Introduction To Cost Estimate
Introduction To Cost Estimate
Prepared by:
Engr. Ralph F. Tan Sanchez
Intended Learning Outcomes
Project Description: You are tasked with estimating the cost for constructing
a small single-family home. The project will include the following
components:
Answer: ₱ 6,917,295
Plinth Area Cost Estimate
Plinth area cost estimate is prepared on the basis of plinth area of building
which is the area covered by external dimensions of building at the floor
level and plinth area rate of building which is the cost of similar building
with specifications in that locality.
Sample Problem 2: (Plinth Area Estimate)
Answer: ₱ 34,714,247.40
Cube Rate Cost Estimate
Length: 20 meters
Width: 15 meters
Height: 10 meters
Estimated Cost per Cubic Meter: ₱ 8,347.50
Answer: ₱25,042,500.00
Approximate Quantity Method Cost Estimate
In approximate quantity method cost estimate, the total wall length of the
structure is measured, and this length is multiplied by the rate per
running/linear meter which gives the cost of the building. The rate per
running/linear meter is calculated separately for the foundation and
superstructure.
Revised Cost Estimate
The rates of different items are provided according to the current workable
rates and total estimated cost is calculated. 3 to 5 % of estimated cost is
added to this for contingencies as miscellaneous expenditure.
The detailed Estimated should consist following details and documents.
• Report
• General Specifications
• Detailed Specifications
• Schedule of rates
Detailed Estimate of Slab on Grade and
Suspended Slab
Slab on Grade/ Slab on Fill
2.Hook Type:
A 90-degree hook is commonly used for main reinforcement bars, but in some cases, a
180-degree hook may also be employed, especially in areas requiring additional
anchorage.
3.Bar Diameter:
The actual dimensions will vary based on the diameter of the reinforcement bars. For
example:
For a #16 bar (16 mm diameter), the hook length would be 12 x 16 mm = 192 mm.
Direct Counting Method
Note: You may derive the values from the table by referring to the
density of steel which is 7850 kg/m3
Sample Problem 4: (Detailed Estimate on Slab on Grade/Slab on Fill)
Refer to the figure and quantify the total number of rebars needed for the
slab on grade. Use only 6.0 or 7.5 m commercial length for comparison
purposes.
Suspended Slab
Refer to the figure and quantify the total number of rebars needed for the
slab on grade. Use necessary commercial length for comparison purposes.
ANY QUESTIONS?
THANK YOU!