BoQ - PWD Bath Room
BoQ - PWD Bath Room
2 Electrification 6,300
7 Cement plaster 1:4 upto 20' height 1/2" thick 11-09-b Sft 390.875 28.56 11164
Filling, watering and ramming earth under floor with surplus earth from
8 03-18-a Cft 30 2.42 73
foundation, etc
Provide & lay topping of concrete 1:2:4, including surface finishing & dividing
9 10-15-h cft 28.65 109.40 3134
in panels :
Supplying and fixing MS Sheet 18 guage Chowkat (5" x 1.5" )i/c fixing in
11 NSI Rft 66 220.00 14520
position with all charges for holdfast, hinges, and painting etc.
Steel Door of 6'.5 X 2.5 & 6'.5x3', pressed by machine with 18 gauge iorn
sheet,welded with aldaraz bolt locks, clamps, handle etc., prime coat/red
12 NSI Sft 48.75 250 12188
enemal and red oxide paint on steel sections and class B concrete in hold
fasts. complete in all respect as approved and directed by the Engineer.
Providing and applying wall putty of 2mm thickness over plastered surface to
13 11-20-b Sft 541.875 6.08 3295
prepare the surface even and smooth complete. (Internal & External)
14 Distempering New surface : Two coats (Internal) 11-21-a-02 Sft 128.5 12.3 1581
Preparing surface & painting with snowcem /weathershield paint :Two coats
15 13-25-a +13-25-b Sft 379.875 31.39 11924
& subsequent coats (External)
Ventilator (1.5' x 1.5) with wire Mesh & Grill clamps with 18 gauge, handle
etc., prime coat/red enemal and red oxide paint on steel sections and class
16 Job No 2 1500 3000
B concrete in hold fasts, complete in all respect as approved and directed by
the Engineer.
B Electrification
Unit Rate Total Cost
S/N Activities MRS Ref: Unit Quantity
PKR PKR
S/F of electric canceld wiring of 2/3 pin 5 Amp plug in 3/.029 PVC insulated &
sheeted bare cable, Electric points, switches, switches box, holder PVC Job Job 1 4500 4500
1 ducts/ Conduit etc complete
2 S/F of Led Light of 12.5 watts of best quality complete in all respect NSI No 6 300 1800
Sub Total B 6,300
C Sanitary/Plumbing works
Unit Rate Total Cost
S/N Activities MRS Ref: Unit Quantity
PKR PKR
Providing and Fixing 4" dia UPVC pipe including all required specials from WC
3 NSI Rft 20 200 4000
to Septic Tank complete (Tee,elbow, etc)
Providing & Fixing 3" dia UPVC pipe including all required specials for the
4 NSI Rft 30 180 5400
disposal of latrine waste water (Tee,elbow, etc)
Providing and Fixing UPVC ventilation pipe 2” dia with specials & cowal cap
5 NSI Rft 30 50 1500
etc complete
Providing and Fixing glazed earthen ware Indian WC squatting type with built
6 NSi Each 4 1,500.00 6000
in foot rest including all required specials/accessories
10 Providing and Fixing CP bib-cock, heavy type complete : 3/4" 14-39-b No 4 520.11 2080
18 Waste Bin best Quality larg size as per instruction of engineer NSI Each 1.00 2,500.00 2500
Providing and Fixing GI pipe 10' long with 2" dia i/c
19 welding,tee,socket,stoper CP bib-cock, heavy type,proper drainage forwaste NSI Job 1.00 15,000.00 15000
water etc for Group hand washing station as per site requirment
A MAIN BUILDING
1 Excavation in foundation of building, bridges etc complete in all soil
Long wall 2 6.5 1.5 1 20 Cft
Short wall 2 4 1.5 1 12 Cft
Sub Total 32 Cft
2 Cement Concrete in Foundation - Ratio (1:4:8) including placing, compacting, finishing and Curing
long wall 2 6.5 1.5 0.25 4.88 Cft
short wall 2 4 1.5 0.25 3 Cft
Bath floor 1 5 4 0.25 5 Cft
Sub Total 13 Cft
3 Pacca brick work in foundation and plinth in cement, sand mortar 1:4
Long wall 1st step 2 6.5 1.125 0.5 7 Cft
Short Wall 1st step 2 4 1.125 0.5 5 Cft
Sub Total 12 Cft
4 Pacca brick work in ground floor in cement, sand mortar 1:4
Long wall 2nd step up to DPC 2 6.5 0.75 1.75 17 Cft
Short wall 2nd step Up to DPC 2 4 0.75 1.75 11 Cft
Long wall 2nd step above DPC 2 6.5 0.75 6.5 63 Cft
Short wall 2nd step above DPC 2 4 0.75 6.5 39 Cft
Parapet wall (LW) 2 8.5 0.375 0.75 5 Cft
Parapet wall (SW) 2 6 0.375 0.75 3 Cft
Sub Total 138 Cft
Deductions
Door for normal latrine 1 2.5 0.75 6.5 12.1875 Cft
Ventilator 1 1 0.75 1 0.75 Cft
12.9375 Cft
Net Brick Work 125 Cft
Total Quantity of brick work 137 Cft
5 Damp proof course of cem. conc. 1:2:4 (2" thick)
1 21 0.75 15.75 Sft
Net Quantity 15.75 Sft
6 RCC in Roof Slab, beam, columns & other structural members, insitu or precast: Type C (1:2:4)
RCC roof slab 1 8.5 6.5 0.41 23 Cft
Lintel Beam (only front side ) 1 6.5 0.75 0.5 2 Cft
Sub Total 25 Cft
Supply & fabricate M.S. reinforcement for cement concrete (Hot rolled deformed bars Grade 40) 79 Kg
8 Filling, watering and ramming earth under floor with surplus earth from foundation, etc
Latrines inside 1 5 4 1.5 30 Cft
Net Quantity 30 Cft
9 Provide & lay topping of concrete 1:2:4, including surface finishing & dividing in panels :
Latrines inside new+ existing latrine 4 5 4 0.33 6.6 cft
Step 1 1 6.5 2.25 0.5 7.3125 Cft
Step 2 1 6.5 1.5 0.5 4.875
Step 3 1 6.5 0.75 0.5 2.4375
Plinth Protection 1 15 1.5 0.33 7.425 cft
Net Quantity 28.65 Cft
10 Providing and Fixing of Fancy design bath room
Tile in Latrine (Internally)
Long wall PWD/ MHM latrine (New + existing 6 5 5.25 158 Sft
latrine )
Short wall (New + existing latrine ) 8 4 5.25 168 Sft
Floor (New + existing latrine ) 4 5 4 80 sft
Total Quantity 406 Sft
Deduction of doors
4 2.5 5 50
Deducted Quantity of Tile Work 50 Sft
Total Quantity of Tile Work for 04 latrines 356 Sft
11 MS Door Chowkats
Supplying and fixing MS Sheet 18 guage Chowkat (5" x 1.5" )i/c fixing in position with all charges for holdfast, hinges, and
painting etc.
Supplying and fixing MS 18 guage machine pressed door i/c locks, paint etc completed as per intruction of engineer incharge
13 Providing and applying wall putty of 2mm thickness over plastered surface to prepare the surface even and smooth
complete. (Internal & External)
l/w+s/w i/c new +old latrine 4 15.5 1.75 108.5 Sft
Celling of Bathroom New + old 4 5 4 20 Sft
Chajja 3 side (old + new latrine) 1 55 1 55 Sft
External Plaster L/w i/c below Dpc 1 17.5 7.5 131.25 Sft
L/w+ S/w (Old Latrine (3 Nos) 1 35 8 280 Sft
Perapet Wall (New latrine) 1 21.5 0.75 16.125 Sft
Sub Total 610.875 Sft
Deductions
Doors 4 2.5 6.5 65 Sft
Ventilators 4 1 1 4 Sft
Deducted Quantity 69 Sft
Net Quantity 541.875 Sft
14 Distempering New surface : Two coats (Internal)
l/w+s/w i/c new +old latrine 4 15.5 1.75 108.5 Sft
Celling of new +old latrine 4 5 4 20 Sft
Sub Total 128.5 Sft
Preparing surface & painting with snowcem
15 /weathershield paint :Two coats & subsequent
coats (External)
Chajja 3 side 1 21.5 1 21.5 Sft
L/w + s/w i/c 1 17.5 7.5 131.25 Sft
L/w+ S/w (Old Latrine (3 Nos of latrine ) 1 35 8 280 Sft
Perapet Wall (New latrine) 1 21.5 0.75 16.125 Sft
Sub Total 448.875 Sft
Deductions
Doors 4 2.5 6.5 65 Sft
16 Ventilators 4 1 1 4 Sft
Deducted Quantity 69 Sft
Net Quantity 379.875 Sft
17 Electrification
Total
ule
Total weight Total Weight Total Weight
(lbs) (Kgs) (Ton)
73.70 33 0.03
73.70 33 0.03
17.34 8 0.01
9.78 4 0.00
79 0.08