Ring Road 1
Ring Road 1
prepared surface of granular base including clearing of road surface and spraying emulsion at the rate of
0.70 kg/sqm using emulsion pressure distributor for finished item of work etc., complete as per MoRT&H
of 0.20 kgs per sqm on the prepared bituminous surface cleaned with mechanical broom for finished item of
work as per MoRT&H Specification 503 (5th revision) and as directed by the Engineer-in-Charge.
For BC
Km 0/0 - 6/5 BHS 1 x 2 6500.00 7.00 91000.00
91000.00
91000.00 11.80 1073800.00
sqm
6 Providing and laying of 50 mm thick Dense Graded Bituminous Macadam with 100 - 120 TPH batch type hot
mix plant producing an average output of 75 tones per hour using hard blasted granite crushed aggregates
of Grading - II as per table 500-10 of MoRT&H Specification 505 (5th revision) premixed with bituminous
binder of VG 30 grade @ 4.50% of weight of total mixture, transported to site, laid over a previously
prepared surface with a hydrostatic paver finisher with sensor control to the required grade, level and
alignment and rolled as per Clauses 501.6 and 501.7 to achieve the desired compaction for finished item of
work as directed by the Engineer-in-Charge including hire and operational charges all T&P and all other
contingent charges necessary including cost of (excluding seigniorage) charges of all materials etc.,
complete in all respects as directed by Engineer-in-Charge and as per MoRT&H specification No. 505 (5th
Revision)
DBM
Km 0/0-1/0 LHS 1 x 1 280.00 7.00 0.05 98.00
Km 0/0-1/0 RHS 1 x 1 370.00 7.00 0.05 129.50
Km 1/0-2/0 LHS 1 x 1 350.00 7.00 0.05 122.50
Km 1/0-2/0 RHS 1 x 1 300.00 7.00 0.05 105.00
Km 2/0-3/0 LHS 1 x 1 320.00 7.00 0.05 112.00
Km 2/0-3/0 RHS 1 x 1 330.00 7.00 0.05 115.50
Km 3/0-4/0 LHS 1 x 1 250.00 7.00 0.05 87.50
Km 3/0-4/0 RHS 1 x 1 400.00 7.00 0.05 140.00
Km 4/0-5/0 LHS 1 x 1 260.00 7.00 0.05 91.00
Km 4/0-5/0 RHS 1 x 1 390.00 7.00 0.05 136.50
Km 5/0-6/5 LHS 1 x 1 330.00 7.00 0.05 115.50
Km 5/0-6/5 RHS 1 x 1 320.00 7.00 0.05 112.00
1365.00
say 1365.00 8720.00 11902800
Cum /Cum
7 Providing and laying of 30 mm thick Bituminous Concrete with 100 - 120 TPH batch type hot mix plant
producing an average output of 75 tones per hour using hard blasted granite crushed aggregates of
Grading – II as per Table 500-17 of specification 507 of MoRT&H (5th revision), premixed with Bituminous
binder of VG 30 Grade @ 5.4 % of mix and filler, transporting the hot mix to work site, laying with
hydrostatic sensor paver finisher to the required grade, level and alignment, rolling with smooth wheeled,
vibratory and tandem rollers to achieve the desired compaction as per MoRT&H Specification 507 (5th
revision) complete for finished item of work in all respects as directed by Engineer-in-Charge
For BC
Km 0/0 - 6/5 BHS 1 x 2 6500.00 7.00 0.03 2730.00
2730.00
2730.00 9742.00 26595660
Cum /Cum
8 Forming shoulders with borrowed useful seclected earth having MDD of not less than 1.75 gms/cc from
outside road boundary by mechnical means with all leads and lifts including pre-watering of soil at borrow
area, removal of top soil, excavation of soils at borrowed area, conveyance of soil, depositing the soils on
the embankment, spreading soils, breaking clods, sectioning and consolidation with vibratory road roller @
OMC to meet requirement of table 300-2 of MORT&H including all hire and operational charges of T&P ,
complete for finished item of work as per MORT&H specification 305 (5th revision) (Payment will be made
based on levels for finished item of work)
BM+BC Stretches
Km 0/0-1/0 LHS 1 x 1 560.00 1.50 0.10 84.00
Km 0/0-1/0 RHS 1 x 1 740.00 1.50 0.10 111.00
Km 1/0-2/0 LHS 1 x 1 700.00 1.50 0.10 105.00
Km 1/0-2/0 RHS 1 x 1 600.00 1.50 0.10 90.00
Km 2/0-3/0 LHS 1 x 1 640.00 1.50 0.10 96.00
Km 2/0-3/0 RHS 1 x 1 660.00 1.50 0.10 99.00
Km 3/0-4/0 LHS 1 x 1 500.00 1.50 0.10 75.00
Km 3/0-4/0 RHS 1 x 1 800.00 1.50 0.10 120.00
Km 4/0-5/0 LHS 1 x 1 520.00 1.50 0.10 78.00
Km 4/0-5/0 RHS 1 x 1 780.00 1.50 0.10 117.00
Km 5/0-6/5 LHS 1 x 1 660.00 1.50 0.10 99.00
Km 5/0-6/5 RHS 1 x 1 640.00 1.50 0.10 96.00
1170.00
1170.00 261.00 305370
Cum /cum
Cum
47163317.50
Superintending Engineer
(R&B) Circle.Kadapa
Specification report to accompany the estimate for the work of " Special Repairs to R-R Road at
Km 138/0 to R-R Road at Km 122/6 crossing Kadapa-Pulivendula road and Kadapa-Rayachoty
road from KM: 0/0 to 6/5 in YSR District.".
Estimate amount Rs :: 580.00 Lakhs
Authority ::- As per the instructions of the higher authorities.
Necessity : - The R-R Road at Km 138/0 to R-R Road at Km 122/6 crossing Kadapa-
Pulivendula road and Kadapa-Rayachoty road from KM: 0/0 to 6/5 in YSR District in Kadapa
Sub Division and number of link roads are connected to this road . This road is widely used as
ByePass Road for the Kadapa Town. Hence the traffic intensity on this road is considerably high.
The existing carriageway in R-R Road at Km 138/0 to R-R Road at Km 122/6 crossing Kadapa-
Pulivendula road and Kadapa-Rayachoty road from KM: 0/0 to 6/5 is badly damaged due to
heavy traffic and continuous heavy rains in the precedent years.The vehicular traffic is facing
much in conveyance to pass on the road. The last renewals of these road is Hence, it is
proposed to take up special Repairs in the above said stretches as per the instructions of the
higher authorities. It is proposed to strengthen badly distressed stretches with Bituminous
Concrete(BC) 30 mm thick for free flow of vehicular traffic.
Rates :- The rates adopted in this estimate are as per common SSR for all Engineering
departments for the year 2024-25 and the work will be carried out as per IRC, MORT&H
specifications.
Assistant Executive Engineer Deputy Executive Engineer Executive Engineer
(R&B) Section Sidhout (R&B) Sub Division, Kadapa (R&B) Division, Kadapa
Superintending Engineer
(R&B) Circle, kadapa
GOVERNMENT OF ANDHRA PRADESH
3 Price Adjustment
7 Avagahana Sadassulu
LS provision for Unforeseen Items and
8
Rounding off
Total #REF!
Note: All the specifications in the detailed estimate & Abstract estimate may be
modified as specified in the data
Sand
cum
Quantity
10
0.00
100.00
0.00
DATA WITH SSR 2024-25
Whether to Add MAA or Any other Area Allowance Yes/No Allowable%
Name of Work ::- Special Repairs to R-R Road at Km 138/0 to R-R Road at Km 122/6 crossing Kadapa-
Pulivendula road and Kadapa-Rayachoty road from KM: 0/0 to 6/5 in YSR District.
Quantity Description of Item Rate per
1 Scarifying the existing B.T surface to a depth of 50 mm by Mechanical means and disposal of scarified material with all
leads and lifts upto 1000 Mtrs as per MoRT&H (5th Revision) Specn. No.305.4.3
2 Providing, Laying, Spreading and compacting graded HBG crushed stone aggregate to Wet Mix macadem
specification ( 5th Revision) as per Table 400-13, including cost of all materials and including premixing the
material with water at OMC in Mechanical mix plant carriage of mixed material by tipper to site , laying in uniform
layers with paver in base courses on well prepared surface and compacting with Vibratory roller to acheive the
desired density etc., as directed by the Engineer-in-Charge and as per MoRT&H specification.406 (5th revision) for
finished item of work.
3 Providing and applying prime coat with bitumen emulsion (SS1) Bulk using emulsion pressure distributor on prepared
surface of granular base including clearing of road surface and spraying emulsion at the rate of 0.70 kg/sqm using
emulsion pressure distributor for finished item of work etc., complete as per MoRT&H Specification 502 (5th revision)
and as directed by the Engineer-in-charge
Unit = sqm
Quantity Description of Item Rate per
Taking output = 3500 sqm
a) Labour
0.080 day Mate 645.00 day
2.000 day Mazdoor 595.00 day
25.00 % Add MAA or Any other Area Allowance 1241.60
b) Machinery
2.800 hr Mechanical broom @ 1250 sqm 460.00 hour
2.800 hr Air compressor 250 cfm 651.58 hour
2.000 hr Emulsion pressure distributor @ 1750 sqm per hour 1084.00 hour
1.000 hr Water tanker 6 KL capacity @ 1 822.00 hour
c) Material
2.450 MT Bitumen emulsion @ 0.7 kg per sqm 73796.20 MT
a+b+c
4.615 % d) OH Charges on (a+b+c)
a+b+c+d
e) Contractor's profit @ 10 % input on
(a+b+c+d)
Cost for 3500 sqm =
Rate per sqm =
(a+b+c+d+e)/3500
4 Providing and applying tack coat with bitumen VG-10 (Bulk) using Bitumen pressure distributor at the rate of 0.20
kgs per sqm on the prepared bituminous surface cleaned with mechanical broom for finished item of work as per
MoRT&H Specification 503 (5th revision) and as directed by the Engineer-in-Charge.
Total
(C) Material
0.70 MT Bitumen VG-10 (Bulk) @ 0.20 Kgs/sqm 39051.20 MT
Total
(D) Over head charges @ 4.615%
4.615 % Add for Over head charges @ 4.615% on (A)+(B)+( C)
(E) Total of (A) + (B)+( C)+(D)
(F) Add Contractors Profit at 10% on (E)
Cost per 3500 sqm (E) + (F)
Rate per 1 sqm
Rate to be adopted
5 Providing and applying tack coat with bitumen VG-10 (Bulk) using Bitumen pressure distributor at the rate of 0.25
kgs per sqm on the prepared Granular surface treated with primer cleaned with mechanical broom for finished
item of work as per MoRT&H Specification 503 (5th revision) and as directed by the Engineer-in-Charge.
Total
(C) Material
0.875 MT Bitumen VG-10 (Bulk) @ 0.25 Kgs/sqm 39051.20 MT
Quantity Description of Item Rate per
Total
(D) Over head charges @ 4.615%
4.615 % Add for Over head charges @ 4.615% on (A)+(B)+( C)
(E) Total of (A) + (B)+( C)+(D)
(F) Add Contractors Profit at 10% on (E)
Cost per 3500 sqm (E) + (F)
Rate per 1 sqm
Rate to be adopted
6 Providing and laying of 30 mm thick Bituminous Concrete with 100 - 120 TPH batch type hot mix plant producing
an average output of 75 tones per hour using hard blasted granite crushed aggregates of Grading – II as per Table
500-17 of specification 507 of MoRT&H (5th revision), premixed with Bituminous binder of VG 30 Grade @ 5.4 % of
mix and filler, transporting the hot mix to work site, laying with hydrostatic sensor paver finisher to the required grade,
level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as
per MoRT&H Specification 507 (5th revision) complete for finished item of work in all respects as directed by
Engineer-in-Charge
5.00 nos. Skilled Mazdoor for checking line and levels. 661.00 1.00
25.00 % Add MAA or Any other Area Allowance 12176.80
TOTAL A=
(B) Machinery
6.00 hour Batch mix Hot Mix Plant @ 75 Tonne per hour 31115.00 1.00
6.00 hour Paver finisher hydrostatic with sensor control 3891.00 1.00
6.00 hour Generator 250 KVA 2572.00 1.00
6.00 hour Front end loader 1 cum capacity 2043.00 1.00
3.90 hour Power road roller 8 ton for initial break down rolling 1737.71 1.00
3.90 hour Vibratory roller 8 ton for intermediate rolling 3488.54 1.00
Finish rolling with 6-8 ton. smooth wheeled tandem
3.90 hour roller 2208.00 1.00
TOTAL B=
(C) Material
Bitumen VG 30 @ 5.40 %
24.30 MT Wi. of Bitumen = 450 x 5.4 / 100 = 24.30 MT 39851.20 1.00
ii) Aggregate
TOTAL weight of mix = 450 tones
Weight of bitumen - 24.30 tones
Weight of aggregate = 450-24.30 = 425.70 tones
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 283.8 cum
Grading - II (13 mm nominal size)
IRC & MORT&H HBG M/C chips 13.2-10 mm @ 30% -
85.14 cum Avg. of (12-14 mm),(9.5-11.2 mm) 1608.46 1.00
Unit = cum
Taking output = 100 cum
(A) Labour
0.04 nos Mate 645.00 day
1.00 nos Mason unskilled 595.00 day
25.00 % Add MAA or Any other Area Allowance 620.80
Total
(B) Machinery
1.67 hr Hydraulic Excavator 1 cum bucket capacity @ 60 cum 3594.04 hr
per hour
800.00 t.km Tipper 160 5 800 8.60 cum
Add 10% extra towards cost of carriage to cover cost
of loading and unloading
8 Providing and laying of 50 mm thick Dense Graded Bituminous Macadam with 100 - 120 TPH batch type hot mix
plant producing an average output of 75 tones per hour using hard blasted granite crushed aggregates of Grading -
II as per table 500-10 of MoRT&H Specification 505 (5th revision) premixed with bituminous binder of VG 30 grade
@ 4.50% of weight of total mixture, transported to site, laid over a previously prepared surface with a hydrostatic
paver finisher with sensor control to the required grade, level and alignment and rolled as per Clauses 501.6 and 501.7
to achieve the desired compaction for finished item of work as directed by the Engineer-in-Charge including hire and
operational charges all T&P and all other contingent charges necessary including cost of (excluding seigniorage)
charges of all materials etc., complete in all respects as directed by Engineer-in-Charge and as per MoRT&H
specification No. 505 (5th Revision)
TOTAL A=
(B) Machinery
6.00 hour Batch mix Hot Mix Plant @ 75 Tonne per hour 31115.00 1.00
6.00 hour Paver finisher hydrostatic with sensor control 3891.00 1.00
6.00 hour Generator 250 KVA 2572.00 1.00
6.00 hour Front end loader 1 cum bucket capacity 2043.00 1.00
Smooth wheeled roller 8-10 tonesfor initial break
3.90 hour 1737.71 1.00
down rolling
3.90 hour Vibratory roller 8 tones for intermediate rolling 3488.54 1.00
Finish rolling with 6-8 tones smooth wheeled tandem
3.90 hour 2208.00 1.00
roller
TOTAL B=
Quantity Description of Item Rate per
(C) Material
20.25 MT Wt. of Bitumen = 450 x 4.5/100 = 20.25 MT 39851.20 1.00
ii) Aggregate
TOTAL weight of mix = 450 tones
weight of bitumen = 450*4.5 / 100 = 20.25 tones
Weight of aggregate = 450-20.25 = 429.75 tones
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 286.50 cum
Grading - II (19 mm nominal size)
IRC & MORT&H HBG M/C chips 25-10 mm @ 30 % -
85.95 cum Avg. of (25-27 mm),(19-22 mm),(12-14 mm) (9.5-11.2 1777.83 1.00
mm)
6.45
148.75
38.80
194.00
43.84
408.60
291.32
743.76
43.28
98.10
1079.14
10.79
10.80
1 Sqm
acting graded HBG crushed stone aggregate to Wet Mix macadem
ble 400-13, including cost of all materials and including premixing the
al mix plant carriage of mixed material by tipper to site , laying in uniform
well prepared surface and compacting with Vibratory roller to acheive the
Engineer-in-Charge and as per MoRT&H specification.406 (5th revision) for
309.60
1322.00
5950.00
1895.40
9477.00
13226.40
11016.00
12258.00
17166.00
13605.31
2466.00
69737.71
157847.78
181773.50
78860.63
418481.91
22968.70
520665.32
52066.53
572731.85
2545.47
2545.00
Cum
h bitumen emulsion (SS1) Bulk using emulsion pressure distributor on prepared
ing of road surface and spraying emulsion at the rate of 0.70 kg/sqm using
d item of work etc., complete as per MoRT&H Specification 502 (5th revision)
ge
Amount
51.60
1190.00
310.40
1552.00
1288.00
1824.42
2168.00
822.00
6102.42
180800.69
188455.11
8697.20
197152.32
19715.23
216867.55
61.96
62.00
1 Sqm
bitumen VG-10 (Bulk) using Bitumen pressure distributor at the rate of 0.20
ous surface cleaned with mechanical broom for finished item of work as per
n) and as directed by the Engineer-in-Charge.
51.60
1190.00
310.40
1552.00
1288.00
1824.42
3814.00
6926.42
27335.84
27335.84
1652.83
37467.09
3746.71
41213.80
11.78
11.80
1 Sqm
bitumen VG-10 (Bulk) using Bitumen pressure distributor at the rate of 0.25
r surface treated with primer cleaned with mechanical broom for finished
on 503 (5th revision) and as directed by the Engineer-in-Charge.
51.60
1190.00
310.40
1552.00
1288.00
1824.42
3814.00
6926.42
34169.80
Amount
34169.80
1968.22
44616.44
4461.64
49078.08
14.02
14.00
1 Sqm
Bituminous Concrete with 100 - 120 TPH batch type hot mix plant producing
ur using hard blasted granite crushed aggregates of Grading – II as per Table
H (5th revision), premixed with Bituminous binder of VG 30 Grade @ 5.4 % of
to work site, laying with hydrostatic sensor paver finisher to the required grade,
h wheeled, vibratory and tandem rollers to achieve the desired compaction as
revision) complete for finished item of work in all respects as directed by
541.80
8330.00
3305.00
3044.20
15221.00
186690.00
23346.00
15432.00
12258.00
6777.07
13605.31
8611.20
266719.58
968384.16
136943.86
103699.10
120991.22
5023.71
1335042.05
1616982.63
74623.75
169160.64
1860767.02
9742.24
9742.00
1Cum
Amount
eful seclected earth having MDD of not less than 1.75 gms/cc from outside
h all leads and lifts including pre-watering of soil at borrow area, removal of top
ea, conveyance of soil, depositing the soils on the embankment, spreading soils,
dation with vibratory road roller @ OMC to meet requirement of table 300-2 of
tional charges of T&P , complete for finished item of work as per MORT&H
ent will be made based on levels for finished item of work)
25.80
595.00
155.20
776.00
6002.05
6880.00
688.00
1525.52
3288.00
3488.54
21872.11
1045.21
23693.32
2369.33
26062.65
260.63
261.00
1 Cum
Dense Graded Bituminous Macadam with 100 - 120 TPH batch type hot mix
5 tones per hour using hard blasted granite crushed aggregates of Grading -
cification 505 (5th revision) premixed with bituminous binder of VG 30 grade
ransported to site, laid over a previously prepared surface with a hydrostatic
e required grade, level and alignment and rolled as per Clauses 501.6 and 501.7
finished item of work as directed by the Engineer-in-Charge including hire and
ther contingent charges necessary including cost of (excluding seigniorage)
te in all respects as directed by Engineer-in-Charge and as per MoRT&H
541.80
8330.00
3305.00
3044.20
15221.00
15221.00
186690.00
23346.00
15432.00
12258.00
6777.07
13605.31
8611.20
266719.58
Amount
806986.80
152804.49
117247.95
113620.74
5071.51
1195731.49
1477672.07
68194.57
154586.66
1700453.30
8720.27
8720.00
COST OF BITUMEN / MT WITH LEADS
N.W:- Special Repairs to R-R Road at Km 138/0 to R-R Road at Km 122/6 crossing Kadapa-
Pulivendula road and Kadapa-Rayachoty road from KM: 0/0 to 6/5 in YSR District.
Ref ::- For Emulsion (Bulk) , IOCL Price List with effect from Dt. 16.09.2024
For Bulk Bitumen VG-30 & VG-10 IOCL Price List With effect from Dt. 16.09.2024
20 329.33 316.74 9.5 to 11.20 mm IRC & MoRTH HBG M/C metal 840.00
22 359.73 345.98 2.36 to 5 mm IRC & MoRTH HBG M/C metal 487.00
34 532.01 511.66
35 544.68 523.84
36 557.35 536.02
40 608.03 584.74
41 620.70 596.92
42 633.37 609.10
43 646.04 621.28
49 722.06 694.36 Dozer 80 HP for spreading @ 200 cum per hour 3051.04
59 848.76 816.16 Tractor with ripper attachment @ 60 cum per hour 548.00
67 950.12 913.60 Hydraulic self propelled chip spreader @ 1500 sqm/hr 3264.00
68 962.79 925.78 Finish rolling with 6-8 tonne smooth wheeled tandem r2208.00
75 1051.48 1011.04 Tipper 5.50 cum capacity per Tonne per km 8.60
78 1089.49 1047.58
107 1456.92 1400.80 Picking old metal 40 mm Size Si No-152 SoR (part-II) 70
Unit = t.km
Taking output 10 tonnes load and lead 10 km = 100 t.km
Surfaced Road
Speed with load : 25 km / hour.
a) Machinery.
Tipper 10 tonne capacity
Time taken for onward haulage with load hour 0.400 1266.61
Time taken for empty return trip. hour 0.290 1266.61
b) Overhead charges @ input on (a)
c) Contractor's profit @ input on (a+b)
506.64
367.32
873.96
8.70
N.W:-
Si. No. Description of item Quantity in loose quantity per Seigniorage Amount in Rs.
Cum cum Charges per unit
Road work
E/W for forming embankment 38226.00 1.00 30.00 1146780.00
1 with side earth
E/W for forming embankment 13591.00 1.00 30.00 407730.00
2 with carted earth
3 Shulders with borrowed earth 7493.00 1.00 30.00 224790.00
DRAINS
14 E/W excavation 1716.00 1.00 30.00 51480.00