NATIONAL GOVERNMENT CONSTITUENCY DEVELOPMENT FUND BOARD
MUHORONI CONSTITUENCY NG-CDF
PROJECT IMPLEMENTATION REPORT AS AT 30 JUNE 2022 FINANCIAL YEAR 2021/2022 Financial Allocated Implimentation Project Name Approved Activity Estimated Cost Completion Date Expected Beneficiaries Remarks Year Amount(KSHS) Status 2021/2022 Employees’ Salaries Payment of staff salaries 3,635,760.00 3,635,760.00 30/06/2022 Complete 13 Staffs Complete 2021/2022 NHIF Employees contribution to NHIF 104,400.00 104,400.00 30/06/2022 Complete 13 Staffs Complete 2021/2022 Employees’ gratuity Payment of staff gratuity 2,828,355.90 2,828,355.90 30/06/2022 Complete 12 Staffs Complete 2021/2022 NSSF Employers contribution to NSSF 250,560.00 250,560.00 30/06/2022 Complete 12 Staffs Complete Purchase of fuel, repairs and maintenance, printing, 2021/2022 Goods and Services stationery, telephone, travel and subsistence, office 886,256.84 886,256.84 30/06/2022 Complete Office operations Complete tea Payment of Committee sitting allowances, 2021/2022 Committee Expenses 520,000.00 520,000.00 30/06/2022 Complete The Committee (10 members) Complete transport, conferences. NG-CDFC/PMC Undertake Training of the PMCs/NG-CDFCs and 2021/2022 1,272,666.37 1,272,666.37 30/06/2022 Complete PMCs22 X5 people each, Staffs (12) CDFs (10) Complete Capacity Building NG-CDFC staff. Purchase of fuel, repairs and maintenance, printing, 2021/2022 Goods and Services 2,112,000.00 2,112,000.00 30/06/2022 Complete Office operations Complete stationery, Airtime, travel and subsistence. Payment of Committee sitting allowances, 2021/2022 Committee Expenses 728,000.00 728,000.00 30/06/2022 Complete The Committee (10 members) Complete transport, conferences. 2021/2022 Emergency fumugation and pest controls 2,711,830.00 2,711,830.00 30/06/2022 Complete 2500 students Complete supply of meals to police officers during boarder 2021/2022 Emergency 1,675,000.00 1,675,000.00 30/06/2022 Complete 150 police officers Complete clashes 2021/2022 Emergency fumugation and pest controls 1,025,100.00 1,025,100.00 30/06/2022 Complete 1800 students Complete 2021/2022 Emergency Supply of relief food to flood victims in kibigori 830,277.00 830,277.00 30/06/2022 Complete 400 contituents Complete 2021/2022 Emergency Purchaes of water dispensing tanks 950,000.00 950,000.00 30/06/2022 Complete P100 institutions Complete Fully sponsored National students = 163X53,544.00 = 8,727,672, students with special cases (PWD) 52 @ Kshs. 5,000.00 totaling to Kshs. 255,000.00 directed Bursary Secondary Payment of bursary to needy students in secondary to their respective schools, Day-scholars Students 2021/2022 32,481,107.65 32,481,107.65 30/06/2022 Complete Complete Schools schools each awarded Kshs. 4,000.00 X1,200 applicants totaling to Kshs. 4,800,000.00 and Boarders awarded 1,871, Kshs. 10,000 each totaling to 18,710,000.00 distributed equally to students in all 5 Wards 80 Engineering and Medicine Sponsored Students = Payment of bursary to needy students in 3,192,734, College students @ Kshs. 7,000.00 Bursary Tertiary 2021/2022 universities, middle level colleges, driving schools 15,500,000.00 15,500,000.00 30/06/2022 Complete awarded to 607 totaling to Kshs. 4,402,600.00 and Complete Institutions and any other tertiary schools 798 University students 2 Kshs. 10,000.00 totaling to Kshs. 7,980,000.00 2021/2022 Kibigori Primary School Construction of 2 No Classrooms to completion 2,200,000.00 2,200,000.00 ongoing 100 students procurement process 2021/2022 Achego Primary School Construction of 2 No Classrooms to completion 2,200,000.00 2,200,000.00 ongoing 100 students procurement process 2021/2022 Amilo Primary School Construction of 2 No Classrooms to completion 2,200,000.00 2,200,000.00 ongoing 100 students procurement process 2021/2022 Angogo Primary School Construction of 1 No Classroom to completion 1,100,000.00 1,100,000.00 ongoing 50 students procurement process 2021/2022 Kang’o Primary School Construction of 2 No Classrooms to completion 2,200,000.00 2,200,000.00 ongoing 100 students procurement process Kibos Prison Primary 2021/2022 Construction of 2 No Classrooms to completion 2,200,000.00 2,200,000.00 ongoing 100 students procurement process School 2021/2022 Marega Primary School Construction of 2 No Classrooms to completion 2,200,000.00 2,200,000.00 ongoing 100 students procurement process Mashambani Primary 2021/2022 Construction of 2 No Classrooms to completion 2,200,000.00 2,200,000.00 ongoing 100 students procurement process School 2021/2022 Mikiria Primary School Construction of 2 No Classrooms to completion 2,200,000.00 2,200,000.00 ongoing 100 students procurement process Muhoroni Primary 2021/2022 Construction of 2 No Classrooms to completion 2,200,000.00 2,200,000.00 ongoing 100 students procurement process School Muhoroni Township 2021/2022 Construction of 2 No Classrooms to completion 2,200,000.00 2,200,000.00 ongoing 100 students procurement process Primary School 2021/2022 Ng’eny Primary School Construction of 1 No Classroom to completion 1,100,000.00 1,100,000.00 ongoing 50 students procurement process Nyang’oma Primary 2021/2022 Construction of 2 No Classrooms to completion 2,200,000.00 2,200,000.00 ongoing 100 students procurement process School Obumba Primary 2021/2022 Construction of 2 No Classrooms to completion 2,200,000.00 2,200,000.00 ongoing 100 students procurement process School Ogwedhi Primary 2021/2022 Construction of 2 No Classrooms to completion 2,200,000.00 2,200,000.00 ongoing 100 students procurement process School Ogwodo Primary 2021/2022 Construction of 2 No Classrooms to completion 2,200,000.00 2,200,000.00 ongoing 100 students procurement process School 2021/2022 Okwach Primary School Construction of 1 No Classroom to completion 1,100,000.00 1,100,000.00 ongoing 50 students procurement process Osiri Migere Primary 2021/2022 Construction of 2 No Classrooms to completion 2,200,000.00 2,200,000.00 ongoing 100 students procurement process School God Abuoro Secondary 2021/2022 Construction of 1 No Classroom to completion 1,100,000.00 1,100,000.00 ongoing 50 students procurement process School Hon koyoo Mixed 2021/2022 Construction of 2 No Classrooms to completion 2,200,000.00 2,200,000.00 ongoing 100 students procurement process Secondary School Our Lady Queen of 2021/2022 Construction of 2 No Classrooms to completion 2,200,000.00 2,200,000.00 ongoing 100 students procurement process Peace Secondary Nyakoko Girls 2021/2022 Construction of 2 No Classrooms to completion 2,200,000.00 2,200,000.00 30/06/2022 ongoing 100 students procurement process Secondary School Muhoroni Subcounty Construction of three residential quarters and an 2021/2022 4,000,000.00 4,000,000.00 30/06/2022 Complete 0ver 1000 constituents Complete Headquarters Office to completion Completion of ACCs two bedroomed staff house; Electrical works, plumbing works, painting, plastering, fixing windows, doors, tiling and ceiling (Kshs.1,450,000) installation of rain water harvesting goods; gutters, purchase of 10,000 litres Miwani Assistant tank, construction of tank base, installation of 2021/2022 County Commissioner's concrete handwashing area complete with fittings 2,150,000.00 2,150,000.00 30/06/2022 Complete D.O and the family Complete House (Kshs.250,000) fencing of 50*100 metres compound using chainlink and concrete poles and installation of one steel gate (kshs.250,000) and construction of 4 door pit latrine with one door set aside for persons living with disability to completion (Kshs.200,000) Construction of access to Rapid Development Unit Kenya Rapid at Songhor Road distance is 700m (Drain not yet 2021/2022 Deployment Unit - excavation, Boulder removal, Heavy bush clearing, 3,000,000.00 3,000,000.00 Approx 1000 constituents pending approval impletemented Songhor Heavy grading, Graveling with compaction and Concrete drift 3X6m Kenya Rapid 2021/2022 Deployment Unit - Purchase of one acre piece of Land for expansion 700,000.00 700,000.00 30/06/2022 Complete 50 police officers and over 1000 Complete Songhor
Renovation of Ngcdf Office, Twelve offices in
number, three toilets, four external pit latrine and 3 bathrooms - one for people living with disability - (Namely constituency Office which includes Office and Mini-boardrom, CDF Charman's Office, Constituency Manager's Office, Fund Account Manager's Office, Two waiting rooms, PA's office, Muhoroni NGCDF Reception's office, Account's Assistant Office, 2021/2022 5,444,010.08 5,444,010.08 30/06/2022 Complete Approx 1000 constituents Complete Office Boardroom, Pool Office, CACC and Uwezo Offices). - The actitivies includes Repainting entire office, Electrical work , Plumbing - installation of sewer line and construction of 1 door toilet and bathroom for the Constituency Office, replacement of ceiling and installation of modern gypsum ceiling at the constiteuncy Office, reroofing of the entire Office and retiling
Construction of a 2 roomed Chief’s office to
2021/2022 Koru Chiefs' Office 1,200,000.00 1,200,000.00 ongoing Approx 1000 constituents procurement process completion. Ngere Kagoro – Police Construction of a 2 roomed Police office in an 2021/2022 1,200,000.00 1,200,000.00 ongoing Approx 1000 constituents procurement process Post existing police post to completion. Construction of a 2 roomed Police office in an 2021/2022 Miwani Police Station 1,200,000.00 1,200,000.00 ongoing Approx 1000 constituents procurement process existing police post to completion. Construction of a 2 roomed Police office in an 2021/2022 Muhoroni Police Post 1,200,000.00 1,200,000.00 ongoing Approx 1000 constituents procurement process existing police post to completion. Purchase and installation of one 10,000ltrs water Our Lady Queen of 2021/2022 tank, construction of tank base and installation 260,000.00 260,000.00 30/06/2022 Complete About 800 Students Complete Peace Secondary gutters. Purchase and installation of one 10,000ltrs water God Abuoro Secondary 2021/2022 tank, construction of tank base and installation 260,000.00 260,000.00 30/06/2022 Complete About 800 Students Complete School gutters. Purchase and installation of one 10,000ltrs water Muhoroni Primary 2021/2022 tank, construction of tank base and installation 260,000.00 260,000.00 30/06/2022 Complete About 800 Students Complete School gutters. Purchase and installation of one 10,000ltrs water Chemelil B1 Primary 2021/2022 tank, construction of tank base and installation 260,000.00 260,000.00 30/06/2022 Complete About 800 Students Complete School gutters. Purchase and installation of one 10,000ltrs water Chemelil Factory 2021/2022 tank, construction of tank base and installation 260,000.00 260,000.00 30/06/2022 Complete About 800 Students Complete Primary School gutters. Purchase and installation of one 10,000ltrs water Kibos Research 2021/2022 tank, construction of tank base and installation 260,000.00 260,000.00 30/06/2022 Complete About 800 Students Complete Secndary School gutters. Purchase and installation of one 10,000ltrs water Mutwala Primary 2021/2022 tank, construction of tank base and installation 260,000.00 260,000.00 30/06/2022 Complete About 800 Students Complete School gutters. Purchase and installation of one 10,000ltrs water Kibigori Secondary 2021/2022 tank, construction of tank base and installation 260,000.00 260,000.00 30/06/2022 Complete About 800 Students Complete School gutters. Purchase and installation of one 10,000ltrs water 2021/2022 Ngeny Special School tank, construction of tank base and installation 260,000.00 260,000.00 30/06/2022 Complete About 800 Students Complete gutters. Purchase and installation of one 10,000ltrs water 2021/2022 Kibigori Primary School tank, construction of tank base and installation 260,000.00 260,000.00 30/06/2022 Complete About 800 Students Complete gutters. Purchase and installation of one 10,000ltrs water 2021/2022 Obago Primary School tank, construction of tank base and installation 141,777.58 141,777.58 30/06/2022 Complete About 800 Students Complete gutters. Carry out Constituency Sports tournament and the Constituency Sports 25 teams football Teamx11= 275 people, Netbal 2021/2022 winning teams to be awarded with trophies, balls, 2,741,777.58 2,741,777.58 30/06/2022 Complete Complete Tournament Ladies 10 teams =35 Volleyball 12 =72 and games kits GRAND TOTAL 137,088,879.00 137,088,879.00 ONGOING / NOT STARTED / STALLED PROJECTS Financial Allocated Implimentation Project Name Approved Activity Estimated Cost Completion Date Expected Beneficiaries Remarks Year Amount(KSHS) Status 2021/2022 Kibigori Primary School Construction of 2 No Classrooms to completion 2,200,000.00 2,200,000.00 ongoing 100 students procurement process 2021/2022 Achego Primary School Construction of 2 No Classrooms to completion 2,200,000.00 2,200,000.00 ongoing 100 students procurement process 2021/2022 Amilo Primary School Construction of 2 No Classrooms to completion 2,200,000.00 2,200,000.00 ongoing 100 students procurement process 2021/2022 Angogo Primary School Construction of 1 No Classroom to completion 1,100,000.00 1,100,000.00 ongoing 50 students procurement process 2021/2022 Kang’o Primary School Construction of 2 No Classrooms to completion 2,200,000.00 2,200,000.00 ongoing 100 students procurement process Kibos Prison Primary 2021/2022 Construction of 2 No Classrooms to completion 2,200,000.00 2,200,000.00 ongoing 100 students procurement process School 2021/2022 Marega Primary School Construction of 2 No Classrooms to completion 2,200,000.00 2,200,000.00 ongoing 100 students procurement process Mashambani Primary 2021/2022 Construction of 2 No Classrooms to completion 2,200,000.00 2,200,000.00 ongoing 100 students procurement process School 2021/2022 Mikiria Primary School Construction of 2 No Classrooms to completion 2,200,000.00 2,200,000.00 ongoing 100 students procurement process Muhoroni Primary 2021/2022 Construction of 2 No Classrooms to completion 2,200,000.00 2,200,000.00 ongoing 100 students procurement process School Muhoroni Township 2021/2022 Construction of 2 No Classrooms to completion 2,200,000.00 2,200,000.00 ongoing 100 students procurement process Primary School 2021/2022 Ng’eny Primary School Construction of 1 No Classroom to completion 1,100,000.00 1,100,000.00 ongoing 50 students procurement process Nyang’oma Primary 2021/2022 Construction of 2 No Classrooms to completion 2,200,000.00 2,200,000.00 ongoing 100 students procurement process School Obumba Primary 2021/2022 Construction of 2 No Classrooms to completion 2,200,000.00 2,200,000.00 ongoing 100 students procurement process School Ogwedhi Primary 2021/2022 Construction of 2 No Classrooms to completion 2,200,000.00 2,200,000.00 ongoing 100 students procurement process School Ogwodo Primary 2021/2022 Construction of 2 No Classrooms to completion 2,200,000.00 2,200,000.00 ongoing 100 students procurement process School 2021/2022 Okwach Primary School Construction of 1 No Classroom to completion 1,100,000.00 1,100,000.00 ongoing 50 students procurement process Osiri Migere Primary 2021/2022 Construction of 2 No Classrooms to completion 2,200,000.00 2,200,000.00 ongoing 100 students procurement process School God Abuoro Secondary 2021/2022 Construction of 1 No Classroom to completion 1,100,000.00 1,100,000.00 ongoing 50 students procurement process School Hon koyoo Mixed 2021/2022 Construction of 2 No Classrooms to completion 2,200,000.00 2,200,000.00 ongoing 100 students procurement process Secondary School Our Lady Queen of 2021/2022 Construction of 2 No Classrooms to completion 2,200,000.00 2,200,000.00 ongoing 100 students procurement process Peace Secondary Construction of access to Rapid Development Unit Kenya Rapid at Songhor Road distance is 700m (Drain not yet 2021/2022 Deployment Unit - excavation, Boulder removal, Heavy bush clearing, 3,000,000.00 3,000,000.00 Approx 1000 constituents pending approval impletemented Songhor Heavy grading, Graveling with compaction and Concrete drift 3X6m Construction of a 2 roomed Chief’s office to 2021/2022 Koru Chiefs' Office 1,200,000.00 1,200,000.00 ongoing Approx 1000 constituents procurement process completion. Ngere Kagoro – Police Construction of a 2 roomed Police office in an 2021/2022 1,200,000.00 1,200,000.00 ongoing Approx 1000 constituents procurement process Post existing police post to completion. Construction of a 2 roomed Police office in an 2021/2022 Miwani Police Station 1,200,000.00 1,200,000.00 ongoing Approx 1000 constituents procurement process existing police post to completion. Construction of a 2 roomed Police office in an 2021/2022 Muhoroni Police Post 1,200,000.00 1,200,000.00 ongoing Approx 1000 constituents procurement process existing police post to completion. GRAND TOTAL 49,600,000.00 49,600,000.00