CPCI Arch PrecastConc Walls Best Practice Guide - FINAL
CPCI Arch PrecastConc Walls Best Practice Guide - FINAL
Architectural Precast
Concrete Walls
by
www.cpci.ca
All rights reserved. This book or any part thereof must not
be reproduced in any form without the written permission of the
Canadian Precast/Prestressed Concrete Institute.
Disclaimer: This Guide is not intended to replace professional expertise. When the information contained within this Best Practice
Guide is used as guidance and incorporated into the design of buildings, it must be reviewed by knowledgeable engineering and
building envelope professionals and reflect the specific and potentially unique conditions and design parameters of each building.
Readers are advised to evaluate the information, materials and techniques cautiously for themselves and to consult appropriate
professional resources to determine whether information, materials and techniques are suitable for their application. The drawings
and text are intended as general best practice guidelines only. The project and site specific factors of climate, cost, aesthetics, and so
on must be taken into consideration. Use of the Guide does not relieve designers of their responsibility to comply with local building
codes, standards and bylaws with respect to the design and construction of the building envelope.
CHAPTER 7 Maintenance........................................................................................................................................7-1
CHAPTER 8 Glossary...............................................................................................................................................8-1
CHAPTER 9 References...........................................................................................................................................9-1
CHAPTER 10 Bibliography....................................................................................................................................10-1
Architectural and Building Science References:................................................................................................10-1
Technical Bulletins and Manuals:........................................................................................................................10-1
Sustainability Resources:.....................................................................................................................................10-1
Figure 5-5: Sealant joint detailing for double wythe precast concrete insulated wall panel....................................5-7
Figure 6-1: Visual Schematic of the Sustainable Plant Tracking Program showing the input materials
through their life cycle stages of extraction, processing, and finally their optimization in the precast
manufacturing process...........................................................................................................................................6-12
Detail drawing 5-2: Single wythe precast panel—lateral foundation wall connection...........................................5-21
Detail drawing 5-4a: Single wythe precast panel—slab bearing connection total precast....................................5-24
Detail drawing 5-4b: Single wythe precast panel—slab bearing connection total precast....................................5-25
Detail drawing 5-8: Single wythe precast panel—connection to curtain wall jamb...............................................5-29
Detail drawing 5-11: Single wythe precast panel—projecting exterior column cover...........................................5-32
Detail drawing 5-12: Double wythe precast panel—bottom bearing foundation wall connection........................5-33
Detail drawing 5-13: Double wythe precast panel—suspended soffit and lateral connection. ............................5-34
Detail drawing 5-14: Double wythe precast panel—bearing connection to slab edge.........................................5-35
Detail drawing 5-14a: Double wythe precast panel—bearing connection total precast.......................................5-36
Detail drawing 5-21: Double wythe precast panel—connection to brick veneer cladding....................................5-43
it. It is important to consider the overall requirements of the building envelope during both the design and the
construction stages. Understanding how architectural precast concrete can be utilized as an integral part of the
complete building envelope enables designers to make appropriate design choices.
Disclaimer: This Guide is not intended to replace professional expertise. When the information contained
within this Best Practice Guide is used as guidance and incorporated into the design of buildings, it must
be reviewed by knowledgeable engineering and building envelope professionals and reflect the specific
and potentially unique conditions and design parameters of each building. Readers are advised to evaluate
the information, materials and techniques cautiously for themselves and to consult appropriate professional
resources to determine whether information, materials and techniques are suitable for their application.
The drawings and text are intended as general best practice guidelines only. The project and site specific
factors of climate, cost, aesthetics, and so on must be taken into consideration. Use of the Guide does
not relieve designers of their responsibility to comply with local building codes, standards and bylaws with
respect to the design and construction of the building envelope.
manufacturers who fabricate structural, architectural and specialty precast concrete products. The purpose of the
audit based program is to provide owners and designers with the confidence that when a CPCI certified precast
concrete manufacturer is awarded a contract, the precaster will be qualified to manufacture the products they
supply to the marketplace, are competent to provide quality precast and have adequate personnel and facilities to
do so. The intent of this program is to certify only those precast manufacturers who demonstrate strict conformance
to current standards, and who are committed to continually improving the quality of their products and systems. The
CPCI Certification program has reintroduced common, measurable, nationwide standards for precast certification. In
accordance with the requirements of the National Building Code of Canada, CPCI Certification is aimed to make the
CPCI certification designation, a recognized requirement for all project specifications and for all precast operations.
CPCI Certification should always be the default certification in architectural specifications. More information can be
found in Section 3.1.4 or by visiting www.precastcertification.ca.
An architectural precast concrete wall panel is a high quality, durable, economical, sustainable, factory produced
cladding panel with the inherent architectural features of shape, colour, texture and finish that can provide the
aesthetic and all of the specified building envelope performance requirements for the exterior wall (see Chapter 4).
Architectural precast concrete wall panels are of consistent high quality as they are produced in the controlled
environment of a CPCI certified precast plant by certified personnel using quality materials. The high quality of
manufacture ensures the durability of the product which ultimately leads to its sustainability.
Finish selection requires an understanding of how the panels are manufactured and the effects material selection
has on mix design, finish consistency and durability. For instance, the selection of architectural aggregates, local to
the manufacturer will typically be more cost effective and have a lower environmental impact, owing to the shorter
shipping distances.
The use of architectural precast concrete wall panels is cost-effective for many reasons, including production in a
controlled environment and reduced site construction time and site labour. The advent of larger capacity hauling
and lifting equipment has allowed precasters to install larger panels and reduce construction time, enclosing the
building more quickly. This can be very beneficial in regions with a shorter construction season such as the majority
of Canada.
Typically, architectural precast concrete wall panels used as cladding are supported from the structure. The
gravity, wind and seismic loads must be resisted by the panels and the resultant loads transferred to the structure
through the connections. The CPCI Design Manual and CSA Standard A23.4-16 “Precast Concrete–Materials and
construction” provide useful guidance.
ensure the continuity of the air, vapour and water management layers while still allowing for proper
precast panel anchor installation.
3. The introduction of a separate air barrier layer in the wall system must also be integrated with the
back-up wall construction. When located at the exterior face of the back-up wall construction, this
air barrier layer must be constructed prior to the installation of the precast panels, which will then
be compromised when the precast anchors are installed. Penetrations must be provided through
the introduced air barrier layer for the panel anchors and once the precast panels are installed,
these penetrations must then be properly sealed. When one considers the construction sequencing,
the complete, impermeable air barrier backup wall, once constructed, would be punctured and
compromised in multiple locations to accommodate the fastening of the precast panels. Depending
on panel size and loading, every precast panel requires a minimum of 4 and sometimes up to 10
connections to the structural frame (See section 3.2.3). Therefore, a structure with 500 panels would
require at least 2000 penetrations, and potentially 5000 penetrations (if the panels are large) that would
be introduced into this newly constructed barrier layer– and these would all require resealing.
4. There is an increased opportunity in the winter for interior warm air to bypass the insulation layer and
find its way into the “cold” drainage layer, resulting in condensation accumulating on the back of the
panels and in the cavity, creating water problems, a loss of thermal performance and an increase of
the loads on connections. This phenomenon has been observed with significant consequences.
5. There is an opportunity for the introduction of a significant amount of water into the body of a
double wythe insulated precast concrete wall panel with an integral drainage layer due to wind gusts
related to the stiffness of the panel wythes and the pressure equalization of the drainage cavity within
the wall panels.
6. The compartmentalization of the joints is almost impossible as the drainage layer would also have to
be compartmentalized and all compartmentalizing beads would have to coincide. Logistically, this is
impossible to achieve and verify.
joints between panels, joints at the interface with other material types, and joints at the interface of windows and
doors. Details for interfacing are covered in Chapter 5.
When considering panel layout, the number and location of joints in the architectural design should be minimized
to reduce the risk of water and air leakage. Water and air leakage may occur when either: 1. The sealant reaches
the end of its typical service life and starts to fail, 2. The sealant is not maintained according to the sealant
manufacturer’s guidance, or 3. Premature joint failure occurs due to poor adhesion or poor joint profile. See
Section 5.3 on ways to avoid possible sealant failure and Chapter 7 on maintenance.
Panel layout is important for all precast systems. It is particularly important with double wythe insulated precast
concrete wall panels as they provide all of the building science functions in one system. When installed with the
recommended two-stage jointing system, they provide an excellent continuous thermal insulation layer, an air and
vapour barrier and act as the rain screen or perfect barrier as integrated components within the overall precast
panel design. However, the joints between panels, since they can act as discontinuities in the wall system when
not addressed properly, must be located such that they can be easily and properly sealed. Joints between panels
are typically located near structural elements, and designers must locate panel joints to avoid problems of access
for sealant installation, maintenance and replacement. Panel size must also reflect the realities of precast panel
manufacturing, transportation, and job-site handling.
Precast horizontal panels with column covers. Alternating bands of Precast Punched windows within precast
Source: M. E. Hachborn Engineering Panels and Windows. panels. Source: CPCI
Source: CPCI
Figure 2-4: Precast horizontal panels with column covers. Source: M. E. Hachborn Engineering
Solid wall panels with alternating patterns of smooth and ribbed textures.
Source: CPCI
Figure 2-7: Solid wall panels with reveals. Source: M. E. Hachborn Engineering
• The maximum panel dimensions and weight should be determined based on manufacturing,
handling, transportation and installation limitations.
• The maximum dimension of composite double wythe precast concrete insulated wall panels will
generally be in the order of L = 48t, where “L” is the maximum dimension and “t” is the overall panel
thickness, excluding the thickness of any ribs or other architectural features.
• The maximum dimension of non-composite precast concrete insulated panels will generally be in the
order of L = 48c, where L is the maximum panel dimension and c is the concrete thickness, i.e. the
overall panel thickness less the thickness of the insulation.
• Typical panel thickness can vary from 170 to 350 mm depending on structural design considerations
and the required thermal performance.
Consult the CPCI Design Manual and CPCI members for specific design information. CPCI members can assist
in the optimization of the building design for maximum economy by using the manufacturer’s standard panel
widths as much as possible. The designer is encouraged to seek input from precast manufacturers in the design
development discussions to ensure that the desired design and sizes can be properly accommodated.
Depth of sandblast or acid etching can produce distinct colours. Source: CPCI
them. These full or partial scale mock-ups illustrate the finished product and
should include panel elements such as reveals, corners, returns and other
unique features. The architect may also require proof of repair capabilities
for damage such as chips and spalls. In addition, the owner may want to
consider performance testing of mock-ups incorporating transitions at
glazing systems and other materials, to evaluate the building envelope
performance. By testing at the mock-up stage, corrective measures can be
implemented inexpensively and systematically as required to improve the
entire building performance prior to the actual building construction.
Sections 2.4.1 and 2.4.2 provide an overview on the topics of colour,
texture and finish. Form liner patterns and textures can be found on form
liner manufacturer’s websites to give the designers and owners a good
idea of what can be achieved. A great deal of additional information,
including photographs of sample colours and textures, can be found in
the CPCI Architectural Precast Concrete Colour and Texture Selection
Guide available by following this link. http://www.cpci.ca/en/resources/
technical_publications/
2.4.1 Colour
Colour varies with aggregate colour and matrix colour, size of aggregate, Pigments in the concrete mix can be
finishing process and depth of aggregate exposure. As with most natural used to replicate materials such as
materials, colour variations do occur, and reasonable variations should masonry. Source: CPCI
be expected when specifications are written for the acceptance of
architectural precast concrete. Colour variations will occur due to variations in quarrying, crushing, and screening
of aggregates. Precast manufacturers control the curing conditions of the precast concrete in order to reduce the
variations attributable to temperature and humidity variations in the plant. The precast manufacturer can assist the
designer in the selection of shapes, colours and textures and finishes to minimize variations.
Surface applied stain can be used for interesting Efflorescence on a precast concrete panel.
architectural effect. Source: M. E. Hachborn Engineering Source: CPCI
Colour can also be introduced by using pigments to colour the concrete matrix to enhance the tone of the
aggregates in the concrete mix or to duplicate the appearance of other materials.
Stains can also be used to colour the precast to give more vibrant colours or to create interesting colour
combinations on buildings.
Colour and finish can sometimes be affected by efflorescence. Efflourescence is a white, powdery deposit that
can form on the surface of all concrete and masonry products including brick, cast-in-place concrete and precast
concrete. Efflourescence is typically caused by the migration of free soluble salts from within the masonry or
concrete to the surface following periods of wetting and drying, and tends to be most visible at the beginning
of the cladding’s life and diminishes as the salts are bound and retained or washed away by natural rain.
Efflourescence changes the surface aesthetics by leaving a temporary white “stain” on the surface. Possible
methods to reduce the occurrence of efflourescence are presented in the CPCI Architectural Precast Concrete
Colour and Texture Selection Guide. The guide also suggests ways to address efflourescence if it is already
present.
Table 1. The relative cost of different texture treatments for architectural precast concrete wall panels
Bond
• Select face units 13 mm to 20 mm thick with
the back of the unit scored or keyed to improve
bond.
• Face units with a high initial rate of absorption
(IRA greater than 1 gram per minute per
square inch) should be soaked in water prior to
placement.
• Clay products are subject to expansion due to
re-absorption of water following removal from
the kiln, whereas concrete undergoes shrinkage
during the early stages of curing. Generally Masonry elements being placed in the rubber form
the bond between concrete and clay masonry liner, prior to concrete placement in the precast
adequately overcomes these strains for panels up plant. Source: M. E. Hachborn Engineering
to 9 m in length.
Aesthetics
• Bricks must be dimensionally accurate (+0, -3
mm or better) for use with typical pre-formed
placement grids.
Panel Bowing
Material properties of clay product facings and concrete
panels are significantly different and can contribute
to panel bowing. The designer and precaster need to
consider the following:
• Colour of the facing material, as dark clay faced
veneers absorb heat from sun exposure and
can contribute to significant thermal bowing,
especially on southern and western exposures.
• Interior-to-exterior temperature differentials Brick-faced precast panels.
across the panel. Source: M. E. Hachborn Engineering
Form liners provide options for colour and texture. Form liners can be used to create interesting visual
Source: M. E. Hachborn Engineering effects. Source: M. E. Hachborn Engineering
Master Forms
A Master Form can be developed that includes the ability to accept
minor changes such that variations in the appearance of each
panel can be easily accommodated. Alternate panel shapes can be
provided through pre-engineered modifications to the Master Form.
Panels are normally produced from largest to smallest to minimize
damage to the form surfaces.
Envelope Forms
Envelope forms are box forms with all sides remaining in place
during casting and stripping. Set-up cost is higher and this
approach is not normally considered economically feasible unless
a minimum of 25-30 units are required. The appropriate draft
angle is required to allow for stripping and will result in slightly
wider panel-to-panel joints at the face of the panels. The precast
manufacturer should be consulted.
Combination of Envelope and Conventional
3.1.3 Materials Form (Only One Side is Removed for
Stripping). Source: CPCI
The design team must define the performance characteristics of
the various elements within the precast panel assembly and select
the desired finished appearance. Final concrete mix design should be left to the precast manufacturer in keeping with
national standards, good engineering practice, specific structural and environmental loads expected, and the local
climate where the panels are to be in service.
Where possible, the designer should work with the precast manufacturer to ensure the performance expectations
and capabilities of the materials are properly integrated into the aesthetic design and cost balance of the project.
This includes:
1. Concrete mix design,
2. Concrete admixtures,
3. Grout and Mortars,
4. Reinforcement, and
5. Anchor materials and design.
The CPCI Design Manual provides information on these considerations.
1. Determine the degree of conformity of the manufacturer’s quality system and the finished products
with the specified requirements.
2. Determine the effectiveness of the implemented quality system in meeting specified quality
objectives.
3. Provide the Manufacturer with an opportunity to improve their quality system.
4 . Confirm that the Manufacturer meets the requirements of the national standards.
Adherence to the CPCI Precast Concrete Certification Program is monitored by an Accredited Certification
Organization (ACO) that is responsible to conduct quality audits in a fair and objective manner with equal
treatment of all precast concrete manufacturers. Auditors are professional engineers, knowledgeable and trained in
the evaluation of precast concrete manufacturing plants and procedures. The ACO, using a detailed audit system,
determines a grade for each Division of the CPCI Audit Manual, a grade for each Product Group and an Overall
Plant Grade. A passing grade for Certification in each Product Group is a minimum of 80 and a minimum of 70
for any one Division. The CPCI Precast Certification Program is unique in Canada in that plants are audited to the
more stringent requirements of both CSA A23.4 and the U.S. requirements of PCI MNL 116 and 117, on a clause by
clause basis.
The CPCI Precast Concrete Certification Program is governed by a Quality Assurance Council (QAC), a third-
party multi-disciplinary body that oversees the implementation of the program. The Accredited Certification
Organization (ACO) is responsible to the Quality Assurance Council which plans, formulates, oversees and reviews
the CPCI Precast Concrete Certification Program by:
1. Establishing auditing criteria and grading standards,
2. Providing administrative review to ensure that policies and procedures are administered uniformly
and are followed by all manufacturers,
3. Developing, reviewing and approving all information related to the CPCI Precast Concrete
Certification Program,
4. Initiating and overseeing Accredited Certification Organization policies and manuals, and
5. Issuing special advisories to clarify standards or to add to the requirements in the standards.
More information and instructions on the process can be found at www.precastcertification.ca
1. Types of trailers,
2. Types of frames,
3. Supporting material, and
4. Transportation limitations for weight, width and height. (Load limits, seasonal load limits,
overhead clearances, width restrictions, trailer capacity, height, width, distance from project site,
and condition of roads to the site all influence panel size limits).
For further detailed information on methods, materials and equipment used in handling and transporting all types
of precast concrete units, consult your local CPCI member precast concrete manufacturers.
Erection of a precast panel using a tower crane. Erection of a precast panel using a mobile crane.
Source: CPCI Source: CPCI
Storage of precast panels in yard. Storage of precast panels on site. Source: CPCI
Source: M. E. Hachborn Engineering
Limitations may be necessary to balance loads by elevation, to require rigidity of shear walls or to make sure that
the schedule allows for the effects of concrete frame shortening due to shrinkage and creep.
The designer must clearly envision the erection process to utilize architectural precast concrete successfully. The
following are some of the fundamental requirements for consideration:
6. Provide layout points for the survey of the structural frame, the location of cast-in hardware and the
final position of the precast on the structure.
7. Consider the erection requirements of panels left off to accommodate the construction man-hoist.
It is critical that the capacity of locally available erection equipment be considered when sizing precast panels.
Tower crane capacities of 10,000 kg are common in most urban locations. Panel sizes should be maximized in
accordance with crane capacities.
Speed of erection and economy are directly related to crane type and size, panel size, type of connections and the
arrangement of the building frame. Connections should allow for initial setting of the panel, release of the crane and
final alignment of the panels that is completed independently of crane support. Mobile cranes may provide more
flexibility and accommodate larger panel sizes. Reach and crane access conditions must be carefully reviewed.
3.2.3 Connections
Critical to the successful application of architectural precast concrete panels in construction is the design of the
anchorage connections which attach the precast wall panels to the building frame. Typically, the engineering
consultant does this in concert with the precast fabricator, precast engineer and precast erector.
Connections of architectural precast concrete wall panels to the building must provide adequate anchorage to
resist gravity, wind and seismic loads. At the same time, the connections must also allow for horizontal and vertical
adjustment to account for construction tolerances, final alignment of the panels during erection and sliding
capabilities where they are designed to allow for seismic, thermal, and/or shrinkage movements. Connections must
also be designed to minimize thermal bridging and to avoid penetrations of air and vapour barriers. Most precast
concrete wall panel anchoring systems involve one or more of the following connection types:
• Direct Bearing (Gravity): Direct-bearing connections transfer gravity loads to the supporting
building structure or foundation. They are also used where panels are stacked and self-supporting
for vertical loads, and may include horizontal lateral tie-back connections to resist lateral forces.
• Shims: Shims are occasionally used to align panel edges. Care must be taken to avoid crushing of
shims or staining that may result from shim corrosion/degradation. Plastic (Korolath) shims can be
used to eliminate the corrosion concerns.
Figure 3-2: Detail of Sealant and Shim placement. Shim placement for aligning panels.
Source: M. E. Hachborn Engineering Source: M. E. Hachborn Engineering
Eccentric (indicated by arrows) and lateral load Eccentric lateral load connection.
connections. Source: Morrison Hershfield Source: Morrison Hershfield
Lateral tie anchors. Source: Morrison Hershfield Lateral tie anchors. Source: Morrison Hershfield
• Eccentric Bearing (Gravity): Eccentric bearing connections are needed above the first support level
when movements of the support system are possible. Eccentric connections may be created by
reinforced concrete corbels, cast in steel shapes or steel shapes welded to embedded plates after
casting.
• Lateral tie-back: Lateral tie-back connections restrain the panel in the required position and resist
wind and seismic loads perpendicular to the panel only. They do not carry vertical loads like gravity
load. It is advantageous to have adjustment in these connections as panel alignment may need to
be modified once other panels are installed.
• Seismic connection: Seismic connection design can be incorporated into one or more of the gravity
or lateral connections. Additional connections may be required and can be added as required.
Panel to panel alignment and lateral load connections. Lifting Loop (arrow)
Source: Morrison Hershfield Source: M. E. Hachborn Engineering
• One or more degrees of freedom for movement in connections may allow for thermal and
shrinkage movement within panels.
• Panel Alignment: Some connectors are used for panel alignment with respect to adjacent building
assemblies and may or may not transfer design loads.
• Lifting / Transportation / Installation Hardware: Hardware is also provided on precast wall panels to
assist with:
1. transferring the panels from the precast manufacturers plant to the storage yard,
2. placing the panels on the transportation trailer, and
3. lifting the panels from transportation trailer onto the building.
These devices range from the simplest form of a looped braided steel cable inset into the precast panel to any
number of proprietary lifting hardware, each with their own specific advantages. Each precast manufacturer has a
preferred system and it is up to the precast manufacturer to use the one best suited for the project.
An individual panel will typically require a minimum of six connections:
• two gravity connections (eccentric or direct bearing), normally located at the same elevation near
columns in multi-level building frames, and
• a minimum of four lateral load tie-backs. In some instances the gravity connections can
accommodate lateral loads in addition to the gravity loads with minimal additional cost, thereby
reducing the number of separate connections by two.
The need for more connections is determined by the precast manufacturer’s engineer, and considers the panel
articulation, the panel loads and the connection capacities. In some instances, additional connections are required
to maintain the panel alignment or to reduce bowing.
The design and the location of connections can have a significant impact on the structure as a whole, and the
performance of the building envelope. They may also contribute to the success of the project as they affect the
ease and speed of erection. The designer should provide sufficient space for the precast panel connections. It is
preferable to locate the load bearing connections close to columns to avoid the effect slab deflection has on the
precast panel alignment. Lateral connections are normally connected to columns, floor beams or floor slabs.
Additional considerations:
• Locate connections for ease of access during installation. For example, locate connections above
floor slabs, not below, to allow faster and better access to the connections.
• The use of grout, dry-pack or epoxies in connections is often not considered reliable and should be
avoided whenever possible. Special provisions must also be made in cold weather with these types
of connections. The verification of this type of connection by the design engineer is very difficult.
When shims are used for load bearing, care must be taken to ensure the shims are not overloaded
and crushed and that corrosion and the resulting staining of the panels does not occur.
• Keep connection hardware consistent throughout the project where possible. Greater capacities
than the minimum required will maintain hardware size and bolt torque requirements (for
mechanical connections) across the entire project. This simplifies panel design, drawings,
production, and installation and connection verification. Larger sizes will also accommodate minor
changes and any unexpected damage that may occur during handling.
• Use temporary shims in joints of non-load-bearing panels to establish panel spacing as required
during erection. Removal of these temporary shims is important before project completion to
ensure the proper articulation of the panels and to allow sealants to be applied as designed. It is
critical that the shims used for alignment purposes do not transfer loads from one panel to the next
unless the panel connections have been designed for these loads.
• Design connections to reduce penetration of the air and moisture barriers, and thermal insulation.
This requires considerable planning and careful detailing. The installation of precast panels after the
installation of a back-up wall is not recommended and usually results in significant cost implications
and performance problems. The logical sequencing of construction is a must to ensure continuity of
the air and moisture barrier, and thermal insulation, particularly around the connections.
Steel anchor materials include plain black steel, zinc-rich paint coated steel, zinc plated steel, hot-dipped
galvanized steel or stainless steel. The choice depends on the expected degree of exposure to corrosive elements
while in service, and the required design life of the structure. The connection design may have varying degrees of
complexity to provide for construction tolerances and adjustment in both the horizontal and vertical axes as well as
in and out of the plane of the panel.
Design connections to resist or avoid corrosion. This is especially important for connections that rely on welding of
steel elements, as weld locations can affect the corrosion resistance of steel materials and can nullify the benefits of
zinc galvanizing. As a minimum, zinc plating or hot-dip galvanizing is recommended, with zinc-rich paint touch-ups
of any chipped coating or field-cut components. If connections are expected to have long term moisture exposure,
more rigorous corrosion protection may be necessary, such as the use of stainless steel connection hardware.
The anchorage system must be compatible with the type of building frame and the anticipated exposure
conditions. Connect to or near the columns wherever possible. Concrete frames require hardware to be cast
into the frame to receive the panels. Steel frames may require larger beam sizes and stiffening at the precast
connections as well as additional adjustment capability in the connection hardware to account for frame deflection
and rotation as the precast is attached. The specifications should indicate who supplies and installs these frame
elements. Brackets may be required for large offsets of panels from the building frame or building face. Seismic
requirements can play a significant role in the anchorage design. It is usually beneficial for both the precast
manufacturer and the steel fabricator to meet prior to the completion of precast and steel shop drawings in order
to ensure all connection hardware is located appropriately and steel member sizes are adequate to carry the
precast loads.
Architectural precast concrete wall assemblies are designed to provide effective control of air infiltration and
moisture penetration through the building envelope while at the same time providing the aesthetic appeal
desired by the architect and the owner. With the proper understanding of building science, particularly the use of
insulation and the treatment of joints between interfacing materials, an efficient design can be achieved. Good
detailing and proper construction of the components in these assemblies will enhance the integrity of the entire
building envelope, and reduce the potential for future problems. Choosing the best products available will reduce
maintenance costs during the life of the structure and provide an efficient, long term sustainable solution.
To ensure continuity of thermal insulation, air barriers and vapour retarders, it is important to treat the envelope as
a complete assembly, specifically the interface between adjacent materials and components such as foundation,
wall assemblies, windows, and roof. The key is to understand the physical properties of each material, to optimize
its performance, and use building science principles to ensure that the interaction with adjacent materials does not
adversely affect the overall goal as part of the building envelope. It is helpful to identify each component in each
material assembly and follow these components, one by one, from one assembly to the next.
Without proper integration of all components, the weather tightness of the enclosure may be compromised.
Consideration of the climatic conditions outside the envelope, as well as the activities that may take place within
the interior space of any building, are paramount.
7. Control of fire
8. Provision for strength and rigidity
9. Durability
10. Aesthetic appeal
11. Economy
As outlined in the National Building Code of Canada, the environmental separation requirements – control of
heat, air, water vapour, precipitation, and noise – depends on the loads that are imposed by the location and
the intended functions within the building. Minimum acceptable performance for health and safety is also set by
applicable building codes. These performance requirements will influence the selection of panel type and design
details, and the precast manufacturer’s engineer and the building’s design team should work together to develop
the appropriate design details.
Sustainability and the environmental impact of building materials and systems and their manufacturing and
transportation processes are also important considerations. (See Section 4.13).
Other important issues that need to be considered by the building designer to facilitate the expected building
envelope performance include;
• Materials that will perform for the expected design service life of the building (This includes all com-
ponents of the precast concrete mix design.),
• Efficient operation of a building once commissioned,
• Careful use of energy resources (energy efficiency), and
• Required maintenance of the building envelope components to ensure all components continue to
perform as originally designed.
Creep shortening is cumulative (floor-to-floor) and is most significant in high-rise concrete frames. When not
accommodated within the cladding attachment system, it can cause closing of horizontal joints and potential
compression failure and spalling of exterior precast panels. Connection design and calculation of joint size must
recognize the effect of creep shortening.
The building designer must collaborate with the structural design engineer to determine the expected concrete
frame shortening from shrinkage and creep such that this adjustment can be accommodated within the cladding
joint and anchorage system.
Figure 4-1: Horizontally and vertically ribbed precast concrete panels. Source: M. E. Hachborn Engineering
Load bearing panels can be classified as flat or ribbed; both options can have window, door or other openings.
Examples of horizontal and vertical ribbed elements are illustrated in Figure 4-1. The size and configuration as well
as the selection of horizontal elements or vertical window elements, are impacted by handling, transportation and
erection requirements, and the anchor design. The structural dimensions and thickness of an element can also be
affected by:
• The minimum dimension to support the installation of proper joint seals.
• The minimum dimension for adequate cover of steel reinforcement.
• The space requirements for panel handling devices.
• The space required to accommodate connection elements.
The vertical load resistance of load bearing panels can be determined using the design methods covered in
Section 2.7 of the CPCI Design Manual.
design and detailing, such as additional panel anchor connections. For non-composite double wythe insulated
wall panels, the use of outer wythe control joints can divide the element into smaller units but this is not usually
necessary.
The design of panels at corners in composite double wythe insulated wall panels deserves special consideration
due to this bowing tendency. The thermal bowing in the warm summer season is opposite to that occurring
during the cold winter season and this can induce strain on the sealants in corner joints. During the warm summer
months the panels will bow outward in the middle and thereby separate at the mid height of the corner joint.
During the cold winter months, the panels will bow inward at mid height of the corner joint and thereby push the
joint together at mid height but separate the joint at the top and the bottom. With non-composite double wythe
insulated wall panels, this tendency is significantly reduced as the interior wythe is kept at a relatively consistent
temperature and the outer wythe is allowed to expand and contract unrestrained by the interior structural wythe
and is only subject to the thermal gradient within the outer wythe. Refer to Chapter 5 of the CPCI Design Manual
for further guidance on composite design considerations.
to provide a compatible bonding adhesive in a full bed of adhesive or a closed bonding pattern. This prevents
the air from bypassing the insulation layer. Continuous contact between the insulation and the precast panel back
face is preferred to prevent thermal air short-circuiting the system and resulting in condensation problems. The
adhesive used must also be capable of performing in the anticipated environmental conditions (hot and cold and
allow for thermal movement of the panel relative to the insulation.
Proper detailing for moisture management is critical to avoid degradation of the insulation from moisture
absorption and retention, in both single wythe and double wythe applications.
Balcony Slabs
Conventional cast-in-place concrete balcony slab construction creates significant thermal bridging that has
traditionally been ignored due to the perceived difficulties in separating the projecting concrete slab elements
from the inner floor slab construction. As building energy codes have become more stringent and increased
energy efficiency is pursued, alternate construction methods and technologies, such as the use of precast concrete
balcony slabs, are being implemented. In addition to strategies that minimize thermal bridging, sloping for slab
drainage, and waterproofing of the slab-to-wall transition can be integrated in the precast balcony slab design to
ensure that all of the required building envelope performance criteria are continued at this interface.
Precast balcony slab, with integrated perimeter curbs and thermal insulation break
between balcony and interior slab. Source: CPCI
Precast panel connection prior to encapsulation to Precast panel anchor after spray foam encapsulation to
prevent thermal bridging. Source: Morrison Hershfield prevent thermal bridging. Source: Morrison Hershfield
For an air barrier to be effective, it must be continuous across all building elements and building envelope
assemblies. This is a critical principle that must be fully addressed in the design and construction of the assembly.
Unfortunately, insufficient attention is typically given to this principle, which often leads to premature assembly
failure.
Leakage of interior air outward through the building envelope (exfiltration) can result in accumulation of significant
quantities of condensation (and / or frost) and is a primary cause of moisture-related building problems. These
problems can be avoided if sufficient air-tightness is achieved in the building envelope through implementation of
proper detailing and construction.
In single wythe architectural precast concrete wall panel assemblies, the plane of air tight continuity is located
within the precast concrete, and continues from panel-to-panel through the inner seal of the two-stage sealant
joints. If spray applied polyurethane foam is applied to the back of the single-wythe panels, it too can be
considered an air tight element and can be used to transfer the plane of air tightness to adjacent assemblies when
properly detailed and constructed. Spray applied polyurethane foam insulation does however become rigid with
time and may crack if the precast panel moves due to thermal expansion and contraction.
In double-wythe insulated precast concrete wall assemblies, the inner structural wythe of the panel is designed
as the air barrier plane, with continuity of the air seal through the inner seal of the two-stage sealant joints. This
inner wythe experiences very little thermal expansion and contraction as it remains at a fairly constant temperature,
thereby reducing stresses on the inner seal of the two-stage joint adding to its longevity.
Careful selection of materials is needed when transferring the air barrier seal from the precast panels to adjacent
assemblies such as other cladding materials, fenestration systems, and roofing. Materials must be compatible with
the materials that they contact, and the attachment must be both strong enough to withstand the expected air
pressure loads and durable enough to perform for the expected life cycle of the wall system.
Table 2: Examples of relationship between air temperature, relative humidity, and dew point temperature.
It is important to understand what the intended interior air temperature and moisture content conditions will be
when designing the appropriate vapour control strategy in an assembly. The underlying intent is to prevent air
from reaching its dew point, unless the condensation of moisture will not affect performance of the materials,
components, or assemblies. Different materials have different vapour control properties, referred to as vapour
permeance or vapour permeability. The amount of vapour control required is directly related to the anticipated
environmental conditions on the two sides of the wall assembly, including temperature and air moisture content
ranges. The vapour control strategy must allow for drying of the wall assembly when conditions allow. It is
very important that the wall be designed to provide the correct amount of vapour control for the climate and
environmental conditions on each side of the wall.
Construction materials have different vapour permeance characteristics, and vapour permeance changes for some
materials depending upon the temperature and moisture content conditions of the surrounding air. Well designed,
mixed, and cured concrete has a relatively low vapour permeance, which varies with concrete thickness. Foil or
asphalt impregnated paper wrapping fiber insulation, polyethylene films, asphalt membranes, vinyl wallpaper, and
certain types of paint all have low vapour permeance properties.
For most buildings built in Canada, an appropriate vapour control strategy is needed to prevent interior
warm, moist air from reaching colder components of the assembly during the winter months. Precast concrete
architectural panels will perform as an appropriate vapour control strategy. The other advantage of precast
concrete panels is that they are unaffected by moisture and are not a food source for mould, thereby being able to
withstand some degree of moisture accumulation, remain intact and not become a health concern.
tend to be large in value but do occur on a continuous basis. A reduction in the height of the air column reduces
this effect but does not eliminate it.
Wind against a building creates air pressure differentials that vary in magnitude, location, and type depending
upon the speed, duration, and direction of the wind. They are also dependent upon the plan dimensions and shape
of the building as well as influences from the local surrounding landscape. Positive and negative wind pressures
vary around the building as well as across a building facade and it is difficult to determine the precise effect of wind
on a building surface. Wind studies of a proposed building shape set in its local context and environment can assist
with determination of the limits of wind pressures such that proper building envelope design can be provided.
Mechanical ventilation systems can also create internal positive and negative air pressure differentials depending
upon the design of the system and its controls. Often, mechanical systems attempt to reduce the impact of stack
effect pressures to improve the operational use of the building, such as opening of doors, and the control of air
quality. Poorly designed or controlled HVAC systems can create unwanted air pressure differentials across the
building envelope that can result in water penetration through openings.
4.5.2.4 Gravity
Water flows from higher to lower elevations due to the force of gravity. When a hole exists in the exterior of the
building envelope (either purposefully or not), rain water will shed over the building envelope component and not
enter if the hole is shaped to allow gravity to move the water down. It is preferable to lead water away from holes in
the building envelope, regardless of design, to ensure water will not enter and create problems.
Figure 4-2: Examples of mass or storage approach to precipitation management. Image copyright RDH
Building Science Inc., used with permission
Release of the absorbed water is very important for this approach to wall design and relies upon evaporative
drying when the wetting period has ended. The rate of drying is dependent upon capillary/surface tension forces
and differences in water vapour pressure. Drying can occur either to the exterior, to the interior, or both. Careful
attention to the overall wall design is required, including placement and amount of insulation, vapour permeance
of surrounding materials, and the anticipated amount of
heat flow through the wall system.
Examples of mass wall assemblies include;
• multi-wythe stone, masonry, and/or rubble walls
• porous concrete or cinder or concrete block
walls
lead out of the wall system by way of through-wall flashings and weep holes. Walls where the cladding incorporates
holes at the base of wall are typically described as “vented”, whereas those that include two openings (typically
at the top and bottom of the wall) are called “ventilated”. Pressure equalized or pressure-moderated walls are a
specific type of rain screen where the air pressure behind the cladding is managed by the wall design so that it
closely resembles the air pressure outside, so that the driving force of the moisture due to air pressure difference
across the layer is minimized.
Modern brick veneer, lap siding and metal panel systems are good examples of successful drained cladding
systems.
Although precast concrete panels can be installed in a drained assembly, where the precast panels are installed
after the construction of a back-up wall, this practice is discouraged for new construction due to the penetrations
that must be made through the thermal, air and vapour layers for connections (See Section 2.2.1) – and since it is
also typically very difficult to provide a continuous drained cavity behind a precast assembly. When it is done for
retrofit projects it should also include proper two-stage drained joints for the drainage (See Section 5.3.1).
Figure 4-3: Examples of drained approach to precipitation management. Image copyright RDH
Building Science Inc., used with permission
Figure 4-4: Examples of the perfect barrier approach to precipitation management. Note that the
architectural precast panel joints should be designed as two-stage joints (See Section 5.3.1). Image
copyright RDH Building Science Inc., used with permission
systems is attributed to water ingress and accumulation at joints and cracks and an inability of the sheathing
membrane to provide long-term water tightness or water durability under these conditions.
Single wythe architectural precast concrete wall panels with a single-stage joint are considered by many to be a
form of perfect barrier, face sealed cladding system, but are not recommended.
However, single wythe precast concrete panels and double wythe precast concrete insulated wall panels with
a two-stage joint system are a combination of a perfect barrier and a concealed barrier system. The two-stage
joint system provides the exterior seal that acts as the barrier to rain for the interior seal which is concealed and
protected from the damaging elements of the environment. As long as the quality control of the precast concrete
is high and the two-stage joint system between precast panels are properly designed, installed and maintained,
the assembly has proven to provide good long-term durability in actual use in all Canadian climates. This is called a
‘perfect barrier drained joint system’, and is the recommended approach for precast concrete wall assemblies.
4.6 Noise
Local codes and by-laws have specific requirements relating to noise transmission. The following table provides
design considerations related to precast wall design:
• Noise separation becomes an important design issue when the building is located near a signif-
icant noise source such as an airport or busy highway. Typically precast concrete elements have
sufficient mass to provide effective damping and sound insulation.
• The sound transmission of a wall is largely determined by the performance of the windows and
doors, and by the air tightness of the assembly. Windows and doors should also be part of the de-
sign strategy for improved sound insulation.
• A continuous air barrier system will also have a positive impact on the sound insulation of the as-
sembly.
• A 100-mm thick concrete wall panel has an STC (sound transmission class) of 50, which is the mini-
mum STC required between dwelling units by the National Building Code of Canada (NBCC, 2015).
• Adding insulation and gypsum board raises the STC further, such that a precast concrete assembly
can easily be designed to exceed the minimum value.
• With the introduction of the new ASTC (apparent sound transmission class), assemblies are now
rated for sound transmission through all flanking paths in an assembly (NBCC 2015)
4.8 Fire
The fire performance of precast panels is usually not a concern since concrete is noncombustible. When a fire
resistance rating is required for an exterior wall, these factors affecting the rating, from the Concrete Design
Handbook (Cement Association of Canada, Fourth Edition), need to be considered
• Concrete type, dependent upon the aggregates used
• Member dimensions
• Type of reinforcement
• Cover to the reinforcement
• Panel restraint and continuity
• Protected construction
The fire-resistance ratings of concrete construction can be determined in accordance with guidelines provided in
the governing building code. Guidance is also included in Chapter 6 of the CPCI Design Manual and in the CAC
Concrete Design Manual.
Fire tests conducted by Gustaferro and Abrams (1975) on wall panel joints demonstrated that the fire endurance,
as given by the increase in temperature of 181ºC over the joint, is affected by the joint type, joint materials, and
the panel thickness. When insulating material of proper thickness is provided, fire endurance equivalent to that
of the panel can be achieved. For example, a single stage joint width of 10 mm filled with 6 mm of ceramic fibre
felt provides a 1 hour fire resistant rating, which is equivalent to that provided by 90 mm concrete panel. Refer to
Chapter 6 of the CPCI Design Manual for more information.
The building code permits the use of minor combustible components such as caulking material at a seal between
the major components of exterior walls in non-combustible construction (refer to NBC Division B, Sentence
3.1.5.2(1)).
Combustible components such as plastic insulation used in non-combustible construction must meet the
requirements of NBCC Div B, Article 3.1.5.6. The combustible insulation must also be covered by one of various
thermal barriers, depending on the flame-spread rating of the material, as per Article 3.1.5.14 of the NBCC (NRCC,
2015). This applies not only to the panels, but also to the joints between panels. Note that, in double wythe precast
concrete insulated wall panel assemblies, the insulation is encapsulated by the concrete wythes, except at the
edges of the panels at the joints.
Precast exterior wall panels incorporating plastic insulation generally meet the requirements for protection of
the exterior building face that are stated in Sentence 3.2.3.8(1) of the National Building Code (NRCC, 2015).
Information on the fire endurance (heat transmission) of concrete walls and slabs as a function of aggregate and
concrete thickness is given in Chapter 6 of the CPCI Design Manual.
By regulation, fire-stopping must be installed to prevent fire and smoke transmission between floors. Since precast
panels are typically hung on the outside of the building frame, fire and smoke seals must be provided at the slab
level between the inside edge of the precast panel and the edge of the floor slab. Designers should confirm the fire
protection requirements of applicable codes and regulations with the authority having jurisdiction.
4.9 Durability
Durability is defined in the CSA Guideline S478, Guideline on Durability in Buildings, (CSA, 1995 (R2007)) as;
“…the ability of a building or any part of its components to perform its required functions
in its service environment over a period of time without unforeseen cost for maintenance
or repair.”
The same guideline also states that the predicted service life of buildings and their components should meet or
exceed their design service life. The design service life of various building types is given in Table 2 of the Standard,
varying from 10 years for temporary buildings, and up to 100 years or more for buildings identified as “permanent”,
with “long life” buildings having a design service life ranging from 50 to 99 years. This latter category typically
applies to residential, commercial, office, health and educational buildings. When properly designed, constructed
and maintained, precast concrete wall systems have been proven to be one of the most durable building envelope
components available, with a proven history of use in Canada of more than 60 years.
There are two avenues in LEEDTM version 4 to recognize qualities of durability. Under the LEED v4 Building Design
+ Construction (BD+C) rating system (which includes New Construction), the first is in the Energy and Atmosphere
credit, Enhanced Commissioning (https://www.usgbc.org/credits/new-construction-core-and-shell-schools-new-
construction-retail-new-construction-healthca-17), a new option for envelope commissioning which specifically
says:
“Fulfill the requirements in EA Prerequisite Fundamental Commissioning and Verification
as they apply to the building’s thermal envelope in addition to mechanical and electrical
systems and assemblies. Complete the following commissioning process (CxP) activities
for the building’s thermal envelope in accordance with ASHRAE Guideline 0–2005 and
the National Institute of Building Sciences (NIBS) Guideline 3–2012, Exterior Enclosure
Technical Requirements for the Commissioning Process, as they relate to energy, water,
indoor environmental quality, and durability.”
4.10 Energy
Sustainability and green building programs such as LEED™ encourage energy savings beyond minimum code
requirements. The energy saved is a cost savings to the building owner through lower monthly utility bills, and
potentially smaller, less expensive heating, ventilating and air-conditioning (HVAC) equipment. The ultimate goal
is to reduce the total greenhouse gas emissions to the atmosphere from fossil fueled power plants and heating
appliances over the entire service life of the building.
The design of an energy-conserving or sustainable building requires the understanding, by the architect, of the
effects of decisions on energy performance. Depending on location, upwards of 50% to 90% of the global warming
potential and total primary energy impacts incurred during the service life of a building may be attributed to
building operation and energy consumption (CPCI, 2012). An integrated design approach considers how each
component interacts with the building, building occupants and/or its HVAC system. The implementation of this
approach early in the design phase helps optimize environmental impact and initial building cost, while reducing
long-term heating and cooling energy costs.
• Higher than normal insulation levels (RSI values of the envelope) designed to take full advantage of
heat retention and release.
• Ventilation designed for thermal mass considerations.
Primary Factors Defining the Effectiveness for Thermal Mass
• The amount, heat capacity and location of building mass in the design.
• Thermal coupling between the concrete mass and the HVAC system.
• Ensuring HVAC system control provisions are in place after construction and during occupancy of
the building to ensure the building operates as designed.
• Ensuring, through design and construction, that building envelope thermal bridging is minimized or
eliminated.
4.11 Aesthetics
The aesthetics of the building facade are the responsibility of the designer, usually an architect and, in the case of
architectural precast wall panels, is achieved in collaboration with the precast manufacturer. Architectural precast
offers unparalleled design flexibility because of it fluidity when in its plastic state, and the range of colours, textures
and finishes available. The aesthetic choices are wide and varied (See Chapter 2). The CPCI Architectural Precast
Concrete Colour and Texture Selection Guide offers excellent guidance and ideas for the design professional.
Table 3. Building envelope and structure type used in the CPCI LCA Study (2012)
* Note: The Thin-Brick Veneer utilized bricks 13-16 mm (1/2 to 5/8”) thick, cast into the
face of the precast concrete panels.
1. During Occupancy (60 and 73 year scenarios) the buildings with the lowest global warming potential
(GWP), regardless of location and service life, were the buildings with precast concrete envelope and
cast-in-place concrete structural frames (P-C, Pi-C, and Pib-C).
2. During Occupancy (60 and 73 year scenarios), as with GWP, the buildings with the lowest total
primary energy (TPE), regardless of location and service life, were the buildings with precast concrete
envelope and cast-in-place concrete structural frames (P-C, Pi-C, and Pib-C).
3. During Occupancy (60 and 73 year scenarios), the buildings with the highest TPE and GWP (60 and
73 year scenarios) were all steel structural frames, regardless of location and service life, with curtain
wall envelope and steel structure (CW-S) having the highest TPE and GWP in all cases.
4. With energy simulation, it was found that the interior thermal mass inherent in cast-in-place concrete
and precast concrete floors (compared to concrete toppings on metal deck) reduced annual heating
energy use by 6 to 15% and reduced total annual energy use by 2 to 3%.
5. Operating energy was responsible for 54 to 75% of the GWP in Vancouver (the range represented
service lives of 60 and 73 years, respectively), and in Toronto, 90 to 91% of the GWP was due to
operating energy (dependant on service life).
6. Operating energy accounted for 90 to 97% (depending on location and service life) of the cradle-to-
grave embodied energy (TPE).
7. For all the buildings in Toronto and Vancouver, for operating energy from cradle-to-grave, electricity
use was responsible for the majority of impacts in most of the impact categories, including: global
warming, acidification, respiratory effects, eutrophication, photochemical smog, solid waste, ozone
depletion, and total primary energy; both fossil and non-renewable.
1. The three buildings with the lowest acidification potential in Toronto were the buildings with
conventional precast concrete envelope and cast-in-place concrete structural frames (P-C, Pi-C, and
Pib-C).
2. The six buildings with the lowest respiratory impact in Toronto were buildings with precast concrete
envelopes.
3. The three buildings with the lowest photochemical smog potential in Toronto were the buildings
with precast concrete envelope and cast-in-place concrete structural frames (P-C, Pi-C, and Pib-C).
4. Buildings with precast concrete or cast-in-place concrete structural frames had less impact in the
water use category than buildings with steel structural frames.
5. Buildings with precast concrete or cast-in-place concrete structural frames had less abiotic resource
depletion than buildings with steel structural frames.
The executive summary of the precast structural assemblies, Life Cycle Assessment of Precast Concrete
Commercial Buildings, can be found by following this link: http://www.cpci.ca/en/resources/technical_
publications/.
The concrete industry is developing and promoting low environmental impact building design, complementing
such current efforts as the new Energy Code and ASHRAE‘s Advanced Energy Design Guidelines to encourage the
elimination of thermal bridging in building facades and the increased use of thermal mass.
The design of a successful building envelope must consider all of the Performance Criteria discussed in Chapter 4
and must successfully integrate the following functions in a comprehensive design strategy:
• Air control
• Water control
• Vapour control
• Thermal control
• Durability
Architectural precast concrete wall panels have been used successfully as part of an integrated exterior wall
assembly and have a proven record of long term performance. All of the above criteria should be addressed in
a straightforward and comprehensive design strategy. When this strategy is implemented during the design and
construction phases of the project, the likelihood of a successful outcome is significantly improved. Architectural
precast concrete wall assemblies provide for expedient construction and successful closure of the envelope. This
latter point can be of critical importance to overall project success.
5.1 Design Criteria for Detailing of Precast Concrete Wall Panel Joints
In architectural precast wall design, one of the critical links to a weatherproof building envelope is the joint design
and the selection and use of sealants and membranes to ensure the continuity between similar and dissimilar
building materials. The design and execution of these joints is extremely important and must be accomplished in
a constructible and economical manner. The overall appearance of the project may be affected by the detailing
and treatment of the joints. Selecting the right product, appropriate joint design, proper surface preparation, and
correct application technique will ensure the joint and sealant provide the desired performance, design service life
and pleasing, long term aesthetics.
Joints are required to accommodate changes in wall panel sizes and/or structural dimensions caused by changes
in temperature, moisture content, and applied loads while at the same time, prevent water, air and vapour
penetration through the building envelope.
Design criteria for joints include the following:
• Exterior exposure (orientation and climatic conditions).
• Structural requirements (amount of movement to be accommodated) such as primary structure
creep, inter-storey drift, building sway from seismic considerations and thermal expansion and
contraction effects of the panels and the structure.
Figure 5-2: Detail of Transverse Baffle Joint Locations. Source: M.E. Hachborn Engineering
5.3.2 Sealant Joints for Double Wythe Vent and weep opening in sealant.
Insulated Wall Panels Source: M. E. Hachborn Engineering
Figure 5-5: Sealant joint detailing for double wythe precast concrete insulated wall panel.
Image copyright RDH Building Science Inc., used with permission
Construction:
• Minimum concrete thickness of 100 mm for single wythe wall panels with two stage joints.
• Thermal movement and sealant capability must be considered in the determination of joint width.
Minimum panel-to-panel joint widths of 20 mm are recommended for single wythe panels, however
25 mm joints are preferred especially for double wythe precast concrete assemblies.
• Install the interior air seal from the exterior to avoid discontinuities at floor slabs, columns and
across shear walls. Placing sealant from the outside with the appropriate setbacks requires the use
of rollers and gauges to place the backer rod at the proper depth, long nozzles on sealant guns
and special tools for tooling the sealant and ensuring the bond between sealant and concrete is
sufficient to provide the required design service life.
• The backer rod must be sufficiently compressed in the joint to remain in place during tooling and
allow proper tooling of the sealant.
• A minimum 25 mm joint width is necessary to access the interior seal from the outside face of the
panel in double wythe precast concrete insulated wall panels.
• Drain and vent the vertical weather seal at approximately 300 mm to 600 mm below and just above
the intersection with the horizontal joints and at the base of panels. This directs any water flow
from the joint cavity down the sealant lines and controls panel staining. Joint vent openings should
be the full width of the joint and 25 mm high. The use of vent tubes to create the opening is not
recommended as they constrict the opening, fill with insects and may create accumulation of water
at the tube / sealant interface inside the panel joint.
• Baffles should also be installed in the horizontal joints at mid span of the panels to prevent the
horizontal movement of air in the joint space due to pressure differentials around the building
caused by wind. When drained precast panel assemblies are employed (not recommended), the
placement of baffles does not achieve the desired result as the air can pass the baffles by moving
through the drainage layer. See Figure 5-2.
and the temperature at which the sealant is applied. Joint width is also influenced by the climatic conditions, the
structural loadings, and environmental loads such as wind and seismic conditions.
• Joint width (Jw) resulting from panel movement due to thermal fluctuations can be calculated with
the following simplified formula:
Jw = (100/Sm) x Ct x ∆T x L
such that,
Sm = sealant movement capacity, in per cent
Ct = coefficient of thermal linear expansion (typical value for concrete
14.5 x 10-6 m/m/°C (8 x 10-6 in/in/°F)
∆T = the range of maximum to minimum temperature, in ºC or ºF
L = effective panel length or height for
movement considerations (in millimetres
or inches). This length is normally
assumed to be the length of the largest
panel but should theoretically be the
largest distance between the points of
fixity of two adjacent panels.
Similar calculations can be carried out for the effects of
expansion/contraction due to moisture absorption in the
precast panels, frame deflection/shortening as well as
creep if it is a concrete structure. Construction tolerances
and seismic considerations should also be addressed, in
consultation with the building structural engineer. Most
panel configurations will likely defer to the minimum joints
sizes (presented below) that account for construction
tolerances, as well as minimum application width for Figure 5-6: Proper Joint Sealant Profile.
sealant installation. Source: M. E. Hachborn Engineering
The minimum joint sizes that can be installed effectively,
efficiently and with a good chance of achieving the
published sealant service life are as follows:
• Jw ≥ 20 mm (3/4 in.) (single wythe precast
concrete panels)
• Jw ≥ 25 mm (1 in.) (double wythe insulated
precast concrete panels)
• Corner joints may be 30 mm wide to
accommodate the extra movement, bowing
and panel expansion often experienced at
these locations.
These minimum, nominal joint widths also account for
construction tolerances. Construction tolerances allow
for variations in precast panel size as well as variations in
site dimensions related to structural frame construction,
Figure 5-7: Proper Joint Sealant Profile.
member sizes and trueness of the structure to the
Source: M. E. Hachborn Engineering
theoretical lines and dimensions. It is prudent to assume that any joint could have a tolerance of ±6 mm (± 1/4 in).
If the joint were to be up to 6 mm narrower than shown on the drawings, the joint sizes for single and double stage
joints would become a minimum of 13 mm (1/2 in.) and 19 mm (3/4 in.), respectively.
The key factors for determining the profile of sealant joints include:
The thickness of sealant at the centre of the sealant bead should be half the joint width. The thickness of the sealant
bead at the interface with the concrete or other material at each end should be between 3/4 and 1 times the joint width.
This profile allows the sealant to stretch and compress without causing undue stress in the body of the sealant bead
(cohesive failure) and along the edges of the sealant bead to the adjacent materials such as the precast or windows
(adhesive failure). The proper joint profile should be slightly concave on the surface to allow for a flush surface when
the joint closes and the sealant is compressed. The back face of the sealant is formed to a concave profile by the
backer rod. See Figure 5-7.
The sealant must be installed with a closed cell backer rod, typically polyethylene or polyurethane foam. The
backer rod serves as a bond breaker, as well as providing a substrate for tooling the sealant to the proper sealant
profile. The backer rod should be 25 per cent larger diameter than the joint width to ensure it is under compression
once placed into the joint and remains in place when the sealant is tooled. The backer rod should be located at
a consistent depth to ensure the proper sealant profile while providing a smooth and uniform face for aesthetics.
The sealant bead should also be carefully tooled without causing the sealant to push the backer rod out of place.
Proper sealant tooling is critical to ensure that the sealant is formed to the desired profile and the sealant is well
bonded to the precast concrete panels on both sides and for the entire length of the joint.
Bellows-type expansion seal. Source: WBA Corp. Expandable foam expansion joint material.
Source: Emseal Corp.
Materials for expansion joints must be chosen for their ability to absorb appreciable movement while maintaining
their primary function of controlling the movement of moisture and air. Bellows-type expansion seals and
expandable foam products can be sized to accommodate a wide range of joint widths.
The joint width should be increased where neoprene or other gasket or compression seals are used.
• The application conditions are critical. High relative humidity and moisture within the concrete
panels may lead to premature adhesion failure of the sealant to the precast substrate. It is important
to ensure that the surfaces are dry, and the air and substrate temperature at the time of application
are within the manufacturer’s recommended range. Priming must also conform to the sealant
manufacturer’s requirements.
• Single component polyurethanes, hybrids and silicones should comply with the requirements of
CAN/CGSB 19.13-M87, “Sealing Compound, One Component, Elastomeric Chemical Curing”
(CGSB, 1987). Multi- component polyurethanes should comply with the requirements of CAN/CGSB
19.24-M90, “Multi-component, Chemical-Curing Compound” (CGSB, 1990). The following material
properties and requirements should be incorporated into the 07900 specification for sealants
applied to precast concrete joints:
u Panel edges must be clean, dry and free of any deleterious material that may affect the adhesion
of the sealant. The sealant should be allowed to cure without direct exposure to precipitation.
u Sealant movement capability should be at least 25 per cent or as required by the design
movement parameters determined for the specific application in relation to the joint size.
u Sealant materials should have demonstrated performance capability, in terms of adhesion and
elasticity, after testing for 2,000–5,000 hours of ultraviolet, accelerated exposure, according to
ASTM C793, the Standard Test Method for Effects of Laboratory Accelerated Weathering on
Elastomeric Joint Sealants (ASTM, 2010).
• Sealant tensile adhesion can be tested in accordance with ASTM C1135, the Standard Test Method
for Determining Tensile Adhesion Properties of Structural Sealants (ASTM, 2011). Adhesion in peel
can be tested in accordance with ASTM C794, the Standard Test Method for Adhesion-in-Peel of
Elastomeric Joint Sealants (ASTM, 2010).
• Most sealants are manufactured and supplied with compatible proprietary primers. The necessity
for primer application can be determined by field testing for sealant adhesion. A simple method
for determining the adhesion of a specific sealant for application into a given joint would be to
create a construction mock-up that would also incorporate other critical building envelope details,
and include a typical sealant joint. Once the sealant is cured, cut the sealant at each side of the
joint—100 mm (4 in.) long—and at the top. Pull out the sealant to review its profile, noting the
dimensions. Then pull on the sealant at a 45-degree angle of incidence from the wall plane. The
sealant should not fail in adhesion or cohesion before the sealant reaches its design movement
capability.
• Elasticity can be measured by testing in accordance with ASTM D412, the Standard Test Methods
for Vulcanized Rubber and Thermoplastic Elastomers – Tension (ASTM, 2013).
• Joint movement capability is tested to ASTM C719, the Standard Test Method for Adhesion and
Cohesion of Elastomeric Joint Sealants under Cyclic Movement (ASTM 2013).
• Field adhesion tests using ASTM C1521 Standard Practice for Evaluating Adhesion of Installed
Weatherproofing Sealant Joints (ASTM, 2013). These tests will determine the adhesion of the
sealant with each contact surface.
• Most hybrid, silicone and polyurethane sealants are suitable for precast concrete panel joints
provided they have a medium to low modulus of elasticity.
• Sealants that have the potential to cause staining tend to be silicone-based, with a high content of
oils that can leach out of the sealant over time. If staining of the substrate is a concern, then one of
two tests can be conducted: ASTM C510 Standard Test Method for Staining and Color Change of
Single or Multi-component Joint Sealants (ASTM, 2011) or ASTM C1248 Standard Test Method for
5.3.9 Primers
Some sealants require primer on all substrates while others require primer for specific substrates or none at all.
Absence of a required primer will cause premature sealant adhesion failure. Primers often help sealant adhesion in
cold weather and are recommended by the sealant manufacturer for the following reasons:
Dry tooling is the only acceptable method for creating a proper sealant
joint. Tooling solutions such as water, soaps, oils, or alcohols should not
be used unless specifically approved by the sealant manufacturer since
they may interfere with sealant curing and adhesion, and may also create
aesthetic issues.
Uncured silicone or polyurethane sealants should never be allowed
to contact surfaces such as polished granites, metal or glass. During
installation these surfaces must be masked, or care taken to prevent
sealant contact since excess sealant cannot be completely removed
with organic or chlorinated solvents. Once a sealant contacts an exposed
surface, it will leave a film that may change the aesthetic surface
characteristics of the substrate. Surfaces contaminated with sealant
materials should be cleaned as work progresses, since removal is likely to
be more difficult after the sealant has cured. A solvent or cleaning agent
recommended by the sealant manufacturer should be used to remove
sealant where not desirable.
be constructible, which means that the materials and the sequence of construction must be considered as part of
the design process.
The following parameters are common to all details:
• The panels are non-load bearing from a primary building structure perspective except details 4A,
4B, and 14A.
• The panels are assembled with two-stage joints, which consist of a “weather seal” installed at the
exterior face of single wythe wall panels or double wythe insulated wall panels, and an “air seal”
installed at the interior of single wythe wall panels or at the outer face of the inner structural wythe
in double wythe insulated wall panel construction. The line of the weather seal and air seals in the
panel joints beyond the panel sections is shown as a dotted line and identified as a bold blue and
green solid line respectively in each section.
• Generally, the “weather seal” and “air seal” are installed from the exterior for continuity of
application. When continuity problems around columns, floors and anchors can be avoided,
installation may effectively be completed from the interior.
It is important to understand that these details are intended to illustrate possible configurations for typical
construction. They are not intended for any specific project and the designer, precaster, authority having
jurisdiction, and contractor must ensure that the actual panel and wall assembly reflects the following;
• The intended use of the facility
• The local climate
• Building, fire, and energy code minimum requirements
• Aesthetic requirements
• The owner’s project specific requirements
• Local construction market capabilities
• Reasonable design practice
The details are divided into two main sets, one for single wythe precast concrete wall panels and one for double
wythe precast concrete insulated wall panels. For each detail, a description is provided that indicates the materials
providing the major building envelope performance characteristics:
• Precipitation management (indicated by a bold blue line)
• Air barrier (indicated by a bold green line)
• Heat flow management (indicated by a varying width yellow line, the width representing the relative
thermal performance at that point)
• Vapour management (indicated by a bold purple line)
Detail drawing 5-1: Single wythe precast panel—bottom bearing and lateral foundation wall
connection. Source: M. E. Hachborn Engineering
Detail drawing 5-2: Single wythe precast panel—lateral foundation wall connection.
Source: M. E. Hachborn Engineering
Detail drawing 5-3: Single wythe precast panel—suspended soffit. Source: M. E. Hachborn
Engineering
Detail drawing 5-4: Single wythe precast panel—slab bearing connection. Source: M. E. Hachborn
Engineering
Detail drawing 5-4a: Single wythe precast panel—slab bearing connection total precast.
Source: M. E. Hachborn Engineering
Detail drawing 5-4b: Single wythe precast panel—slab bearing connection total precast.
Source: M. E. Hachborn Engineering
Detail drawing 5-8: Single wythe precast panel—connection to curtain wall jamb.
Source: M. E. Hachborn Engineering
Detail drawing 5-11: Single wythe precast panel—projecting exterior column cover.
Source: M. E. Hachborn Engineering
Detail drawing 5-12: Double wythe precast panel—bottom bearing foundation wall connection.
Source: M. E. Hachborn Engineering
Detail drawing 5-13: Double wythe precast panel—suspended soffit and lateral connection.
Source: M. E. Hachborn Engineering
Detail drawing 5-14: Double wythe precast panel—bearing connection to slab edge.
Source: M. E. Hachborn Engineering
Detail drawing 5-14a: Double wythe precast panel—bearing connection total precast.
Source: M. E. Hachborn Engineering
Detail drawing 5-21: Double wythe precast panel—connection to brick veneer cladding.
Source: M. E. Hachborn Engineering
Notes:
1) Annex A provides guidance on the requirements for a prequalification program.
2) Users may request that conformity assessment of precast concrete products or elements to this
Standard be performed by an organization accredited to do so.
It is recommended that only precasters who are certified according to the CPCI Precast Concrete Certification
Program be allowed to bid. Any issues arising from CPCI certified producers may be brought to the independent
and third party Quality Assurance Council (QAC) for resolution. Other programs have no such resolution process.
The CPCI certification program is committed to delivering safe and cost-effective building and infrastructure
products to support Canada’s growing infrastructure demands. If you are an owner or specifier and have a concern
about the quality of the precast from a CPCI certified plant, you can download the Quality Concern Reporting
Form at http://www.precastcertification.ca/en/certification_program/#p1 and return the completed form to
[email protected]. All concerns are kept confidential with the CPCI Quality Assurance
Council (QAC).
The following are quality assurance activities that should be undertaken for all projects with architectural precast
concrete wall panels:
• Architect should review client’s output specification
• Independent consultant should review architectural specification to ensure compliance with the
client’s output specification
• Development of a precast concrete panel specification; see section 6.3 below for general
specification requirements
• Precast panel shop drawing review by the project architect of record and by an independent
building envelope consultant to ensure compliance to the client’s output specification (This is very
important to ensure that all building envelope requirements have been met)
• Sample review by the owner and/or the project architect
• Mock-up review by the owner and/or the project architect and the building envelope consultant
• Periodic plant review of panel manufacture by architect or building envelope consultant
• Periodic field review and final construction review by the precast engineer to ensure connections
are completed as detailed and panel articulation will not adversely affect panel and sealant
performance
• Periodic field review and final construction review by the owner and/or architect and the building
envelope consultant
• Warranty review, prior to expiration of the warranty period, as required in the project contract
6.2 Detailing
Architectural detailing is an important task to be undertaken by the designer of record. Performance considerations
need to be well understood and communicated to the contractor before implementation by the contractor. As with
other building envelope systems, the successful performance of precast concrete assemblies relies on details that
consider the following building science components described in detail in Chapter 4:
• Air barrier continuity
• Water penetration management
• Thermal insulation and minimizing thermal bridging
• Vapour diffusion control
The details need to accommodate structural movement, construction tolerances, and access for sealant
installation. Refer to Chapter 5 for more information on panel edge design and joint design. Examples of key
details that should be considered for every precast concrete design package include (as applicable to the project):
• Precast panel-to-precast panel joint design – both plan (vertical joints) and section details
(horizontal joints)
6.3 Specifications
A sample specification for architectural precast concrete panels can be found on the CPCI website
(http://www.cpci.ca/en/resources/specifications/). The sample specification for architectural precast concrete
wall panels is intended to be read in conjunction with the details provided in this best practice guide. Neither the
details nor the specifications purport to illustrate the only design tools available for the construction of architectural
precast. The architectural design team must interact with precasters during design development to review samples
and select the form, texture and final finishes. Specifiers and designers should obtain information regarding local
availability of materials and finishes, manufacturing methods and limitations, and historical evidence of satisfactory
performance for specified materials.
The following paragraphs present information that precast concrete specifications should address, as well as issues
which the specifier and designer should give particular attention:
1. Performance requirements, including, but not limited to, general conformance with the applicable
building code, as well as structural requirements, thermal insulation, maximum air leakage rates,
tolerances, deflection and clearance allowances, as applicable to the project,
2. Fabrication and erection to be conducted in conformance with relevant standards,
3. Certification of the precast manufacturer through the CPCI Precast Concrete Certification Program,
and minimum experience requirements for both the precaster, the precast erector and the
sealant applicator. Refer to the CPCI Architectural Precast Concrete Specification,
http://www.cpci.ca/en/resources/specifications/,
4. Samples that illustrate surface finish, colour and texture, aggregates, pigments, finish depth, patterns,
form liners, reveal profiles, joint treatment, for review and approval by the owner and/or design team.
This includes range and repair samples,
5. Shop drawings by the precaster, with information on concrete to be used, associated materials
(reinforcing steel and required corrosion protection, sealants, and other components under the
responsibility of the precast contractor), connection details, and details showing not only embedments
but may also include details at transitions with adjacent systems. Final shop drawings shall bear the
stamp and signature of a professional engineer registered or licensed in the jurisdiction,
6. Inspection and testing of plant placed concrete and materials, in accordance with CSA A23.4. Optional
testing may include, but is not limited to the following tests; tests to determine the suitability of
colouring pigments, coarse and fine aggregate tests, structural testing of connection hardware, concrete
slump, air void system, concrete compressive strength, and testing for facing materials such as brick,
stone or other materials when used,
7. Field mock-up, of a given size and location, as selected by the consultant, including typical structural
connections, finishes in accordance with approved samples, joint sealant installation and performance
testing,
8. Delivery, storage and protection, in accordance with the manufacturer’s requirements to avoid staining
and damage to panels,
9. Materials, for concrete mixes; cement type, aggregates, reinforcement, chemical admixtures, pigments.
The precast manufacturer is responsible for design of the concrete mix, which must be proportioned to
meet the specified properties. The specified properties should meet the performance requirements of
CSA-A23.1 and CSA-A23.4. A minimum mix design based on exposure classification F-2 (concrete in an
unsaturated condition exposed to freezing and thawing) should be specified. This exposure classification
is appropriate for exterior wall panels in areas not subjected to chlorides (deicing chemicals). A more
severe exposure class may be warranted, for precast panels exposed to seawater spray, deicing salts
at grade, or other corrosive environments (C-1). Manufacturing requirements, such as the need to
often remove forms within 24 hours of casting, may govern the actual mix design, including the use of
supplementary cementitious materials and high early strength cement,
10. Support devices and accessories. Zinc plating or hot dipped galvanizing of precast anchors, support
and lifting hardware is recommended as the minimum required level of corrosion protection. Stainless
steel hardware may also be used, but is only necessary in extreme cases. The preference is for bolted
connections as opposed to field welding, which can negatively affect the corrosion protection of the
support hardware, and may also make future removal and relocation or replacement more difficult if and
when required,
11. Manufacturing capabilities of local precast facilities and historical evidence of long-term performance
of the desired finish are important considerations for the designer. Available manufacturing expertise,
techniques and practices should be discussed. Consultation with the manufacturing plants in the
preliminary design stages is always recommended,
12. Fabrication requirements, including tolerances, and source quality control and testing, with reference to
relevant standards (refer to relevant standards and CPCI’s Architectural Precast Concrete Specification
http://www.cpci.ca/en/resources/specifications/
13. Execution, including; examination of existing conditions prior to panel installation, preparation of
temporary bracing, and erection activities, including panel alignment, structural welding, touching up of
damaged finishes and sealant installation,
14. Repair techniques in the plant and field, and
15. Cleaning, if required, of installed work, and provision of documentation relating to maintenance
requirements. Refer to the guide document Maintenance and Inspection Manual for Precast Concrete
Building Enclosures, by RDH Building Science Inc., relevant standards, and CPCI’s Architectural Precast
Concrete Specification, http://www.cpci.ca/en/resources/specifications/.
6.4 Tender
6.4.1 Samples
Each precaster intending to bid should be required to provide pre-bid colour and finish samples showing the
panel colours and textures (sample size generally 300 mm x 300 mm). Technical descriptions of the concrete mix,
aggregates and finishes should be provided and checked against the specifications. This prequalifies the precaster
and allows competitive bids from firms with adequate capability.
Shop Drawings
Prior to the commencement of precast shop drawing preparation, complete architectural and structural drawings
are required. All details should be fully developed and included in the contract drawing set. Failure to provide
these details at this time may lead to additional costs to the contract due to longer detailing duration and extras
charged by the precast manufacturer and sub trades during construction.
Shop drawings are normally produced by the precast manufacturer. The necessity of accurate shop drawings,
proper coordination by the general contractor and architect, and the thorough review of these drawings by the
architect and all trades is paramount. Many issues need to be carefully considered and incorporated into the
design prior to final approval for production. Examples include review of dimensions, location and tolerance for
connections (for loading on the structure), interface tolerances, and connection interference with the structure
and other elements such as windows and adjacent building envelope assemblies. The inclusion of mechanical
openings, electrical openings and window attachment devices will save all parties time and money during
precast erection and other component construction. Site lifting equipment capacities and access also need to be
considered. Incomplete architectural drawings and frequent drawing changes will cause delays and increase the
cost of the project.
Preparation of shop drawings stamped by a qualified professional engineer is the responsibility of the precast
manufacturer. Requirements for the shop drawings are specified in CSA A23.3 and CSA A23.4. Shop drawings
include general arrangement drawings, erection drawings, connection details, and cast in place and/or pre-weld
hardware drawings showing the location of embedded or pre-welded hardware to the structure. Internal plant
drawings for connection hardware and production drawings for the individual precast panel elements are also
required for production to proceed.
The prime consultant, typically the project architect, is responsible for the review of the precast manufacturer’s shop
drawing submissions and coordination with the design team. The general contractor is responsible for coordination
with the various trades.
A key element in the shop drawing review process is to ensure proper coordination of the work of other trades,
particularly at interfaces between the precast wall panels and other building envelope assemblies and components
such as windows, louvers, electrical devices and roofing materials. The location and detail of the precast anchors
to the structural frame of the building should be reviewed by the structural engineer, and the details developed to
maintain the integrity of the building envelope should be reviewed by the building envelope consultant.
Window shop drawings should be reviewed in conjunction with the precast shop drawings. Responsibility for
continuity of thermal insulation or connection of the air barrier and vapour barrier between the precast and
adjacent building envelope assemblies should be defined on the project drawings and coordinated between the
trades at the time of shop drawing review. Reviewed shop drawings should be copied to all trades affected by
the work. Confirmation of window sizes and window openings should be the responsibility of both the window
subcontractor and the precast concrete panel subcontractor.
6.6 Mock-Ups
6.6.1 Production Approval Samples
The small samples suggested for the pre-bid conference stage are adequate to prequalify precasters, but one
quarter to full size mock-ups are recommended to demonstrate materials, colour, texture, scale and patterns
under changing light conditions. Mock-ups are particularly important for precast concrete wall panels with multiple
finishes, textures or veneers. As concrete is a natural material, an acceptable range of colour variation should be
established using a series of range samples.
Assessment of mock-ups and samples should be made at distances and orientations similar to those possible at the
project site, under varied light conditions and when the mock-up is both wet and dry. Reviewing the finish of mock-
up panels should be done in typical lighting with the unaided naked eye from a minimum 6 metre viewing distance.
The architect and/or an owner’s representative should sign off on the approved samples.
Clarifications to the design details should be formalized by issuing supplementary details as site instructions or
bulletins. Changes to the design details should similarly be documented and issued to all parties. It is critical that
variances from the design, including dimensional relationships between elements within the exterior wall assembly,
and details (and materials) for connection and continuity of the building envelope, be resolved at the mock-up
stage and preferably prior to completion of the precast shop drawings and absolutely prior to the production of
precast panels and final installation of the panels on the project site.
The prime consultant should accept overall responsibility for the review of mock-ups and any changes required,
but the structural engineer and the building envelope consultant also play key roles in this review and the
resolution of any problems. The general contractor and the sub trade contractors must also be included in this
process to ensure that what is detailed can be constructed without need for further revision later.
1. Quality System, including but not limited to the plant QA program, the personnel, design
responsibilities and project samples,
2. Production practices, including but not limited to general objectives and safety, production and
curing facilities, welding, form and mould construction, hardware installation, product identification,
handling, surface finishes, repairs, appearance and sealers or coatings,
3. Raw materials and accessories, including but not limited to cement, aggregates, admixtures,
reinforcement and hardware, insulation and other ancillary devices,
4. Concrete, including but not limited to mix proportioning, air entrainment, structural lightweight
aggregates, compatibility of mixes, water-cement ratios, storage and handling of cement,
aggregates and admixtures and concrete mixing equipment requirements,
5. Reinforcement (and prestressing, as required), including but not limited to reinforcing steel,
composite reinforcement, fibres, and pre-tensioning and post-tensioning equipment and
procedures,
6. Quality control, such as inspection, testing, documentation and testing facilities, and
7. Product tolerances, including but not limited to product dimensions, hardware locations and finish
consistency and limits.
CPCI certified precast manufacturers must develop an exhaustive Quality System Manual (QSM) for the fabrication
of architectural precast panels. Once developed and approved by the Accredited Certification Organization (ACO),
the precast manufacturer must follow this QSM for all products manufactured and ensure they conform to the
requirements as set out in the program standards. The QSM is generally based on standards such as:
• PCI Manual MNL-117-13 Fourth Edition, Manual for Quality Control for Plants and Production of
Architectural Precast Concrete Products (PCI, 2013)
• PCI Manual MNL-116-99 Manual for Quality Control for Plants and Production of Precast and
Prestressed Concrete Products (PCI, 1999)
• CSA A23.4-16, Precast Concrete – Materials and Construction
• Other applicable ACI, ASTM and CSA Standards
• Special Advisories issued by the Quality Assurance Council
The CPCI standard specification (http://www.cpci.ca/en/resources/specifications/) for quality assurance practices
calls for the materials and manufacturing procedures to be conducted as per CAN/CSA A23.1, Concrete Materials
and Methods of Concrete Construction and the materials and products to be tested and verified in accordance
with CAN/CSA A23.2, Test Methods and Standard Practices for Concrete. The CPCI standard specification also
requires that the precast elements shall be designed to CAN/CSA A23.3, Design of Concrete Structures, and the
CPCI Design Manual. CSA A23.4, Precast Concrete – Materials and construction is also referenced as it applies
specifically to precast concrete wall panel construction.
Annex A of CSA A23.4 provides detailed information on the general responsibilities of the owner and precast panel
manufacturer, as well as three options for the specific design and engineering responsibilities of the owner and the
precast panel manufacturer (refer to Table A.1 of the standard). These responsibilities shall be clearly established in
the contract documents. It is the precast manufacturer’s responsibility in all cases to develop shop and installation
drawings. The owner’s choice of the three design options defines what the precast manufacturer’s responsibilities
are as far as design is concerned,
Consideration should be given to the inclusion of the text of Annex A in the specifications.
It is the precast manufacturer’s responsibility to establish the precast panel properties to meet the performance
criteria, develop and implement the quality control plan in accordance with the owner’s requirements, submit the
required quality documentation and to certify that the concrete complies with these criteria.
When the owner assumes responsibility for the complete drawings and specifications, including aesthetics,
functional requirements, and panel dimensioning, the precaster plans the construction methods based on the
design parameters provided by the owner. The precaster will need to obtain approval for any changes made to
improve the economics, structural soundness or performance, or to address anticipated problems with the design
parameters, however, full responsibility remains with the owner.
In any case, the precaster can be asked to verify that all plant equipment and materials used in the fabrication of
the precast concrete panels meets the requirements of CSA A23.4.
CSA A23.4 provides information on testing for quality control purposes, such as, but not limited to testing for air
content, compressive strength, water absorption, low density concrete and accelerated curing. The owner may
request documentation confirming compliance with quality control specifications, design criteria or parameters.
Silica Fume
Silica fume is a waste product recovered from the reduction of high-purity quartz with coal in electric arc furnaces
in the production of silicon and ferrosilicon alloys. Silica fume improves the quality, strength and durability of
concrete by making the concrete much less permeable to chlorides and more resistant to corrosion of the steel
reinforcement.
Fly Ash
Fly ash is a pozzolan waste product collected from coal-fired power plants. Fly ash refines the pore structure of the
concrete, making it more resistant to chloride penetration. Fly ash must conform to the requirements of CSA A3000
and must be specified in accordance with Table 8 in CSA A23.1.
Although fly ash offers environmental advantages, it also improves the performance and quality of concrete. Fly ash
affects the plastic properties of concrete by improving workability, reducing water demand, reducing segregation
and bleeding, and lowering heat of hydration. Fly ash increases strength, reduces permeability, reduces corrosion
of reinforcing steel, increases sulphate resistance, and reduces alkali-aggregate reaction. Concrete with fly ash
reaches its maximum strength more slowly than concrete made with only hydraulic cement.
Normally 10% to 20% of the cement can be replaced with fly ash to reduce the environmental burden of the
concrete. Substitution of fly ash at levels exceeding 25% is considered to be a high volume SCM application. Care
must be taken to perform appropriate testing to ensure desired performance. The use of fly ash can increase
setting times. This may be an economic factor in precast concrete manufacturing if casting and stripping cannot be
maintained on a daily cycle.
Designers and specification writers should consult with the precast panel manufacturer to optimize the use of fly
ash to achieve the required performance prior to the project tender.
Figure 6-1: Visual Schematic of the Sustainable Plant Tracking Program showing the input materials
through their life cycle stages of extraction, processing, and finally their optimization in the precast
manufacturing process. Source: CPCI
potential (GWP) impacts for a building in Toronto were associated with the operation of the building. These
findings were consistent with other recent studies (Verbeeck and Hens, 2010; UNEP, 2009). In addition, these
studies support the sustainable movement towards net-zero construction, and the Architecture Canada 2030
Challenge. In the same study, concrete manufacturing was determined to be responsible for approximately only 9%
of the GWP and TPE impacts.
In 2012, CPCI also launched the CPCI Sustainable Plant Program to benchmark the Canadian precast concrete
industry’s impact on the environment in the areas of global warming, energy and water use, waste, dust and noise
generation (refer to Figure 6.1). At the center of the Sustainable Plant Program is the Sustainable Precast Concrete
Benchmark Calculator (v3.0), a tool that measures and quantifies the impacts of all input materials through their
life cycle stages of extraction, transportation, processing, and finally through their optimization in the precast
manufacturing process. Environmental impact is of particular interest to architectural projects, where long term
performance and total cost of ownership are well understood in the decision-making process, but the cradle-
to-construction environmental impacts have not yet been readily or clearly defined or available. The innovative
tracking software enables individual manufacturers to measure their “cradle-to-gate” environmental footprint on
a facility, product or client project basis (with cradle being raw material resource extraction and gate being the
finished product leaving the precast plant for the construction site) .
Ultimately, the precast industry is striving to reduce the environmental impact at the manufacturing level while
creating a culture of sustainability. The CPCI Life Cycle Assessment Study for Commercial Buildings has helped
to identify where the industry can improve its manufacturing stage life cycle impacts, with a goal to positively
influence the environmental impact over the entire life of the precast product in use. This program has now been
adopted by both the National Precast Concrete Association (NPCA) and Precast/Prestressed Concrete Institute
(PCI) and is currently known as the North American Sustainable Plant Program. Visit www.sustainableprecast.ca for
more information.
Precast concrete is a durable, low maintenance building material. As with all building envelope assemblies, when
a simple program of inspection and maintenance is followed, precast concrete panels can meet and exceed the
building’s design service life. In CSA S478-1995 (r2007) Guideline on Durability in Buildings, there is an expectation
that the building’s performance will be monitored for deterioration or distress; problems will be investigated and
addressed, so that the building and its systems achieve the design service life.
It is important to address issues of access to the exterior face, for window replacement, reglazing, reapplication of
sealants and cleaning of the precast panels.
Annual inspection: In order to ensure the continued performance of the precast wall assembly and maintain
warranty, visual inspections should be conducted. Particular attention should be paid to the sealant joints, and
the surface appearance. Signs of deterioration should be documented with pictures, and a report sent to the
manufacturer. Applicable defects reported during the warranty period should be remedied by the manufacturer as
soon after detection as possible to limit possible deterioration of other elements.
Annual inspections are encouraged after expiration of the warranty period as well in order to promote the
continued performance of the building envelope.
Suggested maintenance activities are summarized below:
Immediately after erection:
• Clean precast concrete elements.
Annual inspection during the building service life:
• Review sealant joints to ensure precast joints are properly sealed.
• Replace damaged joint sealant precast panel to precast panel and precast panel to adjacent non-
precast components by:
1. Removing the damaged joint sealant,
2. Cleaning the substrate(s) with solvents to remove any deleterious substances (consult the sealant
manufacturer to confirm appropriate solvent types),
3. Applying primer, as required by the manufacturer, and
4. Re-applying sealant, as per the manufacturer’s instructions. There may be benefit in matching the
new caulking with the existing, for compatibility purposes.
Periodic cleaning:
• Power wash precast panels every four to six years, based on environmental exposure (e.g. acid rain)
to maintain its original appearance.
• If acid is used for cleaning purposes, pre-test a sample to confirm that the precast panels, and any
other adjacent assemblies, will not be damaged by the cleaning process.
• If pigments are used in the concrete mix, a non-acid treatment is recommended. Follow applicable
by-laws regarding the use of sand-blasting or acid-cleaning.
For all maintenance activities, ensure that access equipment does not damage precast surfaces. As well, ensure
that window cleaning solution runoff is cleaned from precast units to prevent staining.
General information on periodic review of building envelopes can be found in Protocols for Building Condition
Assessment (NRCC/IRC, 1993) and ASTM E2270, the Standard Practice for Periodic Inspection of Building Facades
for Unsafe Conditions (ASTM, 2005). Maintenance and cleaning guidelines for precast panels can be found in
Insulated Wall Panel Technical Guide (CPCI, 2010) (http://www.cpci.ca/en/resources/technical_publications/).
The Architectural Precast Concrete Technical Guide (CPCI, 2009) (http://www.cpci.ca/en/resources/technical_
publications/) provides guidance on how to remove stains from precast concrete surfaces.
For more information on precast building maintenance and inspection, refer to the guide Maintenance and
Inspection Manual for Precast Concrete Enclosures, prepared by RDH Building Sciences Inc. The manual provides
an inspection checklist template for architects and engineers to use when performing inspections of precast
building enclosures to ensure consistency and all components are reviewed.
Absorption: The process by which one substance (solid or liquid) takes up or dissolves another
substance (liquid or gas).
Accelerator: An admixture which, when added to concrete, mortar, or grout, increases the rate of
hydration of the hydraulic cement, shortening the set time and increasing the rate of
strength gain,
Adhesion: the action, process or property of a material to stick to or bond to the surface to which
it is applied.
Adhesion failure: Failure of a compound by pulling away from the surface to which it was bonded.
Adhesion peel test: The separation of a bond, whereby the material is pulled away from the mating surface
at a 90-degree or 180-degree angle to the plane to which it is adhered.
Admixture: A material other than water, aggregates, and portland cement that is added to the mix
immediately before or during mixing.
Air barrier system: The assembly installed (in the building envelope) to provide a continuous barrier to the
movement of air (NBC’95)
Air entraining agent: An admixture for concrete or mortar which intentionally introduces minute air bubbles
into concrete or mortar during mixing.
Air infiltration: The unintentional introduction of outside air into a building through cracks in walls,
windows and doors.
Anchor: A device used to secure a building part or component to the adjoining construction or
supporting member.
Architectural precast: Precast concrete units which, through finish, shape, colour and texture, define the
architectural aesthetic and function of the structure.
Backer rod: A polyethylene or polyurethane cylindrical shaped foam material installed in the joints
between building materials
Back-up: A material placed into a joint, primarily to control the size and flow of materials.
Bead: A material after application in a joint between two elements, irrespective of the method
of application, such as caulking bead.
Blast furnace slag: A non-metallic waste product developed simultaneously with iron in a blast furnace.
It consisting of a mixture of lime, silica and alumina, the same oxides that make
up portland cement, but not in the same proportion or form. It is used both in the
manufacture of portland blast furnace slag cement and as an aggregate for lightweight
concrete.
Bleeding / Bleed A form of segregation in which some of the water in a concrete mix rises to the surface
water: of freshly placed concrete.
Bond breaker: A material, usually plastic film or foam used to prevent adhesion between two
materials.
Bush-hammer: A tool having a serrated face, used to texturize a surface and create an architectural
finish on a concrete surface.
Carbonation: Reaction between the products of Portland Cement (soluble calcium hydroxides), water
and carbon dioxide to produce insoluble calcium carbonate (efflorescence).
Caulk (v): The application of a sealant to a joint or crack. A compound used for sealing that has
minimum joint movement capability; sometimes called low performance sealant.
Cement, Portland: A powdery substance made by burning, at a high temperature, a mixture of clay and
limestone producing lumps called “clinkers” which are ground into a fine powder
consisting of hydraulic calcium silicates. This is the main adhesive ingredient in
concrete.
Cold joint: A visible lineation which forms when the placement of concrete is delayed. The
concrete in place sets prior to the next placement of concrete against it.
Compatibility: The ability of two or more materials to exist in close and permanent association for an
indefinite period with no adverse effect of one on the other.
Concrete: A composite building material made from the combination of aggregate and cement
binder.
Condensation: The appearance of moisture (water) on the surface of an object caused by warm moist
air coming into contact with a colder surface.
Construction joint: A plane of weakness to control contraction cracking in concrete. A joint can be
initiated by forming or created the in plastic or green concrete and shaped with later
process.
Convection: The transfer of heat by mass motion where air flows downward due to cooling against a
cold surface and flows upward due to heating against a warm surface.
Double wythe A precast concrete panel where thermal insulation is sandwiched between an exterior
insulated wall panel: architectural precast concrete wythe and an interior precast concrete structural wythe.
They have been commonly referred to as a “sandwich panel” or an “insulated panel” in
the past.
Elastomeric material: An elastic, rubber-like substance capable of stretching and having the ability to recover
to its original configuration.
Entrained air: (See air entrainment) Microscopic air bubbles intentionally incorporated in mortar or
concrete, to improve workability and durability (for increased freeze/ thaw resistance).
Face sealed: A wall system with a single seal on its exterior surface to prevent water and air leakage.
Fenestration: Any glass panel, window, door, curtain wall or skylight unit on the exterior of a building.
Fillet bead: Caulking or sealant placed in such a manner that it forms an angle between the
materials being joined.
Fly ash: The finely divided residue resulting from the combustion of ground or powdered coal.
Fly ash is a by-product of burning coal in coal fired power stations.
Hydraulic cement: Cement that gains strength through a process of hydration, not drying. All portland
and blended cements are hydraulic cements. “Hydraulic cement” is merely a broader
term. ASTM C1157, Performance Specification for Hydraulic Cement, is a performance
specification that includes portland cement, modified portland cement, and blended
cements.
IGU or IG unit: Insulating Glass unit formed by two or more panes (sheets) of glass on either side of a
rigid spacer creating a hermetically sealed air space.
Modulus of elasticity: A measure of the resistance of material to deformation. The elastic modulus, or Young’s
Modulus is usually given the symbol E.
Portland cement: (ASTM C 150) the product obtained by pulverizing clinker consisting essentially of
hydraulic calcium silicates.
Post-tensioning: A method of prestressing reinforced concrete in which the steel is stressed in tension
against the hardened concrete to place the hardened concrete in compression prior
loads being applied to the element due to use
Prestressed Concrete in which stresses have been introduced prior to use which are opposite in
concrete: sense to those that the structural member will be expected to carry during its use.
Pre-tensioning: A method of prestressing reinforced concrete in which the steel is stressed tension
before the concrete is placed around it and then released to create compression in the
concrete after the concrete has gained sufficient strength to bond to the reinforcement
and hold the stressed material in tension.
Rain screen: A design methodology for cladding to shed water and prevent water penetration into
the building envelope by creating a capillary break in the wall assembly.
Sealant: Compound used to fill and seal a joint or opening, as opposed to a sealer which is a
liquid used to seal a porous surface.
Single wythe wall A precast concrete cladding panel consisting of a single layer of precast concrete
panel: providing both the aesthetic and structural properties of the cladding. Single wythe
wall panels are commonly referred to as “conventional” precast panels.
Slag: A non-metallic waste product developed in the manufacture of pig iron, consisting of
a mixture of lime, silica and alumina, the same oxides that make up portland cement,
but not in the same proportions or forms. It is used both in the manufacture of portland
blast furnace slag cement and as an aggregate for lightweight concrete.
Slump: A measure of the workability and consistency of plastic concrete. (See ASTM C143).
Spandrel panel: A horizontal opaque panel used to cover other building elements that would otherwise
have a negative impact on the aesthetics of a building facade.
Stack effect: The movement of air or gasses into or out of buildings or building spaces resulting
from the buoyancy of warm air.
STC (Sound A single number rating derived from individual transmission losses at specified test
Transmission Class): frequencies. It is used for interior walls, ceiling and floors.
Vapour barrier: The elements installed (in the building envelope) to control or resist the diffusion of
water vapour (NBC’95)
Venting: Providing circulation of air or ventilation between various layers in a wall assembly.
Water-Cement ratio: The ratio of the amount of water, exclusive of that absorbed by the aggregates, to the
amount of cementing materials in a concrete mix.
Weeps (or weep Drain holes or slots in the panel joints to allow the evacuation of water.
holes):
ASTM. 2005. ASTM E2270-05, Standard Practice for Periodic Inspection of Building Facades for Unsafe Conditions.
West Conshohocken: American Society for Testing and Materials.
ASTM. 2010. ASTM C793-05(2010), Standard Test Method for Effects of Laboratory Accelerated Weathering on
Elastomeric Joint Sealants. West Conshohocken: American Society for Testing and Materials.
ASTM. 2010. ASTM C794-10, Standard Test Method for Adhesion-in-Peel of Elastomeric Joint Sealants. West
Conshohocken: American Society for Testing and Materials.
ASTM. 2011. ASTM C1135-00(2011), Standard Test Method for Determining Tensile Adhesion /Properties of
Structural Sealants. West Conshohocken: American Society for Testing and Materials.
ASTM. 2013. ASTM D412-06a(2013), Standard Test Methods for Vulcanized Rubber and Thermoplastic Elastomers –
Tension. West Conshohocken: American Society for Testing and Materials.
ASTM. 2013. ASTM C719-13, Standard Test Method for Adhesion and Cohesion of Elastomeric Joint Sealants
under Cyclic Movement. West Conshohocken: American Society for Testing and Materials.
ASTM. 2010. ASTM C794-10 Standard Test Method for Adhesion-in-Peel of Elastomeric Joint Sealants. West
Conshohocken: American Society for Testing and Materials.
ASTM. 2013. ASTM C1521-13, Standard Practice for Evaluating Adhesion of Installed Weatherproofing Sealant
Joints. West Conshohocken: American Society for Testing and Materials.
ASTM. 2011. ASTM C510 - 05a(2011), Standard Test Method for Staining and Color Change of Single- or Multi-
component Joint Sealants. West Conshohocken: American Society for Testing and Materials.
ASTM. 2012. ASTM C1248-08(2012), Standard Test Method for Staining of Porous Substrate by Joint Sealants. West
Conshohocken: American Society for Testing and Materials.
ASTM. 2013. ASTM C1193, Standard Guide for Use of Joint Sealants. West Conshohocken: American Society for
Testing and Materials.
Cement Association of Canada. 2006. Concrete Design Handbook, 3rd ed. Cement Association of Canada, Ottawa,
ON.
CGSB. 1987. CAN/CGSB 19.13-M87, Sealing Compound, One Component, Elastomeric, Chemical Curing.
Gatineau: Canadian General Standards Board.
CGSB. 1990. CAN/CGSB 19.24-M90, Multi-component, Chemical-Curing Compound. Gatineau: Canadian General
Standards Board.
CPCI. 2017. Design Manual, Precast and Prestressed Concrete, 5th edition. Ottawa: Canadian Precast/Prestressed
Concrete Institute.
CPCI. 2009. Architectural Precast Concrete Technical Brochure. Ottawa: Canadian Precast/Prestressed Concrete
Institute, 535 p. Available at: http://www.cpci.ca/downloads/national_architectural_2009_2009.pdf
CPCI. 2010. Insulated Wall Precast Concrete, Technical Brochure. Ottawa: Canadian Precast/Prestressed Concrete
Institute. Available at http://www.cpci.ca/downloads/national_insulated_2010_20096.pdf
CPCI. 2004. Architectural Precast Concrete Colour and Texture Selection Guide. Ottawa: Canadian Precast/
Prestressed Concrete Institute. Available at http://www.cpci.ca/en/resources/technical_publications/
CPCI. 2011. Life Cycle Assessment of Precast Concrete Commercial Buildings, CPCI Technical Research Bulletin
#12-01. Ottawa: Canadian Precast/Prestressed Concrete Institute. Available at http://www.cpci.ca/downloads/
Life_Cycle_Assessment_of_Precast_Commercial_Buildings.pdf
CPCI. 2012. CPCI Life Cycle Assessment Study for Commercial Buildings. Ottawa: Canadian Precast/Prestressed
Concrete Institute.
CPCI, 2013. Architectural Precast Concrete Specification. Ottawa: Canadian Precast/Prestressed Concrete Institute.
Available at http://www.cpci.ca/en/resources/specifications/
CSA. 1995. CSA S478-95 (R2007), Guideline on Durability in Buildings. Toronto: Canadian Standards Association.
CSA. 2000. CAN/CSA A251-00, Qualification Code for Architectural and Structural Precast Concrete Products.
Toronto: Canadian Standards Association.
CSA. 2014. CAN/CSA-A23.3-14), Design of Concrete Structures. Toronto: Canadian Standards Association.
CSA. 2008. CAN/CSA A3000-08, Cementitious Materials Compendium. Toronto: Canadian Standards Association.
CSA. 2014. CSA A23.1-14, Concrete Materials and Methods of Concrete Construction. Toronto: Canadian Standards
Association.
CSA. 2014. CSA A23.2-14, Test Methods and Standard Practices for Concrete. Toronto: Canadian Standards
Association.
CSA. 2016. CSA A23.4-16, Precast Concrete – Materials and Construction. Toronto: Canadian Standards
Association.
Gustaferro, A. H. and Abrams, M. S. 1975. Fire Tests of Joints between Precast Wall Panels: Effect of Various Joint
Treatments. Chicago: PCI Journal, vol. 20, no. 5, Sept.-Oct., pp. 44-64, as cited in CPCI, 2007.
Hutcheon, N.B. 1963. Canadian Building Digest-48: Requirements for Exterior Walls.
Kerr, D. 2004. Keeping Walls Dry. Ottawa: Canada Mortgage and Housing Corporation.
Masonry Council of Canada. 1982. Guide to Energy Efficiency in Masonry and Concrete Buildings. Downsview, ON.
Morrison Hershfield. 2011. Thermal Performance of Building Envelope Details for Mid- and High-Rise Buildings
(1365-RP). Atlanta: American Society of Heating, Ventilating and Air-Conditioning Engineers.
Neville, A.M. 2011. Properties of Concrete, 5th ed. Essex: Pearson Education Limited.
Ontario Masonry Contractor Association. 1976. Masonry Design Handbook.
NRCC/IRC. 1993. Protocols for Building Condition Assessment. Ottawa: National Research Council of Canada,
Institute for Research in Construction.
NRCC. 2015. National Building Code of Canada. Ottawa: National Research Council of Canada.
PCI. 2013. MNL117-13. Manual for Quality Control for Plants and Production of Architectural Precast Concrete
Products, 3rd ed. Chicago: Precast/Prestressed Concrete Institute.
PCI. 1999. MNL116-99, Manual for Quality Control for Plants and Production of Precast and Prestressed Concrete
Products, 4th ed. Chicago: Precast/Prestressed Concrete Institute.
RDH Building Science Corporation. 2013. High Performing Precast Concrete Building Enclosures: Rain Control.
Waterloo, ON: Building Science Corporation, Waterloo.
ULC. 2007. Standard Methods of fire Endurance Tests of Building Construction and Materials. Toronto:
Underwriters Laboratory of Canada.
UNEP. 2009. Buildings and Climate Change. Sustainable Buildings & Climate Initiative. Paris: United Nations
Environment Programme.
Verbeeck, G. and H. Hens. 2010. Life cycle inventory of buildings: A contribution analysis. Building and
Environment, vol. 45.
Disclaimer: This Guide is not intended to replace professional expertise. When the information contained within this Best Practice Guide is used as guidance and incorporated
into the design of buildings, it must be reviewed by knowledgeable engineering and building envelope professionals and reflect the specific and potentially unique conditions
and design parameters of each building. Readers are advised to evaluate the information, materials and techniques cautiously for themselves and to consult appropriate
professional resources to determine whether information, materials and techniques are suitable for their application. The drawings and text are intended as general best
practice guidelines only. The project and site specific factors of climate, cost, aesthetics, and so on must be taken into consideration. Use of the Guide does not relieve
designers of their responsibility to comply with local building codes, standards and bylaws with respect to the design and construction of the building envelope.