Risk Based Inspection Using API RP 580 A
Risk Based Inspection Using API RP 580 A
Submitted: January 10, 2021 | Revised: February 12, 2021 | Accepted: April 21, 2021
Risk Based Inspection using API RP 580 and DNV RP F116 Towards Free
Spanning Pipelines
Yoyok Setyo Hadiwidodoa, Iftinaniffah Qonitahb,* and Daniel M Rosyidc
a) Senior Lecturer, Department of Ocean Engineering, Institut Teknologi Sepuluh Nopember, Surabaya, Indonesia
b) Undergraduate Student, Department of Ocean Engineering, Institut Teknologi Sepuluh Nopember, Surabaya, Indonesia
c) Professor, Department of Ocean Engineering, Institut Teknologi Sepuluh Nopember, Surabaya, Indonesia
The undersea pipes play an important role in the offshore oil 2. BASIC THEORY
and gas development process. The underwater pipe is used 2.1 Pipeline data
as a transport pipeline for export, pipe-producing production The pipe that is reviewed is a pipe owned by PT. X operating
from a platform to export pipes, production conveying pipes in Madura Strait. This pipe has a length of 65 km to connect
between platforms, subsea doing and satellite wells [1]. Like the central processing platform (CPP) to the onshore
the underwater pipe of PT. X which is located in the Madura receiving facilities (ORF). The fluid that is flowed by this
Strait. This 14 "Subsea pipe delivers gas from the central pipe is gas.
processing platform (CPP) to onshore receiving facilities
(ORF). However, when the use of subsea pipes enters the Table 1. Pipeline Data
deep sea, the unruled underwater topographical state is more Process Data
widely encountered [2]. Parameter Unit Value
Design pressure Mpa 9.3
Uneven topographical conditions can cause the presence Operating pressure Mpa 4.9
of subsea pipes that do not have a buffer, thus forming a free Design temperature ᴼC 75
span [3]. The free span has a significant impact on the safety Operating temperature ᴼC 65
and integrity aspects of the subsea pipeline [4]. The free Content density kg/m3 29.3
Licensed under a Creative Commons Attribution 4.0 International License (URL: http://creativecommons.org/licenses/by/4.0/)
136
International Journal of Offshore and Coastal Engineering Vol. 4 No. 4 pp. 136-141 May 2021
137
Rosyid, et al.: Risk Based Inspection … Spanning Pipelines
138
International Journal of Offshore and Coastal Engineering Vol. 4 No. 4 pp. 136-141 May 2021
Table 9. PoF of DNV RP F116 From the simulation that has been done, the value of PoF in
Severity Description PoF fatigue-induced mode due to VIV is 0.9988 and for local
1 Failure is not expected < 10-5 buckling failure mode is 0.999. At API RP 580.
2 Never heard of in the industry 10-5 - 10-4
An accident has occurred in the
PoF fatigue due to VIV and local buckling are included
3 10-4 - 10-3 in very high category. Meanwhile, in DNV RP F116 second
industry
Has been experienced by most PoF is included in severity 5.
4 10-3 - 10-2
operators
5 Occurs several times per year 10-2 - 10-1
3.2 Consequences analysis
3.2.1 Safety
Based on the location of the pipeline under the sea, possible
failures, both due to fatigue and local buckling, have a small
safety impact. The failure of the free span had a small impact
on safety when it was reviewed based on the failure of a free
span due to buckling [10].
So, it can be said that in the API of RP 580, the safety
aspect is included in category VI (insignificant). Meanwhile,
in DNV RP F116 the aspect of safety is included in category
A.
3.2.2 Environment
Figure 1. Base Inspection Interval DNV RP F116 The fluid flowing by the subsea pipeline affects the
consequences posed for the environment. In this reviewed
3. RESULTS AND DISCUSSION subsea pipeline, the fluid that is flowing is gas. When the
gas is flowing into the leaking pipe, the environmental
3.1 Monte carlo simulation damage will be very small.
This simulation was performed to calculate the reliability of So, it can be said that in the API of RP 580,
the subsea pipeline due to a free span that was considered environmental aspects are included in category VI
critical, the largest span has a length of 183 m and a gap of (insignificant). Meanwhile, in DNV RP F116 environmental
0.2 m. In the local buckling failure mode Equation (4) is aspects are included in category A.
used, because the internal pipe pressure is greater than the
external pipe pressure. The monte carlo reliability 3.2.3 Asset
simulation was carried out as many as 10,000 times the With the failure of the subsea pipeline, production will
simulation. PoF in the 10,000th simulation is used as the cease. This led the company to a loss. It is known that the
PoF value in the risk calculation. gas flow rate of the pipe is 70,000 MMBTU and there are
227.94 MMBTU in the subsea pipeline. Production losses
Table 10. Simulation’s Result ranged from 70,227.94 MMBTU.
VIV Local buckling If multiplied by the current price of gas per MMBTU,
Number Number the total loss of $137646.77 or the equivalent of EUR
No. of Reliabili of Reliabili
simulati ty
PoF
simulati ty
PoF 127209.25 is obtained. In API RP 580, the amount of this
ons ons loss is categorized in category IV (significant). Meanwhile,
1 1000 0.002 0.998 1000 0 1 in DNV RP F116 This loss is included in category C.
2 2000 0.0015 0.9985 2000 0 1
3 3000 0.001 0.999 3000 0 1 3.3 Risk matrix
4 4000 0.0015 0.9985 4000 0 1 From determining the probability of failure and
5 5000 0.0016 0.9984 5000 0 1
consequences of failure, it can be known the level of risk of
each aspect. It is known that the value of PoF against two
6 6000 0.0015 0.9985 6000 0 1
failure modes has the same category.
7 7000 0.0013 0.9987 7000 0 1
Both in API RP 580 and DNV RP F116, then the risk
8 8000 0.0013 0.9987 8000 0 1
matrix displayed already represents the level of risk of both
9 9000 0.0012 0.9988 9000 0 1 the failure modes against all three aspects of the
10 10000 0.0012 0.9988 10000 0.0001 0.9999 consequences reviewed.
139
Rosyid, et al.: Risk Based Inspection … Spanning Pipelines
6. CONCLUSIONS
REFERENCES
140
International Journal of Offshore and Coastal Engineering Vol. 4 No. 4 pp. 136-141 May 2021
Kelautan-FTK, Institut Teknologi Sepuluh Nopember. Inspection (RBI). Tugas Akhir Departemen Teknik
Surabaya. Kelautan-FTK, Institut Teknologi Sepuluh Nopember.
8. Nuraini, Ika Puspita. (2016). Analisis Resiko Pipa Surabaya.
Bawah Laut Akibat Tarikan Jangkar Dengan Metode 11. Alamsyah, M Fruqon. (2013). Analisa Risk Based
Monte Carlo : Studi Kasus Jaringan Pipa Bawah Laut Inspection Pada Pipeline 16” Jalur Sukowati – CPA
Tunu Field, Blok Mahakam, Kalimantan Timur. Tugas yang Mengalami Upheaval Buckling. Tugas Akhir
Akhir Departemen Teknik Kelautan-FTK, Institut Departemen Teknik Kelautan-FTK, Institut Teknologi
Teknologi Sepuluh Nopember. Surabaya. Sepuluh Nopember. Surabaya.
9. Mulyadi, Yeyes, dkk. (2013). Developing Risk Based
12. Erfando, Tomi, dkk. “Free Span Investigation of the
Inspection for Subsea Pipeline in the Madura Strait
Longest Subsea Gas Pipeline in Indonesia Using
using AIS Data. The Japan Society of Naval Architects
Remotely Operated Vehicle ROV”. Abu Dhabi
and Ocean Engineers.
International Petroleum Exhibition & Conference. Abu
10. Rudiyanto, Achmad. (2014). Analisis Risiko pada
Dhabi: 11-14 November 2019.
Offshore Pipeline Milik PT. Trans Pacific
Petrochemical Indotama (PT. TPPI) Tuban akibat Free
Span dengan Menggunakan Metode Risk Based
141