Miscellaneous Topics Module Problem Set June 2024 Review
Miscellaneous Topics Module Problem Set June 2024 Review
Elements in a PERT / CPM Diagram: Slope = Additional Cost / No. of Days to be Reduced
1. Activity - Performance of a specified task
2. Event – Completion or commencement of an activity
3. Duration – Estimated period of time to complete an activity SITUATION 1: The activities, duration, and cost under normal and
4. Network Diagrams – Logical assembly of activities accelerated conditions for a network diagram are shown in the
5. Dummy activity – artificial activity with zero duration; applied accompanying table.
to parallel activities to denote that no succeeding activity
shall commence until all previous activities are completed
6. Critical Path – The longest path in the network; dictates the
earliest completion time of the project.
ACI METHOD
Standard procedures stated in ACI211.1.