(Asce Manuals and Reports On Engineering Practice - Asce Manual and Reports On Engineering Practice) Bruce L. McCartney - Ship Channel Design and Operation-American Society of Civil Engineers (2005)
(Asce Manuals and Reports On Engineering Practice - Asce Manual and Reports On Engineering Practice) Bruce L. McCartney - Ship Channel Design and Operation-American Society of Civil Engineers (2005)
107
Task Committee
Bruce L. McCartney, Chair and Editor
Laurie L. Ebner
Lyndell Z. Hales
Eric E. Nelson
TC175.S56345 2005
627 .23—dc22 2005012333
Any statements expressed in these materials are those of the individual authors
and do not necessarily represent the views of ASCE, which takes no responsibility
for any statement made herein. No reference made in this publication to any spe-
cific method, product, process, or service constitutes or implies an endorsement,
recommendation, or warranty thereof by ASCE. The materials are for general in-
formation only and do not represent a standard of ASCE, nor are they intended as
a reference in purchase specifications, contracts, regulations, statutes, or any other
legal document.
ASCE makes no representation or warranty of any kind, whether express or
implied, concerning the accuracy, completeness, suitability, or utility of any infor-
mation, apparatus, product, or process discussed in this publication, and assumes
no liability therefore. This information should not be used without first securing
competent advice with respect to its suitability for any general or specific applica-
tion. Anyone utilizing this information assumes all liability arising from such use,
including but not limited to infringement of any patent or patents.
ASCE and American Society of Civil Engineers—Registered in U.S. Patent and
Trademark Office.
PREFACE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . xiii
1 INTRODUCTION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
1.1 Purpose . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
1.2 Background . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
1.3 National Defense . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
1.4 Economic Value to the Nation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
1.5 Project Responsibilities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
1.6 Scope . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
2 PROJECT DESIGN . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
2.1 Design Philosophy . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
2.2 Typical Project Elements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
2.3 Preliminary Design Checklist . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
2.4 Design Considerations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13
2.5 U.S. Coast Guard . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14
2.6 Baseline Studies . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14
2.7 Typical Engineering Studies . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
2.8 Cargo Types . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16
3 SHIP CHARACTERISTICS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17
3.1 Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17
3.1.1 Purpose . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17
3.1.2 Methodology and Sources . . . . . . . . . . . . . . . . . . . . . . . . . . . 17
3.1.3 Presentation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18
3.2 Dry Bulk Ships . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18
3.2.1 Description and Purpose . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18
3.2.2 Ship Types . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19
3.3 Container Ships . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21
3.3.1 Description and Purpose . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21
3.3.2 Future Ship Sizes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22
v
vi CONTENTS
5 ESTUARY HYDRAULICS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 33
5.1 Definition . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 33
5.2 Purpose of Estuary Classification . . . . . . . . . . . . . . . . . . . . . . . . . 33
5.3 Classification Options . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 34
5.3.1 Topographic Classification . . . . . . . . . . . . . . . . . . . . . . . . . . 34
5.3.2 Classification by Salinity Structures . . . . . . . . . . . . . . . . . 35
5.4 Flow Predominance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 38
5.5 Null Point . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 38
5.6 Salinity Effects on Shoaling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 39
5.7 Summary of Estuary Classification . . . . . . . . . . . . . . . . . . . . . . . . 39
5.8 Tide-Generating Forces . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 39
5.9 Tide Terms . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 40
5.10 Types of Tides . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 40
5.11 Spring and Neap Tides . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 41
5.12 Influence of Moon and Sun . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 41
5.13 Tide Prediction Tables . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 42
5.14 Nonastronomical Forces . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 42
5.15 Waveforms . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 42
5.16 Winds and Wind-Generated Waves . . . . . . . . . . . . . . . . . . . . . . . 42
5.17 Setup, Setdown, and Storm Surge . . . . . . . . . . . . . . . . . . . . . . . . . 43
5.18 Seiche . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 43
5.19 Freshwater Sources . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 43
5.20 Episodic Events . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 44
CONTENTS vii
6 CHANNEL DEPTH . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 47
6.1 Channel Depth Design Methods . . . . . . . . . . . . . . . . . . . . . . . . . . 47
6.2 Design Ship Loaded Draft . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 49
6.3 Effects of Fresh Water . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 49
6.4 Ship Motion from Waves . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 49
6.5 Squat Underway . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 52
6.6 Safety Clearance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 52
6.7 Advance Maintenance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 53
6.8 Dredging Tolerance. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 54
6.9 Nautical Depth . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 54
6.10 Source . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 55
7 CHANNEL ALIGNMENT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 57
7.1 General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 57
7.2 Variable Alignment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 57
7.3 Straight Alignment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 58
7.4 PIANC Method . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 59
8 CHANNEL WIDTHS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 63
8.1 General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 63
8.2 Maneuvering Lane . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 63
8.3 Ship Clearance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 65
8.4 Bank Clearance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 65
8.5 Channel Types . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 65
8.6 Preliminary Design Guidelines for Straight Segments . . . . . 66
8.7 Preliminary Design Guidelines for Channel Bends . . . . . . . . 69
8.7.1 General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 69
8.7.2 Channel Width in Turns . . . . . . . . . . . . . . . . . . . . . . . . . . . . 74
8.7.3 Turn Design . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 74
8.7.4 Successive Turns . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 76
8.8 Channel Width Final Design . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 76
9 SEDIMENTATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 79
9.1 Native Soils . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 79
9.2 Riverine Sediments . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 79
9.3 River Reaches . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 80
9.4 Littoral Sediments . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 81
viii CONTENTS
11 JETTIES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 93
11.1 Layout . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 93
11.2 Spacing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 94
11.3 Length . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 94
11.4 Types . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 95
11.5 Source . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 99
18 CONSTRUCTION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 153
18.1 General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 153
18.2 Source . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 155
INDEX . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 245
This manual was completed by ASCE’s Task Committee for updating Man-
ual 80, Ship Channel Design, 1993. Task Committee members were: Bruce
L. McCartney, Chairman and Editor; Dr. Laurie L. Ebner, Portland District,
Corps of Engineers; Dr. Lyndell Z. Hales, Waterways Experiment Station,
Corps of Engineers; and Eric E. Nelson, Seattle District, Corps of Engineers.
Chapter 3, “Ship Characteristics’’ was authored by Ogden Beeman, Mar-
itime Consultant. Eric Christensen, Commander, U.S. Coast Guard, au-
thored Chapter 20, “Coast Guard Activities that Support Navigation.’’ All
other chapters and appendices were assembled by Bruce L. McCartney.
Additional contributions were made by the following: Dr. Cyril Galvin,
Coastal Engineer; Andrew M. Tuthill, Cold Regions Research and En-
gineering Laboratory, Corps of Engineers; R. Anne Sudar, Institute for
Water Resources, Corps of Engineers; and Charles C. Calhoun, Jr., President
COPRI, 2003–2004.
Waterways Committee Review was performed by the following:
Dr. Anatoly B. Hochstein, Director, National Ports and Waterways Insti-
tute; Dr. B. K. Lee, Consulting Engineer; and E. Clark McNair, Jr., Consult-
ing Engineer.
Peer review was performed by the following: Dr. James R. Houston,
Director, Engineering Research Directorate, Corps of Engineers; Doug
Thiessen, Chief Harbor Engineer for Port of Long Beach, California; Dr.
William H. McAnally, Research Professor, Mississippi State University;
and Dr. Kees d’Angremond, Professor Emeritus, Delft University of Tech-
nology, Faculty of Civil Engineering and Geosciences, Department of
Hydraulic Engineering.
xiii
This page intentionally left blank
Chapter 1
INTRODUCTION
1.1 PURPOSE
1
2 SHIP CHANNEL DESIGN AND OPERATION
1.2 BACKGROUND
FIGURE 1-2. Columbia River Ship Channel (COE, Digital Visual Library).
4 SHIP CHANNEL DESIGN AND OPERATION
of our economy. Nearly 25 billion tons of cargo are shipped to, from, or
through 40 states each year.
r More than 95% of imported and exported goods to and from overseas
move by ship, including nine million barrels of oil per day.
r The U.S. marine transportation industry supports nearly $1 trillion
in commerce and 13 million jobs.
r The unit cost to transport commodities over inland waterways is
two to three times lower than that of other forms of transportation.
The ability to ship goods safely and reliably via inland waterways
translates into about $7 billion annually in transportation savings for
American businesses.
r More than 67% of all consumer goods purchased by Americans pass
through U.S. harbors.
1.6 SCOPE
r Design philosophy
r Vessel characteristics
r Hydraulic and weather conditions
r Channel dimensions
r Environmental sustainability
r Dredging and disposal
r Model studies
r Coast Guard activities
r NOAA activities
r Construction
r Operations and maintenance
r Lessons learned
r Case histories
The subject of port and harbor safety, for example, potential terrorist at-
tacks, is an ongoing effort and is beyond the scope of this manual.
This page intentionally left blank
Chapter 2
PROJECT DESIGN
When designs of specific structures are studied, one must realize that
for any structure the design process follows certain procedures and
routines. It is important that such procedures and routines are stan-
dardized in the design organization, especially when large numbers
9
10 SHIP CHANNEL DESIGN AND OPERATION
Functionality
Technology (what is feasible)
Environmental (what is allowed or accepted)
Cost and benefit
Paper work (drawing board)
Matter (actual construction)
During the design process, one can also recognize certain phases that
in some countries are related to the general conditions of contract be-
tween employer and consultant. Therefore the phases may vary from
country to country. The contractual contents of each phase are subject
to modifications in the same way. A logical set of phases include:
Initiative
Formulation of the ultimate goals of the design object as part of the
system.
Feasibility
Review of the system with respect to technical, economic, social,
and environmental consequences and feasibility. Requirements are
formulated on the component level.
Preliminary Design
Giving shape to the system on broad lines, including determina-
tion of the exact functionality of the components and definition of
requirements at the element level.
Final Design
Composition of a set of drawings and specifications for the system in
which the final shape of the components is fixed and the functionality
of the elements is determined.
Detailed Design
Composition of a set of drawings and specifications in which the
final shape of the elements is fixed.
PROJECT DESIGN 11
TI
CU
BUOYS
DA
RR
OR
L
EN
JETTY BEACONS
TS
RANGE MARKERS
L
SEA
A
ENTRANCE
IN
M
CHANNEL ANCHORAGE
R
TE
BUOY AREA
JETTY
EB
L
MANEUVERING DOCKS
CH
TS
MARINA
DA
T
B
AN
FL
AN
AREA
EN
TI
N
MI
OO
NE
RR
O
ED L
L
CU
D
TURNING
C
PR EL
TI RE
LI
U
BERTHING
D N
M
W
R
A T
S
IT
BASIN
L S
BASIN
S
BAR OR ENTRANCE INTERIOR
CHANNEL CHANNEL DOCKS
PORT
OCEAN
PROJECT
DEPTH BEACH
CONTOUR
FIGURE 2-1. Generic Harbor with Typical Project Elements (EM1110-2-1613, 2002 Draft).
PROJECT DESIGN 13
The amount and type of ship traffic that will use the navigation channel
are very important in project planning and design. Economic considera-
tions of the project will require information on commodities that will be
moved by the ship traffic. The designer will use the information on traffic
type to select the design ship—usually the largest major commodity mover
expected to most frequently use the project improvements. The amount of
ship traffic and the length of the access channel will determine the mode of
navigation traffic to be provided, whether one- or two-way. Consideration
also should be given to providing one-way traffic for large ships and two-
way traffic for smaller vessels, and to providing channel segments with
passing lanes. The designer should consider a stepped channel with dif-
ferent depths, with the deeper portion intended for loaded ships and the
shallower for empty ships. The project layout should be prepared using
various channel alignments and dimensions, each alternative evaluated
on the basis of economic efficiency involving commodity tonnage to be
moved, ship transit time, safety, environmental and social impact, and
construction and maintenance costs.
The channel design should permit safe passage of the design vessel, at
the helm of a competent pilot or captain, under most weather conditions.
The probability of unsafe conditions for a design vessel that might use the
channel only a few times a year could have some effect on channel design.
Extreme weather or flow conditions should be analyzed for their effects
on the design vessel and smaller commercial vessels, and the frequency of
14 SHIP CHANNEL DESIGN AND OPERATION
The local Coast Guard office should be consulted during the prelimi-
nary and final design processes. Coast Guard recommendations should
be considered for navigation channel and ship safety, ship maneuver-
ability, navigation traffic management, navigation operational restrictions,
stable and unstable shoal locations, and optimum placement of aids to
navigation.
The Coast Guard and Port Authorities are primarily responsible for
harbor safety. Because of the present possibility of terrorist attacks, port
safety will be an evolving effort.
c. Visibility (rain, smog, fog, and snow, including duration and fre-
quency of impairment)
d. Ice (frequency, duration, and thickness)
e. Abnormal water levels (high or low)
4. Characteristics of channel
a. Currents, tidal and river (velocity, direction, and duration)
b. Sediment sizes and area distribution, movement, and serious
scour and shoal areas
c. Type of bed and bank (soft or hard)
d. Alignment and configuration
e. Freshwater inflow
f. Tides
g. Salinity
h. Dredged material disposal areas
i. Temperature
j. Water quality
k. Biological population (type, density, distribution, and migration)
l. Obstructions (e.g., sunken vessels and abandoned structures)
m. Existing bridge and power line crossings (location, type, and clear-
ances)
n. Channel constrictions
o. Submerged cables and pipelines
p. Significant cultural sites (e.g., sites of archeological interest)
1. Design ship
2. Water level
3. Currents
4. Waves
5. Sedimentation
6. Channel depth
7. Channel width
8. Channel alignment
9. Dredging and disposal
10. Turning basins
11. Entrance channel
12. Jetties and breakwaters
13. Environmental impacts
16 SHIP CHANNEL DESIGN AND OPERATION
3.1 INTRODUCTION
3.1.1 Purpose
The design navigation features for channels and harbors generally begin
with selection of the ship types to be accommodated. For single-purpose
channels or port facilities, this is accomplished by selecting the ship type
to be served as the basis for design. For multiuser channels, it is necessary
to look at an array of ships. The selection of the “design ship” often is com-
plicated by the need to look ahead and forecast the future ship types that
are expected to use the channels and facilities. Because marine terminals
and facilities generally have design lives of 25 years and more, this aspect
of the design problem is challenging, to say the least.
The purpose of this chapter is to describe standard ship types and the
characteristics of the present world fleet, and to discuss issues affecting
the characteristics of future fleet for design purposes. It is not intended to
forecast future ship sizes for channel design purposes. That task falls to
the designer.
and container and other ships in the world fleet, with detailed descriptions
of ship characteristics. Lloyds Registry (London) is the most complete
source of ship data, compiled in three large volumes. Containerisation
International and International Bulk Shipping, as well as other maritime
publications, such as the NY Journal of Commerce, are good sources of
news on new orders and ship characteristics. Some shipbuilders post ship
characteristics on the Web or in their marketing material and are, thus,
a source of information on special ship types, such as LNG carriers. The
compilation of tables on ship dimension are from the author’s substantial
file of ship types, which are based on a number of years of maritime
consulting in the United States and abroad.
Because of the variety of information available and used, specific ref-
erences are not called out for each entry. In addition to the sources listed
earlier, Janes Merchant Ships, Ocean Ships by David Hornsby, and data from
the Port of Portland, Oregon, also were used as sources. Where character-
istics are common to many ships in the fleet, these are presented based
on data generally available through public sources. Where dimensions are
for a specific ship, the ship name is given. The selection of such ships was
purely arbitrary and used only to demonstrate the dimensions of a ship in
the size range shown.
The information in this chapter is intended to provide the designer with
an overview both of ship types and their important dimensions for channel
design. For work on a specific design project, in-depth research beyond the
scope of this chapter should be pursued. This may include checking the
references previously mentioned and talking with shipowners, operators,
and builders.
3.1.3 Presentation
The chapter is divided into sections on several common types of ocean
carriers. Included are sections on dry bulk carriers, container carriers, liq-
uid bulk carriers, and other ships, specifically auto carriers and cruise ships.
Each section includes a brief description of the purpose served by the ship
type, with some mention of its typical cargo, as well as further descriptions
of subtypes of ships within general categories, if applicable. Finally, tables
are used to summarize the primary characteristics that are needed for, or
will assist in, channel or harbor design.
to haul mineral ores, grain, and other commodities in bulk. It also can be
used to carry forest products, including logs, chips, and packaged lumber,
as well as finished steel products. It can be adapted to carry break-bulk
commodities, that is, general cargo including commodities packaged and
shipped in bags, boxes, or loose stowed without packaging. This type of
ship also can be used to carry containers, often in conjunction with other
types of general or bulk cargo. This mixed-cargo versatility is usually a
capability of smaller ships. Larger, dry-bulk cargo ships tend to have a
single commodity capability.
is used. “Cape” generally means the ship sails around the Cape Horn
in South America rather than transiting the Panama Canal. Iron ore
and coal are typical commodities carried by this size ship. There is
little incentive to build ships slightly larger than the largest Panamax–
for example, over approximately 80,000 DWT. Therefore, many Cape
Size bulk carriers start in the range of 120,000 DWT and can run up
to 300,000 DWT.
6. Suezmax. This describes a ship that can transit the Suez Canal fully
loaded. This is a ship with a draft of approximately 53 ft and a carrying
capacity in the range of 150,000 DWT.
7. Lakers. This is a special class of ship designed for use on the Great
Lakes and is unique to that trade. They are not covered in this chapter.
Dimensions in Feet
Ship Types DWT LOA Beam Draft Notes
Dimensions in Feet
Ship Type or Name Capy TEU LOA Beam(1) Draft(2) DWT-mt
and call at offshore sites, where refineries are located; at U.S. ports with
natural depths suitable for the ships, such as Puget Sound in Washington;
or at offshore single point mooring systems. The most interesting ships
from the design standpoint are product carriers delivering product from
refineries and the fleet of U.S. flag carriers transporting crude from Alaska
to the U.S. West Coast.
Product carriers transport refined products from refineries to markets.
There also is a significant use of oceangoing barges in this trade. Prod-
uct carriers tend to be in the range of 40,000 DWT and can be accom-
modated in channels designed for larger container and dry bulk ships.
Conversely, crude carriers often exceed deep-draft channel dimensions,
which leads to use of offshore piers or single-point mooring transfer
systems.
Because of increased demand for energy, there is interest in the import
of liquefied natural gas (LNG) to U.S. ports. These carriers are large and
the characteristics of length, beam, draft, and exposed surface to wind are
all of interest in channel design.
Crude oil carriers have several categories. Smaller tankers are called
product tankers, and newer ships are double-hulled in accordance with
current practice and regulations. The Suezmax carrier is the largest that can
transit the Suez Canal loaded. The draft constraint is around 53 ft, which
results in ships of around 150,000 DWT. Larger crude oil carriers transit the
Suez Canal in ballast on return trips to the Middle East. Carriers in the range
of 300,000 DWT are called Very Large Crude Carriers (VLCC); the largest
ships are Ultra Large Crude Carriers (ULCC), which range in sizes up to
and exceeding 500,000 DWT. Of increasing interest are LNG carriers, which
carry natural gas under pressure. They are usually rated in cubic meters of
capacity.
Table 3-3 shows characteristics of typical ships in these trades.
Dimensions in Feet
Ship Type or Name DWT LOA Beam Draft Comment
Another important user of ship channels is the U.S. Navy, with Naval
ships coming in many sizes. Following is a list of surface ships in the U.S.
Navy active fleet:
Aircraft carriers
Ammunition ships
Amphibious assault
Amphibious command
Amphibious transport dock
Command ships
Cruisers
Destroyers
Dock landing ships
Fast combat support ships
Frigates
Landing craft, air cushioned
Landing craft, mechanized
Mark U special operations craft
Minehunter, coastal
Mine countermeasures
Patrol coastal
Rescue and salvage
Submarine tender
The largest of these ships is the Nimitz Class aircraft carrier, which is
also the largest warship in the world. This carrier class has the following
dimensions:
Length 1,092 ft
Deck Width 252 ft
Beam 132 ft
Displacement approximately 97,000 tons full load
Length 567 ft
Beam 55 ft
Displacement 9,600 tons
Dimensions in Feet
Ship Type or Name Capy Units LOA Beam(1) Draft DWT
Dimensions in Feet
Ship Type or Name LOA Beam(1) Draft GT(2)
ships in the fleet had Panamax beams. This has changed in recent years
with the addition of one-ocean ships or Cape Class, which require long
voyages to redeploy the ship. As is the case with auto carriers, the large
exposed surface of the ship along with the shallow draft raises concerns
about course-keeping ability. Furthermore, the wide beams of the Post
Panamax fleet can provide governing dimensions for channel width.
Large cruise ships today carry upward of 3,000 passengers; this is com-
parable to the Titanic, which was put into service in 1911. However, today’s
ships are longer and wider. The Titanic was 882 ft long, with 92-ft beam,
and 35-ft draft.
Tables 3-4 and 3-5 show the dimensions of some typical carriers in the
world fleet of auto ships and cruise ships, respectively.
3.7 SUMMARY
This chapter described the dimensions of certain ships and ship types
affecting channel design. These ships are typical of much of the world’s
fleet. However, the designer should use these ship types and characteris-
tics as the starting point for further research when performing deep-draft
channel design.
3.8 SOURCE
The National Ocean Service (NOS) predicts tide height and tide ranges.
Figure 4-1 shows spring tide ranges for the continental United States. Pub-
lished tide predictions are sufficient for many channel designs; however,
prototype observations often are required. Water-level datum generally
is selected to conform to the chart datum on applicable NOS navigation
charts for tide-affected waterways. Mean lower low water or mean low
water is normally the tidal datum plane.
The projected vessel fleet over the economic life of the project is required
for channel design and economic studies. Channel dimensions should be
selected to safely and efficiently accommodate the volume and type of
traffic anticipated. The design vessel is selected from the vessel fleet and
normally will be one of the larger vessels expected to use the channel. The
maximum-size and least-maneuverable vessels in the fleet must be able to
make a safe transit, but the following special conditions may exist:
4.5 SEDIMENTATION
Marine accident records are available from the U.S. Coast Guard. Ac-
cident data on existing navigation channel projects proposed for enlarge-
ment or improvement should be studied to determine the number, cause,
and location for analysis. In some accidents, the Coast Guard will conduct
an inquiry, which also may be valuable in determining navigation prob-
lems. The National Transportation Safety Board (NTSB) also reviews spe-
cific accidents and develops reports and recommendations on site-specific
30 SHIP CHANNEL DESIGN AND OPERATION
safety issues. Information from the local pilots and, at some ports, data
from vessel traffic services (VTS), if available, can provide valuable in-
formation in designing proposed channel improvements. The local Coast
Guard District Office and Captain of the Port should be consulted for any
available data and investigation summaries.
At present, marine risk can be addressed by model studies that calculate
the risk of vessels “meeting,’’ given a pattern of movement to and from ter-
minals. The models can be calibrated and validated with historic accident
figures and then be used to assess additional risk by changes in port de-
sign or traffic density. See Section 15.5 for additional discussion of a vessel
traffic flow model.
1. Salinity
2. Tide heights (water levels)
3. Current velocities and duration
4. Water circulation pattern
5. Shoaling and erosion in the vicinity of the channel
6. Possible effects on adjacent shoreline resulting from changes in wave
patterns
7. Tidal flushing rate
8. Pollution dispersion rate
channel navigation safety and wind and wave conditions to be used for
design analysis as well as the feasibility and safety of proposed channel
design alternatives.
5.1 DEFINITION
There are many types of estuaries, and design problems may vary
greatly with the type of estuary. Correct classification alerts the de-
signers to potential environmental and maintenance-dredging problems.
To more fully understand what an estuary is, a classification system
must be established. Pritchard’s definition refers to a positive estuary
(Pritchard, 1952a), an estuary in which freshwater input (river flow
and precipitation) exceeds losses as a result of evaporation. Thus, the
surface salinities in a positive estuary are lower than in the open
ocean. When freshwater input is less than freshwater losses because of
evaporation, a negative estuary results, such as the Laguna Madre in
Texas. Most estuaries are positive; however, a negative situation can
occur, resulting in different circulation patterns caused by hypersaline
conditions.
33
34 SHIP CHANNEL DESIGN AND OPERATION
a.
b.
c.
d.
are mixed in the upper layers, more fluid enters the estuary near
the bottom to compensate for the loss; more fluid leaves the estu-
ary in the upper layers to attain equilibrium of forces (Figure 5-2a).
In these river-dominated, poorly mixed estuaries, such as Southwest
Pass on the lower Mississippi River, upstream flow occurs in the
salt wedge regardless of tidal phase, with downstream flow on the
surface. In the shallower South Pass; also on the Mississippi River,
upstream flow occurs in the wedge during flood tide simultaneously
with surface downstream flow, whereas during ebb tide flow at all
depths is in the seaward direction. Examples include the lower Mis-
sissippi River (United States) and Vellar Estuary (India). Another
ESTUARY HYDRAULICS 37
6 6
TOTAL AREA SUBTENDED BY BOTH EBB AND FLOOD CURVES = TOTAL FLOW
4 4
VELOCITY. FEET PER SECOND
0 0
EBB
2 2
4 4
AREA SUBTENDED BY EBB CURVE DIVIDED BY TOTAL AREA = PERCENT OF TOTAL FLOW DOWNSTREAM
6 6
0 2 4 6 8 10 12
TIME, HOURS
IN PERCENT OF TOTAL
IN PERCENT OF TOTAL
EBB
10 50
FLOOD
PREDOMINANCE
NULL POINT
0 25
Several basic terms are used to describe tides. High water is the water-
surface level at its highest extent during one cycle. The term is also used
to denote the time at which highest water-surface level occurs.
Similarly, low water refers to the lowest water level. Two unequal high
waters and two unequal low waters occurring in one day are distinguished
by referring to them as higher high water, lower high water, lower low
water, and higher low water. A tidal current that flows landward is termed
a flood current, whereas one that flows seaward is called an ebb current.
The basic tide is the cyclic rise and fall of the water surface as the re-
sult of the tide-generating forces. There are three types of tides—diurnal,
semidiurnal, and mixed—which are a result of tide-generating forces and
location on earth.
1. Diurnal. A diurnal tide is one high and one low water level in a
lunar day (24.84 hrs). Diurnal tides occur in the Gulf of Mexico (at
most locations); in some parts of the Pacific Ocean, for example, the
Philippines; and in certain places in Alaska.
ESTUARY HYDRAULICS 41
Another factor that influences tide is the declination of the moon and
sun—the angular distance north or south of the equator. The relationship of
the earth’s axis to the plane of its orbit around the sun results in an apparent
yearly north-south movement of the sun. The plane of the moon’s orbit
is tilted also, and the apparent north-south migration across the equator
occurs every 27.33 days. This monthly migration results in observable tidal
changes. During this month, spring tides (new and full moon) happen
to occur when the moon is crossing the equator. Neap tides occur at the
quarter moon, and apogee (moon furthest from the earth) and perigee
(moon closest to the earth) effects are noted. The spring tide occurring at
perigee is larger because of the increase in tidal forces. The tides at New
York are semidiurnal with a strong spring and neap influence. Tides at Port
Adelaide, Australia, go from mixed to semidiurnal when the moon is over
the equator, whereas tides at Seattle, Washington, are mixed at all times.
Tides at Los Angeles, California, and Honolulu, Hawaii, are diurnal during
neap tide when the moon is south of the equator, semidiurnal during spring
tide, and mixed at other times of the month. Tides at Pakhoi, China, are
strongly diurnal except when the moon is over the equator.
42 SHIP CHANNEL DESIGN AND OPERATION
5.15 WAVEFORMS
is blowing, and the extent of open water over which it blows (fetch). Water
depth is also a factor in limiting growth of waves.
In addition to the creation of wind waves, wind also can cause a condi-
tion known as “setup’’ or “setdown.’’ Wind stress on the water surface can
result in a pushing or piling up of water in the downwind direction and
a lowering of the water surface in the upwind direction. When the wind
blows landward, water will set up against the land. This setup, superim-
posed on the normal tidal elevation, causes apparent higher than normal
tides. This frequently produces flooding during storms. A seaward wind
will push water toward the sea and away from land, causing a lower than
normal water level. When the wind stops, the setup or setdown water sur-
face will return to normal levels. In enclosed waters, this return may occur
as successive oscillations that are diminished by friction.
During a storm, there may be a substantial rise in sea level along the
coast, called a “storm tide’’ or surge caused by wind setup, wave setup,
and air pressure drop. The difference in pressure between an atmospheric
low-pressure area and the surrounding high-pressure area causes the sea
surface to “hump.’’ The wind-generated storm waves superimposed on
the normal tides and storm surge can have disastrous effects on shore
structures and lead to flooding of coastal and inland areas.
5.18 SEICHE
from the drainage basin of the river, ground water, discharge from dams
and reservoirs, and rain falling on the water surface. The U.S. Geological
Survey (USGS) Water Resources Division, in cooperation with state and
local governments, collects and disseminates hydrologic data of stream
discharge or stage, reservoir and lake storage, groundwater levels, and the
quality of surface and ground water. All data is stored in the USGS Na-
tional Water Storage and Retrieval System (WATSTORE) and is available
on request from the USGS regional office or the USGS in Reston, Virginia.
Sea level rise or the apparent rise in the ocean surface when compared
to a stable landmark is a very general description for a more complicated
event. The actual rise in the ocean is not one that is readily noticeable,
especially when historic records indicate an average value of 0 to +1 centi-
meters per year. The geologic record indicates that shifts in climate and the
associated changes in sea level are attributed to the global freeze and thaw
cycles. These trends have been most noted in the Pleistocene Epoch, or ice
age, when the ocean level was much lower because much of the available
water was frozen in the glaciers. Other events and factors can affect the
rate of change:
Although historic estimates of sea level rise could impact shoreside facil-
ities over the long term, it would have a negligible effect on a navigational
channel which has a 50 year design life. A rise in the sea level datum would
result only in less dredging to maintain authorized channel depth.
5.24 SOURCE
The depth of the project design channel should be adequate to safely ac-
commodate ships with the deepest drafts expected to use the waterway.
Normally, depth is based on the development of one or more design ships
with an appropriately loaded or ballasted draft. Selection of the design
ship and project design depth is determined by an economic analysis of
the expected project benefits compared with project costs.
The two most commonly used methods for channel depth selection
are the Permanent International Association of Navigation Congresses
(PIANC) guidance report and the U.S. Army Corps of Engineers engi-
neering manuals.
The design details of these two methods are very similar. Site-specific
wind, wave, and ship motion are evaluated with the use of vessel simula-
tors or other mathematical or physical models.
The PIANC method, used to estimate channel depth for concept de-
sign, is presented in PIANC (1997), page 20. This supplement states the
following:
The values for draught (draft), which include water density effects, squat,
wave-induced motions, and margin, are additive. After the depth/draught
(draft) ratio has been calculated, it should be checked to ensure that it is
not less than a safe minimum. A minimum of 1.10 should be allowed in
47
48 SHIP CHANNEL DESIGN AND OPERATION
Fnh = V/(gh) /2
1
where
V = the speed through the water in feet/second
h = the undisturbed water depth in feet
g = the acceleration due to gravity (about 32.2 ft/sec2 )
When Fnh approaches or equals unity, the resistance to motion reaches
very high values, which most displacement ships have insufficient power
to overcome. In fact, such ships are unlikely to be able to exceed Fnh values
of 0.6 or 0.7 (the former for tankers, the latter for container ships), which
results in an effective speed barrier.
These depth/draft ratios can be applied to channels worldwide. How-
ever, local conditions may indicate that deviations are justified. Detailed
Design, which would follow Concept Design, would address the particular
features of a given site.
The following steps would be used for the (PIANC) channel depth de-
termination during concept design (first rough estimate).
The Army Corps of Engineers method for both preliminary and final
design evaluates each component of channel depth determination for each
CHANNEL DEPTH 49
When passing from sea water to fresh water, the vessel draft increases
because of the decrease in the density of the water. When passing from sea
water with a specific gravity of 1.026 (64 lb/cu ft) into fresh water with a
specific gravity of 0.999 (62.4 lb/cu ft), a vessel’s displacement will increase
approximately 3%. Therefore, a vessel with a saltwater draft of 35 ft will
have a draft of 36 ft in fresh water, and intermediate drafts in brackish
waters.
Waves and swells affect vertical ship motion by three components, pitch,
roll, and heave, as shown in Figure 6-2. The deepest excursion of the vessel
MHHW
MEAN
TIDE
VARIATION
MEAN LOW WATER DATUM
MLLW
DESIGN SHIP
LOADED DRAFT
(SUMMER, SALTWATER)
EFFECT OF
FRESHWATER
50
SHIP MOTION
FROM WAVES
SOUAT
UNDERWAY
SAFETY
AUTHORIZED CHANNEL LEVEL CLEARANCE
ADVANCE MAINTENANCE
DREDGING TOLERANCE
bottom below the water surface, which is caused by waves, must be consid-
ered in the design of channel depth. In open-sea conditions, a pitch angle of
2.5◦ in a 1000-ft-long ship would increase draft forward about 22 ft. Proto-
type observations of ship motion in the Columbia River entrance indicated
downward pitch motions in excess of 25 ft. The maximum vertical excur-
sion, however, did not take place with the deepest draft ship but with a
small ship. It appears this ship was affected by the relationship of the ship
length to wave length during the time of crossing. Some pilots and ship
captains consider the Columbia River bar one of the most severe channel
entrances in the world; thus, this example should be considered an extreme
example. At times, the bar pilots judge the wind, wave, and current con-
ditions too dangerous to navigate, and ships must wait for more favorable
conditions (Wang and Noble, 1982). A 5◦ angle of roll for a ship having
a beam of 100 ft would increase amid-ship draft about 4.2 ft. This is not
an unusual roll at entrances or in some semiprotected waters, caused by
waves, wind, and turn angle.
6.10 SOURCE
7.1 GENERAL
The strength of the hydraulic forces in the estuary will usually dic-
tate channel alignment. Estuaries with high tide ranges and, therefore,
strong ebb currents or large river discharges, normally will have navi-
gation channels with changing alignments. An example is Grays Harbor,
Washington, which has high tides and a large tide prism, as shown in
Figure 7-1.
These systems may have channels that migrate, such as Grays Harbor,
where the channel has migrated to a position adjacent to the South Jetty
(Figure 7-2). Normally, the ship channel alignment is adjusted over time
to follow the natural channel migration.
57
58 SHIP CHANNEL DESIGN AND OPERATION
Notes:
Mean tide range 9.00 feet
Maximum tide range 17.5 feet
ship channel 26 miles long
cross current along the channel. This also applies to wind and waves,
although these may come from any direction. Usually, the prevailing
wind and wave direction are considered in design, with a judgment
on whether possible downtimes as a result of strong winds or high
waves from other directions are acceptable.
Finally, it is advisable (and important in the case of channels navi-
gated by ships carrying dangerous goods) that the channel be aligned
to prevent the ship heading directly at the quay or jetty during its ap-
proach. Any channel whose direction is perpendicular to the berthing
face should be aligned to one side of the quay or jetty, so that a ship
must turn (or be swung) to arrive at the berth. This minimizes the
risk of ships demolishing the jetty or quay in the event of losing all
control on the approach.”
8.1 GENERAL
Channel widths should be designed to provide for the safe and efficient
movement of vessels that are expected to use the channel. The minimum
channel width will depend on the size and maneuverability of the vessels,
channel shape and alignment, traffic congestion, wind, waves, currents,
visibility, quality and spacing of navigation aids, and whether one-way
or two-way traffic is required. Width of the channel is measured at the
bottom of the slope at the design depth. In accordance with Section 5 of
the Rivers and Harbors Act approved on March 4, 1915, “. . . . the channel
dimensions specified shall be understood to admit of such increases at
entrances, bends, sidings and turning places as may be necessary to allow
free movement of boats.’’Channel widths have to provide for the width
of the maneuvering lane, clearances between vessels when passing, and
bank clearances, particularly in restricted channels. Additional clearances
will be required in channel entrances and in channel bends. The elements
of channel width analysis are shown in Figure 8-1.
The bank clearance width, maneuvering lane width, and ship clearance
width are expressed as multiples of the ship beam, as shown in Tables 8-1
through 8-7. For example, in Table 8-1, the maneuvering lane width for
a vessel with good controllability in a straight channel would be 160% of
the beam, or 1.6B. If the design vessel has a beam (B) of 100 ft, then the
maneuvering lane width would be 160 ft (1.6B).
The maneuvering lane is that portion of the channel width within which
the vessel might deviate from a straight line without encroaching on the
safe bank clearance or entering a zone that would cause danger to passing
ships.
63
64 SHIP CHANNEL DESIGN AND OPERATION
Vessel Controllability
Channels with
Location Very Good Good Poor Yawing Forces
∗
Maneuvering lane, 160(1.6B) 180(1.8B) 200(2.0B) Judgment
straight channel
Bend, 26-degree turn 325(3.25B) 370(3.7B) 415(4.15B) ∗ Judgment
Bend, 40-degree turn 385(3.85B) 440(4.4B) 490(4.9B) ∗ Judgment
Ship clearance 80(0.8B) 80(0.8B) 80(0.8B) 100 but not less
than 100 feet
Bank clearance 60(0.6B) 60 plus 60 plus 150(1.5B)
(0.6+B) (0.6+B)
∗
Judgment will have to be based on local conditions at each project.
FIGURE 8-2. Two Lakers Passing in the St. Clair River, Michigan
(COE, Digital Visual Library).
66 SHIP CHANNEL DESIGN AND OPERATION
FIGURE 8-3. 1,000-Foot Laker in the Rock-Cut Portion of the St. Mary’s River,
Michigan (COE–Digital Visual Library).
depth. The current canal dimensions are 197-ft bottom width and 58-ft
depth with several passing segments. The long-term plan is to continue
deepening the canal to an eventual depth of 92 ft.
Both preliminary and final designs normally assume that the vessel (or
vessels) are guided by a competent pilot or captain and that the vessel is in
good operational condition (i.e., it has had no vessel breakdowns). How-
ever, simulations can be used to evaluate blackout (breakdown) scenarios
to investigate how serious the consequences could be.
The U.S. Army Corps of Engineers used the values presented in Ta-
ble 8-1 for preliminary design and final design from the 1960s until the
development of computer simulation models in the 1980s.
These values were first presented in Report No. 3 of the Committee on
Tidal Hydraulics, U.S. Army Corps of Engineers, May 1965, “Evaluation
of Present State of Knowledge of Factors Affecting Tidal Hydraulics and
Related Phenomena.’’These values were again presented in EM 1110-2-
1613, Hydraulic Design of Deep-Draft Navigation Projects, April 8, 1983.
Some recent work by the Corps (2nd Ed of EM 1112-1613, 2002, Draft
awaiting publication) using information generated from ship simulation
studies suggested the minimum channel widths presented in Table 8-2.
The canal- and trench-type channels are shown in Figure 8-4.
FIGURE 8-4. Canal and Trench Type Channels (EM 1110-2-1613, 2002 Draft).
CHANNEL WIDTHS 69
TABLE 8-3. Basic Maneuvering Lane Width (PIANC, 1997, page 20).
8.7.1 General
The swept path of a ship that is making a turn is wider than its swept
path in a straight channel simply because of the ship’s geometry. Experience
has shown that controllability of a ship while it is turning is degraded
compared to its maneuverability in a straight channel, thus causing a wider
swept path. The width of the swept path is dependent on the following
factors:
r Ship yaw angle when turning
r Length and beam of the ship
r Ship rudder angle
r Location and spacing of aids to navigation in the turn
r Local current and other environmental conditions
Outer Channel
Width Vessel Exposed to Inner Channel
WI Speed Open Water Protected Water
Outer Channel
Width Vessel Exposed to Inner Channel
WI Speed Open Water Protected Water
Channel
Maneuvering Ship Maneuvering Total
Method Traffic Bank Lane Clear Lane Bank Width
FIGURE 8-5. Channel Width Increase in Turns (EM 1110-2-1613, 2002 Draft).
74 SHIP CHANNEL DESIGN AND OPERATION
0–10 0 0 Angle
10–25 3–5 2.0–1.0 Cutoff
25–35 5–7 1.0–0.7 Apex
35–50 7–10 0.7–0.5 Curved
>50 >10 0.5 Circle
STRAIGHT SEGMENTS CURVED SEGMENTS
S = 25° − 35°
S ≤ 10°
W
+W
∆W
S = 10° − 25° W
W
W
ANGLE TURN R
wW W+∆W ∆W = WIDTH INCREASE
∆W+W R−
2
W+∆W
R+
W ∆W = WIDTH INCREASE 2
R CURVED TURN
S = 25° − 35° S > 50°
75
W
∆W + W CUTOFF TURN
W
∆W = WIDTH INCREASE ∆W + W
w
W
L
L
∆W = WIDTH INCREASE
R R
W + ∆W > W
APEX TURN
CIRCLE TURN
FIGURE 8-6. Recommended Channel Turn Configurations (EM 1110-2-1613, 2002 Draft).
76 SHIP CHANNEL DESIGN AND OPERATION
Preliminary channel width guidance given in Table 8-7 for the Corps
1983 method indicates minimum channel width of 5.2B for two-way traf-
fic with ideal conditions. This would result in the following preliminary
channel design width:
156 + 140
Phase I Average Beam Width = 148 ft
2
Preliminary Channel Width 148 × 5.2 = 769.6 ft
173 + 140
Phase II Average Beam Width = 157 ft
2
Preliminary Channel Width 157 × 5.2 = 816.4 ft
CHANNEL WIDTHS 77
The simulations show that the Phase I 530-ft wide and Phase II 600-ft
wide channels were adequate for safe two-way vessel traffic. Therefore,
considerable channel excavation was saved; however, this was only after
numerous ship simulation runs using local pilots. Additional information
on ship simulation studies and the Houston ship channel enlargement
studies is presented in Chapter 15.
This page intentionally left blank
Chapter 9
SEDIMENTATION
and silts and clays carried as suspended load. When the project channel in-
cludes the zone in which rivers enter embayments, the coarse and medium
sands and even some of the fine sands and silts may deposit as flow veloc-
ities are reduced below the velocity necessary to maintain motion of the
sediment particles. These deposits of sand and silt are often in the form of
delta-shaped shoals that recur annually, and are the reason why mainte-
nance dredging for control is required. The finer sands and silts usually
will be deposited in the lower reaches of the navigation project, but the
deposition usually will be distributed over a fairly long reach of the chan-
nel. High stage-discharge events may alter the pattern of deposition from
time to time and distribute the coarser particles over a longer reach of the
channel. Deposition of clay particles depends on the hydrodynamics and
water characteristics of the lower reaches of the navigation project. If the
project is in an estuarine setting in which salty water from the ocean can
mix with the sediment-carrying riverine waters (e.g., Savannah Harbor)
a phenomenon known as flocculation occurs, whereby clay particles ag-
gregate into larger and heavier flocs that are likely to deposit. In some
instances, very heavy concentrations of flocs remain in suspension in a
layer near the bottom. This is referred to as fluff or fluid mud. Before per-
manent deposition of clay sediments, which is a time-dependent process,
the tidal hydrodynamics of an estuarine system tend to concentrate the
location of the flocs. If the estuarine system is of the stratified type (i.e.,
there is a well-defined saltwater layer underlying the freshwater layer) the
bulk of the clay-particle shoals will be concentrated in a zone mapping the
upstream intrusion of the saltwater layer. If the saltwater-freshwater inter-
face is less defined, the clay-particle shoals will be distributed more widely
through the middle and lower reaches of the project. In nonsaltwater set-
tings, such as the Great Lakes, the clay particles may remain in suspension
and be introduced into the lake region as suspended load. Maintenance
dredging is almost always required to maintain channel depths and widths
throughout the areas of clay particle deposition.
In cases in which the deep-draft project extends well upriver (above the
zone of flow reversal), such as the Columbia River or the lower Mississippi
River, deposition of medium to coarse sands occurs in the river crossings,
with most of the fine sand and silt moved downstream to estuarine or
coastal zones. Not all river crossings along a navigation project require
maintenance dredging. In many cases, the minimum crossing depth that
occurs naturally over a water year is greater than the project depth. For
example, of the several river crossings that exist on the lower Mississippi
River from Baton Rouge, Louisiana, downstream to the Head of Passes,
SEDIMENTATION 81
a distance of about 225 river miles, only about 7 of the 225 miles require
annual maintenance dredging. Of course, if the project were deepened, the
number of crossings requiring maintenance dredging would most likely
increase.
Sediments are introduced into the navigation project from the littoral
systems that exist in all lakes and oceans. Near shore, currents driven by
waves, wind, or tides cause sediment particles (usually medium to fine
sands but occasionally clays and silts) to be moved along the shore. As
the sand-size sediments reach the deeper waters of the navigation project,
deposition occurs in and near the entrance channel. Clays entering from
the lower end may be transported upstream by estuarine circulation. Struc-
tures such as jetties are used to trap the sands and keep shoals from forming
in the navigation project. A sand-bypassing arrangement may be necessary
to maintain the trapping capability of the jetty structures and to minimize
damage to adjacent beaches that interruption of the littoral process usually
causes. The planner/designer is required to study and develop predictions
of erosion and accretion for a distance of 10 miles on either side of an en-
trance channel improvement project.
be stressed that both physical and numerical models rely heavily on proto-
type observations; therefore, if model studies are anticipated, the lead time
and resources must be provided to collect the quality and quantity of data
necessary to support these studies. In some cases, combinations of the
various techniques that involve the application of physical and numerical
models may be used, as well as prototype data and analytical procedures
to take advantage of the strong points of each technique.
Sediment budget and shoaling studies are needed for before- and
after-construction conditions. These studies provide the basis for estimat-
ing maintenance dredging requirements, disposal area locations, training
structures, and entrance sand-bypass assessment. Shoaling rates are also
needed for river expansions caused by port facilities and turning basins.
9.8 SOURCE
10.1 DREDGES
Dredges used for ship-channel dredging fall into two categories: hy-
draulic and mechanical.
Hydraulic dredges use pumps and pipes to pull channel-bottom sed-
iment up to the dredge, where it is held for later disposal or pumped
through a pipeline to a disposal site. Self-propelled hopper dredges and
cutter-head pipeline dredges are the most common hydraulic dredges.
Mechanical dredges, such as clamshell and dipper dredges, lift bottom
sediment using a bucket/crane arrangement.
83
84 SHIP CHANNEL DESIGN AND OPERATION
a.
b.
FIGURE 10-1. Self-propelled Seagoing Hopper Dredge (COE Portland District,
Dredge Biddel).
and twin rudders which provide the required maneuverability. Table 10-1
gives available specifications for vessels in the Corps hopper dredge fleet
at the time of writing (2004). Nongovernment hopper dredges generally
are larger, with capacities of up to 32,000 cu yd.
Operation of a seagoing hopper dredge involves greater effort than
that required for an ordinary ocean cargo vessel, not only because of the
needs of navigation of a self-propelled vessel but also because the needs
DREDGING AND DISPOSAL 85
FIGURE 10-2. Hopper Dredge Splits Its Hull in Gulf of Mexico near Galveston,
Texas (COE, Digital Visual Library).
NORTH
BAY
DAMON W E S T P ORT
PT. PT. CHEHALIS
DISPOSAL HALF
SITE MOON
BAY
GRAYS
HARBOR
S. JETTY
DISPOSAL SITE
OC E A N SOUTH
JETTY
SH O R E S
NORTH
JETTY
FEDERAL
CHANNEL
The two major types of mechanical dredges are the dipper and bucket
dredges. The dipper dredge is basically a barge-mounted power shovel.
It is equipped with a power-driven ladder structure and operated from
a barge-type hull. A schematic drawing of the dipper dredge is shown
in Figure 10-6. A bucket is firmly attached to the ladder structure and is
forcibly thrust into the material to be removed. To increase digging power,
the dredge barge is moored on powered spuds that transfer the weight of
the forward section of the dredge to the bottom. Dipper dredges can work
in depths of up to 50 ft. Although there is a great variability in production
rates, dipper dredges routinely achieve 30 to 60 cycles per hour.
The best use of the dipper dredge is for excavating hard, compacted
materials, rock, or other solid materials after blasting. Although it can be
used to remove most bottom sediments, the violent action of this type of
equipment may cause considerable sediment disturbance and resuspen-
sion during maintenance digging of fine-grained material. There will be a
significant loss of the fine-grained material during the hoisting process. The
dipper dredge is most effective around bridges, docks, wharves, pipelines,
piers, or breakwater structures because it does not require much area to
maneuver; there is little danger of damaging the structures as the dredg-
ing process can be controlled accurately. No provision is made for dredged
material containment or transport, so the dipper dredge must work along-
side the disposal area or be accompanied by disposal barges during the
dredging operation.
The bucket type of dredge is so named because it utilizes a bucket to
excavate the material to be dredged (Figure 10-7). Different types of buckets
can perform various types of dredging. The types of buckets used include
the clamshell, orangepeel, and dragline, and can be quickly changed to suit
operational requirements. The vessel can be positioned and moved within a
limited area using only anchors; however, in most cases, anchors and spuds
90 SHIP CHANNEL DESIGN AND OPERATION
are used to position and move bucket dredges. The material excavated is
placed in scows or hopper barges that are towed to the disposal areas. The
crane is mounted on a flat-bottomed barge, on fixed-shore installations, or
on crawler mounts. Twenty to thirty cycles per hour is typical, but large
variations exist in production rates because of the variability in depths and
materials being excavated. The effective working depth is limited to about
100 ft. Figure 10-8 shows a clamshell dredge in New York Harbor.
10.6 DISPOSAL
r Open ocean
r In-channel at a dispersal location
r Uncontained site in the estuary
r Returned to water column by agitation or overflow method
r marsh
r upland
r island
r aquatic
10.7 SOURCE
Most of the information for this chapter was taken from EM 1110-2-5025.
This page intentionally left blank
Chapter 11
JETTIES
11.1 LAYOUT
11.2 SPACING
11.3 LENGTH
FIGURE 11-1. Coos Bay Jetties, Oregon Coast (COE, Digital Visual Library).
JETTIES 95
11.4 TYPES
FIGURE 11-3. Armor Rock for Yaquina Jetty Repair Work (COE, Portland
District).
FIGURE 11-4. Examples of Concrete Armor Units (EM 1110-2-1100, Part VI,
awaiting publication).
JETTIES 97
FIGURE 11-5. Dolos Armor Units Cast in Tacoma, Washington (COE, North
Pacific Division).
FIGURE 11-6. Cellular Jetty (EM 1110-2-2904, 1986).
11.5 SOURCE
Locks often are an integral part of a ship channel. Locks can (1) provide
flat pools for waterways with elevation changes; (2) prevent flooding from
high water on connecting rivers, storm surges, or high tides; and (3) prevent
salinity intrusion. Locks are used in the following situations:
Table 12-1 lists the ship locks presently operating in the United States.
Some planned changes to these locks include a replacement of the Davis
and Sabine Locks with a single lock that has the same dimensions as the
Poe Lock. Also, the Inner Harbor Lock in New Orleans is scheduled to
be replaced with a 1,200-ft-long and 110-ft-wide lock at the same site. The
Inner Harbor lock planned construction is unique in that lock modules will
be fabricated off-site and floated in by barges. The estimated construction
start date for this project is October 2006. A photo of the existing site is
shown in Figure 12-2.
101
102 SHIP CHANNEL DESIGN AND OPERATION
FIGURE 12-1. Soo Locks at Sault St. Marie, Michigan; Ship Departing from
Poe Lock (COE, Digital Visual Library).
FIGURE 12-2. Inner Harbor Canal Lock (COE, Digital Visual Library).
TABLE 12-1. Ship Locks in the United States.
Minimum
Name/ Width Length Depth on Sill Normal Lift
Year Opened Waterway Location in Feet in Feet in Feet in Feet
Superior
St. Marys River, Mich.
Poe Connection between
1968 Lake Huron and Lake 110 1200 32 22
Superior
St. Marys River, Mich.
Davis Connection between
1914 Lake Huron and Lake 80 1350 23 22
Superior
St. Marys River, Mich.
Sabine Connection between
1919 Lake Huron and Lake 80 1350 23 22
Superior
St. Marys River, Mich.
104 SHIP CHANNEL DESIGN AND OPERATION
The St. Lawrence Seaway/Great Lakes is the most extensive ship chan-
nel and lock system in North America. This navigation system is 2,038 nau-
tical miles long and extends from the Atlantic Ocean to Duluth, Minnesota.
There are 14 locks at 6 different locations for a total lift of 600 ft. The 15
locks between Lake Erie and the Atlantic are 766 ft long, 80 ft wide, and 30
ft of clearance over the gate sill. The maximum size of vessels using these
locks is 740 ft long, 78-ft beam, and 26-ft, 3-in draft.
The four parallel locks at Sault St. Marie, Michigan, are of various sizes;
the largest is the Poe Lock, which is 1,200 ft long, 110 ft wide, and 32 ft
minimum depth over the sill.
In contrast, the Panama Canal locks are 1,000 ft long and 110 ft wide.
The maximum size of ships that use this system is 950 ft long, 105.75-ft
beam, and 39.5-ft draft in fresh water (smaller in the dry season).
Table 12-2 compares these two systems.
This page intentionally left blank
Chapter 13
OTHER PROJECT FEATURES
13.1 GENERAL
This chapter covers ship channel features that are found in some but not
all projects. These features include the following:
1. Turning basins
2. Anchorage areas
3. Salinity barriers
4. Diversion works
5. Bridges
6. Hurricane barriers
7. Sediment traps
8. Training dikes and revetments
9. Port berthing and maneuvering areas
107
108 SHIP CHANNEL DESIGN AND OPERATION
TURNING BASIN
TU
GS 1.2L
TO
1.5L
IP
SH
CURRENT
CHANNEL WIDTH
TURNING BASIN
FUNCTION OF CURRENT
DISTANCE
CURRENT DRAFT
1.5 L + +
13.2.1 Size
The size of the turning basin should provide a minimum turning
diameter of at least 1.2 times the length of the design ship, where prevailing
currents are 0.5 knot or less. Recent simulator studies have shown that
turning basins should provide minimum turning diameters of 1.5 times the
length of the design setup, where tidal currents are less than 1.5 knots. The
turning basin should be elongated along the prevailing current direction
when currents are greater than 1.5 knots and designed according to tests
conducted on a ship simulator (Figure 13-1). Turning operations involving
empty ships or ships with high sail areas and wind speeds of greater than
25 knots should also be designed using a ship simulator.
Where traffic conditions permit, the turning basin should use the
navigation channel as part of the basin area. The shape of the basin is usu-
ally trapezoidal or elongated trapezoidal, with the long side coincident
with the prevailing current direction and the channel edge. The short side
should be at least equal to the design multiple (1.2 or 1.5, depending on the
current) times the ship length. The ends should make angles of 45◦ or less
with the adjacent edge of the channel, depending on local shoaling tend-
encies. Modifications of this shape are acceptable to permit better sediment
flushing characteristics or accommodate local operational considerations.
13.2.2 Depth
Normally, the depth of a turning basin should be equal to the chan-
nel depth leading to or adjacent to the basin proper to prevent confusion,
which could cause grounding accidents. The normal dredging tolerance
and advance maintenance allowance are included in the depth of the turn-
ing basin.
13.2.3 Shoaling
A turning basin will tend to increase shoaling rates above normal chan-
nel rates because of the increase of the channel cross-sectional area, which
modifies current patterns. Increased shoaling in the basin could cause mod-
ifications in shoaling patterns farther downstream or upstream.
13.3 ANCHORAGES
Anchorages are provided near the entrance to some ports for vessels
waiting for berthing space, undergoing repairs, receiving supplies and
crews, waiting for inspection, and lightering off cargo. In cases when a
ship must transit a long navigation channel and encounter heavy traffic
110 SHIP CHANNEL DESIGN AND OPERATION
(the scope of the anchor). The U.S. Navy (1981) calculated a set of tables
giving these required dimensions, from which the following approxima-
tion can be developed for average 50-ft-depth conditions and design ship
lengths of 700 to 1,000 ft:
D/L = 3.0
where
D = diameter of anchor swing in feet
L = ship length in feet
This formula assumes that the length of the anchor-chain swing circle is six
times the depth and that 90 ft of anchor drag occurs. Large free-swinging
anchorages can be expensive to construct and maintain, as sedimentation
frequently becomes a problem. The designer should consider the use of
fixed mooring dolphins, which can substantially reduce the dredging area
costs. Figure 13-2 presents two design anchorage configurations for two
ships with free-swinging and fixed mooring situations.
in San Francisco Bay to reduce possible saltwater migration into the San
Joaquin Delta. A temporary erodible sill was implemented in the Lower
Mississippi River during the 1988 drought to help protect the freshwater
supply of New Orleans. The barrier made from dredged material was
successful (Figure 13-3). For maximum efficiency, the barriers should be
impervious. Rubble-mound structures with an impermeable core and a
curtain of impermeable fabric have been suggested and model-tested for
submerged salinity barriers, but none has been built to date. The barrier
must be submerged low enough to permit safe navigation in the channel;
however, its crest can be higher outside the project limits. Inflatable or
movable barriers can be lowered to permit passage of shipping, then raised
to reduce or eliminate salinity intrusion. Air bubble screens or water jets
also may be used in certain situations to minimize the effects of channel
deepening on saltwater intrusion.
13.6 BRIDGES
13.6.4 Examples
The Golden Gate Bridge, shown in Figure 13-4, is an excellent example
of generous vertical and horizontal clearance for ships. Figure 13-5 shows
a more restricted vertical clearance in the Charleston Harbor, Charleston,
South Carolina. Figure 13-6 shows a restricted horizontal clearance at Coos
Bay, Oregon. The railroad bridge in the background has a center mounted
swing span.
Storm and hurricane surges historically have caused major floods and
damage in Europe. In the United States, structural barriers located near and
across the entrance to rivers, bays, and coastal regions have been proposed,
designed, and, in some cases, built in a number of developed areas. The
following discussion presents important navigational impacts that should
be considered in barrier planning and design.
Hurricane and storm surge barriers are normally located as close to the
ocean as possible to increase the area of protection inside the river or bay.
OTHER PROJECT FEATURES 115
FIGURE 13-4. Golden Gate Bridge Provides Generous Clearance For Ships
[USS Enterprise (Navy Web, chinfo.navy.mil)].
FIGURE 13-6. Inbound Ship in Coos Bay Ship Channel After Passing Through
Railroad Bridge (COE, Portland District).
Sediment traps or deposition basins are areas in the waterway that are
excavated in or near the navigation channel to reduce shoaling in the project
navigation channel and manage the sedimentation processes so that the
project maintenance dredging is conducted in the most cost-effective man-
ner. Navigation projects in both estuarine and littoral environments pro-
vide for sediment traps. The effects of the sediment trap on navigation
should be considered in the design, and trap location should consider the
range of conditions and proposed dredging operations at the sediment
trap. For example, the location of a sediment trap on the outside edge of a
turn may eliminate the bank cushion effect normally used by pilots to as-
sist in turning the ship. The investigation procedures, which use physical
and numerical models of sediment traps for estuarine areas, are outlined
in EM 1110-2-1607.
13.9.1 Dikes
In rivers and waterways with high sediment transport subject to shoal-
ing, training structures frequently are required to help maintain deep-draft
navigable channel depths during low-water season. Several different types
of training dikes have been developed to control navigation channel align-
ments and maintain adequate channel depths, including spur dikes, vane
dikes, longitudinal dikes, and L-head dikes. Training structures usually
are designed to constrict flow at low-water seasons, thus increasing water
currents to help flush sediment from the navigation channel. Longitudinal
dikes extending along the waterway often are used to help guide or direct
currents to reduce shoaling and improve navigation conditions. Dikes are
usually constructed of timber pile clusters, stone, or piling with stone fill.
Refer to EM 1110-2-1611, Layout and Design of Shallow-Draft Waterways for
a more thorough discussion of this topic.
13.9.2 Revetments
Bank erosion caused by currents or wave wash from navigation is
frequently a problem in natural streams and waterways with erodible
banks. Protection from bank erosion with the use of revetments should
be considered during project design. Rock riprap and articulated concrete
mattress have both been used as revetments to control bank erosion. In
most ship channel projects, wind waves and river or tide currents exceed
the erosion power of ship waves. This is because the ship is usually moving
118 SHIP CHANNEL DESIGN AND OPERATION
1. Vessel speed
2. Vessel draft and hull shape
3. Water depth
4. Blockage ratio of ship to channel cross-section
The effects of waves will depend on the height of the wave generated
and the distance between the ship and the smaller boats or shoreline.
Figure 13-7 shows a schematic of the ship wave form.
Figure 13-8 shows a ship-generated wave in the Columbia River channel.
If ship waves will be higher than those occurring naturally from wind
or ocean swell or those created by fast-moving pleasure craft, mitigation
measures may be required. The two most common mitigation measures
are reduced speeds and shore protection. In some cases, it may be practi-
cal to place the navigation channel at a sufficient distance from the shore
so that the waves reaching the shore will not be destructive. Reducing
speed could affect the efficiency of the project and have some effect on the
maneuverability of the vessel. Physical model studies using the vessels
expected to use the channel could provide a more accurate indication of
FIGURE 13-7. Schematic of Ship Wave System (EM 1110-2-1613, 2002 Draft).
OTHER PROJECT FEATURES 119
the wave heights that will be developed under different conditions and
the most effective means of reducing their effects. For example, a reach
of the Sacramento River Deep Water Channel has experienced repetitive
failure of riprap along its levees. A model study indicated that riprap fail-
ure occurred with ship speeds of 7.8 and 8.1 miph, with waterway to ship
cross-sectional area ratios of 4.3 and 6.1, respectively. This indicated that
riprap failure in the Sacramento channel was caused by the stern wave
or bore and subsequent rapid drawdown generated by vessel speeds in
excess of 6.8 miph. It was determined that the average vessel speed in the
channel was 8.4 miph, which induced a stern wave with a 4 ft drawdown
in one minute that could remove filter or embankment material and cause
subsequent failure of the riprap. Restricting the vessel speed to a maxi-
mum of 6.8 miph reduces the stern wave and rapid drawdown and was
considered more practical than enlarging the channel to a value equal to
or greater than seven times the typical vessel cross-sectional area.
Another example of ship wave mitigation is the Lake Washington ship
canal, Seattle, Washington. This confined canal is used by pleasure craft,
commercial fishing vessels, and NOAA ships (over 300 ft long), which are
based in the fresh water of Lake Union. A speed limit of 7 knots is in place
to control ship wave heights. The speed limit is enforced by the Seattle
Police Department.
120 SHIP CHANNEL DESIGN AND OPERATION
123
124 SHIP CHANNEL DESIGN AND OPERATION
FIGURE 13-14. Length and Width of Slips (Piers and Wharves, Military
Handbook 1025/1, October 1987).
operations require all but the smallest tankers to anchor in the main bay
and off-load a substantial part of the cargo into shallower draft tankers that
can be accommodated with the 35-ft-deep channel. The proposed channel
will reduce transportation costs as well as reduce the possibility of oil spills
in San Francisco Bay.
Tests for the base and proposed channel conditions were conducted us-
ing 87,000-dwt partially laden (30-ft draft) and 150,000-dwt partially laden
OTHER PROJECT FEATURES 125
(40-ft draft) tankers, respectively. Both flood and ebb current conditions
were simulated. In addition to ship track plots, several other critical pa-
rameters were plotted and studied, such as ship speed and docking posture
as it approaches the Long Wharf. The main container ship used to simulate
future size ships calling at Richmond Harbor was 810 ft long and 106-ft
beam loaded to a 32-ft draft. A smaller container ship with 638-ft length
and 100-ft beam also was used to simulate present-day ship sizes. All sim-
ulations were run with a 20-knot wind blowing from the southwest.
Test results indicate that it is very important to reduce tanker speed in
Southampton Channel for inbound transits to about 5 knots before starting
the large right turn into the maneuvering area. Acceptable docking pos-
tures can be achieved for both existing and proposed channel conditions
under both ebb and flood tide so as to allow safe tanker docking into the
Long Wharf. The container ship tests indicate that it is reasonably safe
to maneuver around the point and line up with the Richmond Harbor
entrance channel on flood tide. Ebb tide conditions require very careful
126 SHIP CHANNEL DESIGN AND OPERATION
control of ship speed and position to execute a safe turn in the maneuver-
ing area when piloting the 8l0-ft container ship. The 638-ft container ship
was much easier to maneuver around the point.
Figure 13-15 shows various configurations of the maneuvering areas.
Figure 13-16 shows typical simulation runs.
Chapter 14
ENVIRONMENTAL CONSIDERATIONS
14.1 GENERAL
14.3 DREDGING
The three main methods of disposal are: (1) open water, (2) upland or
off channel, and (3) agitation.
A A A D A
Vertical Lift Span Bridge (Open) Vertical Lift Span Bridge (Closed)
G F
F F
G
A A A
A A A
Double Opening Swing Bridge Double Opening Swing Bridge
(Open) (Closed)
siltation rates, reduced levels of available light, and other effects of elevated
suspended sediment concentrations.
1. The loss of benthic habitat and benthos in the area covered by the
structure(s)
2. The displacement of benthos as a result of scouring effects
3. The development of plant and animal communities on the substratum
provided by the structure(s)
4. The altered transport of egg and larval stages of fish and shellfish
through coastal inlets
5. The altered movement patterns of juvenile and adult stages of fish
and shellfish
14.7 SOURCE
15.1 GENERAL
Physical scale models are used to investigate flow patterns when com-
plicated three-dimensional (3-D) effects are necessary. Recent dramatic
advances in computer hardware and software have led to the use of
numerical models to replace and supplement physical model studies.
The following types of navigation investigations can be conducted with
physical models:
133
134 SHIP CHANNEL DESIGN AND OPERATION
ASCE Manual No. 97, Hydraulic Modeling Concepts and Practice (2000),
provides details of physical model design, operation, and application.
This model emerged in the 1980s as the best design tool to determine
safe channel widths and alignments. This model enables designers to study
the interactions of ships with the currents, wind, and banks as they are ma-
neuvered through navigation channels and waterways. Simulators allow
the use of both automatic controlled vessel navigation as well as navi-
gation with human pilots with realistic ship/tow controls in a simulated
ship-bridge environment. A test scenario is developed for channel design
dimension/alignment alternatives and conditions, such as flow rates, tidal
conditions, wind, visibility, and navigation marking. Test runs are con-
ducted through the simulated conditions, and can be conducted in real
time, simulating the prototype vessel transit speed or fast time (similar to
fast forward on a VCR), allowing for more runs. As the vessel is navigated
through the test areas, it is subjected to forces resulting from environmen-
tal factors and the vessel’s motion is determined one step at a time. As the
vessel progresses through the scene or changes its orientation, a computer-
generated view from the pilot’s window is displayed in color on a large
screen (Figure 15-1). This allows a pilot to observe the vessel in motion rel-
ative to physical objects as would occur in actual vessel transit. In addition,
the simulator generates a radar image of the vessel’s location. As the ves-
sel progresses through the channel, the scene is updated periodically. Key
navigation information also can be displayed on a precision navigation
136 SHIP CHANNEL DESIGN AND OPERATION
FIGURE 15-2, Top and Bottom: “Texas Chicken” Maneuver at Barbour’s Cut
on the Houston Ship Channel; approach and passing sequence. (U.S. Coast
Guard Digital). (Continued)
138 SHIP CHANNEL DESIGN AND OPERATION
Tests were conducted in the upper reach where the channel has several
bends, as shown in Figure 15-3.
Figure 15-4 shows a typical simulation run for the Phase II condition.
The simulation results confirmed the adequacy of Phase I (530 ft wide)
and Phase II (600 ft wide), and recommended some relatively minor mod-
ifications on the bends.
Construction started in 1999 on this 1/2-billion-dollar channel dredging
project.
Details of the Houston Ship Channel simulation study can be found in
the U.S. Army Corps of Engineers WES Technical Report HL-94-3, Ship
Navigation Simulation Study, Houston–Galveston Navigation Channels,
Texas, Report 2, Houston Ship Channel, Bayou Segment, April 1994.
SAN JACINTO RIVER
CARPENTER BAYOU
SAN JACINTO
STATE PARK
GO
AT
IS
LA
ILL
ND
RG
S
CA PEGGY’S LAKE
H EM
Y -C
OX EXXON TERMINAL
JOGGY BAYOU
139
ALEXANDER ISLAND
BAYTOWN BRIDGE
SPILM
ANS IS HO
LAND G
IS
LA
ND
CUT
OURS
BARB
AT
KI
NS
PHASE I CHANNEL
ON
EXISTING CHANNEL MORGANS POINT
POWER LINE TOWERS
IS
LA
SCALE IN FEET
ND
0 5000 10,000
FIGURE 15-3. Houston Ship Channel, Bayou Section Project Map (TR HL-94-3).
R
VE
RI
O
NT
CI
JA
N
SA
PAS
SING LYNCHBURG
ARE
A
140
101-F
HA
T CL
EAR
IC
ANC
E
EI
SAN JACINTO
AS
LS
STATE PARK ESSE
EN V
PH
WE
T BET
444 F
E
ANC
EAR
T CL
202-F
A traffic flow model (SHIPRISK) has been developed by the Delft Uni-
versity of Technology and Marine Safety Port of Rotterdam to assess the
comparative safety of port channel configuration and traffic management
scenarios.
This model is particularly applicable to existing ports with vessel track-
ing systems (VTS).
Two models are used for this simulation:
16.1 GENERAL
All vessels, but particularly long cargo ships with vertical sides and a
blunt bow, have difficulty turning in ice. Because very few prototype tests
have been made to determine turning radii in ice, no specific recommen-
dations can be made for channel widths in bends or turning basins. Local
conditions of ice thickness and extent of coverage will be necessary to de-
velop adequate channel designs. It is important to keep turning basins
clear to allow ship maneuvers and prevent damage to hulls. It should be
noted that conventional commercial ships not specifically designed for ice
operation usually are unable to leave the navigation channel through an
ice cover once it has been created. Furthermore, repeated transits through
the channel may lead to accumulation of brash ice and the formation of
underwater ice ridges along the edges of the channel.
143
144 SHIP CHANNEL DESIGN AND OPERATION
Line bubblers have been used with some success in the Great Lakes. Ad-
ditional depth might be required for the installation of a bubbler system
unless the channel is sufficiently wide to permit the placement of the bub-
bler line outside of the ship channel. Bubbler systems do not provide ice
clearing but do create a line of weakness which makes ice breaking easier.
Channels should be aligned so that navigation can rely on range lights and
markers rather than floating navigation aids, which can be covered by ice
or displaced by ice movements.
In addition to the navigation impact of ice formation on the surface of
the water, under certain conditions ice can accumulate on the bottom of
vessel hulls. As a vessel progresses at slow speed through brash ice, pieces
become submerged and can be entrained underneath the hull, and the
relative water speed is insufficient to flush the ice. This process is enhanced
when the vessel’s bow is sloped or raked, as for a barge on inland waters
or when an oceangoing ship is empty. Under extremely cold conditions,
the brash ice can adhere to the hull of an empty or near-empty vessel.
This is because of heat loss as the result of air contact through the sparsely
loaded hold. The result of this is increased draft and resistance causing
maneuvering difficulties.
16.3 LOCKS
to indicate any change in the rate of shore erosion resulting from ice.
Ice formed on a shore or riverbank could isolate and protect the shore.
However, ice formation may cause damage to training and stabilization
structures or the shoreline by gouging, removing protective vegetation, or
entraining sediment within the ice. Ice cover tends to damp ship-induced
bow and stem waves, which have relatively short periods. However, ice
cover has little effect on relatively long water-level fluctuations, such as
those resulting from drawdown, which can be significant, particularly in
restricted channels. Greater power will be required to move a ship through
ice, and, occasionally, a ship will get stuck with its screws turning with max-
imum power. High power and propeller rotation will tend to increase scour
and bottom sediment movement; these should be considered, particularly
when the ship is above underwater cable and pipeline crossings.
16.5 VIBRATION
16.7 SOURCE
17.1 GENERAL
17.2 CHANNELS
147
148 SHIP CHANNEL DESIGN AND OPERATION
17.3 STRUCTURES
The construction cost generally will increase as the design level in-
creases.
Maintenance cost generally decreases as design level increases. Replace-
ment cost is less frequent, and the average annual costs of replacement are
less as design levels increase. Benefits generally increase as design lev-
els increase because frequency of losses decreases. For example, a jetty
with a low crest may overtop occasionally and force closure of the channel
because of unsafe wave conditions. The severity or magnitude of design
events (such as wave heights, water levels, or ice thickness) has a statisti-
cal distribution that can be ordered into a probability of exceedance. The
exceedance probability is plotted against the design level (Figure 17-1).
A series of project designs and cost estimates are developed for various
design levels. For example, a jetty could be designed for wave heights of
14, 16, 18, and 20 ft. Each wave height (design level) would have an ex-
ceedance probability similar to that shown in Figure 17-1. In the absence of
prototype information, average annual maintenance is often estimated to
be 1% of the initial construction cost. However, this approach does not con-
sider exceedance probability of the design level. A more realistic approach
would be to estimate average annual maintenance cost by multiplying the
exceedance probability of the design level by the construction first cost.
This maintenance cost should be compared with maintenance of similar
existing projects to assure realistic values. Average annual replacement
costs are obtained by estimating the cost of replacement and the year re-
quired. The current value of the replacement cost is converted to average
annual cost by using an appropriate interest rate and economic project life.
The project cost curves generally are similar to those shown in Figure 17-2.
17.4 BENEFITS
Project benefits are compared with project costs to determine the eco-
nomic optimum design. Achievable project benefits are developed through
economic studies, assuming that no constraints exist because of the de-
sign level. Achievable benefits are reduced by the benefits lost because the
design level is exceeded. Lost benefits are computed by multiplying the
annual achievable benefits by the probability of navigation loss for each
design studied. The results are typically displayed as shown in Figure 17-3.
A comparison of total project cost, actual benefits, and design level is shown
in Figure 17-4. The optimum economic design level occurs when net ben-
efits are at the maximum point, as shown in Figure 17-4. Normally, the
150 SHIP CHANNEL DESIGN AND OPERATION
FIGURE 17-3. Benefits versus Design Level (ASCE Manual No. 80).
design level associated with the maximum net benefits will be selected for
project design. However, if the net benefit level is not well defined, it may
be prudent to select a higher design level to increase the factor of safety.
FIGURE 17-4. Cost and Benefits versus Design Level (ASCE Manual No. 80).
ECONOMIC OPTIMUM DESIGN 151
shoaling tendencies. Deeper channels will permit the use of larger ships,
which are more economical to operate. Some ships with a deeper draft and
greater cargo loading could use the channel; this may eliminate or reduce
the need for offloading (lighterage) some of the cargo before proceeding
to the port. Benefits are evaluated by determining the transportation costs
per ton of commodity for each increment of channel depth. This evaluation
must consider trends in shipbuilding to anticipate future ship sizes and
type of ship fleet that will be using the channel. Transportation costs are
based on the annual operating costs for each type of ship, including fixed
costs and annual operating expenses.
The basic economic benefits from navigation projects include the reduc-
tion of costs required to transport commodities and the increase in the value
of output for goods and services. These benefits usually are based on costs
not included with the proposed project improvements. Project benefits also
may be “lost opportunity” costs because of unimproved or undeveloped
navigation channels. Specific transportation savings may result from the
following:
17.7 SOURCE
18.1 GENERAL
1. Dredging
2. Structures
3. Relocations
wish to replace the pipelines, a new or modified permit from the Army
Corps of Engineers is required.
Another constraint on the construction schedule is availability of funds.
The Houston ship channel project had 12 separate contracts spread over
6 years. This helped spread the project fund requirement of $719,090,000
over 6 budget cycles.
Construction schedules and activities should always consider the exist-
ing channel traffic. Delays and hazards to navigation need to be minimized.
18.2 SOURCE
Weather predictions
Water levels
Hazards to navigation
Ship movement
Ice conditions
Other relevant navigational information
NOAA provides weather and channel hydraulic (tide and current) predic-
tions. The Coast Guard disseminates information on aids to navigation,
hazards, and other maritime-related topics. This information is available
on the World Wide Web and on marine radio channels. More information
on these subjects can be found in Chapters 20 and 21.
Other channel condition systems are implemented at the port level. The
Port of Portland, Oregon, has in place a system called LOADMX, which
monitors and reports actual and forecasted river levels. The system allows
pilots and ship masters to optimize loaded draft by predicting river and
tide levels at various points during the 100-mile long voyage on the river
(Beeman, 1985; PIANC Bulletin No. 51).
The Coast Guard provides Vessel Traffic Services (VTS) on eight water-
ways in the continental United States and Alaska. These systems monitor
ship movements and provide this information to other vessels in the sys-
tem. Operational VTS sites for ship channels can be found at the following
locations:
157
158 SHIP CHANNEL DESIGN AND OPERATION
19.3 PILOTAGE
Pilots are required in every major seaport in the world. They are re-
sponsible for navigating ships safely through the ocean entrance channel.
Pilots usually go through a lengthy apprentice period, during which they
become knowledgeable about local conditions, as well as proficient in ship-
handling.
Many ports have specialized pilots to direct the ship in different seg-
ments of the ship channel. The licensed Columbia River bar pilots board
an incoming ship in the ocean, and are responsible for navigating the
vessel across the 17-mile stretch of river mouth. The bar pilot can delay
the ship passage if weather conditions are too severe for a safe crossing.
After crossing the river mouth, the bar pilot transfers pilotage to a licensed
Columbia River pilot. River pilots are responsible for navigating vessels to
their final destination on the 100-mile shipping channel. River pilots also
determine the draft of ships that may safely navigate the river.
The pilots of the State of Maryland are examples of specialized pilots.
The Chesapeake Bay is the longest pilotage route in the U.S. East Coast; it
is nearly 200 miles long. Each ship engaged in foreign trade coming into
a Maryland port is required to take on a local ship-handling specialist to
navigate the vessel safely into port. There are both bay pilots and docking
pilots. Docking pilots are specialized pilots who are uniquely trained to
maneuver commercial vessels in close quarters during docking, undock-
ing, and shiftings (with tugboat assistance) within Maryland waters.
Pilots are a valuable resource in channel design. Because of their local
knowledge, they can identify problem areas, and are generally asked to
participate in ship simulation studies for navigation channel enlargement
projects.
Ship channel maintenance falls into two categories: structure repair and
channel dredging. Structural repairs are needed on a periodic basis because
OPERATIONS AND MAINTENANCE 159
FIGURE 19-1. Yaquina Bay, Oregon Jetty Repair (COE, Portland District).
of the constant attack of waves, currents, debris, and ice. For example, in
the U.S. West Coast, wave attack is fairly uniform year-round. A typical
12-second-period swell can produce 7,200 wave impacts per day on a jetty.
After several years, this constant attack will degrade the jetty, and the outer
end wall will need periodic rebuilding. An example of jetty repair is shown
in Figure 19-1.
Other ship channel structures that need periodic repair are shoreline
revetment and river training structures that are meant to confine flow to
keep sediment moving. Floating debris and ice often cause damage to these
structures.
Dredging is usually the most costly normal maintenance item. The lo-
cation and volume of this work can often be predicted based on past expe-
rience. Usually, the same river-crossing shoal will require dredging at the
same rate, unless an extreme event occurs. Dredging equipment, practice,
and disposal alternatives are presented in Chapter 10.
FIGURE 19-2. Mount St. Helens Erupting (COE, Digital Visual Library).
19.5.1 Volcanoes
The Mount St. Helens volcanic eruption on May 18, 1980 (Figure 19-2),
resulted in massive sediment and debris flows into the Toutle River, which
is a tributary of the Columbia River. This sediment clogged the Columbia
River ship channel and required extensive dredging before project depths
were reestablished.
A long-term problem remained, that is, increased sediment flow into
the ship channel from the massive sediment sources (i.e., Toutle River
and the slopes of Mt. St. Helens). The solution was twofold; dredge the
Toutle River to preeruption levels (to return the river to its original flood
level of protection) and construct a sediment retention structure in the
North Fork of the Toutle River. This roller-compacted embankment with
a multilevel outlet is working, and the high-level ungated spillway has
been successful in stopping large sediment movement to the lower Toutle
River and Columbia River ship channel. The sediment retention structure
is shown in Figure 19-3.
19.5.2 Earthquake
The 1964 earthquake in Alaska caused a shift in the ocean floor (both
upheaval and subsidence). The shift generated a tsunami and several land-
slides. This 9.2 magnitude quake was the second most powerful earthquake
OPERATIONS AND MAINTENANCE 161
FIGURE 19-3. Mount St. Helens Sediment Retention Structure (COE, Digital
Visual Library).
ever recorded. The consequences in Alaska were 115 dead and $84 million
in damages in 1964 dollars. The damages would be equivalent to $2 billion
in 2004 dollars. The effects of the resulting tsunami was felt as far away as
San Francisco, California, and Hawaii. The tsunami caused a temporary
hazard to ship traffic, as shown in Figure 19-4. The fishing boat in the photo
was deposited by the tsunami from the Kodiak boat harbor to Third Street.
The Volkswagen near the bow gives an idea of the ship size. The majority of
the buildings on First, Second, and Third Streets were destroyed. A longer-
term navigation problem was caused by the ocean floor shift, which made
all the nautical charts in the region invalid. The fault line ran north and
south through Prince William Sound. East of the fault line, the bottom had
uplift with a maximum of about 30 ft near Montague Island. Figure 19-5
shows barnacles on the sea floor that had been below the lowest tide level
before the earthquake.
The Alaska town of Cordova in Prince William Sound experienced about
6 ft of uplift, as can be seen in Figure 19-6.
The immediate need for chart revisions was achieved by establishing
tide gauges near benchmarks that were used in previous hydrographic
surveys. Because the sea level had not changed, running a level line from
the gauge to the benchmark would determine a new elevation for the
benchmark. With this knowledge, charts could be revised for navigation
162 SHIP CHANNEL DESIGN AND OPERATION
19.5.4 Hurricanes
Some of the Gulf Coast channels extend several miles out to sea with
no protective jetties. These channels are vulnerable to heavy shoaling from
passing hurricanes. Large hurricane-generated waves and strong currents
can easily deposit sediment in deeper ship channels, a convenient sediment
trap.
19.6 ACCIDENTS
set free. Six tug boats were used to free the vessel when it ran aground in
the Mississippi River near the Head of Passes.
The agency or agencies responsible for the operation of a ship channel
normally have an accident response plan in place, for rapid and appropriate
action. This action includes rescue, vessel removal to reopen the channel,
and pollution clean up.
1. Changes and costs: The predicted physical changes with time after
construction and the anticipated O&M costs.
2. Surveillance plan: This plan covers minimum monitoring of the
project performance to verify safety and efficiency. Included are the
type and frequency of surveys, data collection, and a periodic inspec-
tion schedule. Hydrographic surveys, beach profiles, tide and wave
records, and jetty stability data collection costs should be used to
determine operation costs.
3. Project performance assessment: An assessment of the project perfor-
mance is desirable. Inspections and analysis of comparative surveys
can be used to verify design information, such as rates of erosion,
shoaling, and jetty deterioration, as predicted during the design
effort.
4. Accident or Emergency Response plan. This plan would identify re-
sponsibilities, communication links, and actions to be taken in the
event of accidents, oil spills, or other problems that could compro-
mise the waterway operation.
Chapter 20
COAST GUARD ACTIVITIES THAT
SUPPORT NAVIGATION
20.1 GENERAL
The Coast Guard carries out numerous safety missions and tasks, in-
cluding port safety and security, waterways management, and commercial
vessel safety. It is responsible for providing a safe, efficient, and navigable
waterway system to support domestic commerce, international trade, and
military sealift requirements for national defense. The services the Coast
Guard provides include long- and short-range aids to navigation; charting;
tide/current/pilotage information through “Notices to Mariners’’; vessel
traffic services; domestic and international icebreaking and patrol services;
technical assistance and advice; vessel safety standards and inspection;
and bridge administration standards and inspection. These services can be
consolidated into five fundamental roles:
Maritime Mobility
Maritime Safety
Maritime Security
National Defense
Protection of Natural Resources
Many Coast Guard missions benefit more than one of its roles. For exam-
ple, whereas the aids to navigation mission primarily supports the service’s
maritime mobility role by facilitating the movement of people and goods,
the system of aids also supports the Coast Guard’s role of keeping maritime
safety and protecting natural resources by preventing accidents.
FIGURE 20-1. U.S. Aids to Navigation. (See also Plate 1, following page 130.)
170
FIGURE 20-2. Aids to Navigation Placement. (See also Plate 2, following page 130.)
COAST GUARD ACTIVITIES THAT SUPPORT NAVIGATION 171
FIGURE 20-3. Visual Buoyage Guide. (See also Plate 3, following page 130.)
20.2.3.1 River Bank Names. When travel is downstream, the banks are
named “right’’ and “left.’’ The right bank has green aids and the left bank
has red aids; thus, the west bank of the Mississippi is its right bank and
has green aids. To avoid confusion, commercial river traffic often calls the
right bank the right descending bank, and the left bank, the left descending
bank.
COAST GUARD ACTIVITIES THAT SUPPORT NAVIGATION 173
20.2.3.2 Mile Markers. These markers are some of the most useful aids
on a river. They are attached to daybeacons or displayed in other easily
seen places. Because the U.S. Corps of Engineers erects them, they show
distance in statute miles rather than in nautical miles. With the exception
of the Ohio River, mile markers indicate the distance upstream from the
mouth of a river. Ohio River markers start at its headwaters and indicate
the distance downstream. Mile Markers also help a vessel operator locate
his/her position on a river chart.
14th
20.2.5.1 East Coast Domestic Ice Breaking. The Coast Guard deploys
14 vessels that are designed primarily to perform icebreaking services
along East Coast waterways between Maine and Virginia. Two 140-foot
icebreaking tugs are stationed in New Jersey and another is stationed in
Rockland, Maine. These small cutters are specially configured for icebreak-
ing along U.S. coastal waters. These vessels incorporate an advanced hull
design and engineering plant, along with a “bubbler’’ hull air lubrication
175
FIGURE 20-5. Coast Guard Polar Icebreaker Polar Star (WAGB 10) (U.S. Coast Guard Digital Library).
176 SHIP CHANNEL DESIGN AND OPERATION
FIGURE 20-6. CGC Sturgeon Bay USCG (U.S. Coast Guard Digital Library).
FIGURE 20-7. Coast Guard Cutters Biscayne Bay (WTGB 104) and Katmai
Bay (WTGB 101) Break Ice in the Straits of Mackinac (U.S. Coast Guard
Digital Library).
Act of 1972. To implement these statutes, the Coast Guard has published
the following regulations in 33 CFR Chapter I, Subchapter J (Bridges):
1. Part 114—General;
2. Part 115—Bridge Locations and Clearances; Administrative Proce-
dures;
3. Part 116—Alteration of Obstructive Bridges;
4. Part 117—Drawbridge Operation Regulations; and
5. Part 118—Lighting of Bridges.
20.2.6.1 Bridge Lighting and Other Signals. In U.S. waters, the Coast
Guard prescribes certain combinations of fixed lights for bridges and struc-
tures extending over waterways (Figure 20-8). In general, red lights (A) are
used to mark piers and supports and green lights (B) mark the centerline of
the navigable channel through a fixed bridge. If there is more than one
channel through the bridge, the preferred route is marked by three white
lights (C) placed vertically. Red lights (D) also are used on some lift bridges
to indicate the lift is closed, and green lights (E) are used to indicate that
the lift is open to vessel traffic. Double-opening swing bridges are lighted
COAST GUARD ACTIVITIES THAT SUPPORT NAVIGATION 179
B B
C
Lift
Open Spans Open
B
Closed Closed
A A D
(Main Channel)
A A
Fixed Bridge Double Leaf (Lift) Bascule Bridge
A A A D A
Vertical Lift Span Bridge (Open) Vertical Lift Span Bridge (Closed)
G F
F F
G
A A A
A A A
Double Opening Swing Bridge Double Opening Swing Bridge
(Open) (Closed)
with three lanterns on top of the span structure; when viewed from an ap-
proaching vessel, the swing span when closed will display three red lights
(F) and when open for navigation will display two green lights (G).
Clearance gauges are extremely valuable to vessel operators because
they indicate the vertical distance (clearance) between the “low steel’’ of
the bridge channel span and the waterline. (They do not indicate the depth
of water under the bridge.) These gauges, located on the right side of the
channel facing approaching vessels, are permanently fixed to the bridge
pier or structure. Each gauge is marked by black numbers and foot marks
(lines) on a white background board.
Further information on drawbridge regulations and opening signals
for bridges over the Navigable Waterway can be found in the U.S. Coast
Pilot books.
VTIS LA/LB
20.2.7.0.1 VTS New York. The control center is located at Fort Wadsworth
in Staten Island, New York. In 1995, Coast Guard Activities, New York,
COAST GUARD ACTIVITIES THAT SUPPORT NAVIGATION 181
20.2.7.0.2 VTS San Francisco. The San Francisco Vessel Traffic Center is lo-
cated at Yerba Buena Island in San Francisco Bay. VTS San Francisco is
responsible for the safety of vessel movements along approximately 133
miles of waterway from offshore to the ports of Stockton and Sacramento.
On May 3, 1995, federal regulations established regulated navigation areas
within the San Francisco Bay Region. These regulations, developed with
input from the Harbor Safety Committee of the San Francisco Bay Region,
were designed to improve navigation safety by organizing traffic flow pat-
terns; reducing meeting, crossing, and overtaking situations in constricted
channels; and limiting vessels’ speeds. VTS San Francisco also operates
an Offshore Vessel Movement Reporting System (OVMRS), which is com-
pletely voluntary and operates using a broadcast system with information
provided by participants.
20.2.7.0.4 VTS Puget Sound. The Vessel Traffic Center is located at Pier 36
in Seattle and monitors the Strait of Juan de Fuca, Rosario Strait, Admi-
ralty Inlet, and Puget Sound south as far as Olympia. Since 1979, the U.S.
Coast Guard has worked cooperatively with the Canadian Coast Guard in
managing vessel traffic in adjacent waters. Through the Cooperative Vessel
Traffic Service (CVTS), two Canadian Vessel Traffic Centers work hand in
hand with Puget Sound Vessel Traffic Service. Tofino Vessel Traffic Service
manages the area west of the Strait of Juan de Fuca. North of the Strait of
182 SHIP CHANNEL DESIGN AND OPERATION
20.2.7.0.6 VTS Prince William Sound. The Prince William Sound Vessel
Traffic Center is located in Valdez. Geographically, the area is comprised
of deep open waterways surrounded by mountainous terrain. The Coast
Guard has installed a dependent surveillance system to improve its ability
to track tankers transiting Prince William Sound, and requires these ves-
sels to carry position and identification reporting equipment. The ability
to supplement radar with dependent surveillance bridges the gap in areas
in which conditions dictate some form of surveillance and radar coverage
is impractical. Once the dependent surveillance information is returned to
the vessel traffic center, it is integrated with radar data and presented to
the watchstander on an electronic chart display. VTS Prince William Sound
is required by the Trans-Alaska Pipeline Authorization Act (Public Law
93-153), pursuant to authority contained in Title 1 of the Ports and Water-
ways Safety Act of 1972 (86 Stat. 424, Public Law 92-340). The southern
terminus of the pipeline is on the south shoreline of the Port of Valdez.
Port Valdez is at the north end of Prince William Sound.
20.2.7.0.7 VTS St. Mary’s River. The St. Mary’s River Vessel Traffic Center
is located at Coast Guard Group Sault Ste. Marie, Michigan. In October
1994, it became a mandatory system operating year-round with an area of
responsibility along the entire length of the St. Mary’s River (approximately
80 miles). Within the VTS area the water level drops approximately 21 ft
from the level of Lake Superior to the level of the lower lakes. The Soo
Locks were constructed and are presently maintained by the Corps of
Engineers. In most areas of the river there is adequate room for vessels
to maneuver or anchor during periods of low visibility, or when other
problems hinder safe navigation. However, three areas are extremely
hazardous to transit or anchor in low visibility: West Neebish Channel
(downbound traffic only), Middle Neebish Channel (upbound traffic only),
and Little Rapids Cut (two-way traffic). During periods of low visibility, it
is customary to close the entire river.
COAST GUARD ACTIVITIES THAT SUPPORT NAVIGATION 183
20.2.7.0.8 VTS Berwick Bay. The Berwick Bay Vessel Traffic Center is lo-
cated at Coast Guard Marine Safety Office Morgan City, Louisiana. VTS
Berwick Bay manages vessel traffic on one of the most hazardous water-
ways in the United States due to strong currents and a series of bridges
that must be negotiated by inland tows traveling between Houston, Baton
Rouge, and New Orleans. The area of responsibility encompasses the junc-
tion of the Atchafalaya River (an outflow of the Mississippi River), the Gulf
Intracoastal Waterway, the Port Allen-Morgan City Alternate Route, and
several tributary bayous. Narrow bridge openings and a swift river cur-
rent require the VTS to maintain one-way traffic flow through the bridges.
During seasonal high-water periods, the VTS enforces towing regulations
requiring inland tows transiting the bridges to have a minimum amount of
horsepower based on the length of tow. VTS Berwick Bay is unique among
Coast Guard Vessel Traffic Services because it maintains direct control of
vessel traffic.
20.3.1 Prevention
Safety prevention activities include developing commercial and recre-
ational vessel standards, enforcing compliance with these standards, li-
censing commercial mariners, operating the International Ice Patrol to
protect ships transiting the North Atlantic shipping lanes, and educating
184 SHIP CHANNEL DESIGN AND OPERATION
the public. The Coast Guard develops operating and construction criteria
for many types of vessels from commercial ships to recreational boats. The
Coast Guard is America’s voice in the International Maritime Organization
(IMO), which promulgates measures to improve shipping safety, pollution
prevention, mariner training, and certification standards. The Coast Guard
is the agency primarily responsible for developing domestic shipping and
navigation regulations.
Navigation and shipping regulations are published in Chapter I of Titles
33 and 46, Code of Federal Regulations (CFR). These regulations provide
detailed guidance for the design and operation of inspected vessels, and
establish minimal requirements for uninspected vessels.
The Coast Guard ensures compliance with safety regulations in many
ways. Members of the Coast Guard inspect U.S. flag vessels and mobile
offshore drilling units and marine facilities; examine foreign-flag vessels
based on the potential safety and pollution risk they pose; review and
approve plans for vessel construction, repair, and alteration; and document
and admeasure U.S. flag vessels. The Port State Control program is aimed
at eliminating substandard foreign-flagged vessels from U.S. ports and
waterways. Port State Control is a key element in the safety enforcement
program because 95% of large passenger ships and 75% of cargo ships
operating in U.S. waters are foreign-flagged.
Maritime law enforcement and border control are the oldest of the Coast
Guard’s numerous responsibilities, dating back as the Revenue Marine in
1790. Congress established the Revenue Marine specifically to patrol the
coasts and seaports to frustrate smuggling and enforce the customs laws of
the fledgling republic. The Coast Guard’s maritime law enforcement role
and the task of interdicting ships at sea provide the foundation on which
the much broader and complex present-day mission set has been built.
Maritime Security Missions include:
Throughout American history, the Coast Guard has served alongside the
U.S. Navy in critical national defense missions, beginning with the Quasi-
War with France in 1798, through the Civil War, World Wars I and II, to
the Vietnam War and the Persian Gulf War. A 1995 agreement between the
Secretaries of Defense and Transportation assigned the Coast Guard five
specific national defense missions in support of the Unified Commanders-
in-Chief (CINCs) in addition to their general defense operations and polar
icebreaking duties. These missions (i.e., maritime interception operations;
military environmental response operations; port operations, security, and
defense; peacetime military engagement; and coastal sea control opera-
tions) require the Coast Guard to execute essential military functions and
tasks in support of joint and combined forces in peacetime, crisis, and war.
The Coast Guard’s protection of natural resources role dates to the 1820s,
when Congress required the Revenue Marine to protect federal stocks
of Florida live oak. As the exploitation of the nation’s valuable marine
resources—whales, fur-bearing animals, and fish—increased, the Coast
Guard was given the duty to protect these resources as well. Today, with
the U.S. EEZ supporting commercial and recreational fisheries worth more
than $30 billion annually, the Coast Guard serves as the primary agency
for at-sea fisheries enforcement. This role has expanded over the last few
decades to include enforcing laws intended to protect the environment as
a public good. As a result, the Coast Guard now actively protects sensitive
marine habitats, marine mammals, and endangered marine species, and
enforces laws protecting U.S. waters from the discharge of oil and other
hazardous substances.
COAST GUARD ACTIVITIES THAT SUPPORT NAVIGATION 189
The Coast Guard operates the National Response Center (NRC) around
the clock to receive notification of pollution incidents and to ensure that
information is passed to the predesignated Coast Guard or EPA OSC for
response. The NRC provides a toll free number (800-424-8802) for making
pollution reports from anywhere in the United States.
20.6.2 Enforcement
The federal responsibility for the removal of discharged oil and haz-
ardous substances is shared by the Coast Guard and the EPA. The federal
agencies cannot require anyone to clean up an oil spill; however, if federal
funds are used for the clean up, the costs (up to certain limits) are passed to
the owner or operator of the discharging vessel or facility or, under certain
circumstances, to the person causing the discharge.
20.7 SOURCE
Marine navigation tools are necessary to ensure safe and efficient marine
transportation and commerce, offshore engineering projects, naval opera-
tions, and recreational activities. The Office of Coast Survey, which is part
of NOAA’s National Ocean Service (NOS), is responsible for providing
these tools, such as nautical charts and hydrographic surveys. These must
be kept accurate and up to date at all times.
The mandate to create nautical charts of the nation’s coasts dates back to
1807, when President Thomas Jefferson ordered a survey of the young na-
tion’s coast. The Organic Act of 1807 authorized the newly formed coastal
survey agency to construct and maintain the nation’s nautical charts. This
agency, the Office of Coast Survey (OCS), is the oldest scientific organiza-
tion in the United States. It has been a part of NOS since 1970, when the
National Oceanic and Atmospheric Administration was created.
OCS remains the primary agency responsible for constructing and main-
taining the nation’s nautical charts. The U.S. Army Corps of Engineers
produces “navigational maps’’ for some inland rivers, primarily the
Mississippi, Ohio, Tennessee, Columbia, and their tributaries. NOAA
charts are available from NOAA field offices and a network of local sales
agents. Corps of Engineers river charts are available from district offices.
Nautical charts contain information about the nature and form of the coast,
the depth of the water, and general character and configuration of the sea
191
192 SHIP CHANNEL DESIGN AND OPERATION
bottom, locations of dangers to navigation, the rise and fall of the tides,
locations of navigational aids, and characteristics of the earth’s magnetism.
The charts are compiled by using a fleet of hydrographic vessels that op-
erate in the coastal waters of the continental United States and Alaska and
Hawaii. A typical NOAA ship is shown in Figure 21-1.
NOS collects marine hydrographic data (depth soundings) to construct
and maintain more than 1,000 nautical charts. In addition, NOS makes
available a historical map and chart collection—more than 20,000 maps and
charts dating from the late 1700s. The collection includes nautical charts,
hydrographic surveys, topographic surveys, geodetic surveys, city plans,
and Civil War battle maps.
NOAA’s National Geographic Data Center (NGDC) is the repository
of all NOAA (and many other organizations) hydrographic and bathy-
metric data. NGDC and the collocated World Data Center for Marine
Geology & Geophysics compile, maintain, archive, and distribute data
from extensive databases in both coastal and open ocean areas. Key data
types include bathymetry and gridded relief, trackline geophysics (grav-
ity, magnetics, seismic reflection), sediment thickness, data from ocean
drilling and seafloor sediment and rock samples, digital coastlines, and
data from the Great Lakes. In addition to operating the collocated World
Data Center for Marine Geology & Geophysics, part of the International
Council of Scientific Unions (ICSU) World Data Center system, NGDC
NOAA ACTIVITIES THAT SUPPORT NAVIGATION 193
NOAA’s National Ocean Service (NOS) has been monitoring sea level
variations for many years. For some U.S. locations, sea level records exist
for more than 100 years. Water level data is used for a variety of practical
purposes, including hydrography, nautical charting, maritime navigation,
coastal engineering, and tsunami and storm surge warnings. Mariners use
the information to time their approach to and exit from ports. Long-term
194 SHIP CHANNEL DESIGN AND OPERATION
Tide gauge stations are separated into two types: long-term, which are
usually located in major harbors, such as Seattle and San Francisco; and
temporary (operating for a few months), which support fieldwork, such as
hydrographic surveys or current surveys. An example of this temporary
tide gauge is shown in Figure 21-3.
The center also provides tidal and storm surge information online for
U.S. coastal areas and the Great Lakes region. The Web site is updated every
10 minutes to reflect changing conditions. In addition, the center provides
products that supply predictive information about tides and currents for
more than 3,000 tide stations.
21.5 CURRENTS
The U.S. Coast Pilot consists of a series of nautical books that covers
information important to navigators of coastal and intracoastal waters and
the Great Lakes. Issued in nine volumes, these books contain supplemental
information that is difficult to portray on a nautical chart.
Topics in the Coast Pilot include channel descriptions, anchorages,
bridge and cable clearances, currents, tide and water levels, prominent fea-
tures, pilotage, towage, weather, ice conditions, wharf descriptions, dan-
gers, routes, traffic separation schemes, small-craft facilities, and federal
regulations applicable to navigation. Coast Pilot publications are available
through NOAA-authorized network nautical agents.
21.8 PORTS
21.10 SOURCE
NOAA Web pages provided most of this information; the 1964 photos
were taken by Lieutenant (jg) B. McCartney.
Chapter 22
CASE HISTORIES
This chapter revisits and updates the 3 case histories presented in ASCE
Manual 80, 1993. These case histories are intended to show the applica-
tion of design principles presented in earlier chapters. The unique features
of these navigation projects are briefly summarized with more detail pro-
vided in the later part of the chapter.
a safer passing zone along this congested river reach. The final design
consists of a ship simulation study to evaluate the safety benefits for the
wider channel.
The strongest winds are from the west, southwest, and south. These winds
can reach 70 miles per hour from April to September.
Significant wave heights of 20 to 30 ft can be expected each year off Grays
Harbor. Swells generally approach the coast southwest to northwest. The
majority of the swell periods are 12 to 18 s. Sea conditions often have a
more southerly approach in winter and north-northwest approach in the
summer. Wind-generated waves in the estuary can reach 5 ft, although
1- to 3-ft-high waves are more common.
202 SHIP CHANNEL DESIGN AND OPERATION
personnel. Two reaches of channel were tested, 8.5 miles of the outer chan-
nel from Moon Island through the south reach and about 4 miles of the
inner channel reaches Aberdeen and South Aberdeen. Vessels tested were
a 535-ft-long by 34-ft design draft ship for existing channel conditions and
a 625-ft-long by 36.5-ft design draft ship for improved channel conditions.
All outbound simulations were run with fully loaded vessels. Inbound
simulations were made with light-loaded vessels transiting through the
bridges and turning at Elliott Slough. Summary of the test results follows.
22.4.11 Mitigation
The channel enlargement causes an impact on crabs and fish habitat.
Several crab mitigation sites were selected in North and South Bays. The
mitigation consisted of placing oyster shells in the site to allow cover and
reduced predation on young crabs. The fish mitigation consisted of creating
additional habitat in the river above the navigation channel.
22.4.12 Relocations
The relocations for this project consist of moving utility lines crossing
under the channel and replacing a railroad bridge. The existing railroad
bridge has a 125-ft horizontal clearance between piers. The options were
to replace the bridge with a longer span or remove the bridge. Bridge
removal was selected. With removal of the railroad bridge, the highway
bridge would become the width constraint with its 195 ft of horizontal
clearance.
month of the year has been over 50 miph, with a maximum speed on
record of 80 miph.
Wave climate throughout the project region is generally mild, except
during abnormal weather conditions. Under normal conditions, wave ac-
tion causes few navigation problems throughout the project area. The
mildest wave conditions prevail throughout Norfolk Harbor and Hamp-
ton Roads, where the surrounding topography minimizes development
of substantial waves. The representative wave climate of Hampton Roads
and vicinity follows.
Wave Climate of Hampton Roads and Vicinity
The largest waves in the project area occur in the vicinity of the Atlantic
Ocean Channel. At this location, severe wave heights, often associated
with northeasters and hurricanes, can cause navigational problems. Nor-
mally, this wave action comes from the northeast. A study of 20 years
of wave data offshore of Cape Henry was used to develop the following
information.
Vessel draft 52 ft 52 ft
Safety clearance 2 ft 2 ft
Heave, pitch, roll, squat, and trim 1 ft 6 ft
55 ft 60 ft
22.5.10 Mitigation
Extensive environmental-impact studies determined that there were no
mitigation requirements for this project. These environmental studies in-
cluded the following:
Benthic invertebrates
Finfish
Plankton
Phytoplankton
Zooplankton
Sediment quality
Sediment movement in both the ocean and the estuary
Water quality
22.5.11 Relocations
Relocations investigations identified water lines, tunnels, power lines,
and a ship-degaussing range for the Navy in the project area. The power
lines were a minimum of 75 ft below MLW in the Norfolk Channel so that
they were not affected by the deepening project.
The two water lines under the Norfolk Channel are at 52 ft and 60 ft
MLW and will need relocation. The Navy degaussing range in the Norfolk
Channel will need relocation.
The Thimble Shoal Channel tunnel (part of the Chesapeake Bay Bridge
Tunnel) has a top clearance of 63 ft below MLW. There is a minimum earth
cover of 10 ft over the top of the tunnel. This channel-deepening project will
put the new channel bottom at 57 ft below MLW (55 ft authorized depth,
212 SHIP CHANNEL DESIGN AND OPERATION
2 ft of over-depth dredging); this will encroach on the cover over the tunnel
and risk damage to the tunnel structure. A protective rock blanket was
recommended for this channel segment over the tunnel. See Table 22-4 for
further details.
Project location:
distance above mouth of Savannah River: 13.1 to 18.5 mi
Channel dimensions widened section:
length: 28,340 ft
Bottom width: 500 ft
Side slopes: 1 on 3
Harbor line from edge of channel: 100 to 150 ft
Construction quantities:
material dredged from channel: 1,894,000 cu yd
ASCE. (1994). Planning and design guidelines for small craft harbors. ASCE Manuals
and Reports on Engineering Practice, No. 50, ASCE, Reston, Va.
ASCE Task Committee on Hydraulic Modeling, Environmental and Water
Resources Institute. (2000). Hydraulic modeling: Concepts and practice. ASCE Man-
uals and Reports on Engineering Practice, No. 97, ASCE, Reston, Va.
ASCE Task Committee on Inland Navigation for the Committee on Waterways,
Waterways, Ports, and Ocean Division. (1998). Inland navigation: locks, dams, and
channels. ASCE Manuals and Reports on Engineering Practice, No. 94, ASCE,
Reston, Va.
ASCE Task Committee on Ship Channel Design for the Committee on Waterways,
Waterways, Port, Coastal, and Ocean Division. (1993). “Report on ship channel
design.’’ ASCE Manuals and Reports on Engineering Practice, No. 80, ASCE,
Reston Va.
Beeman. (1985). “Channel optimization: The Columbia River deep draft channel
project.” PIANC Bulletin, No. 51.
Berger, R. C. Jr., et al. (1985). “Norfolk Harbor and channels deepening study: Rep. 2,
sediment investigation; Chesapeake Bay hydraulic model investigation.’’Techni-
cal Rep. HL-83-13,’’ U.S. Army Waterways Experiment Station, Vicksburg,
Miss.
Berger, R. C., McAdory, R. T., Martin, W. D., and Schmidt, J. H. (1995). “Houston-
Galveston navigation channels, Texas project; Report 3, Three-dimensional hy-
drodynamic model verification,” Technical Report HL-92-7, U.S. Army Water-
ways Experiment Station, Vicksburg, Miss.
Committee on Tidal Hydraulics, Corps of Engineers, U.S. Army. (1965). Evaluation
of present state of knowledge of factors affecting tidal hydraulics and related phenomena,
U.S. Army Waterways Experiment Station, Vicksburg, Miss.
Committee on Tidal Hydraulics. (1995). “Review of problems in the tidal water-
ways considered by the Committee on Tidal Hydraulics.’’ U.S. Army Waterways
Experiment Station, Vicksburg, Miss.
d’Angremond, K., and Roode, F. C. (2001). Breakwaters and closure dams, Delft
University Press, The Netherlands.
Groenveld, R., Beimers, B., and Vis, F. C. (2003). “A simple method to assess nautical
risk.’’ Proc., COPEDEC VI Conference, Colombo, Sri Lanka.
Hansen, D. V., and Rattray, M., Jr. (1966). “New dimensions in estuary classifica-
tion.” Liminol Oceanog, 11, 319–326.
217
218 SHIP CHANNEL DESIGN AND OPERATION
Hewlett, J. C., Eagles, K. E., Huval, C. J., and Daggett, L. L. (1991). “Ship simulation
study of Grays Harbor navigation project, Grays Harbor, Washington.’’ Technical
Rep. HL-91-18, U.S. Army Waterways Experiment Station, Vicksburg, Miss.
Huval, C. J., ed. (1993). Planning, design and maintenance of deep draft navigation chan-
nels, PROSPECT training course notes, U.S. Army Waterways Experiment Station,
Vicksburg, Miss.
Huval, C., Combs, B., and Garner, R. T. III. (1985). “Ship simulation study of John F.
Baldwin (Phase II) Navigation Channel, San Francisco Bay, California.’’ Technical
Rep. HL-85-4, U.S. Army Waterways Experiment Station, Vicksburg, Miss.
Ippen, A. T., ed. (1966). Estuary and coastline hydrodynamics, McGraw-Hill, New
York.
Ippen, A. T., and Harleman, D. R. F. (1961). “One dimensional analysis of salinity
intrusion in estuaries.” Technical Bulletin No. 5, Prepared for Committee on Tidal
Hydraulics, Corps of Engineers, U.S. Army, U.S. Army Waterways Experiment
Station, Vicksburg, Miss.
McCartney, B. L., Herrmann, F. A. Jr., and Simmons, H. B. (1991). “Estuary water-
way projects—Lessons learned.” Journal of Waterway, Port, Coastal and Ocean En-
gineering, Vol. 117, No. 4, ASCE, Reston, Va.
Norfolk District Corps of Engineers. (2000). Navigation management plan for the Port
of Hampton Roads, Virginia.
Office, Chief of Engineers, U.S. Army. (1980). “Layout and design of shallow-draft
waterways.” Engineer Manual 1110-2-1611, Washington, D.C.
Office, Chief of Engineers, U.S. Army. (1983). “Dredging and dredged material
disposal.’’ Engineer Manual 1110-2-5025, Washington, D.C.
Office, Chief of Engineers, U.S. Army. (1986). “Design of breakwaters and jetties.’’
Engineer Manual 1110-2-2904, Washington, D.C.
Office, Chief of Engineers, U.S. Army. (1987). “Environmental engineering for deep
draft navigation projects.” Engineer Manual 1110-2-1202, Washington, D.C.
Office, Chief of Engineers, U.S. Army. (1990). “Winter navigation on inland water-
ways.’’ Engineer Manual 1110-8-1, Washington, D.C.
Office, Chief of Engineers, U.S. Army. (1991). “Tidal hydraulics.’’ Engineer Manual
1110-2-1607, Washington, D.C.
Office, Chief of Engineers, U.S. Army. (1995). “Hydraulic design of navigation
locks.’’ Engineer Manual 1110-2-1604, Washington, D.C.
Office, Chief of Engineers, U.S. Army. (2002). “Ice engineering.’’ Engineer Manual
1110-2-1612, Washington, D.C.
Office, Chief of Engineers, U.S. Army. “Hydraulic design of deep draft naviga-
tion projects.’’ (2002 draft of 2nd Ed.). Engineer Manual 1110-2-1613, Washington,
D.C., awaiting publication.
Office, Chief of Engineers, U.S. Army. (Forthcoming). “Coastal engineering manual,
Part VI.” Engineer Manual 1110-2-1100, Washington, D.C.
PIANC. (1997). “Approach channels—A guide for design.’’ Supplement to bulletin
no. 95, First Rep. of the Joint Working Group PIANC and IAPH, in cooperation with
IMPA and IALA, PIANC.
Pritchard, D. W. (1952a). “Estuaries hydrography.” Advances in Geophysics, 1, 243–
280.
APPENDIX A: BIBLIOGRAPHY 219
East Coast
New York, N.Y. 45 2000
Baltimore, MD 50 1000
Wilmington, NC 40 500
Charleston, SC 35 1000
Port Everglades, FL 45 500
Miami, FL 38 500
Great Lakes
Milwaukee, WI 30 800
Green Bay, WI 26 500
Gulf Coast
Houston, TX 40 400
Galveston, TX 42 800
Mississippi River, LA 45 600–750
Mobile, AL 47 600
Panama City, FL 42 450
Tampa, FL 46 700
San Juan, P.R. 48 500
West Coast
Grays Harbor, WA 46 1,000
Mouth of Columbia River, WA 55 2,000
Coos Bay, OR 45 700
San Francisco, CA 45 2,000
Los Angeles, CA 40 1,000
San Diego, CA 42 800
Honolulu, HI 45 500
221
This page intentionally left blank
Appendix C
ESTUARY WATERWAY PROJECTS
LESSONS LEARNED
During the last 100 years, the U.S. Army Corps of Engineers built,
and continues to maintain, over 300 navigation projects in tidal waters.
These projects include deep-draft ship channels, small boat harbors, and
intracoastal waterways for barges. The majority of these projects func-
tion very well with minimal maintenance cost. However, a few experience
higher-than-expected shoaling rates and require considerable maintenance
dredging.
The Corps’ Committee on Tidal Hydraulics has studied these problem
projects since 1950 and has identified a list of dos and don’ts for estuary nav-
igation projects. These generic lessons involve two categories—entrance
channels and interior channels. These were identified during a detailed
review of 24 of the 109 projects in which the committee had provided ad-
vice. Case histories for each of the reviewed projects included an analysis
of the various lessons that were learned. The study was published by the
Committee on Tidal Hydraulics in 1995.
Some of the lessons are obvious and may seem too trivial to list. How-
ever, the experience of the committee is that such lessons tend to become
lost and must then be relearned by subsequent generations. Restating
those lessons in this manual will make relearning them somewhat more
likely.
223
224 SHIP CHANNEL DESIGN AND OPERATION
FIGURE C-15. Side Channels, Basins, and Pier Slips as Sediment Traps.
particularly effective when they are combined with a tide gate, al-
lowing sediment-laden water into the trap and forcing cleaner water
(after deposition during slack tide) into the main channel to en-
hance flushing in a problem area. Example: Savanna Harbor. Such
a scheme can be used to relocate deposition areas closer to dredged
material disposal sites.
9. Docks should be located in naturally deep water, where possible
(Figure C-21). For example, the approach channel to a marginal
wharf at Anchorage Harbor is incised into a natural shoal that is
about half as deep as the channel. It experiences heavy shoaling.
10. Harbors should be located on the outside of river bends because
the inside of bends will shoal (Figure C-22). Example: Gold Beach
Harbor, Rogue River, Oregon.
11. Abandonment or relocation of harbor projects should be considered
when rapid shoaling prevents effective maintenance (Figure C-23).
Example: Gastineau Channel, Alaska.
12. Confined disposal—either in upland or diked in water sites—will
prevent the return of dredged materials to the channel, thereby re-
ducing future channel shoaling (Figure C-24). Example: Delaware
Bay.
FIGURE C-29. Saltwater Wedge and Shoaling Shifts Upstream with Deeper
Channel.
C.3 SOURCE
This information was taken from McCartney, Hermann, and Simons (1991)
“Estuary waterway projects—lessons learned.’’Journal of Waterways, Part 3,
Coastal and Ocean Engineering, 117(4), July/August, and the Commit-
tee on Tidal Hydraulics, U.S. Army Corps of Engineers (1995) “Review
of Problems in Tidal Waterways considered by the Committee on Tidal
Hydraulics,’’ June.
This page intentionally left blank
INDEX
245
246 INDEX