CERN Presentation MLS
CERN Presentation MLS
1
Description of the way factories behave
Title of a book first published in 1996
Name of a company that offers services to manufacturing companies
2
Context
Supply Flow
E F D I
E F D I
E F D I
E F D I
3
Definitions
4
Inventory, WIP, Stock and Queues
5
Modeling
Analytic and Queueing
Monte Carlo Discrete Event Simulation
6
Fundamentals
Little’s Law:
WIP=CT×TH
TH is demand
WIP is “visible cycle time”
7
What is “Pull?”
WIP and TH are ‘leading’ indicators, CT lags
Pull controls WIP, Push controls TH
Pull is more robust than Push
Performance Curves
8
FLOW STOCK
Variability
Demand and Production are never synchronized
There is always variability!
9
Variability in a production system will be buffered with some combination of:
1. Inventory
2. Time
3. Capacity
Operations Science
10
Almost everything we do involves operations
Manufacturing
Transportation
Medical services
Project execution
Operations Science
11
Little’s Law = Little’s Tautology
Does throughput always go up with additional WIP?
How do the three buffers interact?
Adan, I., J. Van der Wal. 1989. Monotonicity of the Throughput of a Closed Spearman, M.L., W.J. Hopp. 2021 The Case for a Unified Science of Operations,
Queueing Network in the Number of Jobs. Operations Research, 5 (6), 953- Production and Operations Management, 30 (3), 802-814
957.
12
Operations Science
13
Process
Demand
14
Projects
Creation of a unique device, structure, software, etc.
The creation is unique but composed of many repetitive processes
15
Maintain the Rates Make the Dates
TAKT
TH
16
Simple production-inventory system
𝝁, 𝒄𝟐 𝜆, 𝜓
S
Buffers
Time—demand waits on unit or task
Inventory—units or tasks wait on demand
Capacity—productive ability that exceeds average demand
17
Time and Inventory Buffers mirror each other
Time-Inventory Buffer
18
Copyright © 2021 Project Production Institute. All Rights Reserved.
Time-Inventory Buffer
The standard deviation of lead time demand
Capacity Buffer
Capacity less Average Demand
19
Let 𝜓 = 𝑐 = 𝑉
Vary V and 𝜇 − 𝜆 while keeping 𝜎 constant
𝜆 = 1, 𝜇 = 1.25 → 1.05
𝜓 = 𝑐 = 0.93 → 0.22
𝜎 ≈ 4.4
Copyright © 2020 Project Production Institute. All Rights Reserved.
20
𝜎 +𝜎
𝜇−𝜆 𝜎 ≈
2
Inventory /
Time Buffer
Inventory /
Time Buffer
Capacity Buffer
Capacity Buffer
21
Can you have an inventory of completed projects?
Efficiency (utilization)
22
Copyright © 2021 Project Production Institute. All Rights Reserved.
23
Must have a capacity buffer to avoid the “time buffer”
Project Duration
24
Too much WIP
long cycle times
inefficient production
Too little WIP
insufficient production
Optimal Typical
WIP Level WIP Level
25
Routings
Rates
Yields Production System Model
Downtime
Etc.
Production System Model
Little’s Law:
Cycle Time
CT = WIP / TH
Utilization
Throughput
Cycle Time Formula:
VUT Equation:
RPT = PT + ST + DT
Cycle Time
BT = (Waiting for Batch) + (Waiting in Batch)
WIP
Stock
Work-in-Process
Parameters Batch
Capacity
Cashflow
Questions?
26