0% found this document useful (0 votes)
9 views10 pages

Methodology Iloboto

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
9 views10 pages

Methodology Iloboto

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 10

METHODOLOGY AND MOBILIZATION SCHEDULE

Introduction
The intent of this Construction Work Plan is to present the general sequence of pre-construction and
construction activities which are planned to take place. This plan also summarizes the proposed
methodology for performing various phases of the work. It describes possible equipment and
personnel to be used, general sequencing of the work activities, the use of the site for staging,
stockpiling and other activities, and security.

SITE ORGANIZATION & STAFFING

SITE AGENT’S SITE STORE


SITE
OFFICE CLERK’S
SITE OFFICE
OFFICE

Site Organization Chart

SITE AGENT

ASSISTANT
SURVEYOR
SITE AGENT

FOREMAN

CASUALS

METHODOLOGY 1
Head Office Organization Chart

MANAGING
DIRECTOR

BUSINESS
DEVELOPMENT
MANAGER

OPERATIONS ADMINISTRATION
MANAGER ASSISTANT

PROJECTS MARKETING AND ACCOUNTS


ENGINEER/ TENDERING ASSISTANT
EXECUTIVE
DIRECTOR

ENGINEERING OFFICE ASSISTANT


ASSISTANT

Schedule of Key Personnel


DESIGNATION NAME QUALIFICATIONS
Project Director
Site Agent
Electro-Mechanical
Engineers
Drilling Inspectors

Pipeline Foreman/Water
Inspector

Surveyor

Support Staff/Civil
Engineers
(Please find the attached company profile containing CVs)
MATERIALS

In-situ soils (pan wall)-Excavation from pan reservoir

Concrete – outlet pipe trenches and ancillary concrete

Pipes and fittings-both GI and HDPE-in draw off system and distribution to tapping points

METHODOLOGY 2
Hardcore-rock fill, riprap, stone pitching –In Slope Protection

Scope
The following is the scope of works we intend to cover in the execution of project as described in the bills of
quantities:
1. PRELIMINARIES AND GENERAL ITEMS
2. CONSTRUCTION OF WEIR OFFTAKE I & II
• Concrete Weir
• Draw-off System for Gravity Mains
• Installation of Filter Media Surround
• Draw-off Pipeline Including Fittings
• Anchorage to pipeline
3. CONSTRUCTION OF ILOBOTO-MUTANDA GRAVITY MAINS
4. CONSTRUCTION OF MUTANDA JUNCTION-MBUINUI-KITUIUNI GRAVITY MAINS
5. CONSTRUCTION OF KAEANI-KIVUUNI LINE
6. CONSTRUCTION OF NGILIANI-KITHANGATHINI LINE
7. MATUNDA LINE RIDGE 2 DISTRIBUTION LINE
1.0 PRELIMINARIES & GENERAL ITEMS
1.1 MOBILIZATION.
Upon being notified of the award and consequent order to commence the works the following will be
effected:
 Providing the Performance Security and Insurances for works, plant/machinery and labour/personnel.
 Identifying suitable sites to set up material sites and camp site for the Site Agent and his site staff. The
camp will accommodate the Site Agent’s offices, stores, workshop, land plant/machinery. The Engineer’s
representative will be facilitated by provision of offices, supervision vehicles, miscellaneous items and
support staff.
 Making good all access pans to Camp site and material sites. All personnel shall then be induced to health
& safety matters before works commence.
 Establishing contacts with the Police and the local administration.
 Works execution cycle

1.2 PLANT AND EQUIPMENT


We shall mobilize the following Equipment type and characteristics , and achieve atleast the Minimum
number required
1) HDPE Pipe Butt Fusion/Welding Machine minimum diameter 150mm 2no
2) Borehole drilling rotary rigs (to depth>200 and nominal internal bore diameter of 254mm) 2no
METHODOLOGY 3
3) Air compressors 1000/300psi capacity or equivalent 1no
4) 7-Ton lorry 1no
5) 0.75m3 Concrete Mixers with vibrator 1no
6) 0.75m3 Concrete dumpers 1no
7) Generator (15Kva) 1no
8) Dewatering pumps (with 50mm inlet) 2no
9) Pick up 2no

2.0 CONSTRUCTION OF WEIR OFFTAKE I & II


2.1 WEIR AND INTASKE CHAMBER CONSTRUCTION
2.1.1 Setting out positions for the structures

This shall be done once the pan area has been identified and limits marked. The positioning will be set not to
affect the pan embankment construction activities.

2.1.2 Formwork & reinforcement.

As specified and/or as directed by the engineer, the relevant formwork shall be erected to give the required
finish. BRC wire mesh or any other reinforcement shall be used as specified and to the engineers’ approval.

Cutting and bending of steel reinforcement to approved schedule shall be done at the site and fixed according
to the structural requirements.

Setting for reinforcement shall be inspected by the engineer for conformity with specification and drawing
requirement in readiness for fixing formwork.

2.1.3 Concrete works


Approved concrete materials-coarse and fine aggregate/sand shall be transported to site using trucks and
stored in accordance to the specification and the engineer approval. Concrete shall be mixed on site by use of
a mechanically propelled concrete mixer.

Mixed concrete (by the appropriate ingredient design mix ratio) shall be transported to the placing locations
with hand tools like wheel barrows and concrete dumpers and shall be compacted with a poker vibrator.

Necessary concrete tests as specified and directed by the engineer shall be performed by our laboratory
technicians and samples taken for testing in approved laboratory per the engineer approval.

Curing of concrete shall commence immediately the concrete has hardened. It shall be covered with woolen
materials or sand and maintained wet by soaking with water.

Here he shall have to construct drift according to specifications’ as may be directed by the engineer.

METHODOLOGY 4
2.2 WEIR CONSTRUCTION METHODOLOGY
2.2.1 Excavation of River foundation:
While keeping construction site dry, we will excavate the river/stream bed of the construction site until all
the organic materials deposited therein have been removed and to the depth where hard foundation is found.
Abutment will also be excavated at least 2 m to the horizontal direction into river bank on both sides.
Foundation of the diversion weir to be constructed will further be excavated 50 cm to 70 cm in depth unless
otherwise there is already rock foundation.
If there is rock on the bottom of river bed, chipping will be done to make concrete to firmly contact with the
foundation.
2.2.2 Assembling Reinforcement bars (for base concrete)
We will assemble the reinforcement bars including the base concrete portion (reinforcement bars will start
from the base concrete). It is recommended to assemble the bars at intervals of 25-30cm. (usually 30cm). As
for the size of reinforcement bar, Y12 (12mm) and Y16 (16mm) of diameter are usually used for weir
construction.
2.2.3 Assembling Reinforcement bars (for weir wall)
We will assemble the reinforcement bars including the base concrete portion (reinforcement bars should start
from the base concrete). It is recommended to assemble the bars at intervals of 25-30cm. (usually 30cm). As
for the size of reinforcement bar, Y12 (12mm) and Y16 (16mm) of diameter are usually used for weir
construction.
2.2.4 Concrete Mixing Mixing and Placing:
In order to get proper concrete for weir construction, we will adopt the standard mixing proportion of cement
to sand and crushed stone is: 1 : 2 : 4 in terms of volume, which is equivalent to 1 bag of cement (50kg), 2
bags of sands and 4 bags of crushed stones. We will use batch boxes to measure the materials for making
concrete.
Placing the base concrete-The base concrete with horizontally placed wire mesh and reinforcement bars
vertically arranged is placed on the bottom of construction space (excavated area). The thickness of the base
concrete is expected to be the same as further excavated depth. We shall until concrete dries up while giving
it proper curing.
2.2.5 Assembling Framework (Shuttering)
We shall assemble framework (Shuttering) to place the concrete while covering reinforcement bars
assembled. The inside of frame works will be coated with a bit of oil; to help smooth removal of the
framework after concrete is ready.
2.2.6 Placing Concrete to Weir Wall
We will pour concrete into the framework layer by layer. 30cm thickness is recommended to place for each
layer. Interstices and gaps inside of the framework should be filled thoroughly with concrete by poking the

METHODOLOGY 5
concrete with a porker vibrator.

3.0 PIPE LAYING


3.1 TRENCH EXCAVATION and BACKFILLING
We shall ensure that all works relating to stripping of surface materials, trench excavation and
storage of excavated materials is appropriate and keep the excavation to the minimum practical so as
to reduce the extent of disturbance. Slopes of excavations shall be formed to avoid the collapse. All
exposed surfaces shall be maintained in a stable condition to avoid erosion of excavated surfaces and
storage areas. Trenches shall be levelled to provide even and continuous support to the pipeline, and
any organic materials, stones, boulders or obstructions shall be removed and disposed. Suitable
excavated material, other than surface materials, if suitable for backfill, shall be stock piled at one
side of the trench and after pipe laying works completed, backfilled to the trench. Pipe will be
covered by soft sand at 200 mm layers to protect the pipe coating from any damage. It shall be
thoroughly compacted by hand rammers.
Excavation shall be carried out in accordance with the “Trench Excavation and Backfilling Method
Statement’’.

All crossings shall be installed in accordance with the drawings. Reinforced concrete protective slabs
shall be placed over the pipeline, at service crossings. The concrete slabs shall be a minimum of 150
mm thick and shall extend beyond the pipe, for at least 150 mm on either side.
On completion of backfilling operations, permanent surface warning tiles shall be placed on the
pipelines to indicate their points of intersection with other services. Drainage systems shall be
installed within the construction area if necessary to protect existing waterways and to control storm
water runoff. The systems shall be designed to discharge water to a collecting pits. If required, oil
separator and/or sediment traps shall be installed in the drains, to prevent the contamination of
ground water.

3.2 PIPELINE CONSTRUCTION


Handling:
Pipe Stringing: Pipes shall be offloaded and strung along the route of the pipeline, not parallel or
perpendicular to trench direction but with some degree’s angle. Pipes and fittings shall not be placed
directly onto the ground. End protection caps shall be retained in position, as long as practicable.
The pipeline shall at all times be kept free of foreign material and water, and when work is not in

METHODOLOGY 6
progress, the open ends of pipes, fittings and pipeline shall be securely capped.
Pipeline Lowering-in: The pipeline shall be lowered into the trench as soon as possible after the
trench has been excavated.

DIVERSE AND OTHER


Quality control. Plan
We consider Quality Control as a top priority in the execution of works. The following aspects will be
ensured as part of our Quality Control program: -
 Superintendence Staff: - We will ensure adequate qualified and experienced Engineers are engaged in the
Project from the onset. Such Engineers are readily available from our pool of staff. The Engineers will fully
be supported by an equally qualified technical team [Surveyors, Foremen, Headmen, Technicians and
Draughtsmen etc.] from our pool of staff.
 Materials: - All materials shall be of their respective kinds as described in the contract or equally approved
alternatives.
 We will ensure that, no material will be delivered to the site without being tested and accompanied by a
Compliance Certificate.
 All Quarries and Borrow Pits will have to be approved by the Engineer’s Representative once identified.
 Sampling from the Quarries and Borrow pits will be done jointly with the Engineer’s team.
 Mix designs for concrete and asphalt concrete will be done and approved by the Engineer before being
incorporated into permanent works.
 Control tests will be carried out as the work progresses to ensure that quality is maintained through and
through.
Machineries: - We will ensure all the machines allocated to various sections of works are in good working
conditions, properly calibrated and of the right kind for the activity. Qualified operators will be employed on
these machines for the best result.

Safety, Health and Environmental


Plan Environmental Awareness:
An induction course will be conducted by the ECO on the construction site at commencement of
works. Environmental awareness training of new and follow up of older staff members as well as
subcontractors will be conducted at regular intervals or as deemed necessary. Emergency procedures
and Fire hazard: There will be two fire extinguishers at the fuel bowser and employees will be
trained how to use them in case of emergency. All fire equipment will be serviced monthly and they
will be checked bi-weekly by the acting fire officer. No open fires will be allowed on site. A water
truck with capacity of 10 000 liters will be on site in case of any fire emergency. The site agent of

METHODOLOGY 7
the contractor will also act as the environmental officer on behalf of the contractor if a dedicated
person or agent is not appointed.

Safety precautions are to be adhered by ensuring that, all plants are operated by authorized operators. Besides,
all workers in the concrete section will be provided with safety gears including dust masks, hand gloves,
gumboots, helmets, goggles and others as applicable.

Introduction;
We employ sound and high standard work methodologies aimed at: -
a. Achieving safe structures of high quality
b. Observing and Maintaining safety and health of the workers,
c. Maintaining safety of the adjacent structures and neighbors,
d. Preventing environmental degradation

Health & Safety Policy


Health and Safety are two of our Company’s most important responsibilities and functions and is regarded as
the essential foundation for successful business and social operations.We believe that a superior safety
approach is indicative of assertiveness and responsiveness to employee needs and policies procedures, which
creates higher morale and loyalty amongst employees, leading to enhanced productivity and therefore
enhanced profitability.
This ensures that we sustain our consistency and vision as top achievers in the Construction and development
environment.
Supreme Fortitude Limited has a legal and moral responsibility to safeguard its employees and the general
public, so far as reasonably practical, from injury, annoyance or risk to Health from all processes associated
with all operations and Activities.

Workers Health & Safety: - We don’t take the health and safety of our workers for granted. We take the
following measures to ensure it is maintained: -
1. We provide our site gangs with safety gear such as: Helmets, safety goggles, safety gloves, dust masks,
boots, and safety ropes etc.
2. We train our workers on proper operation of tools and machinery.
3. We restrict operation of machinery only to the qualified workers.
4. Routine examination of tools and scaffolds is carried out to prevent any possible accidents arising from
faulty machines of loose scaffolds.

METHODOLOGY 8
Occupants’ Safety & Satisfaction
1. We shall use dust screens to prevent dust from spreading all over the place.
2. We shall use scaffolds as shown in the figure below to protect the occupants from falling materials.
3. We shall mark off the areas which un-authorized persons will not be allowed to go to by either hoarding or
using warning tape as may be instructed by the project manager.
4. In order to achieve safe structures, we engage our own experts and work with the consultants appointed by
the client, observe high standard supervision and adhere to the designs and specifications.

We employ highly skilled artisans and craftsmen to ensure high standard of workmanship and the intended
aesthetics is achieved. This makes the structure usable for the intended use.
5. We shall follow the Project engineer’s instructions on how to carry out these works as well as the
specifications and drawings. In addition, we shall follow all the laid down procedures and regulations
pertaining to construction
6. All concrete works and masonry & plaster works will be cured thoroughly either by surface flooding or
covering as necessary.

Sediment and Erosion Control:


No sediment will be able to enter the stream as the newly constructed pan wall will act as a buffer to
contain sediment from the construction area. Topsoil from temporary stockpiles will be used to
cover exposed areas to encourage the fast growth of vegetation to prevent unnecessary erosion.

Storm Water Management:


Existing storm water ditches will be maintained in order to let water flow freely to the river without
eroding the soil. Existing drainage furrows will be maintained and kept clean at all times in order to
prevent rainwater from scouring and eroding surrounding areas and sedimenting the stream.

Dust and Noise Control;


Working hours will be from 7am till 6pm during weekdays, plant will be equipped with standard
factory fitted silencer systems. Dust will be controlled by watering dusty areas with water truck.
Contaminated Water Control:
Discharges such as cement, lubricants, fuels, etc, will be minimized in accordance with the EMP.
No Go Areas:
All activities will be limited to the agreed and dedicated construction areas.

DEMOBILIZATION.

METHODOLOGY 9
Once the pan is substantially complete, we will clear the camp and leave the campsite in a good state. We
shall retain skeleton staff to carry out routine maintenance and remedy any defects on the pan during the
Defects Liability Period.

METHODOLOGY 10

You might also like