RCC Work BOQ .
RCC Work BOQ .
Item Description Unit Quantuty Price/ Unit Amount (In BDT) Remarks
Mixture Machine
4 Pump For Curring work (5.5 Hp) PKG 1 95000 95,000.00 Emergency
5 Sefty Canopy (West Side) Sft 1600 220 352,000.00
6 Sefty Railing (Up 2nd Floor) Sft 3200 80 256,000.00
7 Any others L.S 1 100000 100,000.00
TOTAL TK/- 22,523,172.19
Inword : Two Crore Twenty Five Lac Seven Thousand One Hundred Seventy TwoTaka Only
Md.Monirul Islam
Seal Pile
Analysis of 01 No. Pile 20"dia pile](Length:-25'-0'')-
R.C.C. Work
Sl Description No. Length Area
1 Casting 1 25 1.08
Labour
Shoulder Beam
(Length:-314'-0'')-
R.C.C. Work
Sl Description No. Length Area
1 Casting 1 314 2.83
M.S Rod :
Sl Description No. Length Wt./ft
16mm 6 0 0.48
20mm 10 332 0.75
12mm 0 51 0.27
10mm 60 5.83 0.19
Total
Casting Labour
Shutter
Nos Total/length
P101 48' length pile18"dia Nos -
P1 27.5' length pile20"dia 22 Nos 605
P2 73' length pile18"dia - Nos -
P3 73' length pile18"dia - Nos -
Total Pile 22 Total- 605
R.C.C. Work
Sl Description No. Length Area
1 Casting 1 27.5 2.189
M.S Rod :
Sl Description No. Length Wt./ft
16mm 12 27.5 0.48
16mm 0 43 0.48
12mm 0 51 0.27
10 mm 56 4.17 0.19
Total
Labour @ 210tk/Rft (Approved rate of this project)
Total
Cost p/rft
Nos Total/length
P101 83' length pile20"dia - Nos -
P4 63' length pile20"dia - Nos -
Total Pile - Total- -
R.C.C. Work
Sl Description No. Length Area
1 Casting 1 83 2.189
M.S Rod :
Sl Description No. Length Wt./ft
16mm 4 86 0.48
16mm 3 31.5 0.48
12mm 3 31.5 0.27
8 mm 122 4.15 0.12
Total
Labour @ 180tk/Rft (Approved rate of this project)
Total
Cost p/rft
Cost p/rft
OJECT
Remarks
25'-0'')-
wt. kg
-
2,490.00
-
66.46
2,684.29 88 236,217
Rft 75 23,550
Sft 20 6,280
#REF!
Say #REF!
605
7.5'-0'')-
45'x8 nos 360
60'x11 nos 0
Volumn cft Rate Amount 70'x63 nos 0
60.1975 294.42 17723.34795
Total- 360 rft
wt. kg
158.40
-
-
44.37 Total-CC Casting 185
212.91 88 18,736
of this project) 5,775 Pile Head Braking 260
42,234
1,535.79
Say 1,536
-
gth:-83'-0")-
wt. kg
165.12
45.36
25.52
60.76
311.59 82 25,550
of this project) 15,770
#REF!
#REF!
Say #REF!
#REF!
Say #REF!
Say #REF!
Analysis: 100 cft
Qty Unit Rate Amount
Sylhet Sand 42 Cft 50 2100
Shuttering work
Column
1 C-1(15x25) 1 6.67 8.00 53.36 Sft
2 C-2(15x25) 1 6.67 8.00 53.36 Sft
3 C-3(15x25) 1 6.67 8.00 53.36 Sft
4 C-4(15x25) 1 6.67 8.00 53.36 Sft
5 C-5(15x25) 1 6.67 8.00 53.36 Sft
6 C-6(15x25) 1 6.67 8.00 53.36 Sft
7 C-7(15x25) 1 6.67 8.00 53.36 Sft
8 C-9(15x25) 1 6.67 8.00 53.36 Sft
9 C-11(15x25) 1 6.67 8.00 53.36 Sft
11 C-13(12x35) 1 7.83 8.00 62.64 Sft
12 C-14(15x25) 1 6.67 8.00 53.36 Sft
13 C-15(15x25) 1 6.67 8.00 53.36 Sft
14 C-16(15x25) 1 6.67 8.00 53.36 Sft
15 C-8(18x25) 2 7.17 8.00 114.72 Sft
16 C-12(18x25) 1 7.17 8.00 57.36 Sft
17 C-10(12x25) 4 4.33 8.00 138.56 Sft
18 C-10(10x13) 4 4.00 8.00 128.00 Sft
Total 1141.600 Sft 350 399560
9132.800 Sft 50 456640
Column Concrete(4000Psi) 144
C-1(15x25) 1 25.00 15.00 10.00 26.04 Cft
C-2(15x25) 1 25.00 15.00 10.00 26.04 Cft
C-3(15x25) 1 25.00 15.00 10.00 26.04 Cft
C-4(15x25) 1 25.00 15.00 10.00 26.04 Cft
C-5(15x25) 1 25.00 15.00 10.00 26.04 Cft
C-6(15x25) 1 25.00 15.00 10.00 26.04 Cft
C-7(15x25) 1 25.00 15.00 10.00 26.04 Cft
C-9(15x25) 1 25.00 15.00 10.00 26.04 Cft
C-11(15x25) 1 25.00 15.00 10.00 26.04 Cft
C-13(12x35) 1 35.00 12.00 10.00 29.17 Cft
C-14(15x25) 1 25.00 15.00 10.00 26.04 Cft
C-15(15x25) 1 25.00 15.00 10.00 26.04 Cft
C-16(15x25) 1 25.00 15.00 10.00 26.04 Cft
C-8(18x25) 2 25.00 18.00 10.00 62.50 Cft
C-12(18x25) 1 25.00 18.00 10.00 31.25 Cft
C-10(12x25) 4 25.00 12.00 10.00 83.33 Cft
C-10(10x13) 4 13.00 10.00 10.00 36.11 Cft
R.C.C Work
Column
C-3(635x635) 1 0.635 0.635 4.343 1.751 Cub.m
C-5(635x635) 1 0.635 0.635 4.343 1.751 Cub.m
D-3(635x635) 1 0.635 0.635 4.343 1.751 Cub.m
D-5(635x635) 1 0.635 0.635 4.343 1.751 Cub.m
E-3(635x635) 1 0.635 0.635 4.343 1.751 Cub.m
E-5(635x635) 1 0.635 0.635 4.343 1.751 Cub.m
F-3(635x635) 1 0.635 0.635 4.343 1.751 Cub.m
F-5(635x635) 1 0.635 0.635 4.343 1.751 Cub.m
G-3(635x635) 1 0.635 0.635 4.343 1.751 Cub.m
G-5(635x635) 1 0.635 0.635 4.343 1.751 Cub.m
H-3(635x635) 1 0.635 0.635 4.343 1.751 Cub.m
H-5(635x635) 1 0.635 0.635 4.343 1.751 Cub.m
I-3(635x635) 1 0.635 0.635 4.343 1.751 Cub.m F.Face c 16.028 Cub.m
I-5(635x635) 1 0.635 0.635 4.343 1.751 Cub.m F.Face c 565.481 Cft
F-6(508x508) 1 0.508 0.508 4.343 1.121 Cub.m
G-6(508x508) 1 0.508 0.508 4.343 1.121 Cub.m
G-1(762x305) 1 0.762 0.305 4.343 1.009 Cub.m
G'-1(762x305) 1 0.762 0.305 4.343 1.009 Cub.m
- - Total 28.78 Cub.m
Total 1015.47 Cft -
Shear Wal
SW-1(1524x305) 2 1.524 0.305 4.343 4.04 Cub.m
SW-2(5892x305) 1 5.892 0.305 4.343 7.80 Cub.m
SW-3(3480x305) 1 3.480 0.305 4.343 4.61 Cub.m
SW-4(4495x305) 1 4.495 0.305 4.343 5.95 Cub.m
SW-5(5486x305) 1 5.486 0.305 4.343 7.27 Cub.m
SW-6(4267x305) 1 4.267 0.305 4.343 5.65 Cub.m
SW-7(2490x305) 1 2.490 0.305 4.343 3.30 Cub.m
SW-8(3480x305) 1 3.480 0.305 4.343 4.61 Cub.m
SW-9(4546x305) 1 4.546 0.305 4.343 6.02 Cub.m
SW-10(2667x305) 1 2.667 0.305 4.343 3.53 Cub.m
SW-11(1524x305) 1 1.524 0.305 4.343 2.02 Cub.m
12 Total 54.81 Cub.m
Total 1933.55 Cft - -
Front Shear Wall
Sw( 5838x254) 1 5.838 0.254 4.343 6.440 Cub.m
Sw( 5385x254) 1 5.385 0.254 4.343 5.940 Cub.m
Sw(2337x305) 2 2.337 0.305 4.343 12.380 Cub.m
Total 24.761 Cub.m
Total 873.56 Cft
Slab & Beam
B-20,ABCDX(305x914) 1 16.329 0.305 0.714 11.659 Cub.m
B-21,A(305x914) 1 18.622 0.305 0.714 13.296 Cub.m
B-21,A(305x508) 1 9.500 0.305 0.308 2.926 Cub.m
B-24,ABA(305x914) 1 14.122 0.305 0.714 10.083 Cub.m
B-24,ABA(305x508) 1 4.750 0.305 0.308 1.463 Cub.m
B-25,X(254x508) 1 9.986 0.254 0.308 3.076 Cub.m
B-25,ABCDE(305x508) 1 20.118 0.305 0.405 8.148 Cub.m
B-26,ABCDE(305x914) 1 13.793 0.305 0.714 9.848 Cub.m
B-4A,12A,6X,10A&11A(635x914) 5 9.652 0.635 0.714 34.458 Cub.m
B-12A,3A(254x914) 1 14.275 0.254 0.714 10.192 Cub.m
B-4A,5,6X(305x508) 1 21.379 0.305 0.308 6.585 Cub.m
B-7&8(254x508) 1 4.908 0.254 0.308 1.512 Cub.m
B-9,10A,B(305x508) 1 14.280 0.305 0.308 4.398 Cub.m F.Face c 98.755 Cub.m
B-11A,(254x508) 1 4.909 0.254 0.308 1.512 Cub.m F.Face c 3484.06821504 Cft
B-14A,12&13(254x914) 1 12.911 0.254 0.714 9.218 Cub.m
Sub/Total 128.37 Cub.m
Slab Casting 1 640.47 0.200 128.09 Cub.m
Total 256.47 Cub.m
Total 9048.19 Cft
G.Total Casting 12870.77 Cft