Project
Project
Management (PADM)
Not shared
Full Name
ID Number
1 point
B. An endeavor, which is planned, executed, and controlled; performed by people; and constrained by
limited resources.
A. Temporary
C. Interrelated activities
1 point
1 point
A. Stakeholder's pressure
B. Business needs
C. Technological obsolescence
D. Observed opportunities
5. The concept of _________ states that changes related to one requirement of scope, time, or cost
that will at least influence one other element.
1 point
A. Three-point estimation
B. Triple constraint
C. Three wise men
1 point
7. A group of related projects that are managed in a coordinated way that usually include an element of
ongoing activity is called a:
1 point
A. Major project.
B. Project office.
C. Program.
D. Group of projects
1 point
A. Project engineer
B. Project manager
C. Quality manager
D. Team member
9. A rough order of magnitude estimate is made during which project management process group?
1 point
A. Project planning
B. Project closing
C. Project executing
D. Project initiating
10. In which project management process group is the detailed project budget created?
1 point
A. Initiating
B. Project closing
C. Planning
D. Executing
1 point
A. Overambitious projects
B. Unsustainable projects
C. Undefined problems
1 point
A. Wasted effort
B. Lost time
C. Increased cost
1 point
C. A and B
D. Neither A nor B
14. The purpose of the review of deliverables and project performance at the conclusion of a project
phase is to:
1 point
A. Determine how many resources are required to complete the project according to the project
baseline
15. What is a visual representation of a project’s planned activities against a calendar called?
1 point
A. A Gantt chart.
D. A Pareto chart
1 point
A. Establish milestones
B. Determining sequence of work
C. Building network
D. Analysis of interdependence
17. A project has more than one critical path. What does this mean to you?
1 point
E. Risk increases
18. In which of the following phases of the project will most of the money be spent?
1 point
A. Initiating
B. Planning
C. Executing
D. Closing
1 point
D. Sub-contractor’s responsibilities.
E. None of the above
1 point
1 point
22. Your organization is considering to run a project which will entail an investment of $1,000,000. The
product from the project is forecasted to create revenues of $250,000 in the first year after the end of
the project and of $420,000 in each of the two following years. What is true for the net present value of
the project over the three years cycle at a discount rate of 10%?
1 point
A. The net present value is positive, which makes the project attractive.
B. The net present value is positive, which makes the project unattractive.
C. The net present value is negative, which makes the project attractive.
D. The net present value is negative, which makes the project unattractive.
23. The project manager is making sure that the product of the project has been completed according to
the project management plan. What part of the project management process is he in?
1 point
A. Planning
B. Executing
D. Closing
24. Whenever you receive a change request, what will be your next step?
1 point
B. Investigate it
C. Reject it
D. Ignore it
25. To control the schedule, a project manager is reanalyzing the project to predict project duration. She
does this by analyzing the sequence of activities with the least amount of scheduling flexibility. What
technique is she using?
1 point
B. Flowchart
C. Precedence diagramming
26. Which of the following Project Scope Management processes involves subdividing the major project
deliverables into smaller, more manageable components?
1 point
B. Define Scope
C. Validate Scope
D. Control Scope
E. Create WBS
1 point
28. You are creating your WBS and find that you keep decomposing tasks into smaller and smaller units.
How can you tell when you are done?
1 point
A. Keep decomposing tasks until you reach an amount of work that is small enough to reliably estimate
required resources and duration.
B. Keep decomposing tasks until you reach an amount of work that can be accomplished in one hour.
C. Keep decomposing work until you reach an amount of work that can be accomplished in your
organization’s basic work unit.
D. Keep decomposing work until you reach a predetermined number of hierarchy levels to keep the WBS
balanced.
1 point
A. Individual work packages using the Work Breakdown Structure.
1 point
A. Gantt chart
B. Milestone chart
C. Fishbone diagram
D. Network diagram
1 point
32. During which phase of the project will risks be the highest?
1 point
A. Initiating
B. Planning
C. Execution
D. Closing
E. Proportionally distributed
1 point
A. Initiating
B. Planning
C. Execution
D. Closing
E. Proportionally distributed
34. Your project is late and to bring it back on track you are adding extra resources to some activities
and giving overtime to your team members. This is an example of:
1 point
A. Critical Chain
B. Fast Tracking
C. Crashing
D. Resource Leveling
35. A project manager in a construction company identified the project activities that were not giving
output as per the performance goals outlined in the project management plan. The finding is the result
of:
1 point
36. A project is typically defined in terms of the triple constraints, and one among the following is other
(4th) parameter?
1 point
A. Benefits.
B. Quality.
C. Schedule.
D. Controls.
1 point
38. The document that identifies what information needs to be shared, to whom, why, when and how is
called the:
1 point
A. A well-defined scope
40. At the beginning of project execution, you notice different opinions between team members relating
to project work and deliverables and to the level of overall complexity. What should you do right now?
1 point
A. Give your team members some time to develop a common understanding of the project scope and
product scope. Upcoming interface problems may be resolved later.
B. Use the risk management processes to identify and assess risks caused by misunderstandings and
develop a plan with measures in order to respond to them.
C. Organize meetings to identify and resolve misunderstandings between team members in order to
avoid interface problems, disintegration and costly rework early in the project.
D. Use interviews in private with each individual team member to inform them of your expectations and
your requirements in an atmosphere of confidence.
1 point
B. Change requests surpassing the formal change control processes can lead to scope creep.
C. Change requests are always a sign of bad planning and should be avoided therefore.
1 point
A. The quality manual (policy manual)
B. Operational procedures
1 point
44. A significant number of projects fail to achieve their intended outcomes on time and within budget
due to:
1 point
1 point
A. Lessons learned databases are an essential element of the organizational process assets.
B. Lessons learned should focus on identifying those accountable for errors and failures.
C. Lessons learned sessions should bring about recommendations to improve future performance on
projects.
D. Phase-end lessons learned sessions provide a good team building exercise for project staff members.
1 point
B. Making stakeholders aware that the project has been closed out.
1 point
48. When a project has completed the handover and closure phase:
1 point
B. The project deliverables are ready for handing over to the users.
49. The Monitor and Control Project Work process results in all of the following EXCEPT:
1 point
A. Change requests
B. Preventive actions
C. Defect repairs
D. Deliverables
50. Project manager of a travel excursion company is currently working on confirming that all project
deliverables have been successfully completed in order to transfer the project to the customer. What
process is the project currently in?
1 point
A. Verify Scope
B. Scope Closure
D. Close Procurements
51. Complete the following sentence: “The later a defect is found, __________ .”
1 point
52. A project is
1 point
A. An interrelated set of activities that has a definite starting and ending point
1 point
B. Operation of a business
C. A temporary endeavor
D. A & B
1 point
A. Stakeholder's pressure
B. Observed opportunities
C. Technological obsolescence
55. One among the following is incorrect regarding the characteristics of a project;
1 point
A. an instrument of change
B. non-routine
1 point
A. Planning
B. Monitoring
C. Motivation
1 point
58. The most common reasons for project failure includes all but one
1 point
59. In addition to a description of the scope and objectives, this will include a justification for the
organizational fit and need for the project.
1 point
A. Project context
B. Rationale
C. Project objectives
D. Project scope
60. There are many reasons why organizations initiate projects. Some of the most common ones include
but one:
1 point
D. New product
61. A major reason for projects going wrong is a failure to properly define the scope. Defining and
agreeing the scope will help in all except one:
1 point
A. Manage expectations
D. Promote misunderstanding
1 point
A. Quality Manager
B. Project engineer
C. Project manager
D. Team members
63. A project manager has just been assigned to a new project and has been given the preliminary
project scope statement and the project charter. The first thing the project manager must do is:
1 point
1 point
65. In which project management process group is the detailed project budget created?
1 point
B. Initiating
C. Planning
D. Executing
66. A rough order of magnitude estimate is made during which project management process group?
1 point
A. Project Planning
B. Project Initiating
C. Project Closing
D. Project Executing
1 point
A. As early into the project as possible. A committed schedule should be there before any initiating or
planning processes are applied for the project.
B. During initiating. The definite project schedule should be developed concurrently with the project
contract (if applicable) and the project charter.
C. Scheduling should be avoided. Agile approaches with a backlog and a weekly to 4-weekly meeting
cycle are sufficient for modern project management
D. When most planning processes from time, scope, and procurement management have been finished.
These will then be iterated when necessary.
68. A group of related projects that are managed in a coordinated way that usually include an element
of ongoing activity is called a:
1 point
A. Major project
B. Project office
C. Program
D. Group of projects
69. To control the schedule, a project manager is reanalyzing the project to predict project duration. She
does this by analyzing the sequence of activities with the least amount of scheduling flexibility. What
technique is she using?
1 point
B. Flowchart
C. Precedence diagramming
70. The project manager is making sure that the product of the project has been completed according to
the project management plan. What part of the project management process is he in?
1 point
A. Planning
B. Executing
D. Closing
71. When considering the following activities, which is the best example of a project?
1 point
B. Producing automobiles
1 point
73. Which of the following is true concerning the work breakdown structure (WBS)?
1 point
B. The WBS is a hierarchical decomposition of the total scope of work to be carried out by the project
team.
D. The WBS is the bill of materials (BoM) needed to accomplish the work of the project.
74. The work defined at the lowest level of the breakdown structure to estimate as well as manage time
and cost is called the:
1 point
A. Activity
B. Task
C. Work package
D. Cost account
75. One among the following is not in common stages of constructing Critical Path in the project?
1 point
76. During human resource planning you identified that your team members are not sufficiently
qualified for their tasks. Which may be an appropriate solution to this problem?
1 point
1 point
A. Mitigation
B. Transfer
C. Acceptance
D. Avoidance
78. During a meeting with some of your project's stakeholders, you are asked to add to the project's
scope of work. The project records contain correspondence from before the Charter was signed in which
the project sponsor specifically declined the work being requested by these stakeholders. The BEST
thing for you to do is:
1 point
1 point
80. In resource planning, three main dimensions have key parts to play. However, which of the following
plays no part, or only a secondary part, in resource planning?
1 point
1 point
82. If a large project is subdivided into subprojects, for the project manager this generally means an
increase in:
1 point
A. project risk
B. coordination effort
C. planning work
D. financial requirements
1 point
A. It is impossible to avoid project risks completely, all projects have inherent risks
B. Add additional resources to a project so the project will be delivered on time should a risk occur.
D. Ensure all 6 project constraints are detailed and planned in order to avoid any risk to the project.
1 point
A. Indefinite
B. One
C. Four
D. Six
1 point
B. Quality, resources, risks, customer satisfaction or schedule may be impacted by a change to project
scope.
1 point
1 point
88. Because tasks are often being completed at the same time, a project manager needs to _____.
1 point
A. Be a good leader
B. Be organized
D. Be able to multi-task
1 point
A. Gantt Chart
B. Milestone chart
C. Fishbone diagram
D. Network diagram
90. What does it mean to understand and define the deliverables of a project?
1 point
1 point
92. In project management, which technique compares current progress with the planned out progress?
1 point
A. Identifying risks
1 point
94. Which one is NOT usually a practice or technique of better project management?
1 point
B. Monitoring progress
D. Planning
1 point
1 point
A. Forming, Storming, Norming, Performing
97. The project is in execution, but your project team is unable to stop arguing about the project
milestones and the specific risks associated with them. This on-going conflict puts the project at risk of
running behind schedule. What would likely have helped avoid this conflict had it been properly created
first?
1 point
A. A project charter
C. Quality metrics
1 point
Page 1 of 1
This content is neither created nor endorsed by Google. Report Abuse - Terms of Service - Privacy Policy
Forms