Hicban, Alcy - Assignment On Material Requirement Planning
Hicban, Alcy - Assignment On Material Requirement Planning
LM-331
ASSIGNMENT ON MRP
Eighty units of end item E are needed at the beginning of week 6.Three cases (30) units per case of J have
been ordered and one case is scheduled to arrive in week 3, one in week 4,and one in week 5. Note: J
must be ordered by the case, and B must be produced in multiples of 120 units. There are 60 units of B
and 20 units of J now on hand. Lead times are two weeks each for B and one week for J.
A. Prepare a material requirements plan for component J.
Master Week 1 2 3 4 5 6
Schedule for
E: Quantity 80
E LT = 2 Beg
Lot size: Lot-for-Lot Inv: 1 2 3 4 5 6
Gross requirements 80
Scheduled receipts
Projected on hand 0 0 0 0 0 0 0
Net requirements 80
Planned-order receipts 80
Planned-order releases 80
B(2) LT = 2 Beg
Lot size: Multiples of 120 Inv: 1 2 3 4 5 6
Scheduled receipts
Projected on hand 60 60 60 60 60 20 20
Scheduled receipts 30 30 30
Projected on hand 20 20 20 50 80 50 50
B. Suppose that in week 4 the quantity of E needed is changed from 80 to 70. The planned order
releases through week 3 have all been executed. How many more B’s and J’s will be on hand in
week 6.
Master Week 4 5 6
Schedule for
E: Quantity 70
E LT = 2 Beg
Lot size: Lot-for-Lot Inv: 4 5 6
Gross requirements 70
Scheduled receipts
Projected on hand 0 0 0 0
Net requirements 70
Planned-order receipts 70
Planned-order releases 70
B(2) LT = 2 Beg
Lot size: Multiples of 120 Inv: 4 5 6
Net requirements
Planned-order receipts
Planned-order releases
Net requirements
Planned-order receipts
Planned-order releases