted according to the contract. The progress chart for
construction will be drafted in details during the development of the
construction.
100MW Solar PV Plant Project Feasibility Study Report
During the construction period, the solar power project shall set up a project
company according to the project objectives, management content and
management depth of the project. The project company is planned to comprise
five departments: the departments of planning, general management,
equipment management, engineering management and finance audit, with a
total of 10 people. These compositions employ a system of linear functions,
co-ordination division and clear responsibilities and carry out various tasks in
project management. The primary authority and responsibilities of the project
department are:
127
100MW Solar PV Plant Project Feasibility Study Report
Responsible for raising fund for the project construction, and timely disbursing
the project funds to the contractor according to the construction contract;
responsible for production preparation;
Responsible for the final accounts, final acceptance and evaluation of the
project, as well as the project operation, loan repayment and demolition tasks
after the photovoltaic power plant is put into operation.
129
100MW Solar PV Plant Project Feasibility Study Report
After the electrical and mechanical equipments of the solar power plant
(including the 33kV substation) enter a steady operation period, the 33kV
substation will follow an "unattended, few people on duty" approach to carry
out management.
The solar power plant has a general manager, who is responsible for the
overall management and production of the plant; there are eight employees in
Operation and Maintenance Department, mainly responsible for component
inspection, routine maintenance and duty, etc., in a two-shift system; the
Technical Department has two staff responsible for the department related
work; Finance Department has two employees responsible for the daily
financial expenditure and material procurement, etc.; there are two people in
Logistics Department responsible for food, sanitation, greenery, reception,
labor safety and so on during the two periods of works.
131
100MW Solar PV Plant Project Feasibility Study Report
Operation Department(8)
Management
Organizational Finance Department(2)
Chart
According to the characteristics and layout of the solar power plant, the entire
solar power plant is divided into two large areas: production area and
management area.
Production area includes the battery unit and the inverter room. The
management area contains management offices and meeting rooms to meet
the management requirements of production on site, and is equipped with
proper amount of rest and activity space to facilitate the production staff’s lives.
The station-service power is drawn from the station transformer, with nearby
33kV utility grid or the 2-kilometre-away 132kV grid as the main power source
and the internal power as a backup power supply.
2) Quality control: ensure that all projects meet the requirements of quality
inspection evaluation standards, ensure the quality of technical and
133
100MW Solar PV Plant Project Feasibility Study Report
organizational measures and the quality level, and ensure the realization of the
target level of contract quality.
Due to the fact that construction project management is carried out in the
market condition and is the management of special trading activities and such
trading activities begin with the bidding and last for the entire process of the
project management, contract must be signed according to law and performed
according to the contract. The quality of contract management is directly
related to the technical and economic effectiveness and the goal achievements
of the project management and construction. So the establishment and
fulfillment of contract shall be strengthened from the bidding period. Since
contract management is an activity of law enforcement and obedience,
combined with the fact that the market is divided into domestic and
international markets, the contract management is bound to involve the
relevant national and international regulations, contract versions and contract
conditions, which shall be paid close attention to in contract management. In
order to achieve economic efficiency, improving claims is necessary, methods
and techniques shall be emphasized, and sufficient evidence shall be
provided.
135
100MW Solar PV Plant Project Feasibility Study Report
In order to ensure the normal operation of the solar power plant, management
and technique personnel shall be properly trained before the plant is delivered
and accepted. The purpose of the training is to form a group of skilled
operation and maintenance staff for the solar power system to ensure the daily
system operation and maintenance, fault elimination, data storage in
communication system, etc., and ensure full play of product functions and
normal operation. Theoretical issues and on-site practical training approaches
are applied.
Numbers of
Duration
Training courses training Training site
(days)
people
Product introduction 3 30 to100 local
After 25 years, the owner can go on operate or remove this solar power plant.
If deciding remove, the owner is responsible for recycling and reusing of the
components of the solar power plant as well as the dismantling of all buildings
and underlying structures.
137
100MW Solar PV Plant Project Feasibility Study Report
1、Land Occupation
2、Impact on Vegetation
During project construction period, part of local plants would be destroyed. The
transportation vehicles and working construction machine would damage the
plants. After project starting, the green rating can be higly increased, thus the
environment of boosting station can be recovered to normal staus.
3、Impact on Soil
The hardness and permeability will be changed under trample of workers and
construction machine which will impact the mechanical and physical properties
of soil.
Improper dealing with domestic sewage and garbage will pollute the soil.
The main pollutions and emission in the project construction period and
operation period refer to table 13-1
100MW Solar PV Plant Project Feasibility Study Report
Table 13-1 Main Pollution and Emission During Project Construction and
Operation Period
13.1.1.1 E
n Concentration and Emission
Content
v Emission Source Pollution Type yield before Concentration
n Construction Period:
COD、
t Sewage, Small Amount Small Amount
Water BOD5、SS
a Construction waste water
Pollution
l COD、
Operation Period:Sewage 285t/a Small Amount
BOD5、SS
139
100MW Solar PV Plant Project Feasibility Study Report
be huge in the site and surrounding areas, especially locating under the
direction of wind. There will be severe pollution in ambient air TSP.
In addition, the mechanical exhaust would have a negative impact on the local
environment air in the construction. After finishing the construction, these
effects will disappear and will not have a big impact on the environment.
Through the above analysis, air pollution is mainly dust pollution during the
construction period. So in the construction period, strict measures must be
taken into consideration and followed, such as:
Construction measures
Foundation excavation must be neatly stacked, and carried out by the artificial
surface film pressure. Temporary land can not be arbitrarily occupied.
Excavation and lifting shall share the same land occupation with reasonable
arrangement.
machinery, stone and other building materials shall not be arbitrarily placed to
prevent the destruction of vegetation and soil erosion. Construction machinery
must run in accordance with the construction route to avoid increasing the land
occupation. Reasonable arrangement shall also be taken to reduce the travel
timesimes of vehicles.
For the stack of materials easy to lose, mainly cement, sand and gravel and
other raw materials, the management measures shall be reinforced. The
windbreaks shall be set around the materials. The roof shall be added. And
reasonable arrangements for the stacking position shall be consided. If
necessary, shelter such as the shed cloth, shall be added to cover on the
stacking surface to reduce material loss caused by wind and reduce the dust.
It is strictly prohibited to carry out the dusting construction in the windy weather
conditions.
After taking these measures, it can effectively reduce the influence of dust on
the environment.
141
100MW Solar PV Plant Project Feasibility Study Report
The propogation distance of the mechanical noise in the open area can range
up to 200m. Therefore, in the construction operation, reasonable
arrangements for all kinds of construction working must be taken to reduce the
impact of these noises on the surrounding environment. At the same time, the
noise control in different construction stage shall be done according to the
"construction site noise limits" (GB12523-90).
In the construction period, the main wastewater is the production and domestic
wastewater. Production wastewater is generated by concrete transport
vehicles, construction machinery, machinery repair, and washing the car
maintenance, but the total is small. In the process of construction, the absolute
quantity of production of wastewater is very small, and period is not continuous.
The water pollution factor is less, mainly for the suspended particles. The
locally produced small amounts of wastewater that can not be reused, wound
not formed in surface runoff flow after surface evaporation and infiltration loss.
Therefore, during the construction, the production of wastewater does not
adversely impact the groundwater and river.
The project design, reasonable planning, the project of land reaches the
minimum degree. Road construction do not arbitrarily to both sides to expand.
Take the hardening measures on construction, road surface, avoid the road
surface caused by erosion due to rainfall.
The base as soon as possible, after excavation, pouring concrete, and timely
backfill, rolling surface, shorten the exposed time, reduce dust emission.
The smooth and repair of construction land shall be taken timly during the
construction period and after the construction. Measures for soil and water
conservation shall be taken to avoid new soil erosion.
In winter, it should consider the use of ground source heat pump for heating
and partial use of electric heating int the complex building and boost station.
Therefore, the photovoltaic power plant construction would not increase the
pollution in air environment in the region, the environmental air quality remains
at the original level.
Living sewage will be disposed with centralized treatment after septic tank in
field until reaching the class III standards in "integrated wastewater discharge
standard" (GB8978-1996) and used for green production in living area. This
does not have a negative impact on the water environment.
The noise of this project is relatively single, mainly for the operation and
personnel living noise. No noise pollution.
143
100MW Solar PV Plant Project Feasibility Study Report
Step-up station electromagnetic noise belongs to the low frequency noise. The
noise value is very low. And the outside electromagnetic noise in 1 meter away
from the step-up station basically meets the type II standards in "the factory
boundary noise emission standard" (GB12348-2008) i.
After the project construction and puting into operation, the solid waste is
mainly the life garbage. And the quantity is less. After being collected in the
fixed place and the uniform dispose in designated garbage field, the waste
would have no adverse effects on the environment.
Step-up station is equipped with concrete emergency oil pool. The upper is
sealing and complies with anti-seepage requirement. When the main
transformer faults, all the oil and water mixture in pit will be piped to accident oil
pool by accident discharge pipe. The accident oil would be recycled by the
recycling company, no discharge. No adverse effects will be on the
environment.
According to research data, long time working and living in the the environment
with white light pollution, the retina and iris of people are subject to varying
degrees of damage, a sharp decline in visual acuity, and up to 45% cataract
incidence rate; also the dizzy upset, or even insomnia, decreased appetite,
mood depressed, body fatigue and other similar neurasthenic symptoms.
The project uses the solar photovoltaic panels as the energy collection device.
Because the photovoltaic assembly has a reflective certain, in the process of
absorbing solar energy, there will be some reflection and refraction of sunlight.
This will cause some light pollution on the people around or building. In order to
improve the conversion efficiency of the solar cell, reducing the light reflection
is an important technology in solar cell production. In order to reduce the
reflection of the solar cell, the surface will be deal with the suede processing
technology or by plating antireflection coating technology. Solar cells using the
above technique can make the reflectivity of incident light to be reduced to
100MW Solar PV Plant Project Feasibility Study Report
within 10%. If the use of plating two layers of anti reflection film or suede
processing and reflecting film is used at the same time, the reflectance of
incident light will be reduced to below 4%.
The light pollution will influence the road and traffic. Planting tree on both sides
of the road in post construction period should reduce the impact on the
pedestrian.
145
100MW Solar PV Plant Project Feasibility Study Report
Green Cement
16~27 Soft Ground 12~20 30~40
Grass floor
The project locates in the area with average annual sandstorm days of 115d/a.
The sandstorm weather is cloudy atmosphere. Then the atmospheric
transparency would be greatly reduced, which has certain influence on the
photovoltaic power generation. The annual maximum wind speed is 28m/s in
Tumushuke region. And the anti-wind ability of the solar module arrays can
fully meet the safety requirements.
13.1.3.1 Conclution
1, this project belongs to the encouraged project list of “the catalogue for the
guidance of industrial structure adjustment ". It complies with the national
industrial policy requirements.
5, The waste oil shall not be spilled optionally in the field. The seepage-poof
and fire protection maintenance work of accident oil should be done well to
avoid the bad impact on the environment.
6, The excavated soil shall be stored separately as backfill soil in the latter part
of the construction. Good ecological vegetation should be restored after the
construction.
13.1.3.2 Suggestions
4, Strengthen the greening in step-up station area with low shrubs and
herbaceous plants.
Total
100MW Solar PV Plant Project Feasibility Study Report
1, wind erosion
Wind erosion occuring should have two conditions: the first is that the wind
speed should be greater than that can blow the sand dust; the second is the
bare surface, dry and low vegetation coverage, to provide source of sand by
wind erosion. The region of site locating mainly consists of the fine sand layer
and gravel layer composed of breccias. This surface covers with certain
vegetation. Topsoil consists of soil, sand and gravel mixture with loose and dry
soil as the main composition. Gravel layer is a good bearing layer and
substratum, where the foundation will be placed.
2, Water Erosion
Site terrain is relatively flat, and the site area micro topography and landforms
change little, which will be good for project.
The prediction of water and soil erosion for this project includes all the
perturbations in the surface region, engineering and extruding surface area
including the excavation, backfilling and occupying, but not including the
undisturbed surface area for the project land acquisition.
149
100MW Solar PV Plant Project Feasibility Study Report
The natural restoration period means the duration that the vegetation of the
soft and bare surface will gradually stabilize and restore without taking any
measures of soil and water conservation after the completion of the project.
According to the natural environmental conditions in project area, the natural
restoration period is normally determined to be 1 years. After 1 years of
recovery period, surface disturbance will restore the original state.
Generally, the control measures of soil and water conservation include four
types: engineering measures, temporary measures, plants and management
measures. The detailed information is shown below:
2, plant measures
Mainly means using dustproof net with gravel cover to shield the surface and
sprinkler control to reduce raising dust in the construction site and road.
100MW Solar PV Plant Project Feasibility Study Report
4, management measures
The the soil erosion damage in project area is not serious, mainly because the
area covers with a certain amount of vegetation and artifical disturbance is less.
In engineering construction, surface material and structure is damaged, if
taking no effective measures, there will have a certain degree of wind erosion.
Trying to control the scope of disturbance is an effective way and experience to
reduce surface disturbance and destruction.
The project construction area refers to the land leasing, land occupation and
jurisdiction scope of development and construction projects, which is area with
damage and disturbance directly caused by project construction. The project
construction area consists of two areas including the photovoltaic field and
construction production and living area.
1, the photovoltaic field zone: includes the area of pv support base area, box
type substation and inverter room, approach road, area for permanent repair
151
100MW Solar PV Plant Project Feasibility Study Report
road, temporary path covering, cable trench covering and overhead lines
covering.
2, production and living area: the construction production and living area is
mainly provided with temporary accommodation, materials yard, mechanical
park field and integrated processing factory. Operation production and living
areas is provided with office buildings, warehouse, etc. in the vicinity of the
construction production and living area.
Direct influence area refers to the area outside the construction area, but with
soil and water loss and damage caused by development activities. Although
this region does not belong to the scope of land requisition, it still belongs to
the scope of wat er and soil loss prevention and control of construction units.
Referring to the influence range of similar project and according to the climate
characteristics of the project area, the construction direct influence area is
mainly considered as the zone where would be mainly affected by the
construction activities of photovoltaic field area and the construction production
and living area. In operation period, the direct influence area mainly considers
the production and living area.
Support direct influence area ranges on the basis cover and external
expansion of 0.5m. Box type substation direct influence area ranges on the
basic foundation and external expansion of 2m consideration. During the
period of construction, the direct influence area of construction personnel and
vehicles may directly affect the 2m wide area outside both sides of the road.
The maintenance road is located in the middle of the construction road
maintenance construction with no direct influence area;
The direct influence area of construction production and living areas refers to
the area of outside the boundary with an expanding of 3m consideration. The
direct influence area of operation production and living area refers to the area
of outside the wall boundary with an expanding of 2m.
Prevention and control area of soil erosion in the project area is divided into the
photovoltaic array control area and the construction of production life
prevention area. The key control period is the construction period.
The disturbance types in photovoltaic array control zone are the digging and
backfilling. And the erosion mode is mainly in the form of wind erosion of
excavation face and temporary pile of soil in construction period. The
disturbance types in construction production and living zone is mainly the
surface erosion damage. The wind erosion mode is mainly in the form of failure
surface, temporary pile of soil.
During the period of construction, the original surface in directly influence the
area will be disturbed to some extent, but the degree of disturbance is lighter,
less disturbance frequency. The vegetation and soil structure can maintain the
original level. After the completion of the project construction and a year of
natural recovery period, the land surface in direct influence area can be
restored to its natural state. Therefore, the prevention measures of area
division are mainly in the implementation of the project construction area.
In this area, the excavation and filling disturbance would destroy the native
landscape and native vegetation, and the soil structure would change. In
construction period, the erosion mode is mainly the wind erosion. So this area
is key area for prevention and control of soil erosion.
153
100MW Solar PV Plant Project Feasibility Study Report
The construction method of main project in this area includes the foundation
excavation, concrete pouring, earthwork base backfill and compaction. The
new measures of soil and water conservation includes the engineering
measures, temporary measures, management measures.
Engineering measures: After backfilling the foundation, the cover with gravel
will be able to play a better role in resisting wind erosion.
2, Soil and water conservation measures for box type substation foundation:
The construction method of main project in this area includes the foundation
excavation, pouring of box type substation foundation, earthwork backfill, tamp
and box type substation. The new adding measures of soil and water
conservation include engineering measures, temporary measures,
management measures.
100MW Solar PV Plant Project Feasibility Study Report
Engineering measures: after the backfill of the basis for the box type substation,
covering the surface with gravel to prevent soil erosion.
The main engineering design push rolling road, the new prevention measures
of soil and water conservation include engineering measures, temporary
measures, management measures.
Engineering measures: covering the surface with gravel will play a better role
in preventing wind erosion.
Management measures: cover the road with gravel according to the width
provisions and do timely watering. Adopt the strict management and control of
the vehicle and heavy machinery work scope. All vehicles using the "-" type
operations method to reduce the range of disturbance, preserve the original
155
100MW Solar PV Plant Project Feasibility Study Report
surface, effectively control the additional soil erosion, protect and restore the
ecological environment in this area.
The construction method of the main project in this area includes the
foundation excavation, backfilling and tamping the earth cable burying. The
prevention measures of new soil and water conservation include the temporary
measures and management measures.
measures, loose soil will be vulnerable to wind erosion and raise dust.
Therefore, using the dust-proof net covering in the soil mound field periphery
and using natural stable slope pile for temporary soil pileup to prevent the soil
and water loss.
The construction method of main project in this area includes the site leveling
before construction and site clean-up after construction. During construction,
the prevention measures of new adding soil and water conservation are the
provisional measures. Referring to similar engineering, the effect of taking
watering treatment in this stage is obvious, and the watering period in
construction period is considered as the 100 day.
After the completion of the project, the construction unit should cleaning,
collecting and pulling the solid waste to the designated garbage station for
dispose. The surface buildings should be classified after the dismantlement, or
buried (such as the waste soil), or pull away (such as plate etc.). The the
surface of the site all after cleaning and 1 years of natural recovery period, can
be restored to the original state.
The project has such features including many types, large earthwork
excavation and filling amount. It is a large and complicated construction project.
Therefore, reasonable selections for project land occupation, general layout of
construction, construction organization, construction method and so on, are
not only conducive to economic, efficient and convenient construction, but also
157
100MW Solar PV Plant Project Feasibility Study Report
good fro reducing the maintenance road, cable trench excavation earthwork
and construction disturbance on original landforms and vegetation area, to
reduce man-made soil erosion.
1, Design the rules for soil and water conservation based on the development
and construction of project. The field does not exist in the ecological fragile
zone of debris flow, collapse and landslide prone areas, danger zone, fixed
and semi fixed dune zone. There is no serious soil erosion and ecological
deterioration of the region in the site area without limiting factor of soil and
water conservation.
2, The general layout design of the main engineering normally use the modular
design, new technology, building integrated layout, strictly control the land
occupation of the road and other means to reduce engineering disturbed
surface area, to better protect the original landform of the field and avoid large
disturbance surface to reduce soil erosion.
3, From the analysis of surface disturbance, earthwork, land use and other
aspects in the construction, the scheme is designed to control the soil erosion.
During project construction, the large foundation excavation, backfilling and
topography disturbance are main causes of soil and water loss.
The project will have certain impact on the ecological environment, but
these influences can be reduced through strengthening the management
and the implementation of environmental protection measures. And the
temporary damage can be restored or minimized. Therefore, the project
construction in the environment of the project area is acceptable.
100MW Solar PV Plant Project Feasibility Study Report
1、Article No.28 of The President of the People's Republic of China “Labor Law
of the People's Republic of China”(1994)
4、”Health Standard
159
100MW Solar PV Plant Project Feasibility Study Report
33、”Safety Color”(GB2893-2008)
161
100MW Solar PV Plant Project Feasibility Study Report
Combine the actual engineering with design, adopting the advanced technical
measures and reliable prevention method, take comprehensive prevention and
treatment measures for the high voltage, inflammable, explosive, fire, dust,
sewage, electromagnetic radiation, noise, corrosion, machinery injury and so
on, to ensure satisfying the requirements of labor security and industry hygiene
after engineering construction, guaranteeing the health and safety of the labors
in manufacturing process.
14.1.4 Design Task and Purpose of the Labor Safety and Industry
Hygiene
The supervisor unite should examine whether construction unite follow the
design to construct at any time, whether to take the safety prevention
measures and rectify the problems in construction.
2、After the photovoltaic been put into production, the danger of fire mainly
comes from storage combustible medium, material facilities or place, like the
possibility of fire caused by transformer, oil storage warehouse; the
transformer and valve battery have potential explosive hazards. To reduce the
above dangerous risks, the below measures should be taken in design.
Limit the storage quantity of the dangerous goods, inflammable and explosive
goods, do not over-storage, and do not even mixed storage with other goods,
require putting them in the special warehouse.
Building and structure design, strictly follow the current fire prevention design
code of the country and execute, make fire protection design. In design, make
163
100MW Solar PV Plant Project Feasibility Study Report
safety measures like the fire protection, anti-explosion and so on, in the design
of boost station road designs, meet the fire protection and staff evacuation
requirements. Set enough fire hydrant and water faucet in boost station.
The cable should choose flame-retardant cable, examine the cable quality
before implementation to avoid the fire accident caused by cable quality.
In workplace, nearby of all main structures should have more than 4m ring fire
escape.
4、In boost station construction, it might cause fire danger because of more
than enough oil.
1、High ,low voltage electric devices like Cables, inverter, box transformer
substation and boost station and so on might cause electric shock ,fire and
explosion injuries.
2、Battery might cause the poisonous gas, fire and explosion damages.
3、This project adopt solar panels as the energy power collector devices, as the
photovoltaic module has certain light reflection, when absorbing the solar
power, it will reflect, refract solar light , might produce certain light pollution to
the surrounding people and structures.
4、Peak temperature rise of part of the electric device shells and steel
structures might cause scald injuries.
1、During construction, the construction unite must comply with the regulations
that safety facilities in new, reconstruct and expansion projects of
manufacture management unit ,must be comply with the safety regulations of
constructing ,designing, implementing, putting into production and using with
main engineering.
165
100MW Solar PV Plant Project Feasibility Study Report
design unit, construction unit, supervision unit, census the related qualification,
condition and extents, specify safety production duties, make corresponding
implementation safety management solution and emergency solution.
8、To avoid workplace fire, forbid dangerous factors like smoking, open fires in
places where are prone to fires in construction.
100MW Solar PV Plant Project Feasibility Study Report
Photovoltaic power plant structure fire prevention design meet the current
related fire prevention design criteria requirements, all its components
reach Grade I, II fire resistance level. Detail implementation solution can be
referred in Chapter 8 Fire Fighting Design.
3、Anti-static design
2、Adopt lightning belt or lightning rods to protect the building roofs, devices
and so on which might suffer from thunder shock.
167
100MW Solar PV Plant Project Feasibility Study Report
6、All high voltage switch cabinets should have five prevention functions.
(3) Prevent earth wire with electric and close grounding switch
7、Portable working lamp for overhaul, should conform to” Low voltage limit
value (ELV) “ LGBT3805-2008)
8、Peak temperature rise of electric device shell and steel structure in normal
working , should be no more than 30K for the frequently contact part of the
operators ,and be no more than 40K for the less frequently contact part of the
operators, no more than 65K for the no contact parts, and it should have
obvious safety signs.
2、Structure roof should have parapet (wall),to protect workers falling down by
accident. Exterior stairway, should consider protecting falling down by accident,
set protective barriers and handrails to adopt anti-skid facilities.
Power plant adopts the overall central monitoring solution based on computers,
sets image supervision control system, therefore, the main duty sections of
duty persons are placed in central control room. Combined with the project
characteristics, according to the “ Industrial noise control design specification”
(GBJ87-1985),the noise limits within 60dB.
1. Ventilation AC design
Install air conditioner for the central control, telecommunication room and duty
room and so on, adopt mechanic air exhaust in other working places, to
169
100MW Solar PV Plant Project Feasibility Study Report
2、Heating design
14.3.2.6 Lighting
Make full use of nature light in working places like central control rooms
and so on, when the light is insufficient; take artificial lighting as
supplement, set accident lighting except normal working lighting. According
to the related regulations of lighting design standard, select appropriate
lamps for all layers in complex building, arrange the lighting source
scientifically, the luminance, light should all satisfy” Building lighting design
standard” ( GB50034-2004 ) and “Architecture lighting design
standards”( GBT50033-2001) requirements
1、Ground in switch cabinet room adopt hard, no dust materials (high standard
concrete and water stone), central control room, telecommunication room
adopt air antenna floor, clean with vacuum device; Ventilation inlet of the
mechanic ventilation system should be outside with cleaner air and should be
upper side of the air outlet.
4、Supporting members, water pipes, air pipes and oil pipes of devices should
have economical and reasonable anti-corrosion methods according to different
environment, anti-corrosion disposal crafts like rust-proof, painting rust,
100MW Solar PV Plant Project Feasibility Study Report
2、Fully consider the wind load while designing solar cell supports, consider
frozen earth problems when doing device civil work and construction.
3、After the gale, sand dust storm, snow ice , organize the dust and snow ice
clearance of the solar modules as fast as possible.
4、Indoor working places where people always stay or equipment rooms where
should have freeze-proof requirements should have heating systems
5、Outside main generating power device protective level should meet the
requirements of sand dust storm prevention.
7、Prepare gale, sand dust storm, snow disaster accident emergency solution.
171
100MW Solar PV Plant Project Feasibility Study Report
Table 14-1 Safety color and safety sign places and types
Safety
Sign Name Set the Place Sign Content
Color
Prohibitory 1. Inlet of cables, the room entrance of oil Forbid fire and
Red
Sign system smoking
Fire hydrant
Fire-fighting and fire prevention are the focus of step-up station’s security, in
order to ensure the strict implementation of regulations, correctly use
fire-fighting equipments of step-up station, enhance staff awareness of
fire-fighting, prevent fire accidents, step-up station should formulate
fire-fighting system in detail. Fire-fighting system establishes content of
fire-fighting management, the duties and rights of fire-fighting management,
fire equipment inspection, and regular fire-fighting knowledge and skills
173
100MW Solar PV Plant Project Feasibility Study Report
Fire personnel should regularly check the step-up station and photovoltaic field
area where fire hazards may exist. Report and process problems found during
the inspection.
Train staffs who work in the step-up station regularly on fire-fighting. Training
contents include the use of fire-fighting equipment, boosting station fire
knowledge, emergency escape etc.
1、In accordance with the national relevant regulations and industry standards,
develop electrically operated ticket system, manage electrical operations
strictly, and strengthen training for the electrical operators.
3、Develop staff training system, execute safety education for staff regularly,
organize staff to learn the relevant regulations of the electrical operations.
100MW Solar PV Plant Project Feasibility Study Report
Work ticket system and operation ticket system are effective management
systems that can ensure power production safety, and important measures to
ensure the normal operation of photovoltaic power plant and personal safety.
For strict and efficient implementation of the work ticket and operation ticket
system, the project combined with its situation, develops detailed efficient work
tickets and operation ticket systems, strictly enforce the "two-vote" system, to
prevent the occurrence of violations.
The project should follow the "Regulations on production safety accident report
and investigation processing" (State Council Decree No. 493rd) regulations,
establish investigation, accident reporting, accident statistic system to ensure
dispose of process accidents in time. The engineering quality
and mechanical equipment accidents should be handled by the
relevant units, to confirm the accident case permissions, close
time. The statistical accident record is recorded by computer technology, in
order to facilitate the statistics. Properly use accident statistics, summarize the
experience and lessons from it, to avoid similar accidents from happening
again, and establish a strict system of rewards and penalties at the same time
In accordance with the relevant provisions of the national and local laws and
regulations, photovoltaic power plant should develop safety management
system for motor vehicles. According to the actual situation, make safety
175
100MW Solar PV Plant Project Feasibility Study Report
Rescue persons first in distress, then save the state property; when fight the
beginning fire, must follow the principle: control the fire first, then put out fire,
rescue people first, the general principle after the first priorities.
(5) The correctly analyze the scene, to delineate the danger range, resolutely
decided to take emergency action;
(6) The correctly analyze risk loss, in as much as possible to reduce casualties,
organizes to save material;
(7) When handling the emergency accident, first consider the safety of
personnel, and then consider reducing property loss and environmental
pollution, according to the principle of restore production to
organize for emergency action;
177
100MW Solar PV Plant Project Feasibility Study Report
1、According to the actual situation and the nature of the accident, type,
influence range and serious consequences level and so on to formulate
corresponding plans in scale. In order to make the plan more targeted
and applied rapidly, generally, formulate emergency plans of different types,
such as fire type, explosion type, etc..
3、Develop emergency plan based on the actual condition of the system and
organization.
5、Make regular exercises and review after plans were made, according to the
actual situation ,make regular inspection and correction.
7、The professional team should build up and be equipped with the appropriate
equipments in usual, emergency equipments should be inspected regularly, to
ensure the performance of equipments.
1、Telecommunication system
3、Transportation system
179
100MW Solar PV Plant Project Feasibility Study Report
All staff in the power plant is compulsory fire brigade team. Should be
timely, all compulsory fire brigade members must obey the command of
emergency command department and emergency office.
1、Danger classification
The danger can be divided into two categories in construction and in operation
after construction of the photovoltaic power plant: one is the natural disaster
risk caused by natural hazard. Mainly
includes: snowstorms, earthquakes, floods and others, the other is
the industrial accidents risk caused by industrial accident dangers, mainly
includes: fire, explosion, poisoning, electric shock, acute infectious
disease, falling, mechanical injury, traffic accident and so on.
2、Danger level
According to the results and harms, the dangers are divided into the following
three levels, see table 13-2 for details.
After discovering the dangers, people should distinguish danger levels at first,
if it is the three level danger, report to the duty monitor station
immediately (report to project ministry in the construction process), and the
duty monitor report to the general manager; if it is two level and above danger,
press the nearest fire alarm button immediately (fire or
explosion dangers), and immediately report to the duty
monitor, the monitor reported to commander in the on grid, and report to plant
leaders at the same time . If the fire, explosion, leakage danger are particularly
serious, you can directly dial 119 calls for help.
181
100MW Solar PV Plant Project Feasibility Study Report
Someone is shocked to
Someone are
Electric Someone is electric death by electric or
electric-shocked but no
shock shocked and injured shocked to be badly
injury
injured by electric
Traffic accident
There are casualties or
Traffic happened, no one was
injuries, huge economic
accidents injured
loss
49 mm, local 50 ~ 99 mm, mm, local 100 ~ 290 mm, has clear flood control
Flood
local has water the local water level task and requirements
The project invests 600000 RMB on labor safety and industrial health, as
shown in table 13-3.
The research design puts forward the preventive measures on possible fire,
explosion, electrical injury, mechanical injury, falling injury, collision damage
and other equipment damage accidents. As long as obeying the the national
relevant laws and regulations, technical standards, seriously implementing
various measures about security and occupation harm prevention, strictly
monitoring Construction and installation , strictly following the relevant
requirements in the regulations and standards of "safety production law"
during operation and maintenance in the engineering design, manufacturing,
operation and maintenance, it can provide safety working environment for the
staff workers, and control various risks and harmful factors within acceptable
range.
183
100MW Solar PV Plant Project Feasibility Study Report
Table 14-3 Labor safety and industrial hygiene special project investment
estimate table
Investment
No. Special project content
(USD)
1 Equipment and ancillary facilities, safety and health testing station 15000
4 The factory overall safety and health signs, environmental color 15000
Total 100000
15 Energy Saving
2,By economic and technical comparison, try adopting mature technology and
reasonable process system, optimize equipment selection and configuration,
to meet the reasonable and applicable requirements. Try best to achieve the
technical solutions which are reliable and practical, innovative, material saving,
simple structure;
4, Strictly control the power plant land targets, conserve land resources;
The construction and operation follow the following rational use and energy
saving design specifications of national and local major standards
100MW Solar PV Plant Project Feasibility Study Report
6、“In hot summer and warm winter area residential building energy efficiency
design standards”(JGJ75-2003);
187
100MW Solar PV Plant Project Feasibility Study Report
1, the construction power of this project is introduced from the nearby 33kV
public utility grid for use in the construction period. Meanwhile, in the
construction site, prepare two sets of 100kW diesel generators (occupied 60%
of total amount), and the rest will use 33kV standby power (occupied 40% of
total amount) which is introduced from the nearby villages.
construction.
The project is located in State-owned unused wasteland with sparse
vegetation, but the surface after construction by machinery and other
man-made disturbances, is easy to form dust, and affect the environment.
Therefore, in the construction general layout design, the space utilization,
functional areas, and process optimized layout are optimized and considered
to take some protective measures in order to achieve rational distribution,
reducing the land and protecting the environment. Temporary land will have no
adverse impacts on local land resources and the environment in the long term.
5, Construction materials
Primary energy oil consumption in this project is 66t, converted into standard
coal is 97t; secondary energy power is approximately 80,000 kWh, converted
into standard coal is 30t. Total energy consumption converted into standard
coal is 127t in construction.
1, Electrical losses
3, water consumption
4, Fuel consumption
As the annual consumption of oil is small, can be purchased from nearby, had
no effect on local fuel.
The water consumption is relatively small, has less impact on the regional
groundwater resources.
100MW Solar PV Plant Project Feasibility Study Report
Direct economic benefit is equivalent to 930 million U.S. dollars GDP within the
economic life of the project. According to energy consumption and economic
output in the economic life of the project, the calculated energy consumption
indicators are: according to the uniform calorific value standard to calculate is
$ 0.028t SCE / 10000 USD GDP. From the result analysis, this power plant
energy consumption indicators are far below the national standard, this project
is an energy-saving project in line with the development of national energy
policy.
191
100MW Solar PV Plant Project Feasibility Study Report
(4) To reduce energy loss of mechanical ventilation, the open area of outside
window should be controlled not less than 30%.
(5) In order to reduce heat losses caused by poor air tightness of the room,
tightness of outside window should be controlled not less than 4, airtight of
glass curtain wall is not less than 3.
(6) In order to reduce indoor heat transfer, new insulation materials are
adopted for exterior walls and roof.
When electricity transmitted from photovoltaic power plant station to the grid,
will cause electric power loss which is power loss during the backbone network
and distribution network. Transmission power loss includes transmission line
power loss and transformer power loss. Power losses include active and
Reactive power loss ,active power loss lose with electric power, increases
energy consumption, reactive power loss will not directly cause power loss,
but increasing current to increase active power loss, thereby increase the
electric power loss.
The power plant engineering design has already considered the scale of power
plant construction, regional network planning, such as the effective number of
operating hours the situation of power plants, besides, considered the output
combined with overall size of power plant.
The station line engineering refers to the collector within the power plant.
Combined with the actual situation of the project, under the guidance of energy
saving circuit design principle, take measures from the aspects of route plan,
wire selection and insulation coordination and so on .
a) Path solution
b) Conductor selection
Combined with effective operation hours, construction scale, the local climate
and other conditions of the photovoltaic power plant, select the appropriate
wire models. Recommend 33kV voltage level.
d) Basic design
193
100MW Solar PV Plant Project Feasibility Study Report
d) Strictly control the construction area, reduce heating area to reduce the
corresponding energy consumption.
The cement consumption in the project is mainly for civil engineering concrete
structures like the civil works of photovoltaic PV modules, step-up station, etc.
In order to reduce the amount of cement, comprehensively utilize resources, all
cement in the project was incorporated with water
Timbers in the project are mainly consumed for timber templates, windows,
furniture, etc, in order to reduce wood consumption, save raw materials,
100MW Solar PV Plant Project Feasibility Study Report
protect environment, therefore, this project does not promote the use of wood,
all the templates and windows are made of steel, only a few doors and
furniture are made of wood.
To reduce damage to arable land, protect arable land resources, the project
does not adopt clay bricks.
The construction time of the project is long with large energy consumption. In
engineering design comparison, the preferred construction method is choosing
solution which is feasible, has advanced construction equipment (low-energy)
and the lowest indicators. In design process, the comprehensively apply
various methods to promote conservation and rational use of resources to
reasonably dispatch and arrange construction time and order in construction
progress, to reduce peak, so that to balance construction strength and reduce
energy consumption, the energy saving saving measures are mainly reflected
in the following aspects.
Make full use of local resources, reduce set-scale of complex processing plant,
thereby reduce the configuration numbers of processing and machine repair
devices. Consider using the new energy-saving equipments when selection.
195
100MW Solar PV Plant Project Feasibility Study Report
Reasonably and scientifically allocate staff and living facilities, maximize the
use of energy-saving equipments, reduce operating costs, save energy and
improve efficiency. Strengthen energy saving management, establish and
improve energy saving management (including saving money, energy
consumption, cost management, energy work responsibilities, promoting
energy conservation and training, dedicated energy engineers, etc.) system.
Changes the thoughts, enhance the sense of resources, energy saving and
responsibility, to form good energy saving habits.
Oil mainly comes from transformers in operation time, includes the oil within
ground washed wastewater generated by run, emit, drip, ground leakage of
production oil and leakage oil of repairing machines. In order to prevent oil
pollution, both control the oil source and intercept the pollution. Strengthen
management, avoid the run, emit, drip, drain of equipment and piping oil to
realize cleaner production; lay oil-absorbing substances like sawdust sinotrans
and so on on the ground , control oil pollution, burning sawdust sinotrans when
transporting them outside .Set the main transformer oil pit under the main
transformer, and set the overall emergency oil pool, recycled by specialized
units. Oily wastewater collection can entrust specialized units to recycle.
197
100MW Solar PV Plant Project Feasibility Study Report
15.7 Conclusion
1
100MW Solar PV Plant Project Feasibility Study Report
AppA Reference A
Note:
List 1 :
List 2: