CTE Report
CTE Report
2) To identify the types of formwork and their uses according to various conditions.
1. We will collect the relevant information about the different types of formwork .
2. We will also find the importance types of formwork according to various conditions.
GROUP – G
Sr. No. Name of the Enrollment Roll No. Exam Seat No.
student NO.
1. Sangram Salunkhe 2200090214 131
Formwork, Mould used to form concrete into structural shapes (beams, columns, slabs,
shells) for building. Formwork can be of timber, steel, plastic, or fiberglass. The inside
surface is coated with a bond breaker (plastic or oil) to keep the concrete from sticking to
the mold. Important for high-rise construction is slip forming, whereby a vertical concrete
element is continuously cast using a short section of formwork that is repeatedly
disassembled and moved upward as each section is finished or that moves slowly and
continuously as concrete is being placed. This is sometimes called a climbing form.
4.0Literature Review
In construction, forms or shutters are mold structures in which concrete is poured and waited to harden over
time. When the strength of the concrete poured reaches the required levels to hold their own weight, the forms
are taken out. So a formwork is a frame of a temporary or permanent structure into which hardening concrete
is poured.
❖
TYPES OF FORMWORK (VISITED SITE)
1) Steel formwork
2) Wooden formwork
➢
Steel formwork
Steel formwork allows re-uses of the shutter for many times and they are used in huge
construction projects. Curved structures like chimneys, huge columns, tunnels, and water
tanks are mostly built with steel formwork. They are strong and last for a long time. Steel
formwork can be re-used at least 100 times. They are easy to install and detach, thereby
allowing the quick and efficient process. The completed surface of the concrete also comes
in smooth and neat. The formwork used does not absorb water and also reduces the chances
of honeycombing.
➢
Wooden formwork
Timber formworks have been used for a long time and they are used in small construction jobs
all around the world. The only condition for this formwork is that the timber used shouldbe
strong, treatable and durable to have strong flats in Chennai. They should be light and hold
nails together firmly. Warps in timbers are not advisable and they should also be properly
seasoned. Timber formworks are flexible and the same makes it easy to handle.
With amazing insulating properties, it is great for construction works in cold places. Their
flexibility allows them to be formed into different forms and sizes.
❖
REQUIREMENTS OF GOOD FORMWORK
The first step for any concrete construction starts with the construction of foundation.
Foundation can be for columns or walls. So, based on type of structural member, the
shape and size of footing are designed. Thus formwork size and shape depends on the
type and dimension of the footing.
In this formwork, the side yokes and end yokes contain two numbers each and are perfectly
placed alongside the peak of the column. Generally, the two-side yokes are comparatively of
the weighted section and are tagged together by two long bolts of 16 mm dia perfectly.
Between the bolts and the end yokes, four wedges, one at each corner, are inserted. The
sheathing is fixed by nail to the yokes.
In order to scale back deflection, the battens could also be propped within the middle of
the span through joists. In the side forms of the beam, 3 cm thick sheathing is used. The
bottom sheathing of the beam form maybe 5 to 7 cm thick.
Fig. 4. Shuttering in Beams and slabs floor – section across beams
As shown in fig.6. The following are the components used in concrete Stairs
formwork: Cross joists, String, Stiffener, Risers, Decking, Ledger, Cut String,
Hangers, Boards, Strut, etc.
The risers planks are 4 to 5 cm thick and equal to the height of the riser. These planks are
beveled at the bottom to permit the whole of the tread faced to be trowelled.
The riser planks are placed after the reinforcement has been fixed in position. The treads are left
open for placement of concreting and vibration. Normally as shown in the fig the stiffener is wired
to cross-joists through the decking.
❖
CAUSES OF FAILURE OF FORMWORK
1) Improper stripping and shore removal.
2) Inadequate bracing.
3) Inadequate control of concrete placement.
4) Inadequate concrete strength development.
5) Excessive vibration and impact.
6) Unstable soil order mudsills and out of plumb shores.
7) Lack of attention of formwork details.
8) When formwork is not at fault.
❖
STRIPPING TIME
In no circumstances, forms shall be struck until the concrete reaches a strength of a minimum of
twice the strain to which the concrete could even be subjected at the time of striking.
As soon as possible for a longer time, the formwork should be kept in contact, because it might
withstand the curing. In normal condition, generally when the temperature is above 20 ⁰C and
where ordinary cement is used, forms can be stripped after the following periods:
1) Can’t be used for long. Have limited re-use. Can only be re-used 5 or 6 times.
2) If the timber is dry, it will absorb moisture from wet concrete which could weaken
the resultant concrete member.
3) Timber with high moisture content (more than 20 % moisture content), wet
concrete will shrink & cup leading to open joints & leakage of grout
1) Deep thinking.
2) Communication skill.
3) Problem solving skill.
4) Co-ordination.