0% found this document useful (0 votes)
239 views9 pages

BoQ - PWD Bath Room

Uploaded by

Engr Imad Khan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
239 views9 pages

BoQ - PWD Bath Room

Uploaded by

Engr Imad Khan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 9

Sanitation Up scaling through PATS

CONSTRUCTION OF 01 LATRINE & REHABILITATION of EXISTING LATRINES in GGPS Mian


Sahib Kaly
ABSTRACT OF COST As Per MRS 2021

S.No. Sub Head Amount (Rs.)

1 Construction & Rehab of Existing Twin Set latrine Block 170,543

2 Electrification 6,300

3 Sanitary/Plumbing Work 79,018

4 Inauguration Plaque/ Sign Board 3,000

Total Cost 258,861


Sanitation Up scaling through PATS
CONSTRUCTION OF 01 LATRINE & REHABILITATION of EXISTING LATRINES in GGPS Mian Sahib
Kaly
A Construction of 01 New latrine & Rehab works in Existing Latrine
Unit Rate Total Cost
S/N Activities MRS Ref: Unit Quantity
PKR PKR
Excavation in foundation of building, bridges etc
1 03-25-c Cft 32 8.77 276
complete : in hard soil or soft soil

Plain Cement Concrete including placing,


2 06-05-i Cft 13 184.00 2369
compacting, finishing & curing (Ratio 1:4:8)

1st class brick work in ground floor Cement, sand


3 07-05-a-03 Cft 137 286.03 39177
mortar 1:4
Damp proof course of cem. conc. 1:2:4 including
4 bitumen coat, 1 layer polythene & 2 coats bitumen 06-26-b-02 Sft 15.75 96.21 1515
(2" thick)
5 RCC in roof slab, beam, column & other structural members (1:2:4) 06-07-a-03 Cft 25 286.98 7200
Supply & fabricate M.S. reinforcement for cement concrete (Hot rolled
6 06-08-c Kg 79 200.36 15865
deformed bars Grade 40)

7 Cement plaster 1:4 upto 20' height 1/2" thick 11-09-b Sft 390.875 28.56 11164

Filling, watering and ramming earth under floor with surplus earth from
8 03-18-a Cft 30 2.42 73
foundation, etc

Provide & lay topping of concrete 1:2:4, including surface finishing & dividing
9 10-15-h cft 28.65 109.40 3134
in panels :

Providing and Fixing of Fancy design bath room


tile of size 12'' x 12'' in cement sand mortar 1 : 2
10 .10-52 Sft 356 121.69 43261
with finishing of joints in white cement /
Readymade filler complete in all respect

Supplying and fixing MS Sheet 18 guage Chowkat (5" x 1.5" )i/c fixing in
11 NSI Rft 66 220.00 14520
position with all charges for holdfast, hinges, and painting etc.

Steel Door of 6'.5 X 2.5 & 6'.5x3', pressed by machine with 18 gauge iorn
sheet,welded with aldaraz bolt locks, clamps, handle etc., prime coat/red
12 NSI Sft 48.75 250 12188
enemal and red oxide paint on steel sections and class B concrete in hold
fasts. complete in all respect as approved and directed by the Engineer.

Providing and applying wall putty of 2mm thickness over plastered surface to
13 11-20-b Sft 541.875 6.08 3295
prepare the surface even and smooth complete. (Internal & External)

14 Distempering New surface : Two coats (Internal) 11-21-a-02 Sft 128.5 12.3 1581
Preparing surface & painting with snowcem /weathershield paint :Two coats
15 13-25-a +13-25-b Sft 379.875 31.39 11924
& subsequent coats (External)

Ventilator (1.5' x 1.5) with wire Mesh & Grill clamps with 18 gauge, handle
etc., prime coat/red enemal and red oxide paint on steel sections and class
16 Job No 2 1500 3000
B concrete in hold fasts, complete in all respect as approved and directed by
the Engineer.

Sub Total A 170543

B Electrification
Unit Rate Total Cost
S/N Activities MRS Ref: Unit Quantity
PKR PKR

S/F of electric canceld wiring of 2/3 pin 5 Amp plug in 3/.029 PVC insulated &
sheeted bare cable, Electric points, switches, switches box, holder PVC Job Job 1 4500 4500
1 ducts/ Conduit etc complete
2 S/F of Led Light of 12.5 watts of best quality complete in all respect NSI No 6 300 1800
Sub Total B 6,300
C Sanitary/Plumbing works
Unit Rate Total Cost
S/N Activities MRS Ref: Unit Quantity
PKR PKR

Providing, laying cutting, jointing, testing PPRC


pipeline in walls/trenches with pipes (confirming
to DIN 8077/8078, PN 20 of approved quality &
1 fittings conforming to DIN 16962,PN25 of the 14-35-b Rft 30 62.88 1886
same manufacturer) for cold/hot water supply
systems including specials complete in all respect
as per specifications: except excavation 1" i/d

Providing, laying cutting, jointing, testing PPRC


pipeline in walls/trenches with pipes (confirming
to DIN 8077/8078, PN 20 of approved quality &
2 fittings conforming to DIN 16962,PN25 of the 14-35-a Rft 40 50.64 2026
same manufacturer) for cold/hot water supply
systems including specials complete in all respect
as per specifications: except excavation 3/4" i/d

Providing and Fixing 4" dia UPVC pipe including all required specials from WC
3 NSI Rft 20 200 4000
to Septic Tank complete (Tee,elbow, etc)

Providing & Fixing 3" dia UPVC pipe including all required specials for the
4 NSI Rft 30 180 5400
disposal of latrine waste water (Tee,elbow, etc)

Providing and Fixing UPVC ventilation pipe 2” dia with specials & cowal cap
5 NSI Rft 30 50 1500
etc complete
Providing and Fixing glazed earthen ware Indian WC squatting type with built
6 NSi Each 4 1,500.00 6000
in foot rest including all required specials/accessories

Providing and Fixing glazed earthen ware wash


hand basin (WHB) complete size 56x40 cm
8 (22"x16"), including bracket set, waste coupling, 14-05-a-02 Each 1.00 9,676.27 9676
complete in all respects: Colour with pedestal
(Best Quality)
Supplying and Fixing Polyethylene Water Tank 200 gallons including all
9 required specials (I/c Values etc) complete in all respect as per instruction of 14-69-b-01 Each 1.00 16,008.98 16008.98
engineer incharge

10 Providing and Fixing CP bib-cock, heavy type complete : 3/4" 14-39-b No 4 520.11 2080

Providing and Fixing brass ball float valve of


11 approved quality: 14-48-b Each 2 476.67 953
3/4" dia
Providing and Fixing brass ball float valve of
12 14-48-c Each 2 758.98 1518
approved quality: 1"
Providing and Fixing 'P' trap of approved quality
13 including GI grating & PCC chamber 4" (100 mm) 14-32-b Each 4 442.70 1771
glazed
Providing and fixing choricum plated soap dish
14 14-14-a Each 6.00 568.05 3408
complete.
Supply and Fixing of CP floor Truff Jalli with
15 14-104-b Each 4.00 372.00 1488
Grating 6"×6" complete
Providing and fixing best quality looking glass 5
17 mm thick neatly fitted with bracket as per 14-17-b Each 1.00 802.00 802
instruction of Engineer In-charge complete

18 Waste Bin best Quality larg size as per instruction of engineer NSI Each 1.00 2,500.00 2500

Providing and Fixing GI pipe 10' long with 2" dia i/c
19 welding,tee,socket,stoper CP bib-cock, heavy type,proper drainage forwaste NSI Job 1.00 15,000.00 15000
water etc for Group hand washing station as per site requirment

Repairing & Fixing of existing plumbing/Fixtures work internal & external as


20 NSI Job 1.00 2,000.00 2000
per instruction of Engineer In-charge complete

Constuction of Manhole (Size: 12"'x12") i/c BB work,PCC & Plaster as per


21 NSI Each 1.00 1,000.00 1000
attached drawing and specifications approved by Engineer In charge

Sub Total C 79018


D Inauguration Plaque/ Sign Board
Supply & Fixing of Steel Inauguration Plaque with standard text as per instruction of Engineer
Incharge (24"x18") i/c Messegs regarding health & heigyn on near by wall in school premises
1 NSI Job 1 3000 3000

Sub Total D 3000

Grand Total= A+B+C+D 258,861


Sanitation Up scaling through PATS

CONSTRUCTION OF TWIN LATRINE BLOCK (BoQ)

S.No Description Nos Length Width Height/Depth Total Unit

A MAIN BUILDING
1 Excavation in foundation of building, bridges etc complete in all soil
Long wall 2 6.5 1.5 1 20 Cft
Short wall 2 4 1.5 1 12 Cft
Sub Total 32 Cft

2 Cement Concrete in Foundation - Ratio (1:4:8) including placing, compacting, finishing and Curing
long wall 2 6.5 1.5 0.25 4.88 Cft
short wall 2 4 1.5 0.25 3 Cft
Bath floor 1 5 4 0.25 5 Cft
Sub Total 13 Cft

3 Pacca brick work in foundation and plinth in cement, sand mortar 1:4
Long wall 1st step 2 6.5 1.125 0.5 7 Cft
Short Wall 1st step 2 4 1.125 0.5 5 Cft
Sub Total 12 Cft
4 Pacca brick work in ground floor in cement, sand mortar 1:4
Long wall 2nd step up to DPC 2 6.5 0.75 1.75 17 Cft
Short wall 2nd step Up to DPC 2 4 0.75 1.75 11 Cft
Long wall 2nd step above DPC 2 6.5 0.75 6.5 63 Cft
Short wall 2nd step above DPC 2 4 0.75 6.5 39 Cft
Parapet wall (LW) 2 8.5 0.375 0.75 5 Cft
Parapet wall (SW) 2 6 0.375 0.75 3 Cft
Sub Total 138 Cft
Deductions
Door for normal latrine 1 2.5 0.75 6.5 12.1875 Cft
Ventilator 1 1 0.75 1 0.75 Cft
12.9375 Cft
Net Brick Work 125 Cft
Total Quantity of brick work 137 Cft
5 Damp proof course of cem. conc. 1:2:4 (2" thick)
1 21 0.75 15.75 Sft
Net Quantity 15.75 Sft
6 RCC in Roof Slab, beam, columns & other structural members, insitu or precast: Type C (1:2:4)
RCC roof slab 1 8.5 6.5 0.41 23 Cft
Lintel Beam (only front side ) 1 6.5 0.75 0.5 2 Cft
Sub Total 25 Cft

Supply & fabricate M.S. reinforcement for cement concrete (Hot rolled deformed bars Grade 40) 79 Kg

7 Cement plaster 1:4 upto 20' heigth 1/2" thick


Long+Short wall internal 1 18 7 126 Sft
Celling 1 5 4 20 Sft
Chajja 4 side 1 30 1 30 Sft
External Plaster L/w +short wall i/c below Dpc 1 24 9 216 Sft
Perapet Wall 1 21.5 0.75 16.125
408.125
Deductions
Doors 1 2.5 6.5 16.25 Sft
Ventilators 1 1 1 1 Sft
Deducted Quantity 17.25 Sft
Net Quantity of plaster 390.875

8 Filling, watering and ramming earth under floor with surplus earth from foundation, etc
Latrines inside 1 5 4 1.5 30 Cft
Net Quantity 30 Cft

9 Provide & lay topping of concrete 1:2:4, including surface finishing & dividing in panels :
Latrines inside new+ existing latrine 4 5 4 0.33 6.6 cft
Step 1 1 6.5 2.25 0.5 7.3125 Cft
Step 2 1 6.5 1.5 0.5 4.875
Step 3 1 6.5 0.75 0.5 2.4375
Plinth Protection 1 15 1.5 0.33 7.425 cft
Net Quantity 28.65 Cft
10 Providing and Fixing of Fancy design bath room
Tile in Latrine (Internally)
Long wall PWD/ MHM latrine (New + existing 6 5 5.25 158 Sft
latrine )
Short wall (New + existing latrine ) 8 4 5.25 168 Sft
Floor (New + existing latrine ) 4 5 4 80 sft
Total Quantity 406 Sft
Deduction of doors
4 2.5 5 50
Deducted Quantity of Tile Work 50 Sft
Total Quantity of Tile Work for 04 latrines 356 Sft
11 MS Door Chowkats
Supplying and fixing MS Sheet 18 guage Chowkat (5" x 1.5" )i/c fixing in position with all charges for holdfast, hinges, and
painting etc.

Door 4 16.5 66 Rft

Net Quantity 66 Rft


12 MS Steel Door

Supplying and fixing MS 18 guage machine pressed door i/c locks, paint etc completed as per intruction of engineer incharge

door 3 2.5 6.5 48.75 Sft


Net Quantity 48.75 Sft

Ventilator (1.5' x 1.5) with wire Mesh & Grill


clamps with 18 gauge, handle etc., prime
coat/red enemal and red oxide paint on steel Job 4 4 No
sections and class B concrete in hold fasts,
complete in all respect as approved and directed
by the Engineer.

Constuction of Manhole (Size: 12"'x12") i/c BB


work,PCC & Plaster as per attached drawing and Job 1 1 No
specifications approved by Engineer In charge

13 Providing and applying wall putty of 2mm thickness over plastered surface to prepare the surface even and smooth
complete. (Internal & External)
l/w+s/w i/c new +old latrine 4 15.5 1.75 108.5 Sft
Celling of Bathroom New + old 4 5 4 20 Sft
Chajja 3 side (old + new latrine) 1 55 1 55 Sft
External Plaster L/w i/c below Dpc 1 17.5 7.5 131.25 Sft
L/w+ S/w (Old Latrine (3 Nos) 1 35 8 280 Sft
Perapet Wall (New latrine) 1 21.5 0.75 16.125 Sft
Sub Total 610.875 Sft
Deductions
Doors 4 2.5 6.5 65 Sft
Ventilators 4 1 1 4 Sft
Deducted Quantity 69 Sft
Net Quantity 541.875 Sft
14 Distempering New surface : Two coats (Internal)
l/w+s/w i/c new +old latrine 4 15.5 1.75 108.5 Sft
Celling of new +old latrine 4 5 4 20 Sft
Sub Total 128.5 Sft
Preparing surface & painting with snowcem
15 /weathershield paint :Two coats & subsequent
coats (External)
Chajja 3 side 1 21.5 1 21.5 Sft
L/w + s/w i/c 1 17.5 7.5 131.25 Sft
L/w+ S/w (Old Latrine (3 Nos of latrine ) 1 35 8 280 Sft
Perapet Wall (New latrine) 1 21.5 0.75 16.125 Sft
Sub Total 448.875 Sft
Deductions
Doors 4 2.5 6.5 65 Sft
16 Ventilators 4 1 1 4 Sft
Deducted Quantity 69 Sft
Net Quantity 379.875 Sft

17 Electrification

S/F of electric canceld wiring of 2/3 pin 5 Amp


plug in 3/.029 PVC insulated & sheeted bare
cable, Electric points,switches, switches box,
holder PVC ducts/ Conduit etc complete
1 1 Job
S/F of LED lights of 12.5 watts of best quality 6 6 No
18 Sanitary/Plumbing works

Providing, laying cutting, jointing, testing PPRC


pipeline in walls/trenches with pipes (confirming
to DIN 8077/8078, PN 20 of approved quality
&fittings conforming to DIN 16962,PN25 of the
same manufacturer) for cold/hot water supply
systems including specials complete in all
respect as per specifications: 1" i/d
1 30 30 Rft

Providing, laying cutting, jointing, testing PPRC


pipeline in walls/trenches with pipes (confirming
to DIN 8077/8078, PN 20 of approved quality
&fittings conforming to DIN 16962,PN25 of the
same manufacturer) for cold/hot water supply
systems including specials complete in all
respect as per specifications: 3/4" i/d
1 40 40 Rft
Providing and Fixing 4" dia UPVC pipe including
all required specials from WC to Septic Tank
complete (Tee,elbow, etc)
1 20 20 Rft

Providing & Fixing 3" dia UPVC pipe including all


required specials for the disposal of latrine waste
water (Tee,elbow, etc)
1 30 30 Rft
Providing and Fixing UPVC ventilation/drainage
of WHB pipe 2” dia with specials & cowal cap
etc complete 1 30 30 Rft

Providing and Fixing glazed earthen ware Indian


WC squatting type with built in foot rest
including all required specials/accessories
4 4 No

Providing and Fixing glazed earthen ware wash


hand basin (WHB) complete size 56x40 cm
(22"x16"), including bracket set, waste coupling,
complete in all respects: Colour with pedestal
(Best Quality)
1 1 No

Supplying and Fixing Polyethylene Water Tank


200 gallons including all required specials
complete in all respect as per instruction of
engineer incharge approved quality
1 1 No
Providing and Fixing CP bib-cock, heavy type
complete : 3/4" 4 4 No

Providing and Fixing brass ball float valve of


approved quality:
3/4" dia
2 2 No

Providing and Fixing brass ball float valve of


approved quality: 1" dia
2 2 No
Providing and Fixing 'P' trap of approved quality
including GI grating & PCC chamber 4" (100 mm)
of cast iron (Best Quality) 4 4 No

Providing and Fixing CP grab rail : 5' long, 1" dia


0 0 No
Providing and fixing choricum plated soap dish
complete. 6 6 No
Supply and Fixing of CP floor Truff Jalli with
Grating 6"×6" complete 4 4 No

Providing and fixing best quality looking glass 5


mm thick neatly fitted with bracket as per
instruction of Engineer In-charge complete
1 1 No
Waste Bin best Quality larg size as per
instruction of engineer 1 1 No

Providing and Fixing GI pipe 10' long with 2" dia


i/c welding,tee,socket,stoper CP bib-cock, heavy
type etc for Group hand washing station as per
site requirment 1 1 Job

Repairing of existing plumbing work internal &


external
1 1 Job
Steel Bar Bending Schedule
Total Cut Unit
No.s of Total
S.No Descripition Dia No's No.s of length weight
Bar Length ft
Bar ft (lbs)
2 Main Bars for Slab 6"c/c #4 1 17 17 6.5 110.50 0.667
3 Dist Bars for Slab 6"c/c #4 1 13 13 8.5 110.50 0.667
Lintel Beam #4 1 4 4 6.5 26.00 0.667
6 Stirrups for Beam 6"c/c #3 1 13 13 2.00 26.00 0.376

Total
ule
Total weight Total Weight Total Weight
(lbs) (Kgs) (Ton)

73.70 33 0.03
73.70 33 0.03
17.34 8 0.01
9.78 4 0.00

79 0.08