Estimating & Costing
Estimating & Costing
Administrative Approval :
For any work in PWD it is necessary to take formal acceptance with
respect to cost and work. It is called as administrative approval.
Technical Sanction :
Technical sanction means the sanction of detail estimate, rules and cost of
work. It is sanction by competent authority.
The work for the execution only after the technical sanction.
Type of Estimate:
A. Approximate Estimating
B. Detail Estimating
Approximate Estimating :
Detailed Estimating :
I. Revised Estimate
II. Supplementary Estimate
III. Revised and supplementary Estimate
IV. Repair and maintenance Estimate
Revised Estimate :
At the time of actual work some changes and additional work has
be done these changes are due to material deviation or difference in
structural design. Separate abstract sheet should be prepared. This
estimate is called supplementary estimate.
Sr.
Revised Estimate Supplementary Estimate
No.
It is prepared the original It is prepared when their additional
1. sanctioned estimate exceeds work is required to supplement
more than 5% original work
It is prepared when there is It is prepared when some items are
2. change in material and labour added or excluded from the original
rates estimate
3 Abstract sheet is not required Separate abstract sheet is required
Revision or additional of Revision or addition of drawing may
4.
drawing is not necessary be required
Renovation Estimate :
Modes of Measurement :
Sr.no. Unit of measurement Sq. m/Lump sum
1. Site clearance cutting big trees No
2. Earthwork Cu. m
3. P.C.C. Cu. m
4. Stone Masonry Cu. m
5. Brick work (30 cm LW) Cu. m
6. Brick work (1/2 brick ) Sq. m
7. Honey – combed brickwork Sq. m
8. R.C.C. Cu. M
9. Steel Quintal/kg
10. D.P.C. Sq. m
11. Flooring Sq. m
12. Wood work for door and window frame Cu. m
13. Door window shutter Sq. m
14. Shuttering, Centring Sq. m
15. Collapsible gate Sq. m
16. Plastering, Pointing Sq. m
17. Coloring/distempering Sq. m
18. Dado Sq. m
19. Skirting up to 30 cm RMT
20. Skirting above 30 cm Sq. m
21. Cornice RMT
22. Riling Raling RMT
23. Water proofing paste/liquid Kg
24. Electric wiring Point
25. Brick on edge Number
26. Manhole and inspection chamber Number
27. Barbed wire fencing RMT
28. Surface dressing and levelling Sq. m
29. Rolled steel beams Quintal
30. Grouting Sq. m
31. Form work Sq. m
32. Rain water pipe RMT
33. Water and sewer pine RMT
34. Sand filling Cu. m
35. Bib cock, stop cock Number
36. W.C. Pan /wash basin
37. Cavity walls Sq. m
38. A.C. Sheets, G.I. Sheets Sq. m