Financial Analysis
Financial Analysis
11.1 Introduction
The financial issues associated with capital investment in energy saving projects are
investigated in this chapter. In particular, the discounted cash flow techniques of net
present value and internal rate of return are discussed in detail.
The capital cost of the DG set is Rs.9,00,000, the annual output is 219 MWh, and the
maintenance cost is Rs.30,000 per annum. The cost of producing each unit of
electricity is 3.50 Rs./kWh. The total cost of a diesel generator operating over a 5-year
period, taking into consideration both fixed and variable cost is:
The concept of fixed and variable costs can be used to determine the break-even
point for a proposed project. The break-even point can be determined by using the
following equation.
Where,
UCutil is the unit cost per kWh of energy bought from utility (Rs./kWh)
UCprod is the unit cost per kWh of produced energy (Rs./kWh)
FC is the fixed costs (Rs.)
Wav is the average power output (or consumption) (kW)
n is the number of hours of operation (hours).
Example 2
If the electricity bought from a utility company costs an average of Rs.4.5/kWh, the
break-even point for the generator described in Example 1, when the average output is
50 kW is given by:
4.5 x 50 x n = (9,00,000 + 150000) + (3.5 x 50 x n)
n = 21000 hours
n = 15000 hours
Thus, increasing the average output of the generator significantly reduces the break-
even time for the project. This is because the capital investment (i.e. the generator) is
being better utilised.
(i) Simple interest: If simple interest is applied, then charges are calculated as a fixed
percentage of the capital that is borrowed. A fixed interest percentage is applied to
each year of the loan and repayments are calculated using the equation.
Where TRV is the total repayment value (Rs.), LV is the value of initial loan (Rs.), IR
is the interest rate (%), and P is the repayment period (years).
TRV = LV x (1 + IR/100) p
The techniques involved in calculating simple and compound interest are illustrated
in Example 3 given below:
Example 3
A company borrows Rs.3,00,00,00 to finance a new boiler installation. If the interest
rate is 10% per annum and the repayment period is 5 years, let us calculate the value
of the total repayment and the monthly repayment value, assuming (i) simple interest
and (ii) compound interest.
4831530
Monthly repayment = = Rs.80,525
5 x 12
It can be seen that by using compound interest, the lender recoups an additional
Rs.33,1530. It is not surprisingly lenders usually charge compound interest on loans.
This is the simplest technique that can be used to appraise a proposal. The simple
payback period can be defined as 'the length of time required for the running total of
net savings before depreciation to equal the capital cost of the project’. In theory,
once the payback period has ended, all the project capital costs will have been
recouped and any additional cost savings achieved can be seen as clear 'profit'.
Obviously, the shorter the payback period, the more attractive the project becomes.
The length of the maximum permissible payback period generally varies with the
business culture concerned. In some companies, payback periods in excess of 3 years
are considered acceptable.
CC
PB =
AS
Where PB is the payback period (years), CC is the capital cost of the project (Rs.),
and AS is the annual net cost saving achieved (Rs.).
The annual net cost saving (AS) is the least savings achieved after all the operational
costs have been met. Simple payback period is illustrated in Example 4.
Example 4
A new small cogeneration plant installation is expected to reduce a company's annual
energy bill by Rs.4,86,000. If the capital cost of the new boiler installation is
Rs.22,20,000 and the annual maintenance and operating costs are Rs. 42,000, the
expected payback period for the project can be worked out as.
Solution
PB = 22,20,000/ (4,86,000 - 42,000) = 5.0 years
The payback method does not consider the fact that money, which is
invested, should accrue interest as time passes. In simple terms there is a
'time value' component to cash flows. Thus Rs.1000 today is more valuable
than Rs.1000 in 10 years' time.
In order to overcome these weaknesses a number of discounted cash flow techniques
have been developed, which are based on the fact that money invested in a bank will
accrue annual interest. The two most commonly used techniques are the 'net present
value' and the 'internal rate of return' methods.
The value of the sum at the end of year 2 = 23,97,600 + (0.08 x 23,97,600) = Rs.25,89,4 08
The value of the investment would grow as compound interest is added, until after n
years the value of the sum would be:
FV = D x (1 + IR/100) n
Where FV is the future value of investment in Rs., and D is the value of initial deposit
(or investment) in Rs., IR is Interest Rate and n is number of years.
Example :
The future value of the investment made at present, after 5 years will be:
The present value of an amount of money at any specified time in the future can be
determined by the following equation.
PV = S x (1 + IR/100) -n
Where PV is the present value of S in n years time (Rs.), and S is the value of cash
flow in n years time (Rs.).
The net present value method calculates the present value of all the yearly cash flows
(i.e. capital costs and net savings) incurred or accrued throughout the life of a project,
and summates them. Costs are represented as a negative value and savings as a
positive value. The sum of all the present values is known as the net present value
(NPV). The higher the net present value, the more attractive the proposed project.
The present value of a future cash flow can be determined using the equation above.
However, it is common practice to use a discount factor (DF) when calculating
present value. The discount factor is based on an assumed discount rate (i.e. interest
rate) and can be determined by using equation.
DF = ( 1 + IR/100) -n
The product of a particular cash flow and the discount factor is the present value.
PV = S x DF
The values of various discount factors computed for a range of discount rates (i.e.
interest rates) are shown in Table 11.1. The Example 5 illustrates the process involved
in a net present value analysis.
Example 5
Using the net present value analysis technique, let us evaluate the financial merits of
the proposed projects shown in the Table below. Assume an annual discount rate of
8% for each project.
.
Project – 1 Project - 2
Capital cost (Rs.) 30 000.00 30 000.00
Solution
The annual cash flows should be multiplied by the annual discount factors for a rate
of 8% to determine the annual present values, as shown in the Table below:
It can be seen that over a 10 year life-span the net present value for Project 1 is
Rs.10,254.00, while for Project 2 it is Rs.10,867.80. Therefore Project 2 is the
preferential proposal.
The whole credibility of the net present value method depends on a realistic
prediction of future interest rates, which can often be unpredictable. It is prudent
therefore to set the discount rate slightly above the interest rate at which the capital
for the project is borrowed. This will ensure that the overall analysis is slightly
pessimistic, thus acting against the inherent uncertain ties in predicting future savings.
Internal rate of return method
It can be seen from Example 5 that both projects returned a positive net present value
over 10 years, at a discount rate of 8%. However, if the discount rate were reduced
there would come a point when the net present value would become zero. It is clear
that the discount rate which must be applied, in order to achieve a net present value
of zero, will be higher for Project 2 than for Project 1. This means that the average
rate of return for Project 2 is higher than for Project 1, with the result that Project 2 is
the better proposition.
The discount rate which achieves a net present value of zero is known as the internal
rate of return (IRR). The higher the internal rate of return, the more attractive the
project.
Solution
It can clearly be seen that the discount rate which results in the net present value
being zero lies somewhere between 12% and 16%.
For12% discount rate, NPV is positive; for 16% discount rate, NPV is negative. Thus
for some discount rate between 12 and 16 percent, present value benefits are equated
to present value costs. To find the value exactly, one can interpolate between the two
rates as follows:
459.5
Internal rate of return = 0.12 + (0.16 - 0.12) x
(459.5 - (-1508.5))
459.5
Internal rate of return = 0.12 + (0.16 - 0.12) x = 12.93%
(459.5 + 1508.5)
Thus the internal rate of return for the project is 12.93 %. At first sight both the net
present value and internal rate of return methods look very similar, and in some
respects are. Yet there is an important difference between the two. The net present
value method is essentially a comparison tool, which enables a number of projects to
be compared, while the internal rate of return method is designed to assess whether
or not a single project will achieve a target rate of return.
Profitability index
Another technique, which can be used to evaluate the financial viability of projects,
is the profitability index. The profitability index can be defined as:
The higher the profitability index, the more attractive the project.
10254
For Project 1 : Profitability index = = 0.342
30000
10 867
For Project 2 : Profitability index = = 0.362
30000
• The capital value of plant and equipment generally depreciates over time
• General inflation reduces the value of savings as time progresses. For
example, Rs.1000 saved in 1 year’s time will be worth more than Rs.1000
saved in 10 years time.
Example 8
Data
Year 1 2 3 4 5
7000 6000 6000 5000 5000
Solution
Discount Capital Net Present
Factor for Investment Savings Value
8% (Rs.) (Rs.) (Rs.)
Year (a) (b) (c) (a) x (b + c)
NPV = +4489.50
It is evident that over a 5-year life span the net present value of the project is
Rs.4489.50. Had the salvage value of the equipment not been considered, the net
present value of the project would have been only Rs.3468.00.
Real value
Inflation can be defined as the rate of increase in the average price of goods and
services. In some countries, inflation is expressed in terms of the retail price index
(RPI), which is determined centrally and reflects average inflation over a range of
commodities. Because of inflation, the real value of cash flow decreases with time.
The real value of sum of money (S) realised in n years time can be determined using
the equation.
RV = S x ( 1 + R/100) -n
Where RV is the real value of S realized in n years time. S is the value of cash flow in
n years time and R is the inflation rate (%).
As with the discount factor it is common practice to use an inflation factor when
assessing the impact of inflation on a project. The inflation factor can be determined
using the equation.
IF = (1 + R/100) -n
The product of a particular cash flow and inflation factor is the real value of the cash
flow.
RV = S x IF
Example 9
Recalculate the net present value of the energy recovery scheme in Example 8,
assuming the discount rate remains at 8% and that the rate of inflation is 5%.
Solution
NPV = +4397.88
The Example 9 shows that when inflation is assumed to be 5%, the net present value
of the project reduces from Rs.4489.50 to Rs.4397.88. This is to be expected, because
general inflation will always erode the value of future ‘profits’ accrued by a project.