04 Monitoring and Control
04 Monitoring and Control
Info:
Maintainer: CertChamp
Home page: http://www.CertChamp.com
Version: 2
Questions
Question - 1
C is the correct answer. Cost performance index(CPI) : The result from dividing the earned
value by the actual cost. A result less than one suggests that the project is at budget risk. A
CPI of 1 or greater suggests that project in delivering more with less COST. This means
project is consuming fewer resources than estimated because CPI is 1.2.
Question - 2
A is the correct answer. Scheduled Performance Index (SPI) : The result of dividing the
earned value by the planned value. A result less than 1 suggests that the project is at schedule
risk. A SPI of 1 or greater suggests that the project is ahead of schedule.
Question - 3
A. Smoothing
B. Formal
C. Coercive
D. Compromise
A is the correct answer. Smoothing is a conflict resolution technique. Others are forms of
leadership technique.
Question - 4
A. Smoothing
B. Formal
C. Coercive
D. Compromise
A is the correct answer. Smoothing is a conflict resolution technique. Others are forms of
leadership technique.
Question - 5
A. Project Manager
B. Sponsor
C. Team Member
D. Senior Management
A is the correct answer. The Project Manager is responsible for the project quality control.
Question - 6
You are calculating total cost of a project in your organization. Which of the following cost
can provide you the best result?
B. Opportunity cost
C. Sunk cost
D. Earned Value
A is the correct answer. Life Cycle cost = project costs + ongoing operations costs +
maintenance costs. Therefore, the Life Cycle cost is the best fit for this.
Question - 7
A. Earned Value
B. Cost Variance
C. Schedule Variance
D. Value Analysis
A is the correct answer. Earned Value: A method for measuring project performance. It
compares the amount of work that was planned with what was actually accomplished to
determine if cost and schedule performance are as planned.
Question - 8
You are the project manager of a project and your project is behind the schedule. Senior
management wants the project to be on time and they won't bother about the cost. Which of
the following technique you are going to use?
A. CRASHING
B. Fast Tracking
D. Schedule Model
A is the correct answer. CRASHING is reducing the project time by expending additional
resources. Senior management want project on time and they won't bother about cost
therefore CRASHING is the best technique.
Question - 9
You are a project manager of a company and you have interchanged the tasks between two
resources. What will be your NEXT step?
A. Do Impact Analysis
B. Change Control
D. Resource levelling
C is the correct answer. Your next step is to update the Project Plan. There may be some
confusing between Option A and Option C .
Question - 10
B. Direct costs
C. Working Capital
C is the correct answer. Working Capital is total assets less total liabilities.
Question - 11
Which of the following displays graphical picture of data over a specific time period for a
process?
A. Control Charts
B. Histogram
C. Pareto Diagram
D. Run Chart
A is the correct answer. Control Charts: Control charts are graphic display of the results over
a time of a process. They are used to determine whether the process is "in control".
Question - 12
You have been assigned to a construction of bridge on a river. After completion of 50 percent
of project, an NGO has raised concern about the environment misbalance. As a project
manager, you should ___________.
B. Stop work
Question - 13
A is the correct answer. If any change occurs, the version control numbers should change.
Question - 14
When more than one person is involved in the discussion on a certain document, why it is
necessary to have the same version of the document in front of the entire meeting?
D. PM wants it.
A is the correct answer. Same version of the document keeps everyone on the same page.
Question - 15
Question - 16
A collection of formal documented procedures that defines how project work will be
authorized to ensure the work is done by the identified organization, at the right time, and in
the proper sequence is called __________.
B. Project Charter
C. SOW
D. Scope Statement
A is the correct answer. A collection of formal documented procedures that defines how
project work will be authorized to ensure the work is done by the identified organization, at
the right time, and in the proper sequence is called Work Authorization System.
Question - 17
A. Small Project
B. Large Project
C. Important Project
D. Temporary Project
A. Small Project
B. Large Project
C. All Projects
D. Temporary Project
Question - 19
If your AC (Actual Cost) = $18,000 and your EV (Earned Value) = $20,000, are you over
budget?
B is the correct answer. If EV-AC value is negative, you are over budget (Not doing well).
Here $20,000 - $18,000 = $2000, so you are not over budget.
Question - 20
Your Earned Value is $6,000 and your Actual Cost is $5,000. CPI is:
A. 1.2
B. .82
C. 1
D. 1000
A is the correct answer. Cost Performance Index (CPI) = EV (Earned Value) / AC (Actual
Cost) = $6000/$5000 = 1.2
Question - 21
Your Earned Value is $6,000 and your Actual Cost is $5,000. How are you doing?
C. It is equal.
A is the correct answer. If the CPI is above the number 1, as it is in this case, this means that
you are doing better than the planned budget. Cost Performance Index (CPI) = EV (Earned
Value) / AC (Actual Cost) = $6000/$5000 = 1.2
Question - 22
Your Earned Value is $5,000 and your Actual Cost is $10,000. How are you doing?
C. It is equal.
B is the correct answer. If the CPI is less than the number 1, as it is in this case, this means
that you are not doing better than the planned budget. Cost Performance Index (CPI) = EV
(Earned Value) / AC (Actual Cost) = $5000/$10,000 = .5
Question - 23
A. 1.25
B. .8
C. 2000
D. 0
Question - 24
A is the correct answer. Schedule Performance Index (SPI): SPI = EV/PV = $10,000/$8,000
= 1.25 SPI more than 1 means you are ahead of plan.
Question - 25
Question - 26
A. Sponsor
B. Customer
C. Project Manager
D. Team Lead
B is the correct answer. Customer gives project acceptance. Customer may be a person or an
organization.