Risk Assessment - Solar System Testing & Commissioning
Risk Assessment - Solar System Testing & Commissioning
Prior to commence the activity make sure that all electrical connection
are installed as per approved drawing
Ensure RSG LOTO Procedure (RSG-HS-COS-0012_Hazardous
Personal Energy Control) to be applied.
4.2 Potential for electrical fires due to short circuits, Injury 4 4 16 All electrical connection to be inspected by competent team prior to 4 1 4 L
H commence the activity
overheating, or arcing. Property
damage Disconnect the appliance from the electricity mains using the external
switch.
Keep the electrical wires away from hot and wet surface
Switch off appliance after use and remove the plug from the socket
ARCHIRODON/ACC JV
11104-AMAALA STAFF VILLAGE ZONE 4
Rev.
FORM Issued For General Use
Activities HSE Risk Assessment
Reference No. 11104-HSE-PRO-10-F01 0.0
Serial No.
Page 9 of 15
Roof access permit shall be taken before commencing the work at roof
or height
Safe access to be available prior to start the testing
Adequate fall protection shall be provided
Safe scaffolding platform with fall protection to be in place for work
at height activity
Guardrails provide a physical barrier that prevents workers from
4.3 Risk of falls from rooftops, ladders, or scaffolding
People 3 3 9 M 4 1 4 L
during installation or testing falling
Ladder shall be only used for light duty work
Experienced, competent & trained personnel will be assigned to the
task.
Follow approved method of statement for testing and commissioning
of solar panel
All personnel shall wear the mandatory PPE’s.
Severity (S) Values: 1-5 Likelihood (L) Values: 1-5 Risk (R) = S x L
Risk Level: 1 – 4 = Low (L) 5 – 12 = Medium (M) 15 – 25: High (H)
Note: Use the HSE Risk Assessment Matrix (RAM) when determining the values of S and L
per year
in industry/ in times per
in
industry/ company industry/ year in a
industry/
PEOPLE ASSETS ENVIRONMENT company company location
Activity is compan
Activity taking place Activity y Activity is
is taking occasionall is taking taking place
Activity
place y place continuousl
is taking
rarely frequentl y
place
y
regularly
First aid
Property
case, no
1 damage Causes slight damage 1 (L) 2 (L) 3 (L) 4 (L) 5 (M)
stoppage to
<$5,000
work
Property
damage Causes minor
Medical
between damage, can be
2 Treatment 2 (L) 4 (L) 6 (M) 8 (M) 10 (M)
$5,000 rectified with minor
Case
and resources
$100,000
Lost time
Property
accident, Serious, often long-
damage
chronic term damage,
between rectified with
4 illness, stop 4 (L) 8 (M) 12 (M) 16 (H) 20 (H)
$200,000 significant resources,
work for 2
and potential legal
days or
$500,000 implications
more
Multiply the severity (1-5) by the likelihood (1-5) to ascertain the risk level.
Resulting action is detailed in table below.
1-4 Record hazard, record risk ratings, recommend upgrades to risk control
Online
(Low) measures if the risk rating is not as low as reasonably practicable
Record hazard, record risk ratings, record the recommended risk control Online
5-12
measure needed to reduce the risk rating below 4 or as low as reasonably Risk score over 10, full
(Medium)
practicable report required
15 – 25 Stop the activity immediately and seek further advice to reduce the risk
Full report
(High) rating below 4 or as low as reasonably practicable.
TABLE 2