RCC Work BOQ .

Uploaded by

mshuvojoty
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
57 views22 pages

RCC Work BOQ .

Uploaded by

mshuvojoty
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 22

SAFARA HOLDINGS LTD.

Budget For Next Floor Fairface & RCC Work

Project Name: Chairman sir House Date: 25th July, 2019

Item Description Unit Quantuty Price/ Unit Amount (In BDT) Remarks

1 F.Face Shutter(Coln,Beam&Slab) Sft 6341.09 460.00 2,916,902.75


2 Normal Shutter Sft 7392.16 380.00 2,809,021.67
3 PROPS Nos 1850 1800.00 3,330,000.00
4 1.5" MS Pipe Rft 1800.00 90.00 162,000.00
5 Scafolding Set 300 7500.00 2,250,000.00
6 3"x3"MS Hollow Box Rft 3445 140.00 482,332.44
7 Grey Cement Bag 1560 440.00 686,400.00
8 White Cement Bag 1510 1020.00 1,540,200.00
9 Stone Chips Cft 8000 190.00 1,520,000.00
10 Sylhet Sand Cft 4000 56.00 224,000.00
Civil

11 Local Sand Cft 1000 28.00 28,000.00


12 MS Rod (20mm) 60Grade Kg 8500 62.00 527,000.00
13 MS Rod (16mm) 60 Grade Kg 3000 62.00 186,000.00
14 MS Rod (12mm) 60 Grade Kg 6500 62.00 403,000.00
15 MS Rod (10mm) 60 Grade Kg 26500 62.00 1,643,000.00
16 Labour Charge Sft 6890 280.00 1,929,329.77
17 Picon Rod Kg 580 85.00 49,300.00
18 Picon Nos 4000 35.00 140,000.00
19 Picon Clump Nos 100 230.00 23,000.00
20 Nut Bold Kg 400 90.00 36,000.00
21 Any others PKG 1 120000.00 120,000.00

1 Conduits work (Pipe, Fitting & Fixture) PKG 1 180000.00 180,000.00


Electrical

2 All kinds of wire PKG 1 2000 2,000.00


3 Labour Charge Sft 6890 12 82,685.56
4 Any others PKG 1 30000 30,000.00
1 Roof Hoast Machine PKG 1 240000 240,000.00
2 Vibrator Machine & Nozzele Set 2 25000 50,000.00
3 PKG 1 130000 130,000.00
Mechanical

Mixture Machine
4 Pump For Curring work (5.5 Hp) PKG 1 95000 95,000.00 Emergency
5 Sefty Canopy (West Side) Sft 1600 220 352,000.00
6 Sefty Railing (Up 2nd Floor) Sft 3200 80 256,000.00
7 Any others L.S 1 100000 100,000.00
TOTAL TK/- 22,523,172.19

Inword : Two Crore Twenty Five Lac Seven Thousand One Hundred Seventy TwoTaka Only

Md.Monirul Islam

Project Manager COO


UTTAR KHAN 6.5 KATHA PROJECT
BOQ FOR RCC WORK

SL Materials Name Unit Quanty Rate Amount


1 20mm Rod Kg #REF! 95 #REF!
2 16mm Rod Kg #REF! 95 #REF!
3 10mm Rod Kg #REF! 95 #REF!
4 Cement Bags #REF! 520 #REF!
5 Stone Chips Cft #REF! 200 #REF!
6 Sylhet Sand Cft #REF! 54 #REF!
7 Pile Labour Charge Rft #REF! 170 #REF!
Total Amount #REF!
8 8%Service Charge Amount #REF!
So,Net Cost Amount For Piling Work #REF!
Per Flat Cost Amount For Piling Work #REF!
25' length Seal pile14"dia 213 30 6,390

Seal Pile
Analysis of 01 No. Pile 20"dia pile](Length:-25'-0'')-

R.C.C. Work
Sl Description No. Length Area
1 Casting 1 25 1.08
Labour
Shoulder Beam

(Length:-314'-0'')-

R.C.C. Work
Sl Description No. Length Area
1 Casting 1 314 2.83
M.S Rod :
Sl Description No. Length Wt./ft
16mm 6 0 0.48
20mm 10 332 0.75
12mm 0 51 0.27
10mm 60 5.83 0.19
Total
Casting Labour
Shutter

King Post Pile Work

Nos Total/length
P101 48' length pile18"dia Nos -
P1 27.5' length pile20"dia 22 Nos 605
P2 73' length pile18"dia - Nos -
P3 73' length pile18"dia - Nos -
Total Pile 22 Total- 605

Analysis of 01 No. Pile 20"dia pile](Length:-27.5'-0'')-

R.C.C. Work
Sl Description No. Length Area
1 Casting 1 27.5 2.189
M.S Rod :
Sl Description No. Length Wt./ft
16mm 12 27.5 0.48
16mm 0 43 0.48
12mm 0 51 0.27
10 mm 56 4.17 0.19
Total
Labour @ 210tk/Rft (Approved rate of this project)
Total
Cost p/rft
Nos Total/length
P101 83' length pile20"dia - Nos -
P4 63' length pile20"dia - Nos -
Total Pile - Total- -

Analysis of 01 No. Pile 20"dia pile](Length:-83'-0")-

R.C.C. Work
Sl Description No. Length Area
1 Casting 1 83 2.189
M.S Rod :
Sl Description No. Length Wt./ft
16mm 4 86 0.48
16mm 3 31.5 0.48
12mm 3 31.5 0.27
8 mm 122 4.15 0.12
Total
Labour @ 180tk/Rft (Approved rate of this project)
Total
Cost p/rft

Cost p/rft
OJECT

Remarks
25'-0'')-

Volumn cft Rate Amount


27 #REF! #REF!
200 5,000
labour #REF!
Say #REF!
Volumn cft Rate Amount
888.62 #REF! #REF!

wt. kg
-
2,490.00
-
66.46
2,684.29 88 236,217
Rft 75 23,550
Sft 20 6,280
#REF!
Say #REF!

605

7.5'-0'')-
45'x8 nos 360
60'x11 nos 0
Volumn cft Rate Amount 70'x63 nos 0
60.1975 294.42 17723.34795
Total- 360 rft
wt. kg
158.40
-
-
44.37 Total-CC Casting 185
212.91 88 18,736
of this project) 5,775 Pile Head Braking 260
42,234
1,535.79
Say 1,536
-

gth:-83'-0")-

Volumn cft Rate Amount


181.687 #REF! #REF!

wt. kg
165.12
45.36
25.52
60.76
311.59 82 25,550
of this project) 15,770
#REF!
#REF!
Say #REF!

#REF!
Say #REF!
Say #REF!
Analysis: 100 cft
Qty Unit Rate Amount
Sylhet Sand 42 Cft 50 2100

Broken shingles 84 Cft 208 17472

Cement 21 Bag 470 9870


29442 294.42
1471.008

18'' Pile Head Breaking:


Analysis No. of Pile Thick Area Volume
22 27 2.189 1300.266
Details Estimate Structural Wohk
UTTAR KHAN 6.5 KATHA PROJECT
Detail Calculation (in)
SL Work Description Remarks
No Length Breadth Height Total Quantity Unit Rate/Unit Total Amount

Shuttering work
Column
1 C-1(15x25) 1 6.67 8.00 53.36 Sft
2 C-2(15x25) 1 6.67 8.00 53.36 Sft
3 C-3(15x25) 1 6.67 8.00 53.36 Sft
4 C-4(15x25) 1 6.67 8.00 53.36 Sft
5 C-5(15x25) 1 6.67 8.00 53.36 Sft
6 C-6(15x25) 1 6.67 8.00 53.36 Sft
7 C-7(15x25) 1 6.67 8.00 53.36 Sft
8 C-9(15x25) 1 6.67 8.00 53.36 Sft
9 C-11(15x25) 1 6.67 8.00 53.36 Sft
11 C-13(12x35) 1 7.83 8.00 62.64 Sft
12 C-14(15x25) 1 6.67 8.00 53.36 Sft
13 C-15(15x25) 1 6.67 8.00 53.36 Sft
14 C-16(15x25) 1 6.67 8.00 53.36 Sft
15 C-8(18x25) 2 7.17 8.00 114.72 Sft
16 C-12(18x25) 1 7.17 8.00 57.36 Sft
17 C-10(12x25) 4 4.33 8.00 138.56 Sft
18 C-10(10x13) 4 4.00 8.00 128.00 Sft
Total 1141.600 Sft 350 399560
9132.800 Sft 50 456640
Column Concrete(4000Psi) 144
C-1(15x25) 1 25.00 15.00 10.00 26.04 Cft
C-2(15x25) 1 25.00 15.00 10.00 26.04 Cft
C-3(15x25) 1 25.00 15.00 10.00 26.04 Cft
C-4(15x25) 1 25.00 15.00 10.00 26.04 Cft
C-5(15x25) 1 25.00 15.00 10.00 26.04 Cft
C-6(15x25) 1 25.00 15.00 10.00 26.04 Cft
C-7(15x25) 1 25.00 15.00 10.00 26.04 Cft
C-9(15x25) 1 25.00 15.00 10.00 26.04 Cft
C-11(15x25) 1 25.00 15.00 10.00 26.04 Cft
C-13(12x35) 1 35.00 12.00 10.00 29.17 Cft
C-14(15x25) 1 25.00 15.00 10.00 26.04 Cft
C-15(15x25) 1 25.00 15.00 10.00 26.04 Cft
C-16(15x25) 1 25.00 15.00 10.00 26.04 Cft
C-8(18x25) 2 25.00 18.00 10.00 62.50 Cft
C-12(18x25) 1 25.00 18.00 10.00 31.25 Cft
C-10(12x25) 4 25.00 12.00 10.00 83.33 Cft
C-10(10x13) 4 13.00 10.00 10.00 36.11 Cft

Total (G.F) 554.861 Cft


1st to 7th 3884.028 Cft
G.Total 4438.889 Cft 330 1,464,833.33
Beam Shutter
B-20,ABCDX(305x914)Bottom 1 16.329 0.000 0.405 6.613 Sqm
Out Side 1 16.329 0.000 0.914 14.925 Sqm
In Side 1 16.329 0.000 0.714 11.659 Sqm
B-21,A(305x914)Bottom 1 18.622 0.405 7.542 Sqm
Out Side 1 18.622 0.914 17.021 Sqm
In Side 1 18.622 0.714 13.296 Sqm
B-21,A(305x508)Bottom 1 9.500 0.405 3.848 Sqm
Out Side 1 9.500 0.308 2.926 Sqm
In Side 1 9.500 0.308 2.926 Sqm
B-24,ABA(305x914)Bottom 1 14.122 0.405 5.719 Sqm
Out Side 1 14.122 0.914 12.908 Sqm
In Side 1 14.122 0.714 10.083 Sqm
B-24,ABA(305x508)Bottom 1 4.750 0.405 1.924 Sqm
Out Side 1 4.750 0.308 1.463 Sqm
In Side 1 4.750 0.308 1.463 Sqm
B-25,X(254x508)Bottom 1 9.986 0.354 3.535 Sqm
Out Side 1 9.986 0.914 9.127 Sqm
In Side 1 9.986 0.714 7.130 Sqm
B-25,ABCDE(305x508)Bottom 1 20.118 0.405 8.148 Sqm
Out Side 1 20.118 0.308 6.196 Sqm
In Side 1 20.118 0.308 6.196 Sqm
B-26,ABCDE(305x914)Bottom 1 13.793 0.405 5.586 Sqm
Out Side
B- 1 13.793 0.914 12.607 Sqm
In Side
4A,12A,6X,10A&11A(635x914)Bo 1 13.793 0.714 9.848 Sqm
ttom 5 9.652 0.735 35.471 Sqm
Out Side 4 9.652 0.914 35.288 Sqm
In Side 6 9.652 0.714 41.349 Sqm
B-12A,3A(254x914)Bottom 1 14.275 0.354 5.053 Sqm
Out Side 1 14.275 0.914 13.047 Sqm
In Side 1 14.275 0.714 10.192 Sqm
B-4A,5,6X(305x508)Bottom 1 21.379 0.405 8.658 Sqm
Out Side 1 21.379 0.358 7.654 Sqm
In Side 1 21.379 0.308 6.585 Sqm
B-7&8(254x508)Bottom 1 4.908 0.354 1.737 Sqm
Out Side 1 4.908 0.358 1.757 Sqm
In Side 1 4.908 0.358 1.757 Sqm
B-9,10A,B(305x508)Bottom 1 14.280 0.405 5.783 Sqm
Out Side 1 14.280 0.358 5.112 Sqm
In Side 1 14.280 0.358 5.112 Sqm
B-11A,(254x508)Bottom 1 4.909 0.354 1.738 Sqm
Out Side 1 4.909 0.358 1.757 Sqm
In Side 1 4.909 0.358 1.757 Sqm
B-14A,12&13(254x914)Bottom 1 12.911 0.354 4.570 Sqm
Out Side 1 12.911 0.914 11.801 Sqm
In Side 1 12.911 0.714 9.218 Sqm
Total 398.09 Sqm
Toatl 4282.79 Sft
Fair Face Area 3314.12 Sft F.Face 1657
Normal Area 968.68 Sft #REF!
Slab & Stair
Stair waist slab 4 2.8 0.00 1.20 13.44 Sqm
Side 4 2.8 0.00 0.45 5.04 Sqm
Landing 4 3.50 0.00 1.20 16.80 Sqm
Riser 20 1.20 0.00 0.50 12.00 Sqm
Slab -1 1 4.625 0 2.696 12.469 Sqm
S-2 1 4.749 5.433 25.801 Sqm
S-3 1 5.384 2.300 12.383 Sqm
S-4 1 5.195 5.372 27.908 Sqm
S-5 1 3.302 2.900 9.576 Sqm
S-6 1 5.372 2.600 13.967 Sqm
S-7 1 10.427 5.372 56.014 Sqm
S-8 1 2.743 3.100 8.503 Sqm
S-9 1 10.287 4.852 49.913 Sqm
S-10 1 15.502 5.575 86.424 Sqm
S-11 1 9.652 5.384 51.966 Sqm
S-12 1 5.220 2.337 12.199 Sqm
S-13 1 10.817 5.220 56.465 Sqm For Making
S-14 1 5.195 5.220 27.118 Sqm F.F #REF!
S-15 1 5.385 5.220 28.110 Sqm Normal 7392.16
S-16 1 4.852 5.220 25.327 Sqm
S-17 1 3.683 4.100 15.100 Sqm
S-18 1 3.48 5.575 19.401 Sqm
S-19 1 5.39 1.430 7.701 Sqm
S-20 1 5.195 0.00 3.683 19.133 Sqm
S-21 1 5.384 0.00 3.248 17.487 Sqm
S-22 1 3.15 0.00 3.248 10.228 Sqm
Total 640.47 Sqm
Total 6890.46 Sft
Fair Face Area 466.98 Sft 426
Normal Area 6423.49 Sft

R.C.C Work
Column
C-3(635x635) 1 0.635 0.635 4.343 1.751 Cub.m
C-5(635x635) 1 0.635 0.635 4.343 1.751 Cub.m
D-3(635x635) 1 0.635 0.635 4.343 1.751 Cub.m
D-5(635x635) 1 0.635 0.635 4.343 1.751 Cub.m
E-3(635x635) 1 0.635 0.635 4.343 1.751 Cub.m
E-5(635x635) 1 0.635 0.635 4.343 1.751 Cub.m
F-3(635x635) 1 0.635 0.635 4.343 1.751 Cub.m
F-5(635x635) 1 0.635 0.635 4.343 1.751 Cub.m
G-3(635x635) 1 0.635 0.635 4.343 1.751 Cub.m
G-5(635x635) 1 0.635 0.635 4.343 1.751 Cub.m
H-3(635x635) 1 0.635 0.635 4.343 1.751 Cub.m
H-5(635x635) 1 0.635 0.635 4.343 1.751 Cub.m
I-3(635x635) 1 0.635 0.635 4.343 1.751 Cub.m F.Face c 16.028 Cub.m
I-5(635x635) 1 0.635 0.635 4.343 1.751 Cub.m F.Face c 565.481 Cft
F-6(508x508) 1 0.508 0.508 4.343 1.121 Cub.m
G-6(508x508) 1 0.508 0.508 4.343 1.121 Cub.m
G-1(762x305) 1 0.762 0.305 4.343 1.009 Cub.m
G'-1(762x305) 1 0.762 0.305 4.343 1.009 Cub.m
- - Total 28.78 Cub.m
Total 1015.47 Cft -
Shear Wal
SW-1(1524x305) 2 1.524 0.305 4.343 4.04 Cub.m
SW-2(5892x305) 1 5.892 0.305 4.343 7.80 Cub.m
SW-3(3480x305) 1 3.480 0.305 4.343 4.61 Cub.m
SW-4(4495x305) 1 4.495 0.305 4.343 5.95 Cub.m
SW-5(5486x305) 1 5.486 0.305 4.343 7.27 Cub.m
SW-6(4267x305) 1 4.267 0.305 4.343 5.65 Cub.m
SW-7(2490x305) 1 2.490 0.305 4.343 3.30 Cub.m
SW-8(3480x305) 1 3.480 0.305 4.343 4.61 Cub.m
SW-9(4546x305) 1 4.546 0.305 4.343 6.02 Cub.m
SW-10(2667x305) 1 2.667 0.305 4.343 3.53 Cub.m
SW-11(1524x305) 1 1.524 0.305 4.343 2.02 Cub.m
12 Total 54.81 Cub.m
Total 1933.55 Cft - -
Front Shear Wall
Sw( 5838x254) 1 5.838 0.254 4.343 6.440 Cub.m
Sw( 5385x254) 1 5.385 0.254 4.343 5.940 Cub.m
Sw(2337x305) 2 2.337 0.305 4.343 12.380 Cub.m
Total 24.761 Cub.m
Total 873.56 Cft
Slab & Beam
B-20,ABCDX(305x914) 1 16.329 0.305 0.714 11.659 Cub.m
B-21,A(305x914) 1 18.622 0.305 0.714 13.296 Cub.m
B-21,A(305x508) 1 9.500 0.305 0.308 2.926 Cub.m
B-24,ABA(305x914) 1 14.122 0.305 0.714 10.083 Cub.m
B-24,ABA(305x508) 1 4.750 0.305 0.308 1.463 Cub.m
B-25,X(254x508) 1 9.986 0.254 0.308 3.076 Cub.m
B-25,ABCDE(305x508) 1 20.118 0.305 0.405 8.148 Cub.m
B-26,ABCDE(305x914) 1 13.793 0.305 0.714 9.848 Cub.m
B-4A,12A,6X,10A&11A(635x914) 5 9.652 0.635 0.714 34.458 Cub.m
B-12A,3A(254x914) 1 14.275 0.254 0.714 10.192 Cub.m
B-4A,5,6X(305x508) 1 21.379 0.305 0.308 6.585 Cub.m
B-7&8(254x508) 1 4.908 0.254 0.308 1.512 Cub.m
B-9,10A,B(305x508) 1 14.280 0.305 0.308 4.398 Cub.m F.Face c 98.755 Cub.m
B-11A,(254x508) 1 4.909 0.254 0.308 1.512 Cub.m F.Face c 3484.06821504 Cft
B-14A,12&13(254x914) 1 12.911 0.254 0.714 9.218 Cub.m
Sub/Total 128.37 Cub.m
Slab Casting 1 640.47 0.200 128.09 Cub.m
Total 256.47 Cub.m
Total 9048.19 Cft
G.Total Casting 12870.77 Cft

Detail Calculation (m)


SL Work Description Dia Of No of Unit Wt. Remarks
Length Weight (kg) Unit Rate/Unit Total Amount
bar Bar (kg/feet)
Reinforcement
Long column
C-3(635x635) 20mm 4.343 16 2.47 171.64 KG
C-5(635x635) 20mm 4.343 16 2.47 171.64 KG
D-3(635x635) 20mm 4.343 16 2.47 171.64 KG
D-5(635x635) 20mm 4.343 16 2.47 171.64 KG
E-3(635x635) 20mm 4.343 16 2.47 171.64 KG
E-5(635x635) 20mm 4.343 16 2.47 171.64 KG
F-3(635x635) 20mm 4.343 16 2.47 171.64 KG
F-5(635x635) 20mm 4.343 16 2.47 171.64 KG
G-3(635x635) 20mm 4.343 16 2.47 171.64 KG
G-5(635x635) 20mm 4.343 16 2.47 171.64 KG
H-3(635x635) 20mm 4.343 16 2.47 171.64 KG
H-5(635x635) 20mm 4.343 16 2.47 171.64 KG
I-3(635x635) 20mm 4.343 16 2.47 171.64 KG
I-5(635x635) 20mm 4.343 16 2.47 171.64 KG
F-6(508x508) 20mm 4.343 16 2.47 171.64 KG
G-6(508x508) 20mm 4.343 16 2.47 171.64 KG 20mm 10mm 16mm
G-1(762x305) 20mm 4.343 10 2.47 107.27 KG 2960.71 1201.48
G'-1(762x305) 20mm 4.343 10 2.47 107.27 KG
Stirrup 10mm 3.840 29 0.617 1099.35 KG
Stirrup 10mm 2.854 58 0.617 102.13 KG
Total 4162.19 KG
Shear Wal
SW-1To11 16mm 4.343 196 1.58 1344.94 KG
SW-1To12 12mm 4.343 530 0.89 2048.59 KG 4134.58 1344.94
Stirrup 10mm 116.020 55 0.617 3937.14 KG
Stirrup 10mm 0.400 800 0.617 197.44 KG
Total 7528.11 KG
Floor Beam 15352.39
B-20,ABCDX(Rod) 20mm 12.000 8 2.47 237.12 KG 4517.67 3257.76 1240.72
B-20,ABCDX(Rod) 16mm 12.000 8 1.580 151.68 7478.38 23946.20 2585.66
B-20,ABCDX(Rod) 10mm 24.000 16 0.617 236.93 KG
Stirrup 10mm 2.600 172 0.617 275.92 5907.52 34010.24
B-21,A(Rod) 20mm 18.622 6 2.47 275.98 39917.76
B-21,A(Rod) 16mm 18.622 6 1.58 176.54
B-21,A(Rod) 10mm 18.622 16 0.617 183.84
Stirrup 10mm 2.600 172 0.617 275.92
B-24,ABA(Rod) 20mm 14.122 6 2.47 209.29
B-24,ABA(Rod) 16mm 14.122 2 1.58 44.63
B-24,ABA(Rod) 10mm 14.122 16 0.617 139.41
Stirrup 10mm 2.600 100 0.617 160.42
B-25,X(Rod) 16mm 9.986 8 1.58 126.22
B-25,X(Rod) 10mm 9.986 16 0.617 98.58
Stirrup 10mm 2.600 72 0.617 115.50
B-25,ABCDE(Rod) 20mm 24.118 4 2.47 238.29
B-25,ABCDE(Rod) 16mm 24.118 4 1.58 152.43
B-25,ABCDE(Rod) 10mm 24.118 4 0.617 59.52
Stirrup 10mm 1.780 172 0.617 188.90
B-26,ABCDE(Rod) 20mm 17.793 3 2.47 131.85
B-26,ABCDE(Rod) 16mm 17.793 6 1.58 168.68
B-26,ABCDE(Rod) 10mm 17.793 16 0.617 175.65
Stirrup 10mm 2.600 127 0.617 203.73
B-4A,12A,6X,10A&11A(Rod) 20mm 10.852 85 2.47 2278.38
B-4A,12A,6X,10A&11A(Rod) 12mm 10.852 16 0.89 154.53
Stirrup 12mm 2.960 494 0.89 1301.39
B-12A,3A(Rod) 20mm 14.275 6 2.47 211.56
B-12A,3A(Rod) 10mm 14.275 16 0.617 140.92
Stirrup 10mm 2.600 110 0.617 176.46
B-4A,5,6X(Rod) 20mm 21.379 8 2.47 422.45
B-4A,5,6X(Rod) 16mm 21.379 4 1.580 135.12
B-4A,5,6X(Rod) 10mm 21.379 4 0.617 52.76
Stirrup 10mm 1.780 152 0.617 166.94
B-7&8(Rod) 16mm 6.908 10 2.470 170.63
B-7&8(Rod) 10mm 6.908 4 0.617 17.05
Stirrup 10mm 1.780 50 0.617 54.91
B-9,10A,B(Rod) 20mm 14.280 6 2.470 211.63
B-9,10A,B(Rod) 16mm 14.280 3 1.580 67.69
B-9,10A,B(Rod) 10mm 14.280 4 0.617 35.24
Stirrup 10mm 1.780 102 0.617 112.02
B-11A,(Rod) 20mm 5.409 6 2.470 80.16
B-11A,(Rod) 10mm 5.409 4 0.617 13.35
Stirrup 10mm 1.780 50 0.617 54.91
B-14A,12&13(Rod) 20mm 14.911 6 2.470 220.98
B-14A,12&13(Rod) 16mm 14.911 2 1.580 47.12
B-14A,12&13(Rod) 10mm 14.911 16 0.617 147.20
Stirrup 10mm 2.600 107 0.617 171.65
10472.08

3rd Floor Slab(B.Rod-2) 10mm 40.80 123 0.617 3096.35 Kg


3td Floor Slab(B.Rod-2) 10mm 30.40 89 0.617 1669.36 Kg
B.Rod-1 10mm 25.20 133 0.617 2067.94 Kg
B.Rod-1 10mm 15.00 137 0.617 1267.94 Kg
B.Rod-3 10mm 3.67 15 0.617 33.97 Kg
B.Rod-X 10mm 6.00 111 0.617 410.92 Kg
B.Rod-X 10mm 30.80 89 0.617 1691.32 Kg
B.Rod-Y 10mm 3.67 58 0.617 131.33 Kg
Top.Rod-5 10mm 40.80 87 0.617 2190.10 Kg
Top.Rod-5 10mm 30.40 63 0.617 1181.68 Kg
Top.Rod-B 10mm 2.50 172 0.617 265.31 Kg
Top.Rod-E 10mm 2.50 260 0.617 401.05 Kg
Top.Rod-A 12mm 2.50 372 0.89 827.70 Kg
Top.Rod-Z 12mm 5.00 354 0.89 1575.30 Kg
Stair
Stair flyight 10mm 10mm 7.00 120 0.617 518.28 Kg
Binder 10mm 1.30 190 0.617 152.40 Kg
Extra top& B. 10mm 2.00 120 0.617 148.08 Kg
Landing top & B. 10mm 3.20 64 0.617 126.36 Kg
Total 17755.39 Kg G.Total 39917.76