Grid Forming An Evolution in STATCOM Technology For Todays Power Grids-1
Grid Forming An Evolution in STATCOM Technology For Todays Power Grids-1
Authorized licensed use limited to: Technische Universitaet Muenchen. Downloaded on October 18,2024 at 18:49:54 UTC from IEEE Xplore. Restrictions apply.
STATCOM solutions come with several types of services contribution of the STATCOM varies with the design of the
and provide a larger dynamic range for reactive power converter and the current carrying capabilities of the
compared to the Synchronous Condenser. The STATCOM semiconductor.
with GFM possesses a higher capability of providing system
During asymmetric faults, the GFM STATCOM will react
strength to the power system. In addition, lower losses and
to boost the positive sequence voltage and reduce the negative
flexibility are achieved with converter solutions.
sequence voltage. On the contrary, the GFL STATCOM only
The Synchronous Condenser has an overload capacity of provides positive sequence current. During the event of a
several times its rated value during short-term overload and symmetrical fault, both STATCOM philosophies will behave
grid faults. Such high overload capability is not typical for a in a similar manner; however, the GFM STATCOM displays
power electronic converter (GFM converter), which emulates the benefit when considering the time of recovery [11].
the machine. The fault current capability of converters is
limited to the converter rating, and converters are designed to C. Reactive Power Compensation
have a robust overload and fault current limiter for protecting When considering the capability to provide reactive power
and ensuring reliable GFM operation during significant compensation to the network, their abilities are equally good.
transient events. Further, the capability of fault current The capacity of the STATCOM to provide reactive power
contribution from a Modular Multi-level Converter (MMC) is compensation to the network is limited to the physical
dependent on the converter configuration and the possibility of limitations of the VSC.
balancing DC capacitors during fault conditions. This must be
considered in the design of the converter system to achieve the D. Operating in Weak Grids
required performance for a power system. As a consequence of the grid expansions and the exploding
increase of offshore wind installations, STATCOMs are being
The following sections will briefly discuss and compare the
operated in locations with weak grids (low SCR). The
difference between GFL and GFM when considering four
STATCOM's ability to operate in weak grids is heavily
main attributes. Figure 4 depicts a comparison of technologies,
assuming identical ratings and topologies. As a reference, dependent on the way the generated voltage waveform is
Synchronous Condenser technology is also presented in the synchronized to the network voltage at the PCC. The GFL
STATCOM is widely acknowledged as a robust solution for
figure.
reactive power compensation when connected to a strong grid.
However, in weak grids, the PLL-based synchronization
method of the GFL STATCOM risks introducing instability
and limits the SCR range in which the GFL STATCOM can
operate [12].
The GFM STATCOM adopts a synchronization method
that makes use of the linearity between the exchanged active
power (contribution from the converter cell capacitors) and the
grid phase angle and allows the STATCOM to maintain
synchronization even in grids with low SCR. Its ability to
operate in various conditions has been demonstrated in studies
[13], as well as field experience from installations, two of
which are presented in the coming section.
Figure 4: Comparison of Technologies for power system services:
Fault Current Injection, Reactive Power Compensation, System V. INSTALLED BASE OF GRID FORMING STATCOMS
Strength Contribution Figure 5 shows the evolution and the installed base for
MMC STATCOMs with GFL and GFM technology for one
A. System Strength Contribution STATCOM vendor. The vendor’s first STATCOM with MMC
The GFM STATCOM will react to improve the system technology was commissioned in 2018, and today, there are
strength in the network to which it is connected by around 30 installations in service. The journey in the
counteracting changes in voltage variations of the network. development of GFM started in 2019, and today, the modern
This behavior results in a STATCOM with an enhanced STATCOM technology supports electrical networks globally,
offering dynamic reactive power compensation with increased
contribution to the network's overall stability. On the other
robustness. As early as 2025, the global footprint of GFM
hand, the GFL STATCOM will experience difficulties in STATCOMs is expected to surpass 10 000 Mvar, as seen in
maintaining the grid voltages in the event of a sudden change Figure 5, and it is expected that most STATCOMs to be
[10]. installed will have GFM behavior. The specific vendor
references are used as a base in this paper due to a lack of
B. Fault Current Injection STATCOM references in the IEEE PES Substation Committee.
The capability to inject fault current is inherent in the Trends for future projects (beyond 2026) are extrapolated from
STATCOM with GFM capabilities. The fault current known awarded projects up to 2026 [14] [15].
Authorized licensed use limited to: Technische Universitaet Muenchen. Downloaded on October 18,2024 at 18:49:54 UTC from IEEE Xplore. Restrictions apply.
weak system conditions. A conventional GFL STATCOM
may find difficulties in achieving this capability while
maintaining stability, as its synchronization relies on a
relatively strong connection. The GFM STATCOM, on the
other hand, is synchronized by the active power angle.
The STATCOM is a 75 Mvar MMC-converter (single VSC
branch) and is connected to the main auto transformer tertiary,
where the primary winding connects to the 69 kV high voltage
bus and secondary to the wind farm. This topology is often
Figure 5:STATCOM evolution: MMC Installed Base – seen in wind farm applications to gain footprint and cost
Grid Following (GFL) vs Grid Forming (GFM) efficiencies.
The South Fork Wind STATCOM marks the first
The following sections will study two STATCOMs
transmission STATCOM with GFM capabilities for offshore
installed and commissioned in the US.
wind applications in the United States and was commissioned
E. South Fork Wind during 2023.
South Fork Wind is New York’s first offshore wind farm, F. Lookout
put in operation to support the supply of the surging power
demand in the Long Island area. The wind farm is rated at In Texas, the electricity network has experienced a
132 MW and is expected to yield the annual energy demand of decrease in grid strength, reduced inertia, and low resilience to
70 000 average households [16]. heavy disturbances. Substantial stability reinforcements have
been applied and continue to be deployed in response to load
growth and the rapid development of renewable power
1
generation from wind and solar. Substantial blackouts in the
4 last couple of years, causing high costs for the utilities and
3 industries, serve as a reminder of the necessity of continued
deployment of stability-improving measures. The Lookout
STATCOM represents a small part of this process. It provides
receiving and dynamic support with the purpose of improving
2 the post-contingency recovery and mitigating Fault-Induced
Delayed Voltage Recovery (FIDVR) related voltage variations
caused by high penetration of induction motor load in the area
Figure 6: Example of a STATCOM installation: 1. Control & [17]. The way to prevent motor stalling is to reduce voltage
Protection 2. Reactors. 3. Power transformer. 4. VSC [9].
drop during the fault and reaccelerate the motors by injecting
In the South Fork Wind project, a STATCOM has been reactive power [18].
installed in the wind farm on-shore substation to ensure that
the wind farm complies with the Long Island Power Authority
requirements for transmission-connected non-synchronous
resources. The minimum reactive power capability at the PCC
is equal to 33% capacitive and reactive Vars based on the wind
farm's nominal power rating. Additional requirements include
STATCOM operating modes to provide dynamic and steady-
state voltage control, constant power factor mode, and constant
reactive power mode. Given the weakness of the network
connection, an additional purpose of the STATCOM is to
provide full capacitive current during faults occurring
internally to the wind farm connection. During such
conditions, delayed current zero crossing occurs, leading to
delayed fault clearance, loss of system selectivity, and Figure 7: Lookout STATCOM
excessive wear or direct damage to circuit breakers. This
An interesting observation with regards to the GFM
drives the STATCOM rating and sets the requirement for GFM
discussion relating to the Lookout case is the improved
capabilities. In addition, the STATCOM supports the network
effectiveness in FIDVR performance compared to GFL. This
by providing its dynamic capabilities during cable energization
is explained by the dynamic negative sequence performance
and capacitor-bank switching.
that improves performance during unsymmetrical faults. The
The wind farm connection's low SCR imposes operational STATCOM is a ±120 Mvar unit connected to 138kV, designed
challenges as the STATCOM is expected to support the wind to emphasize the dynamic reactive negative sequence
farm connection during heavy voltage disturbances during performance of the single converter.
Authorized licensed use limited to: Technische Universitaet Muenchen. Downloaded on October 18,2024 at 18:49:54 UTC from IEEE Xplore. Restrictions apply.
VI. CONCLUSIONS Protection (DPSP 2022), Hybrid Conference, Newcastle, UK,
This paper has elaborated on the functionality of the GFM 2022, pp. 285-290, doi: 10.1049/icp.2022.0954.
STATCOM, its benefits, and its use for the transformation of [9] R. Grunbaum, T. Larsson and B. Ratering-Schnitzler,
the power grid worldwide. GFM technologies have been "SVC Light: A utility's aid to restructuring its grid," in IEEE
recognized as one of the key development areas for the control PES winter meeting, 2000.
strategy of grid-connected power converters for decades. This
paper provides evidence of a substantial installed base of grid- [10] ABB AB FACTS, “A matter of FACTS”, Västerås,
forming STATCOMs, ready to enable a full-scale transition to 2008.
converter-based electricity generation.
[11] M. Halonen, A. Grondona, A. Mikwar, “High
The reference cases depict that GFM capabilities are Penetration of Renewable Energy – Challenges and Impacts on
becoming necessary to comply with the requirements of Today’s Power Grids with Multilevel STATCOM and Grid
network operators. In some cases, conventional GFL Forming Control,” Riyadh, Saudi Arabia, GCC Cigre Power,
STATCOMs are unable to comply with the requirements from 2022
the operator, most noticeable for the interconnection of
renewables. Transmission operators and legislators across the [12] H. Gong, X. Wang and L. Harnefors, "Rethinking
globe have realized the need for GFM technology and are Current Controller Design for PLL-Synchronized VSCs in
including requirements in grid codes and generation Weak Grids," in IEEE Transactions on Power Electronics,
interconnection requirements. However, in order to support a vol. 37, no. 2, pp. 1369-1381, Feb. 2022, doi:
speedy grid transformation and reach the goal of carbon-neutral 10.1109/TPEL.2021.3105549.
electricity systems, more must follow.
[13] R. Heydari, et. al, “Grid-Forming Control for
STATCOMS – a Robust Solution for Networks with a High
REFERENCES
Share of Inverter-Based Resource,” Paris, France, Cigre, 2022.
[1] U.S. Energy Information Agency, “Electric Power
Monthly,” August 2023 [14] IEEE Substation Committee WGI0, Panel Session
“STATCOM and Enhanced STATCOM Technology”,
[2] J. Rocabert, A. Luna, F. Blaabjerg and P. Rodríguez, 23PESGM3874, “Grid-Forming and Grid-Following
"Control of Power Converters in AC Microgrids," in IEEE Technologies and Applications”, presented by M. Halonen,
Transactions on Power Electronics, vol. 27, no. 11, pp. 4734- IEEE PES GM Meeting 2023, Orlando, US
4749, Nov. 2012, doi: 10.1109/TPEL.2012.2199334.
[15] IEEE Electric Machinery (EMC) Committee, Panel
[3] GC0137 Final Modification Report National Grid, UK Session “Grid forming machine advances and planning
[4] Connection of HVDC systems to the public network applications”, 23PESGM4399, “Hitachi GFM
VDE AR-N 4131, Germany STATCOM/BESS Advances and Lessons Learned”, presented
by A. Bostrom, IEEE PES GM Meeting 2023, Orlando, US
[5] ENTSO-E Technical Group on High Penetration of
Power Electronic Interfaced Power Sources: “High Penetration [16] South Fork Wind, “About South Fork Wind.”
of Power Electronic Interfaced Power Sources and the Southforkwind.com. https://southforkwind.com/about-south-
Potential Contribution of Grid Forming Converters” fork-wind. Accessed [2023-10-16]
[6] AEMO Voluntary Specification for Grid-forming [17] Fault-Induced Delayed Voltage Recovery. Version
Inverters May 2023 1.2. Prepared by: NERC Transmission Issues Subcommittee
and System Protection and Control Subcommittee. June 2009
[7] Hawai’I Powered, “Hawaiian Electric’s Protection
Roadmap”, ESIG Webinar, July 20, 2023 [18] A. H. Al-Mubarak, S. M. Bamsak, B. Thorvaldsson,
M. Halonen and R. Grunbaum, "Preventing voltage collapse
[8] D. Liu, Q. Hong, M. A. U. Khan, A. Dyśko, A. E. by large SVCs at power system faults," 2009 IEEE/PES Power
Alvarez and C. Booth, "Evaluation of grid-forming converter's Systems Conference and Exposition, Seattle, WA, USA, 2009,
impact on distance protection performance," 16th pp. 1-9, doi: 10.1109/PSCE.2009.4840189.
International Conference on Developments in Power System
Authorized licensed use limited to: Technische Universitaet Muenchen. Downloaded on October 18,2024 at 18:49:54 UTC from IEEE Xplore. Restrictions apply.