Lecture 4 Construction Processes
Lecture 4 Construction Processes
ENGINEERING PROJECTS
MSCEPM601
LECTURE 4
Construction Management
Dr Eng. ZJ Chihambakwe
Classification of construction projects
Generally speaking, you can separate construction project types into three
categories:
(i) Private construction;
• Residential Construction
• Commercial Construction
• Industrial Construction
(ii) State construction;
• projects commissioned by a county, city, municipality, government board,
public school board or any other state-funded entity
(iii) Federal Construction.
For example courthouses, government buildings, flood control projects, etc
Construction processes
• A typical construction project consists of groups of people, normally from
several organizations, that are hired and assigned to a project to build the
facility.
• Due to the relatively short life of a construction project, these people may
view the construction project as accomplishing short-term tasks. However,
the project manager of the construction team must instill in the team that
building long-term relationships is more important in career advancement
than trying to accomplish short-term tasks.
• With all the diversity involved in a construction project, people must be
managed so they work together efficiently to accomplish the goal
• The key to a successful construction project is properly skilled construction
managers. These individuals possess the ability to recognize the degree of
uncertainty at any point in the execution of the project and to manage the
efforts of others to achieve clearly defined objectives that result in
successful completion of the final product.
Construction processes
• The construction contractor is responsible for the performance of all
work in accordance with the contract documents that have been
prepared by the designer. This includes furnishing all labor, equipment,
material, and know-how necessary to build the project.
• The construction phase is important because most of the project
budget is expended during construction.
• Also, the operation and maintenance of the completed project is highly
dependent on the quality of work that is performed during
construction.
• The contractor must prepare an accurate estimate of the project,
develop a realistic construction schedule, and establish an effective
project control system for cost, schedule, and quality
Construction processes
The Construction Process is composed of six distinct stages, which are:
• Concept.
• Contracts and Bid Documents.
• Bidding.
• Construction.
• Construction Payments.
• Completion.
Construction processes
Stages of construction planning
1. Pretender planning
The contract documentation and tender drawings will provide a useful starting point
but most Estimators will need to visit the proposed site to get a ‘feel’ for the contract
and the environment in which the work will take place.
2. Contract planning
It is the planning after the acceptance of a tender and award after a contract. It
includes following
• Preparation of labor requirement
• Material statement chart
• Master plan for carrying the work
• Detailed drawings
• Dates for making orders for supply of material
• Sequence of operations and their inter relationship to be planned
Construction processes
Contracts
• A contract is an undertaking by a person or a firm to do any work under
certain terms and conditions, which should invariably be in writing. The
work may be for the construction or maintenance and repairs, for the
supply of labor or the transport of materials, etc.
Contract Agreement
Contract agreements are fall into the following categories:
1. Contracts-Contracts are of the following types Item rate Contracts,
Percentage Rate Contracts, Lump sum contracts.
2. Piece work agreements- these are agreements for doing the work at
agreed rates, without reference to the total quantity of work or time, can be
Piece-work or Work Order.
Construction processes
Contractual Arrangements
1. design/bid/build contract
It is a three-party arrangement involving the owner, designer, and contractor.
This method involves three steps: a complete design is prepared, followed by
solicitation of competitive bids from contractors, and the award of a contract
to a construction contractor to build the project
2. design/build contract
is often used to shorten the time required to complete a project or to
provide flexibility for the owner to make changes in the project during
construction. It is a two-party arrangement between the owner and the
design/build firm.
Construction processes
Contractual Arrangements
3. owner/agent arrangement
Some owners perform part of the design with in-house personnel and
contract the balance of design to one or more outside design
consultants. Construction contracts may be assigned to one contractor
or to multiple contractors
4. A construction management (CM) contract
can be assigned to a CM firm to coordinate the project for the owner.
The CM contract is a four-party arrangement involving the owner,
designer, CM firm, and contractor
Construction processes
Selection of design firms and construction contractors
• Selection of the designer and contractor varies depending on many
factors including the type, size, and complexity of the project; the
owner's knowledge in handling engineering and construction
projects, and how soon the owner wants the project completed. The
method of selection depends on the owner's project strategy and the
contract arrangement chosen by the owner.
A Method Statement
A method statement is a document that describes how to do a task safely. You can
think of a method statement like a set of instructions or a plan for the work
A method statement will usually contain a lot of information about a task or activity
such as:
• The project
• The specific activity the method statement is for
• A description of the work
• Start date and duration of the task
• Hours of work
• Who the assessor is
• Who has key responsibilities
A Method Statement